This document provides details for a federal construction contract opportunity with the Department of Veterans Affairs. The project involves repairing a pump station, pipeline, and sewer main for Building 5 at the W.G. Bill Hefner VA Medical Center in Salisbury, North Carolina. The contractor must provide all labor, materials, equipment, permits, and supervision to complete the work within 190 calendar days of receiving the notice to proceed. The estimated value of the construction project is between $250,000 and $500,000. The solicitation number is 36C24621B0005 and the NAICS code is 237120. The bid due date is May 24, 2021 and the virtual bid opening will be held on May 25, 2021.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 659-20-102_Final_SPS Sewer Deficiency-Plans-SealwSig (1).pdf | ||
| 659-20-102_Final_Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C24621B0005 Section M Contract Opportunity Special Notice
PRODUCT SERVICE CODE
SUBJECT
CONTRACTING OFFICE'S
ZIP-CODE
SOLICITATION NUMBER
ARCHIVE
DAYS AFTER THE RESPONSE DATE
RECOVERY ACT FUNDS
NAICS CODE
CONTRACTING OFFICE
ADDRESS
POINT OF CONTACT
(POC Information Automatically Filled from User Profile Unless Entered)
DESCRIPTION
See Attachment
AGENCY'S URL
URL DESCRIPTION
AGENCY CONTACT'S EMAIL
ADDRESS
EMAIL DESCRIPTION
GENERAL INFORMATION
ADDITIONAL INFORMATION
* = Required Field Contract Opportunity Special Notice
Z1DA
659-20-102_B2-SPS-SewerDeficiency (VA-21-00048243) 28144 36C24621B0005 N 237110 Department of Veterans Affairs Network Contracting Office 6 1601 Brenner Ave Salisbury NC 28144 Contracting Officer Mark Griffin mark.griffin2@va.gov 704-638-9000 13630 mark.griffin2@va.gov Project #659-20-102 –B2 SPS Sewer Deficiencies The Department of Veterans Affairs, 1601 Brenner Ave Salisbury, NC has a requirement for a contractor to provide all labor, material, supplies, equipment, transportation, permits, license and qualified supervision for Project 659-20-102. This is a new requirement to Repair the pump station, pipeline, and sewer main for Building 5, at the W.G. Bill Hefner VA Medical Center, Salisbury, NC.
All work, including final cleanup and completion of any punch list items shall be performed within one hundred and fifty (190) days after the receipt of notice to proceed.
Estimated magnitude of construction project is between $250,000 and $500,000.
NAICS CODE: 237120 Size Standard: $39.5 Million
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE
DOCUMENTS (
Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C24621B0005 X 04-23-2021 659-20-102 Department of Veterans Affairs Network Contracting Office 6 1601 Brenner Ave Salisbury NC 28144 Department of Veterans Affairs Network Contracting Office 6 1601 Brenner Ave Salisbury NC 28144 Mark Griffin
(704) 638-9000 13630
PROJECT TITLE: SPS SEWER DEFICIENCY
PROJECT LOCATION: W.G. Bill Hefner VAMC, 1601 Brenner Ave. Salisbury, NC 28144 PROJECT DESCRIPTION: Contractor shall provide all tools, labor, materials, equipment, traffic controls, permits, and supervision to complete work related, but not limited, to:
Please review the attached Statement of Work:
THIS IS A 100% SERVICE
DISABLED VETERAN
OWNED SMALL BUSINESS (SDVOSB) SET-ASIDE IAW 38. U.S.C. 8127 (d).
Deadline for receipt of questions is May 14, 2021 Bid Due Date is May 24,2021 Virtual Bid Opening is May 25, 2021 Bid Location: Virtual Estimated magnitude of construction project is between $250,000 and $500,000.
NAICS CODE: 237120
Size Standard: $39.5 Million
The Department of Veterans Affairs, 1601 Brenner Ave Salisbury, NC has a requirement for a contractor to provide all labor, material, supplies, equipment, transportation, permits, license and qualified supervision for Project 659-20-102 to Repair Sewer pump station, sewer force main, and pipe line at W.G. Hefner VAMC, Salisbury, NC.
