About this file
36C24619Q0688 P0001 Questions for Electronic Door Openers.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| -18474.docx | DOCX document | |
| 36C24619Q0688-P0001000.docx | DOCX document | |
| 36C24619Q0688-001.docx | DOCX document | |
| 36C24619Q0688 36C24619Q0688.docx | DOCX document | |
| 36C24619Q0688-000.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions for Electronic Door Openers
1. Is there a specific hardware manufacturer required for the electronic door equipment?
Required no, preferred yes (Stanley has our maintenance contract)
2. Who is the manufacturer for the existing equipment, which must be interfaced? Tyco (PACS System) must be able to be connected to a switch.
3. It appears the doors are roughed in for push pads. Please confirm. No, they are roughed in for wave to open touchless.
4. For the following doors, please advise if electrical rough in has been completed to the nearest electrical panel:
a. Double Doors accessing room 1G-214 yes
b. Hallway door outside room IG-128 yes
c. Door accessing room IB127A yes
5. Please advise distance/location of nearest electrical panel for each door- electrical service will be run to the opener by in house electricians (but not connected to openers)
6. Please advise if there is adequate space within the panels for additional breakers. See #5
7. Is there an un-used breaker or does contractor have to supply a breaker? See #5
8. If contractor supplies breaker, please advise the panel manufacturer- see #5
9. Page 1 of 29, section 11 of the solicitation mentions the project needs to be complete within 15 calendar days of receiving notice to proceed. Page 6 of 29 mentions contractor has 60 days. 15 days would not be adequate for submittals, material lead time and installation. 60 days, but double door off of C1G-21 heading into the Cardiac Cath Lab Recovery Area must be done first and within 15 days if possible.
10. Please advise how long contractor has to complete project from notice to proceed.
See#9 11 What size, logo/color of Touchless Actuator is desired for the three double doors? Is there a preferred manufacturer? See #1
12. Do Door operators require locking Mechanism? If so, please specify type. No they do not require locking