About this file

This is a Department of Veterans Affairs (VA) Invitation for Bid (IFB) for a sanitary sewer system repair and rehabilitation project at the Hampton VA Medical Center in Hampton, Virginia. The solicitation (36C24625B0025) is a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside with a contract value estimated between $2,000,000 and $5,000,000. The project requires replacing segments and manholes in poor condition, installing epoxy liners to limit infiltration, enhancing manholes with inserts, and addressing additional deficiencies such as securing a sewer pump.

Key procurement details include a pre-bid conference and site visit on Tuesday, June 24th, 2025, at 11:00am EDT, with questions due by June 30th, 2025, at 9:00am. Bids are due by 4:30pm on Wednesday, July 30th, 2025, with a public bid opening via Microsoft Teams on Thursday, July 31st at 11:00am. The contract performance period is 585 calendar days from the Notice to Proceed, and the SDVOSB prime contractor is required to perform a minimum of 25% of the construction work with its own labor force. Bid bonds are required, and all bidders must be registered in the System for Award Management (SAM).

View the file

Other files for this federal contract opportunity

Other files attached to Y1ND--Sanitary Sewer Construction, newest first.
File Type Posted
MH2 INTERIOR.jpg JPG image
MH25 INVERT.jpg JPG image
36C24625B0025 0003.docx DOCX document
Geotechnical Report 1 of 3.pdf PDF
Geotechnical Report 2 of 3.pdf PDF
Geotechnical Borings Report.pdf PDF
36C24625B0025 0002.docx DOCX document
Geotechnical Report 3 of 3.pdf PDF
36C24625B0025 0001.docx DOCX document
Site.Visit.Log.06.24.2025.pdf PDF
Attachment D - Site Visit.docx DOCX document
36C24625B0025_1.docx DOCX document
Attachment B - Bid Specifications.pdf PDF
Attachment C - Bid Drawings.pdf PDF
Attachment A - Wage Determination va198.txt TXT text file
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

of 65

36C24625B0025 X

05-12-2025

590-23-102 36C246

Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667

Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667 Aaron Holmes (757)722-9961 x8845 Project Title: Sanitary Sewer Repair | Project Number: 590-23-102 NAICS Code: 237110 - Water and Sewer Line & Related Structures Construction | Size Standard: $45 million IAW VAAR 836.204, the magnitude of construction is between $2,000,000 and $5,000,000.

Project Description: The Hampton VA Medical Center has a requirement for the repair and rehabilition of its sanitary sewer system in accordance with the Statement of Work. See the BASE BID ITEM LIST, Specifications, and Drawings for details.

THIS IS A 100% SERVICE-DISABLED VETERAN OWNED SMALL BUSINESS (SDVOSB) SET-ASIDE IAW 38. U.S.C. 8127 (d).

The SDVOSB is required to perform a minimum of 25% of the construction work on the project with its own labor force.

This does not include paperwork, submittals, and project management.

This contract will be awarded IAW FAR 14 - Sealed Bidding

IAW established public law, all bidders are required to be registered and current in System for Award Management (SAM) at the time of award. The Official website of the U.S. Government at www.sam.gov.

Pre-Bid Conference: A site visit is scheduled for Tuesday, June 24th at 11:00am EDT. Interested parties shall meet at the canteen, bldg. 17, of the Hampton VA Medical Center in Hampton, Virginia.

See Attachment D - Site Visit for details.

Questions: Please submit all questions via email to Contract Specialist Aaron Holmes at aaron.holmes@va.gov and cc Contracting Officer Guy Brooks at guy.brooks@va.gov. All questions must be submitted by 9:00am on Monday, June 30th.

Answers will be posted by amendment. Do not submit questions regarding this project to any other VA staff.

Bid Due Date: Bids are due no later than 4:30pm on Wednesday, July 30th, 2025. Bids must be submitted by email to Contract Specialist Aaron Holmes at aaron.holmes@va.gov and cc Contracting Officer Guy Brooks at guy.brooks@va.gov.