General Scope: This project will consist of four items:
ITEM 1: DUPLEX SANTIARY SEWER PUPMP STATION-
ITEM II, SANITARY SEWER FORCE MAIN:
ITEM II, SANITARY SEWER FORCE MAIN:
ITEM IV, Plumbing Work
PLEASE SEE THE SOW FOR DETAILS
X 52.211-10 X
NO
12:00PM
EDT
05-24-2021 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
Department of Veterans Affairs
FMS-VA-2(101)
Financial Services Center PO Box 149971 Austin TX 78714-9971
Table of Contents
| PART I - THE SCHEDULE | 3 |
| SECTION A - SOLICITATION/CONTRACT FORM | 3 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 3 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 4 |
| SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTS | 8 |
| B.1 PRICE/COST SCHEDULE | 8 |
| ITEM INFORMATION | 8 |
| SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK | 9 |
| SECTION D - PACKAGING AND MARKING | 11 |
| [For this IFB, there are NO clauses in this Section] | 11 |
| SECTION E - INSPECTION AND ACCEPTANCE | 12 |
| SECTION F - DELIVERIES OR PERFORMANCE | 13 |
| F.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) | 13 |
| F.2 DELIVERY SCHEDULE | 13 |
| SECTION G - CONTRACT ADMINISTRATION DATA | 14 |
| [For this IFB, there are NO clauses in this Section] | 14 |
| SECTION H - SPECIAL CONTRACT REQUIREMENTS | 15 |
| [For this IFB, there are NO clauses in this Section] | 15 |
| PART II - CONTRACT CLAUSES | 16 |
| SECTION I - CONTRACT CLAUSES | 16 |
| I.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 16 |
| I.2 52.204-1 APPROVAL OF CONTRACT (DEC 1989) | 18 |
| I.3 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 19 |
| I.4 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (JUL 2018) | 19 |
| I.5 52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000) | 20 |
| I.6 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (NOV 2020) | 20 |
| I.7 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020) | 23 |
| I.8 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020) | 24 |
| I.9 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010) | 24 |
| I.10 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (FEB 2021) | 26 |
| I.11 52.232-12 ADVANCE PAYMENTS (MAY 2001) | 30 |
| I.12 52.236-4 PHYSICAL DATA (APR 1984) | 36 |
| I.13 52.246-26 REPORTING NONCONFORMING ITEMS (JUN 2020) | 37 |
| I.14 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018) | 39 |
| I.15 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION) | 40 |
| I.16 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 42 |
| I.17 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 42 |
| I.18 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 44 |
| I.19 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020) | 45 |
| I.20 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 46 |
| I.21 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) | 47 |
| I.22 SUPPLEMENTAL INSURANCE REQUIREMENTS | 47 |
| PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS | 49 |
| SECTION J - LIST OF ATTACHMENTS | 49 |
| PART IV - REPRESENTATIONS AND INSTRUCTIONS | 50 |
| SECTION K - REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS | 50 |
| K.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020) | 50 |
| K.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (OCT 2020) | 54 |
| K.3 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (FEB 2021) | 56 |
| K.4 52.222-22 PREVIOUS CONTRACTS AND COMPLIANCE REPORTS (FEB 1999) | 58 |
| SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS | 60 |
| L.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 60 |
| L.2 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE (JAN 2008) | 61 |
| L.3 52.214-25 STEP TWO OF TWO-STEP SEALED BIDDING (APR 1985) | 61 |
| L.4 52.214-31 FACSIMILE BIDS (DEC 1989) | 61 |
| L.5 52.216-1 TYPE OF CONTRACT (APR 1984) | 62 |
| L.6 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 62 |
| L.7 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 63 |
| L.8 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 64 |
| L.9 52.228-1 BID GUARANTEE (SEP 1996) | 65 |
| L.10 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021) | 65 |
| L.11 52.233-2 SERVICE OF PROTEST (SEP 2006) | 66 |
| L.12 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 66 |
| L.13 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 67 |
| L.14 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 67 |
| L.15 VAAR 852.236-92 NOTICE TO BIDDERS—ADDITIVE OR DEDUCTIVE BID LINE ITEMS (APR 2019) | 68 |
| SECTION M - EVALUATION FACTORS FOR AWARD | 69 |
| [For this IFB, there are NO provisions in this Section] | 69 |
SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTS
B.1 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| GRAND TOTAL |
| __________________ |
36C24621B0005 Section B
Page 1 of Page 1 of Page 1 of Page 1 of
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
General Scope: This project will consist of four items:
ITEM 1: DUPLEX SANTIARY SEWER PUPMP STATION: Contractor shall provide all tools, labor, materials, equipment, traffic controls, permits, and supervision to complete work related, but not limited, to:
