J065--Generator Preventative Maintenance Federal contract opportunity
Solicitation number
36C24625Q0480
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6

About this file

This document is an Amendment to Solicitation (Standard Form 30) for a Generator Preventative Maintenance contract issued by the Department of Veterans Affairs Network Contracting Office 6 located in Hampton, VA. The solicitation (RFQ 36C24625Q0480) covers generator maintenance services for the Asheville VA Medical Center, specifically requiring two onsite preventative maintenance trips per year, with provisions for emergency calls if generators run over 500 hours.

Key details include mandatory requirements such as oil, coolant, and fuel sample testing during annual inspections, with a specific note about a known issue of a CAT generator in building 62 burning oil while running. The contractor must submit quotes and receive Contracting Officer approval for any repairs, battery replacements, or fuel polishing services. The solicitation explicitly states that load bank testing is not part of this contract and will be handled separately. The contract is set to be effective on 03-19-2025, and vendors were provided an opportunity to submit questions about the scope of work prior to the amendment date.

View the file

Other files for this federal contract opportunity

Other files attached to J065--Generator Preventative Maintenance, newest first.
File Type Posted
36C24625Q0480 0001.docx DOCX document
QASP.docx DOCX document
36C24625Q0480_1.docx DOCX document
P07--Wage Detrmination Asheville.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7.

ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF

PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED

STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF

CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF

SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 03-19-2025 Kristine Woodbury Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667 Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667 To all Offerors/Bidders

36C24625Q0480

X X X X The purpose of this Amendment is to provide answers to the questions submitted by Vendors on or before March 19, 2025.

Attached are the Answers to Vendors Questions.

Kristine Woodbury Contract Specialist Harold L.

McQuillia, Jr.

Contracting Officer

CONTINUATION PAGE

Asheville VA Medical Center Generator Preventative Maintenance Inspections Vendor’s Questions for Solicitation RFQ 36C24625Q0480

1. Will there be a site visit before the contract award? If so, what is the date, time, and location? No

2. Are the emergency call services included in this solicitation/contract? This solicitation includes emergency calls for preventive maintenance should the need arise to run the generators for more than 500 hours. For example, during the hurricane we ran the generators for 1,000 hours so during that period we would have required 2 emergency calls to perform preventive maintenance.

3. If the Generator’s batteries need to be replaced due to its expiration date or any other damage, does the contractor need to submit a replacement quote for review and approval to the COR? Yes, no repair work shall be completed without notification from the Contracting Officer.

4. If the Contractor identifies an operational problem during the annual or semiannual inspection and a corrective action/repair is needed, does the contractor need to submit a repair quote for review and approval to the COR? Yes, no repair work shall be completed without notification from the Contracting Officer.

5. Regarding the Annual PM, oil samples should be taken and sent to the lab for testing. Does the contractor need to pull out a coolant and fuel samples as well? Yes

6. If the contractor notices fuel contamination during the annual or semiannual inspection, does the contractor need to submit a quote for fuel polishing services? Yes, no repair work shall be completed without notification from the Contracting Officer.

7. We couldn’t find any information regarding any known issues with the units in the solicitation. Are there any known pre-existing conditions on these generators that we need to know? The CAT generator at building 62 is burning oil while running. That is the only problem we are aware of at the moment.

8. Does the generator maintenance consist of two trips onsite per year? Yes, unless the need arises for emergency preventive maintenance if the generators have been running for 500 hours.

9. Is this requirement for only Preventative Maintenance and not the load bank testing as well? Yes, load bank testing is a separate contract.

10. Do you want to include the load bank testing as part of this solicitation? No Generator Preventative Maintenance