A bid opening ceremony will be conducted via MS Teams at 11:00am on Thursday, July 31st, 2025. See Instructions to Bidders for details.

Prime SDVOSB shall comply with subcontracting limitation asdefined in 13 CFR 125.6. Bid Bonds are required.

Please remember to follow all instructions and to include a signed copy of 852.219-75 Limitations on Subcontracting.

52.211-10

(1) emailed 4:30pm

EDT

07-30-2025

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

BASE BID:

Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667

Department of Veterans Affairs Financial Services Center

PO BOX 149971

Austin TX 78714-9971 512-460-5049 512-460-5221

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
A.3 PRICING SCHEDULE5
A.4 INSTRUCTIONS, CONDITIONS, AND OTHER STATEMENTS TO BIDDERS AND OFFERORS6
A.5 STATEMENT OF WORK12
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS15
2.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)15
2.2 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)15
2.3 52.216-1 TYPE OF CONTRACT (APR 1984)16
2.4 52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2020)16
2.5 52.219-14 LIMITATIONS ON SUBCONTRACTING (OCT 2022)16
2.6 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)18
2.7 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)19
2.8 52.228-1 BID GUARANTEE (SEP 1996)20
2.9 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)20
2.10 52.233-2 SERVICE OF PROTEST (SEP 2006)21
2.11 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)21
2.12 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)22
2.13 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)22
2.14 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)22
REPRESENTATIONS AND CERTIFICATIONS24
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2025) (DEVIATION FEB 2025)24
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)28
3.3 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—REPRESENTATION AND DISCLOSURES (DEC 2023)30
3.4 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)32
3.5 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)33
GENERAL CONDITIONS36
4.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)36
4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984)39
4.3 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JAN 2025)39
4.4 52.223-20 AEROSOLS (MAY 2024)42
4.5 52.223-21 FOAMS (MAY 2024)43
4.6 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)44
4.7 SUPPLEMENTAL INSURANCE REQUIREMENTS48
4.8 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)49
4.9 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)49
4.10 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)49
4.11 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)49
4.12 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION)50
4.13 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION)53
4.14 VAAR 852.222-71 COMPLIANCE WITH EXECUTIVE ORDER 13899 (DEVIATION) (APR 2025)54
4.15 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)55
4.16 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)55
4.17 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)55
4.18 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)58
4.19 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)59
4.20 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 2019)60
4.21 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)61
4.22 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)61
4.23 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)61
4.24 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)63
4.25 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)63
ATTACHMENTS65

A.3 PRICING SCHEDULE

Item Number
Description of Supplies/Service
Quantity
Unit
Unit Price
Amount
1.00
JB
_____________
_____________

BASE BID: The contractor shall provide all labor, materials, tools, equipment, and supervision to perform all operations necessary to repair the sanitary sewer system of the Hampton VA Medical Center.

All work shall be in strict accordance with the Statement of Work (SOW) and will include final clean up and completion of any punch list items.

POP Begin:
NTP
POP End:
NTP + 585 calendar days
Principal NAICS:
237110
Water and Sewer Line & Related Structures Construction
Product/Service:
Y1ND
Construction of Sewage & Waste Facilities

A.4 INSTRUCTIONS, CONDITIONS, AND OTHER STATEMENTS TO BIDDERS AND OFFERORS

1. SUBMISSION OF BIDS:

The bidder shall submit the following in response to this Invitation for Bids:

(a) A completed and signed Standard Form 1442. Contractor must acknowledge all amendments in block 19 at the time of the bid opening.

(b) A completed copy of the Representations and Certifications.

(c) A fully executed bid bond.

(d) Documentation of safety record.

(e) Itemized Schedule of Values Cost breakdown.

(f) Signed 52.219-28

(g) Signed 852-219-75 NOTE 1: Offerors must submit an Itemized Schedule of Values Cost breakdown in their bid in sufficient detail to permit a complete analysis of labor, materials, equipment, transportation, supervision, disposal costs, overhead, and profit. This breakdown shall cover all work involved in accordance with (IAW) the Statement of Work (SOW). If an Itemized Schedule of Values Cost breakdown is not provided, the bidder’s or offeror’s bid will be deemed non-responsive.