1. Removal of existing concrete sidewalk as necessary for installation of new pump station.
2. Excavation as required for installation of new pump station.
3. Furnish and install new duplex sanitary sewer pump station and associated control panel.
4. Backfill around new pump station and restore turf grass.
5. Replace portion of concrete sidewalk removed during installation of the pump station.
ITEM II, SANITARY SEWER FORCE MAIN: work includes all tools, labor, materials, equipment, traffic controls, permits, and supervision, etc. to complete work related, but not limited, to:
1. Removal of existing concrete sidewalk as necessary for installation of new 4-inch sanitary sewer force main.
2. Removal of existing asphalt pavement and concrete curb and gutter at proposed force main location in front of the Building 5 dumpster pad.
3. Furnish and install new 4-inch sanitary sewer force main as indicated on the project drawings. This includes:
a. Install portion of new 4-inch force main under existing concrete loading dock area, asphalt driveway to Building 5 dumpster pad, and concrete driveway to oxygen tanks utilizing horizontal directional drilling method as indicated on the project drawings.
b. Install all portions of new 4-inch force main outside existing concrete loading dock area, asphalt driveway to Building 5 dumpster pad area, and concrete driveway to oxygen tanks area utilizing open cut method as indicated on the project drawings.
c. Connect new 4-inch force main to new duplex sanitary sewer pump station and existing sanitary sewer manhole at Parking Lot 19 entrance.
4. Backfill pipe trench and restore turf grass areas.
5. Replace portions of concrete sidewalk removed during installation of sanitary sewer force main.
6. Replace and restore any concrete or asphalt areas damaged during the installation of the 4-inch force main.
ITEM III, Electrical Work: Work includes all labor, material, equipment and supervision to perform the required electrical construction work on this project including, but not limited, to:
1. Furnish and install new power from existing electric panel to new duplex sanitary sewer pump station and associated control panel.
ITEM IV, Plumbing Work: Work includes all labor, material, equipment and supervision to perform the required Mechanical construction work on this project including, but not limited, to:
1. Removal of portions of the existing 4-inch sanitary sewer drainpipe and associated fittings and indicated on the project drawings.
2. Installation of a new 6-inch sanitary sewer drainpipe and connection to new duplex sanitary sewer pump station.
3. Connection of existing SPS equipment to new 6-inch sanitary sewer drainpipe.
All work, including final cleanup and completion of any punch list items shall be performed within one hundred and fifty (190) days after the receipt of notice to proceed.
36C24621B0005 Section C
Page 1 of Page 1 of Page 1 of Page 1 of
SECTION D - PACKAGING AND MARKING
[For this IFB, there are NO clauses in this Section] 36C24621B0005 Section D
Page 1 of Page 1 of Page 1 of Page 1 of
SECTION E - INSPECTION AND ACCEPTANCE
36C24621B0005 Section E
Page 1 of Page 1 of Page 1 of Page 1 of
| FAR Number |
| Title |
| Date |
| 52.246-12 |
| INSPECTION OF CONSTRUCTION |
| AUG 1996 |
| 52.246-16 |
| RESPONSIBILITY FOR SUPPLIES |
| APR 1984 |
SECTION F - DELIVERIES OR PERFORMANCE
| FAR Number |
| Title |
| Date |
| 52.242-14 |
| SUSPENSION OF WORK |
| APR 1984 |
F.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) The Contractor shall be required to (a) commence work under this contract within 7 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 180 days after receipt of notice to proceed. The time stated for completion shall include final cleanup of the premises.
The completion date is based on the assumption that the successful offeror will receive the notice to proceed by . The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
(End of Clause)
F.2 DELIVERY SCHEDULE
| ITEM NUMBER |
| QUANTITY |
| DELIVERY DATE |
36C24621B0005 Section F
Page 1 of Page 1 of Page 1 of
SECTION G - CONTRACT ADMINISTRATION DATA
36C24621B0005 Section G
Page 1 of Page 1 of Page 1 of Page 1 of
SECTION H - SPECIAL CONTRACT REQUIREMENTS
36C24621B0005 Section H
Page 1 of Page 1 of
PART II - CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES
I.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/
(End of Clause)
| FAR Number |
| Title |
| Date |
| 52.202-1 |
| DEFINITIONS |
| JUN 2020 |
| 52.203-3 |
| GRATUITIES |
| APR 1984 |
| 52.203-5 |
| COVENANT AGAINST CONTINGENT FEES |
| MAY 2014 |
| 52.203-6 |
| RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT |
| JUN 2020 |
| 52.203-7 |
| ANTI-KICKBACK PROCEDURES |
| JUN 2020 |
| 52.203-8 |
| CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY |
| MAY 2014 |
| 52.203-10 |
| PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY |
| MAY 2014 |
| 52.203-12 |
| LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS |
| JUN 2020 |
| 52.203-17 |
| CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS |
| JUN 2020 |
| 52.203-19 |
| PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS OR STATEMENTS |
| JAN 2017 |
| 52.204-4 |
| PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER |
| MAY 2011 |
| 52.204-10 |
| REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS |
| JUN 2020 |
| 52.204-13 |
| SYSTEM FOR AWARD MANAGEMENT MAINTENANCE |
| OCT 2018 |
| 52.204-18 |
| COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE |
| AUG 2020 |
| 52.204-25 |
| PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT |
| AUG 2020 |
| 52.209-6 |
| PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT |
| JUN 2020 |
| 52.209-10 |
| PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS |
| NOV 2015 |
| 52.214-29 |
| ORDER OF PRECEDENCE—SEALED BIDDING |
| JAN 1986 |
| 52.215-18 |
| REVERSION OR ADJUSTMENT OF PLANS FOR POSTRETIREMENT BENEFITS OTHER THAN PENSIONS (PRB) |
| JUL 2005 |
| 52.219-8 |
| UTILIZATION OF SMALL BUSINESS CONCERNS |
| OCT 2018 |
| 52.219-27 |
| NOTICE OF SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE |
| MAR 2020 |
| 52.222-1 |
| NOTICE TO THE GOVERNMENT OF LABOR DISPUTES |
| FEB 1997 |
| 52.222-3 |
| CONVICT LABOR |
| JUN 2003 |
| 52.222-4 |
| CONTRACT WORK HOURS AND SAFETY STANDARDS—OVERTIME COMPENSATION |
| MAY 2018 |
| 52.222-6 |
| CONSTRUCTION WAGE RATE REQUIREMENTS |
| AUG 2018 |
| 52.222-7 |
| WITHHOLDING OF FUNDS |
| MAY 2014 |
| 52.222-8 |
| PAYROLLS AND BASIC RECORDS |
| AUG 2018 |
| 52.222-9 |
| APPRENTICES AND TRAINEES |
| JUL 2005 |
| 52.222-10 |
| COMPLIANCE WITH COPELAND ACT REQUIREMENTS |
| FEB 1988 |
| 52.222-11 |
| SUBCONTRACTS (LABOR STANDARDS) |
| MAY 2014 |
| 52.222-12 |
| CONTRACT TERMINATION—DEBARMENT |
| MAY 2014 |
| 52.222-13 |
| COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND RELATED REGULATIONS |
| MAY 2014 |
| 52.222-14 |
| DISPUTES CONCERNING LABOR STANDARDS |
| FEB 1988 |
| 52.222-15 |
| CERTIFICATION OF ELIGIBILITY |
| MAY 2014 |
| 52.222-21 |
| PROHIBITION OF SEGREGATED FACILITIES |
| APR 2015 |
| 52.222-26 |
| EQUAL OPPORTUNITY |
| SEP 2016 |
| 52.222-27 |
| AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION |
| APR 2015 |
| 52.222-37 |
| EMPLOYMENT REPORTS ON VETERANS |
| JUN 2020 |
| 52.222-50 |
| COMBATING TRAFFICKING IN PERSONS |
| OCT 2020 |
| 52.222-54 |
| EMPLOYMENT ELIGIBILITY VERIFICATION |
| OCT 2015 |
| 52.222-55 |
| MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 |
| NOV 2020 |
| 52.222-62 |
| PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 |
| JAN 2017 |
| 52.223-5 |
| POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION ALTERNATE I (MAY 2011) |