NOTE 2: Copies of all subcontractor quotes are required.

2. PRE-BID CONFERENCE: A pre-bid conference/site-visit has been scheduled for Tuesday, June 24th, 2025, at 11:00am EDT. Interested parties shall first meet in the canteen of the Hampton, VA Medical Center Campus. This pre-bid conference will be the only opportunity for potential bidders to visit the site.

NOTE: QUESTIONS REGARDING THIS SOLICITATION MUST BE SUBMITTED VIA E-MAIL TO Contract Specialist aaron.holmes@va.gov AND CC Contracting Officer guy.brooks@va.gov; NO TELEPHONE QUESTIONS WILL BE ACCEPTED. CUT OFF FOR QUESTIONS IS WEDNESDAY, JUNE 30TH, 2025, BY 4:30PM EDT. NO FURTHER QUESTIONS WILL BE ADDRESSED AFTER THAT DATE/TIME.

3. BID SUBMISSION & OPENING: All bids shall be submitted by the prime contractor. Bids must be submitted by electronics means through email to aaron.holmes@va.gov and cc to guy.brooks@va.gov. Submit bids via email to the Contract Specialist and Contracting Officer ONLY. All bids submitted electronically are due no later than 4:30PM EDT on WEDNESDAY, JULY 30TH, 2025. Please do NOT submit bids through the mail or attempt to hand in bids in person. LATE BIDS WILL NOT BE ACCEPTED.

NOTE: To be considered and accepted as timely the bid must be uploaded, mailed, or submitted in its entirety prior to the deadline. Failure to provide a bid in its entirety prior to the deadline will render the bid noncompliant.

A PUBLIC BID OPENING WILL BE CONDUCTED ONLINE VIA MICROSFOT TEAMS. BIDS WILL BE OPENED AND READ ON THURSDAY, JULY 31ST, AT 11:00AM EDT.

Bidders who have submitted timely bids will be sent invitations links to the bid opening. Interested members of the public may listen in via the link below:

https://teams.microsoft.com/l/meetup-join/19%3ameeting_YTUzZjVmYjUtNzJiMS00MjZjLWI4MjItNDY3YzZjZGQ1Y2Fk%40thread.v2/0?context=%7b%22Tid%22%3a%22e95f1b23-abaf-45ee-821d-b7ab251ab3bf%22%2c%22Oid%22%3a%2293a96cec-3c41-4c27-a8a7-f2c25e1f3534%22%7d

SUMMARY OF DATES:

· Pre-Bid Conference/Site Visit: Tuesday, June 24th, 2025, at 11:00am EDT

· Questions Due: Monday, June 30th, 2025, by 9:00am EDT

· Bids Due: Wednesday, July 30th, 2025, by 4:30pm EDT

· Bid Opening: Thursday, July 31st, 2025, at 11:00am EDT

4. BASIS FOR AWARD: The Government intends to award a contract to the responsible offeror with the lowest evaluated price. Offerors must submit a cost breakdown in sufficient detail to permit a complete analysis of labor, burden, materials, equipment, transportation, supervision, and disposal. When price is the only factor considered, award will be based on the lowest reasonable price received. Award will be made to the responsible bidder (see FAR 9.1) whose bid is responsive to the terms of the invitation for bids and is most advantageous to the Government, considering only price and price relate factors included in the invitation, as provided in FAR subpart 14.4.

5. TECHNICAL BID: A technical bid is not required.

6. EVALUATION OVERVIEW: Bids will be evaluated and ranked according to price and price alone, from lowest to highest. All bids shall include a cost breakdown in sufficient detail to permit a complete analysis of labor, burden, materials, equipment, transportation, supervision, and disposal. The Government may use various price analysis techniques and procedures to make a price reasonableness determination. Bids unreasonably high or unrealistically low in price, when compared to the Government estimate, and market conditions evidenced by other competitive bids received, may be indicative of an inherent lack of understanding of the solicitation requirements and may result in bid rejection without discussion.