| MAY 2011 |
| 52.223-6 |
| DRUG-FREE WORKPLACE |
| MAY 2001 |
| 52.223-18 |
| ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING |
| JUN 2020 |
| 52.223-21 |
| FOAMS |
| JUN 2016 |
| 52.225-13 |
| RESTRICTIONS ON CERTAIN FOREIGN PURCHASES |
| FEB 2021 |
| 52.227-1 |
| AUTHORIZATION AND CONSENT |
| JUN 2020 |
| 52.227-2 |
| NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT |
| JUN 2020 |
| 52.227-4 |
| PATENT INDEMNITY—CONSTRUCTION CONTRACTS |
| DEC 2007 |
| 52.228-2 |
| ADDITIONAL BOND SECURITY |
| OCT 1997 |
| 52.228-5 |
| INSURANCE—WORK ON A GOVERNMENT INSTALLATION |
| JAN 1997 |
| 52.228-11 |
| INDIVIDUAL SURETY—PLEDGE OF ASSETS |
| FEB 2021 |
| 52.228-12 |
| PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS |
| MAY 2014 |
| 52.228-14 |
| IRREVOCABLE LETTER OF CREDIT |
| NOV 2014 |
| 52.228-15 |
| PERFORMANCE AND PAYMENT BONDS—CONSTRUCTION |
| JUN 2020 |
| 52.229-2 |
| NORTH CAROLINA STATE AND LOCAL SALES AND USE TAX |
| APR 1984 |
| 52.229-3 |
| FEDERAL, STATE, AND LOCAL TAXES |
| FEB 2013 |
| 52.229-12 |
| TAX ON CERTAIN FOREIGN PROCUREMENTS |
| FEB 2021 |
| 52.232-5 |
| PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS |
| MAY 2014 |
| 52.232-17 |
| INTEREST |
| MAY 2014 |
| 52.232-23 |
| ASSIGNMENT OF CLAIMS |
| MAY 2014 |
| 52.232-27 |
| PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS |
| JAN 2017 |
| 52.232-33 |
| PAYMENT BY ELECTRONIC FUNDS TRANSFER—SYSTEM FOR AWARD MANAGEMENT |
| OCT 2018 |
| 52.232-39 |
| UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS |
| JUN 2013 |
| 52.232-40 |
| PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS |
| DEC 2013 |
| 52.233-1 |
| DISPUTES ALTERNATE I (DEC 1991) |
| MAY 2014 |
| 52.233-3 |
| PROTEST AFTER AWARD |
| AUG 1996 |
| 52.233-4 |
| APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM |
| OCT 2004 |
| 52.236-2 |
| DIFFERING SITE CONDITIONS |
| APR 1984 |
| 52.236-3 |
| SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK |
| APR 1984 |
| 52.236-5 |
| MATERIAL AND WORKMANSHIP |
| APR 1984 |
| 52.236-6 |
| SUPERINTENDENCE BY THE CONTRACTOR |
| APR 1984 |
| 52.236-7 |
| PERMITS AND RESPONSIBILITIES |
| NOV 1991 |
| 52.236-8 |
| OTHER CONTRACTS |
| APR 1984 |
| 52.236-9 |
| PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS |
| APR 1984 |
| 52.236-10 |
| OPERATIONS AND STORAGE AREAS |
| APR 1984 |
| 52.236-11 |
| USE AND POSSESSION PRIOR TO COMPLETION |
| APR 1984 |
| 52.236-12 |
| CLEANING UP |
| APR 1984 |
| 52.236-13 |
| ACCIDENT PREVENTION |
| NOV 1991 |
| 52.236-14 |
| AVAILABILITY AND USE OF UTILITY SERVICES |
| APR 1984 |
| 52.236-15 |
| SCHEDULES FOR CONSTRUCTION CONTRACTS |
| APR 1984 |
| 52.236-17 |
| LAYOUT OF WORK |
| APR 1984 |
| 52.236-21 |
| SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION |
| FEB 1997 |
| 52.242-13 |
| BANKRUPTCY |
| JUL 1995 |
| 52.243-4 |
| CHANGES |
| JUN 2007 |
| 52.244-6 |
| SUBCONTRACTS FOR COMMERCIAL ITEMS |
| NOV 2020 |
| 52.246-21 |
| WARRANTY OF CONSTRUCTION |
| MAR 1994 |
| 52.248-3 |
| VALUE ENGINEERING—CONSTRUCTION |
| OCT 2020 |
| 52.249-4 |
| TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (SERVICES) (SHORT FORM) |
| APR 1984 |
| 52.249-10 |
| DEFAULT (FIXED-PRICE CONSTRUCTION) |
| APR 1984 |
| 52.253-1 |
| COMPUTER GENERATED FORMS |
| JAN 1991 |
| 852.203-70 |
| COMMERCIAL ADVERTISING |
| MAY 2018 |
| 852.228-70 |
| BOND PREMIUM ADJUSTMENT |
| JAN 2008 |
| 852.232-70 |
| PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018) |
| NOV 2018 |
| 852.236-79 |
| CONTRACTOR PRODUCTION REPORT |
| APR 2019 |
| 852.236-80 |
| SUBCONTRACTS AND WORK COORDINATION |
| APR 2019 |
| 852.242-71 |
| ADMINISTRATIVE CONTRACTING OFFICER |
| OCT 2020 |
| 852.246-71 |
| REJECTED GOODS |
| OCT 2018 |
I.2 52.204-1 APPROVAL OF CONTRACT (DEC 1989)
This contract is subject to the written approval of and shall not be binding until so approved.
(End of Clause) I.3 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) The Contractor's representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
(End of Clause) I.4 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (JUL 2018)
(a) Definitions. As used in this clause—Covered article means any hardware, software, or service that—
(1) Is developed or provided by a covered entity;
(2) Includes any hardware, software, or service developed or provided in whole or in part by a covered entity; or
(3) Contains components using any hardware or software developed in whole or in part by a covered entity.
Covered entity means—
(1) Kaspersky Lab;
(2) Any successor entity to Kaspersky Lab;
(3) Any entity that controls, is controlled by, or is under common control with Kaspersky Lab; or
(4) Any entity of which Kaspersky Lab has a majority ownership.
(b) Prohibition. Section 1634 of Division A of the National Defense Authorization Act for Fiscal Year 2018 (Pub. L. 115–91) prohibits Government use of any covered article. The Contractor is prohibited from—
(1) Providing any covered article that the Government will use on or after October 1, 2018; and
(2) Using any covered article on or after October 1, 2018, in the development of data or deliverables first produced in the performance of the contract.
(c) Reporting requirement. (1) In the event the Contractor identifies a covered article provided to the Government during contract performance, or the Contractor is notified of such by a subcontractor at any tier or any other source, the Contractor shall report, in writing, to the Contracting Officer or, in the case of the Department of Defense, to the website at https://dibnet.dod.mil. For indefinite delivery contracts, the Contractor shall report to the Contracting Officer for the indefinite delivery contract and the Contracting Officer(s) for any affected order or, in the case of the Department of Defense, identify both the indefinite delivery contract and any affected orders in the report provided at https://dibnet.dod.mil.
(2) The Contractor shall report the following information pursuant to paragraph (c)(1) of this clause:
(i) Within 1 business day from the date of such identification or notification: The contract number; the order number(s), if applicable; supplier name; brand; model number (Original Equipment Manufacturer (OEM) number, manufacturer part number, or wholesaler number); item description; and any readily available information about mitigation actions undertaken or recommended.
(ii) Within 10 business days of submitting the report pursuant to paragraph (c)(1) of this clause: Any further available information about mitigation actions undertaken or recommended. In addition, the Contractor shall describe the efforts it undertook to prevent use or submission of a covered article, any reasons that led to the use or submission of the covered article, and any additional efforts that will be incorporated to prevent future use or submission of covered articles.
(d) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (d), in all subcontracts, including subcontracts for the acquisition of commercial items.
(End of Clause)
I.5 52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)
(a) The Government may extend the term of this contract by written notice to the Contractor within ; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 60 days before the contract expires. The preliminary notice does not commit the Government to an extension.
(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.
(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed one (1) year.
(End of Clause)
I.6 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (NOV 2020)
(a) Definitions. As used in this clause— Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern—
(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (d) of this clause. Such a concern is ‘‘not dominant in its field of operation’’ when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.
(2) Affiliates, as used in this definition, means business concerns, one of whom directly or indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.
(b) If the Contractor represented that it was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (f) of this clause or, if applicable, paragraph (h) of this clause, upon occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts—
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c) If the Contractor represented that it was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (f) of this clause or, if applicable, paragraph (h) of this clause, when the Contracting Officer explicitly requires it for an order issued under a multiple-award contract.