7. SAFETY AND ENVIRONMENTAL RECORD: In accordance with VHA Directive 7715 the Contract Specialist and Contracting Officer will review the offeror’s safety and environmental record as part of their standard responsibility determinations in accordance with FAR 9.105. In order to be eligible for consideration and award, the contractor shall have no more than two serious, one repeat, or one willful OSHA or EPA Violation(s) in the past 5 years. Should the offeror not meet the standard of having no more than two serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 5 years and an Experience Modification Rate of equal to or less the 1.0, the Contracting Officer will follow the procedures from FAR 19.602-1 and refer the matter to the cognizant SBA Government Contracting Office.

Upon the conclusion of the bid opening, the Government may request any or all of the following:

1. A self-certification on company letterhead that the bidder has no more than two (2) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past five years along with copies of their OSHA logs (OSHA Form 300A) for the past three years. If the firm has been in business for less than three years, they shall submit copies of their OSHA logs for the period of time they have been in business.

2. Information regarding their current Experience Modification Rate (EMR) equal to or less than 1.0. This information shall be obtained from the bidder's/offeror's insurance company and be furnished on the insurance carrier's letterhead. Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state-run worker's compensation insurance rating bureau.

8. TRAINING: All employees of the general contractor and subcontractors shall have the 10-hour OSHA certified construction safety course and/or other relevant competency training, as determined by the COR with input from the ICRA (Infection Control Risk Assessment) team. The General Contractor’s competent person shall have completed the 30-hour OSHA certified construction safety course. Documentation of training shall be submitted to the Contracting Officer for review and approval prior to any work being performed. No ID badge will be issued to an employee who does not provide this documentation. There shall be no exceptions to this requirement.

9. MAGNITUDE OF CONSTRUCTION: IAW VAAR 836.204(f)(2), the magnitude of construction is estimated to be between $2,000,000 and $5,000,000. (https://www.va.gov/oal/library/vaar/vaar836.asp#836204)

10. DESCRIPTION OF WORK: Contractor shall provide all administration, supervision, labor, materials, tools, and equipment, and perform all operations necessary to for repairs of the sanitary sewer system at the Hampton VA Medical Center (HAMVAC) in accordance with the plans and specifications. Work will be performed according to project specifications and drawings. A security Accreditation Package is not required.

11. COMPLETION TIME: All work shall be completed within 585 calendar days from Notice to Proceed (NTP).

12. SDVOSB SET-ASIDE: This procurement is 100% set-aside for Service-Disabled, Veteran-Owned Small Business (SDVOSB). Bids are solicited only from SDVOSB concerns. Bids received from non-SDVOSB concerns will be rejected. In order to be considered, the firm must be registered in the SBA’s Veteran Small Business Certification (VetCert) database as a certified SDVOSB at the time of bid submission (https://veterans.certify.sba.gov).

13. CONTRACTOR RESPONSIBILITY: Contractor shall be required to complete all contract work and schedule a final inspection within the specified contract performance period. Should the Contractor fail to complete the contract work (including scheduling of the final inspection), and it is determined by the Government to be a Contractor-caused delay, the Contractor shall be in default status. If the Government determines it to be in the best interest of the Government to allow the Contractor to continue to perform contract work, the Contractor shall provide equitable consideration to the Government for additional time granted for completion of contract work. Such agreement shall not be deemed a waiver of the Government’s right to terminate this contract in the event the Contractor fails to complete the contract work (including scheduling of the final inspection) on or before the completion date.

14. TB TESTING: In accordance with section 01 35 26 -1.13 Safety Requirement Tuberculosis Screening of the specifications,

(a) The contractor must provide written certification that all contract employees assigned to the work site have had a pre-placement tuberculin screening within 90 days prior to assignment to the worksite and been found have negative TB screening reactions. Contractors will be required to show documentation of negative TB screening reactions for any additional workers who are added after the 90-day requirement before they will be allowed to work on the work site.