(d) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code(s) assigned to this contract. The small business size standard corresponding to this NAICS code(s) can be found at https://www.sba.gov/document/support--table-size-standards.
(e) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.
(f) Except as provided in paragraph (h) of this clause, the Contractor shall make the representation(s) required by paragraph (b) and (c) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause, or with its offer for an order (see paragraph (c) of this clause), that the data have been validated or updated, and provide the date of the validation or update.
(g) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (f) or (h) of this clause.
(h) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
(1) The Contractor represents that it [ ] is, [ ] is not a small business concern under NAICS Code 237110 assigned to contract number .
(2) [Complete only if the Contractor represented itself as a small business concern in paragraph (h)(1) of this clause.] The Contractor represents that it [ ] is, [ ] is not, a small disadvantaged business concern as defined in 13 CFR 124.1002.
(3) [Complete only if the Contractor represented itself as a small business concern in paragraph (h)(1) of this clause.] The Contractor represents that it [ ] is, [ ] is not a women-owned small business concern.
(4) Women-owned small business (WOSB) concern eligible under the WOSB Program. [Complete only if the Contractor represented itself as a women-owned small business concern in paragraph (h)(3) of this clause.] The Contractor represents that—
(i) It [ ] is, [ ] is not a WOSB concern eligible under the WOSB Program, has provided all the required documents to the WOSB Repository, and no change in circumstances or adverse decisions have been issued that affects its eligibility; and
(ii) It [ ] is, [ ] is not a joint venture that complies with the requirements of 13 CFR part 127, and the representation in paragraph (h)(4)(i) of this clause is accurate for each WOSB concern eligible under the WOSB Program participating in the joint venture. [The Contractor shall enter the name or names of the WOSB concern eligible under the WOSB Program and other small businesses that are participating in the joint venture: _____.] Each WOSB concern eligible under the WOSB Program participating in the joint venture shall submit a separate signed copy of the WOSB representation.
(5) Economically disadvantaged women-owned small business (EDWOSB) concern. [Complete only if the Contractor represented itself as a women-owned small business concern eligible under the WOSB Program in (h)(4) of this clause.] The Contractor represents that—
(i) It [ ] is, [ ] is not an EDWOSB concern eligible under the WOSB Program, has provided all the required documents to the WOSB Repository, and no change in circumstances or adverse decisions have been issued that affects its eligibility; and
(ii) It [ ] is, [ ] is not a joint venture that complies with the requirements of 13 CFR part 127, and the representation in paragraph (h)(5)(i) of this clause is accurate for each EDWOSB concern participating in the joint venture. [The Contractor shall enter the name or names of the EDWOSB concern and other small businesses that are participating in the joint venture: _____.] Each EDWOSB concern participating in the joint venture shall submit a separate signed copy of the EDWOSB representation.
(6) [Complete only if the Contractor represented itself as a small business concern in paragraph (h)(1) of this clause.] The Contractor represents that it [ ] is, [ ] is not a veteran-owned small business concern.
(7) [Complete only if the Contractor represented itself as a veteran-owned small business concern in paragraph (h)(6) of this clause.] The Contractor represents that it [ ] is, [ ] is not a service-disabled veteran-owned small business concern.
(8) [Complete only if the Contractor represented itself as a small business concern in paragraph (h)(1) of this clause.] The Contractor represents that—
(i) It [ ] is, [ ] is not a HUBZone small business concern listed, on the date of this representation, on the List of Qualified HUBZone Small Business Concerns maintained by the Small Business Administration, and no material changes in ownership and control, principal office, or HUBZone employee percentage have occurred since it was certified in accordance with 13 CFR part 126; and
(ii) It [ ] is, [ ] is not a HUBZone joint venture that complies with the requirements of 13 CFR part 126, and the representation in paragraph (h)(8)(i) of this clause is accurate for each HUBZone small business concern participating in the HUBZone joint venture. [The Contractor shall enter the names of each of the HUBZone small business concerns participating in the HUBZone joint venture: _____.] Each HUBZone small business concern participating in the HUBZone joint venture shall submit a separate signed copy of the HUBZone representation.
[Contractor to sign and date and insert authorized signer's name and title.] (End of Clause)
I.7 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020)
(a) Definitions. As used in this clause— “Active duty wartime or campaign badge veteran,” “Armed Forces service medal veteran,” “disabled veteran,” “protected veteran,” “qualified disabled veteran,” and “recently separated veteran” have the meanings given at Federal Acquisition Regulation (FAR) 22.1301.
(b) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-300.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified protected veterans, and requires affirmative action by the Contractor to employ and advance in employment qualified protected veterans.
(c) Subcontracts. The Contractor shall insert the terms of this clause in subcontracts valued at or above the threshold specified in FAR 22.1303(a) on the date of subcontract award, unless exempted by rules, regulations, or orders of the Secretary of Labor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
(End of Clause)
I.8 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)
(a) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-741.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified individuals on the basis of disability, and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.
(b) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of the threshold specified in Federal Acquisition Regulation (FAR) 22.1408(a) on the date of subcontract award, unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs of the U.S. Department of Labor, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
(End of Clause) I.9 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010)
(a) During the term of this contract, the Contractor shall post an employee notice, of such size and in such form, and containing such content as prescribed by the Secretary of Labor, in conspicuous places in and about its plants and offices where employees covered by the National Labor Relations Act engage in activities relating to the performance of the contract, including all places where notices to employees are customarily posted both physically and electronically, in the languages employees speak, in accordance with 29 CFR 471.2(d) and (f).
(1) Physical posting of the employee notice shall be in conspicuous places in and about the Contractor's plants and offices so that the notice is prominent and readily seen by employees who are covered by the National Labor Relations Act and engage in activities related to the performance of the contract.
(2) If the Contractor customarily posts notices to employees electronically, then the Contractor shall also post the required notice electronically by displaying prominently, on any Web site that is maintained by the Contractor and is customarily used for notices to employees about terms and conditions of employment, a link to the Department of Labor's Web site that contains the full text of the poster. The link to the Department's Web site, as referenced in (b)(3) of this section, must read, "Important Notice about Employee Rights to Organize and Bargain Collectively with Their Employers."
(b) This required employee notice, printed by the Department of Labor, may be—
(1) Obtained from the Division of Interpretations and Standards, Office of Labor-Management Standards, U.S. Department of Labor, 200 Constitution Avenue, NW., Room N-5609, Washington, DC 20210, (202) 693-0123, or from any field office of the Office of Labor-Management Standards or Office of Federal Contract Compliance Programs;
(2) Provided by the Federal contracting agency if requested;
(3) Downloaded from the Office of Labor-Management Standards Web site at http://www.dol.gov/olms/regs/compliance/EO13496.htm; or
(4) Reproduced and used as exact duplicate copies of the Department of Labor's official poster.
(c) The required text of the employee notice referred to in this clause is located at Appendix A, Subpart A, 29 CFR Part 471.
(d) The Contractor shall comply with all provisions of the employee notice and related rules, regulations, and orders of the Secretary of Labor.
(e) In the event that the Contractor does not comply with the requirements set forth in paragraphs (a) through (d) of this clause, this contract may be terminated or suspended in whole or in part, and the Contractor may be suspended or debarred in accordance with 29 CFR 471.14 and subpart 9.4. Such other sanctions or remedies may be imposed as are provided by 29 CFR part 471, which implements Executive Order 13496 or as otherwise provided by law.
(f) Subcontracts.
(1) The Contractor shall include the substance of this clause, including this paragraph (f), in every subcontract that exceeds $10,000 and will be performed wholly or partially in the United States, unless exempted by the rules, regulations, or orders of the Secretary of Labor issued pursuant to section 3 of Executive Order 13496 of January 30, 2009, so that such provisions will be binding upon each subcontractor.
(2) The Contractor shall not procure supplies or services in a way designed to avoid the applicability of Executive Order 13496 or this clause.
(3) The Contractor shall take such action with respect to any such subcontract as may be directed by the Secretary of Labor as a means of enforcing such provisions, including the imposition of sanctions for noncompliance.
(4) However, if the Contractor becomes involved in litigation with a subcontractor, or is threatened with such involvement, as a result of such direction, the Contractor may request the United States, through the Secretary of Labor, to enter into such litigation to protect the interests of the United States.
(End of Clause)
I.10 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (FEB 2021)
(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is—
(i) A commercial item (as defined in paragraph (1) of the definition at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
Component means any article, material, or supply incorporated directly into construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the end product (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both—
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if—
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of ‘‘cost of components’’.
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
[Contracting Officer to list applicable excepted materials or indicate ‘‘none’’]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—