NOTE: This can be the Center for Disease Control (CDC) and Prevention and two-step skin testing or a Food and Drug Administration (FDA)-approved blood test.

(b) Contract employees manifesting positive screening reactions to the tuberculin must be examined according to current CDC guidelines prior to working on VHA property.

(c) Subsequently, if the employee is found without evidence of active (infectious) pulmonary TB, a statement documenting examination by a physician must be on file with the employer (construction contractor), noting that the employee with a positive tuberculin screening test is without evidence of active (infectious) pulmonary TB.

(d) If the employee is found with evidence of active (infectious) pulmonary TB, the employee would require treatment with a subsequent statement to the fact on file with the employer before being allowed to return to work on VHA property.

15. KEYS: All keys provided the Contractor for use during the project shall be returned to the Contracting Officer's Representative (COR) at completion of the work or upon request. No keys shall be reproduced by the Contractor. There shall be a charge of $10.00 for each key that is lost or not returned to the COR. Payment shall be made to the Richmond VA Medical Center upon receipt of a Bill of Collection.

16. PREPARATION OF BIDS/OFFERS/BIDS: The Government will not pay for any costs incurred in preparation and/or submission of bids.

17. PRIVACY AND CONFIDENTIALITY: Contractors to the Department of Veteran Affairs may be unintentionally exposed to sensitive information. Information may be overheard, seen on documents or electronic devices, or observed that could potentially violate the privacy and confidentiality of our veterans, employees, volunteers, and their families. Regulations such as, but not limited to the Health Insurance Portability and Accountability Act of 1996 (HIPAA), Freedom of Information Act (FOIA) and Privacy Act of 1974 have been enacted to protect sensitive information from being improperly disclosed. Information should not be divulged or released to anyone unless specifically authorized by this contract or attached documents in accordance with the contracted services. Failure to comply with applicable statutes and regulation can result in the termination of this contract and civil/criminal penalties, including fines and/or imprisonment. All suspected or actual breeches of privacy and confidentiality should be reported immediately to the Contracting Officer, Contracting Officer’s Representative (COR) or the Facility Privacy Officer.

18. VETS 100: Title 38, USC Section 4212(d), and Public Law 105-339, requires that federal contractors report, at least annually, the number and category of veterans who are within their workforce. Submission of the VETS 100 reporting information can be done electronically at: http://vets100.cudenver.edu. Award cannot be made unless the awardee has filed their VETS 100 report. Therefore, all bidders/offerors are encouraged to file every year.

19. SYSTEM FOR AWARD MANAGEMENT (SAM): Federal Acquisition Regulations require that federal contractors register in the System for Award Management (SAM) database at http://www.sam.gov and enter all mandatory information into the system. Award cannot be made until the contractor has registered. Bidders are encouraged to ensure that they are registered in SAM prior to submitting their bid.

20. CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM:

(a) FAR 42.1502 direct all Federal agencies to collect past performance information on contracts. The Department of Veterans Affairs has implemented use of the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.1502(b). The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report.

(b) Please furnish the Contracting Officer with the name, position title, phone number, and email address for each person designated to have access to your firm’s past performance evaluation(s) for the contract no later than 30 calendar days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official. The report information must be protected as source selection sensitive information not releasable to the public.

(c) When your Contractor Representative(s) (Past Performance Points of Contact) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, system requirements, and training information for CPARS are available at www.cpars.gov. The CPARS User Manual, registration for online training for Contractor Representatives may be found at this site.

(d) Within 60 calendar days after the end of a performance period, the Contracting Officer will complete an interim or final past performance evaluation, and the report will be accessible at www.cpars.gov. Contractor Representatives may then provide comments in response to the evaluation or return the evaluation without comment. Comments are limited to the space provided in Block 22. Your comments should focus on objective facts in the Assessing Official’s narrative and should provide your views on the causes and ramifications of the assessed performance. In addition to the ratings and supporting narratives, blocks 1-17 should be reviewed for accuracy, as these include key fields that will be used by the Government to identify your firm in future source selection evaluations. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating, “No Comment” in Block 22, and then signing and dating Block 23 of the form. Without a statement in Block 22, you will be unable to sign and submit the evaluation back to the Government. If you do not sign and submit the CPARS within 30 days, it will automatically be returned to the Government and will be annotated: “The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment.” Your response is due within 30 calendar days after receipt of the CPARS.

(e) The following guidelines apply concerning your use of the past performance evaluation:

(1) Protect the evaluation as “source selection information.” After review, transit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the Contracting Officer for instructions.

(2) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.

(3) Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determination, production readiness reviews, or other similar purposes.

(f) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the Contracting Officer no later than seven calendar days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 30-day review period.

(g) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been completed.

NOTICE:

System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations. Examples include 52.222-25, Affirmative Action Compliance, and paragraph (d) of 52.212-3, Offeror Representations and Certifications—Commercial Products and Commercial Services. Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

Page 1 of Page 1 of

A.5 STATEMENT OF WORK

Sanitary Sewer System Survey and Repairs Project 590-23-102 Hampton VA Medical Center, Hampton, VA 23667

Scope:

The Contractor shall be responsible for performing all required work associated with the repairs of the sanitary sewer as defined in the Specifications and Drawings. The contractor shall provide, but not limited to, all tools, labor, materials, equipment, supervision, professional services, and expertise required to perform general construction, alterations, site work, grubbing, grading, select demolition, hauling, disposal, installation of stormwater and sanitary drainage structures and pipes, electrical work, relocation of existing utilities, paver work, concrete work, curb and gutter work, planting, pavement marking, and installation of signage.

The contractor shall:

· replace all selected segments and manholes in poor condition and subject to high infiltration,

· install impervious epoxy liner on all pipes and manholes in poor condition to limit existing and/or future infiltration,

· enhance all manholes with inserts to limit inflow and perform selected Inflow and Infiltration (I&I) repairs, AND

· address all additional deficiencies such as securing a sewer pump at the SE corner of the Engineer Shops.

The contractor shall manage and perform all work as further defined in the Contract to include, but not limited to, permitting, demolition, construction, construction management, submittals, equipment, scheduling, inspection and testing, environmental protection, recording of (As-Built) drawings, and project closeout.

(a) General: The following is a brief summary of the work:

STATEMENT OF BID ITEM(S)

BID ITEM I (BASE BID): Work includes all labor, material, equipment, and supervision to complete all work for the entire project as indicated in the contract documents, including demolition, grubbing and soil removal, adjustments to existing utilities, grading, site alterations, and general construction of roads, walks, curbs and gutters.

Replace a selection of segments and manholes in poor condition and subject to high infiltration. Install impervious epoxy liner on pipes and manholes in poor condition to limit existing and/or future infiltration. Enhance all manholes with inserts to limit inflow and perform selected I&I repairs. Address additional deficiencies such as securing a sewer pump at the SE corner of the Engineer Shops.

1. Completion time: 585 calendar days

2. Magnitude of Construction: $2,000,000 ~ $5,000,000

(b) Place of Performance: Tasks will be performed at the VA Medical Center, Hampton, VA, 23667. Work will be around an occupied healthcare facility in operation 24 hours a day.

(c) Specific Requirements (see drawings for area of work):

SECTION NO ----- DIVISION AND SECTION TITLES

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 01 33 23 Shop Drawings, Product Data, and Samples 01 42 19 Reference Standards 01 45 00 Quality Control 01 45 29 Testing Laboratory Services 01 57 19 Temporary Environmental Controls 01 74 19 Construction Waste Management

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition

DIVISION 03 – CONCRETE

03 30 53 Cast-in-Place Concrete (Short Form)

DIVISION 31 – EARTHWORK

31 20 11 Earthwork (Short Form) 31 23 19 Dewatering

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 32 12 16 Asphalt Paving 32 14 16 Brick Unit Paving 32 17 23 Pavement Markings

DIVISION 33 – UTILITIES

33 30 00 Sanitary Sewer Utilities 33 71 10 Sanitary Sewer Cleaning 33 71 50 Sanitary Sewer Flow Control 33 73 00 Sanitary Sewer Televising/Video Recording and Air Testing for Sanitary Sewers being Lined 33 76 00 Manhole Rehabilitation – Epoxy Lining System 33 77 30 Sanitary Sewer Rehabilitation – Cured-in-Place Lining of Mainline Sewers 33 77 40 Sanitary Sewer Rehabilitation – Cured-in-Place Partial Lateral Liner

ATTACHMENTS

99 00 01 Pre-Construction Risk Assessment (VAMC FORM) 99 00 02 Fire & Safety Review (VAMC FORM)

(d) Period of Performance: Contractor shall commence work under this contract promptly after Notice to Proceed (NTP), execute the work diligently, and achieve final completion and acceptance including final cleanup of the premises within 585 calendar days including submittals.

(e) Specific Site Requirements: Contractor and all subcontractors shall obtain a PIV-I badge from the HR Badging Office (requires scheduling, fingerprinting, and providing two (2) forms of ID; one of which must be an approved photo ID), provide proof of completion from an approved OSHA 10-hour training course (30-hour for superintendent), complete and provide certificate of training for Integrity and Compliance Awareness Training for all Non-Revenue Staff (TMS course 43790), and shall abstain from smoking within the perimeters of the facility. All individuals that enter any VA patient care building(s) are required to be pre-screened for COVID-19 and required to wear a face mask; to include Veterans, employees, visitors, volunteers, and contractors. Contractors entering non-patient care buildings are required to wear a face mask. Contractors working outside within six (6) feet of one another, or any other individual, shall also be required to wear a face mask.

(f) Construction Safety Requirements: See Safety Requirements – section 01 35 26, and Hampton VAMC Construction Safety Handbook – section 01 35 26A.

(g) Submittals: See sections 01 00 00, 01 33 23, and all applicable trade sections.

(h) Quality Control: See section 01 45 00.

(j) Environmental and Waste Management: See sections 01 57 19, and 01 74 19.

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/browse/index/far https://www.va.gov/oal/library/vaar/

(End of Provision)

FAR Number
Title
Date
52.204-7
SYSTEM FOR AWARD MANAGEMENT
NOV 2024
52.204-16
COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING
AUG 2020
52.204-22
ALTERNATIVE LINE ITEM PROPOSAL
JAN 2017
52.214-3
AMENDMENTS TO INVITATIONS FOR BIDS
DEC 2016
52.214-4
FALSE STATEMENTS IN BIDS
APR 1984
52.214-5
SUBMISSION OF BIDS
DEC 2016
52.214-6
EXPLANATION TO PROSPECTIVE BIDDERS
APR 1984
52.214-7
LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS
NOV 1999
52.214-18
PREPARATION OF BIDS—CONSTRUCTION
APR 1984
52.214-19
CONTRACT AWARD—SEALED BIDDING—CONSTRUCTION
AUG 1996
52.214-34
SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE
APR 1991
52.214-35
SUBMISSION OF OFFERS IN U.S. CURRENCY
APR 1991
52.229-11
TAX ON CERTAIN FOREIGN PROCUREMENTS—NOTICE AND REPRESENTATION
JUN 2020

2.2 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)

(a) All actual and potential offerors are encouraged to provide feedback on the preaward and debriefing processes, as applicable. Feedback may be provided to agencies up to 45 days after award. The feedback is anonymous, unless the participant self-identifies in the survey. Actual and potential offerors can participate in the survey by selecting the following link: https:// www.acquisition.gov/360.

(b) The Contracting Officer will not review the information provided until after contract award and will not consider it in the award decision. The survey is voluntary and does not convey any protections, rights, or grounds for protest. It creates a way for actual and potential offerors to provide the Government constructive feedback about the preaward and debriefing processes, as applicable, used for a specific acquisition.

(End of Clause)

2.3 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.4 52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2020)

(a) Definition. Small business concern, as used in this clause—

(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the size standards in this solicitation.

(2) Affiliates, as used in paragraph (a)(1) of this clause, means business concerns, one of whom directly or indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.

(b) Applicability. This clause applies only to—

(1) Contracts that have been totally set aside for small business concerns; and

(2) Orders set aside for small business concerns under multiple-award contracts as described in 8.405-5 and 16.505(b)(2)(i)(F).

(c) General.

(1) Offers are solicited only from small business concerns. Offers received from concerns that are not small business concerns shall be considered nonresponsive and will be rejected.

(2) Any award resulting from this solicitation will be made to a small business concern.

(End of Clause)

2.5 52.219-14 LIMITATIONS ON SUBCONTRACTING (OCT 2022)

(a) This clause does not apply to the unrestricted portion of a partial set-aside.

(b) Definition. Similarly situated entity, as used in this clause, means a first-tier subcontractor, including an independent contractor, that—

(1) Has the same small business program status as that which qualified the prime contractor for the award (e.g., for a small business set-aside contract, any small business concern, without regard to its socioeconomic status); and

(2) Is considered small for the size standard under the North American Industry Classification System (NAICS) code the prime contractor assigned to the subcontract.

(c) Applicability. This clause applies only to—

(1) Contracts that have been set aside for any of the small business concerns identified in 19.000(a)(3);

(2) Part or parts of a multiple-award contract that have been set aside for any of the small business concerns identified in 19.000(a)(3);

(3) Contracts that have been awarded on a sole-source basis in accordance with subparts 19.8, 19.13, 19.14, and 19.15;

(4) Orders expected to exceed the simplified acquisition threshold and that are—

(i) Set aside for small business concerns under multiple-award contracts, as described in 8.405–5 and 16.505(b)(2)(i)(F); or

(ii) Issued directly to small business concerns under multiple-award contracts as described in 19.504(c)(1)(ii);

(5) Orders, regardless of dollar value, that are—

(i) Set aside in accordance with subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 8.405–5 and 16.505(b)(2)(i)(F); or

(ii) Issued directly to concerns that qualify for the programs described in subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 19.504(c)(1)(ii); and

(6) Contracts using the HUBZone price evaluation preference to award to a HUBZone small business concern unless the concern waived the evaluation preference.

(d) Independent contractors. An independent contractor shall be considered a subcontractor.

(e) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees that in performance of a contract assigned a North American Industry Classification System (NAICS) code for—

(1) Services (except construction), it will not pay more than 50 percent of the amount paid by the Government for contract performance to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract;

(2) Supplies (other than procurement from a nonmanufacturer of such supplies), it will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 50 percent subcontract amount that cannot be exceeded. When a contract includes both supplies and services, the 50 percent limitation shall apply only to the supply portion of the contract;

(3) General construction, it will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 85 percent subcontract amount that cannot be exceeded; or

(4) Construction by special trade contractors, it will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 75 percent subcontract amount that cannot be exceeded.

(f) The Contractor shall comply with the limitations on subcontracting as follows:

(1) For contracts, in accordance with paragraphs (c)(1), (2), (3) and (6) of this clause— [X] By the end of the base term of the contract and then by the end of each subsequent option period; or [] By the end of the performance period for each order issued under the contract.

(2) For orders, in accordance with paragraphs (c)(4) and (5) of this clause, by the end of the performance period for the order.

(g) A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph (e) of this clause will be performed by the aggregate of the joint venture participants.

(1) In a joint venture comprised of a small business protégé and its mentor approved by the Small Business Administration, the small business protégé shall perform at least 40 percent of the work performed by the joint venture. Work performed by the small business protégé in the joint venture must be more than administrative functions.

(2) In an 8(a) joint venture, the 8(a) participant(s) shall perform at least 40 percent of the work performed by the joint venture. Work performed by the 8(a) participants in the joint venture must be more than administrative functions.

(End of Clause)

2.6 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.7 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.8 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3 million, whichever is less.

(…

This is the start of the file's text. The full file is on GovTribe.