36C24519B0011-003.pdf
PDF 2 MB Posted
- Attached to
- Construction Site Preparation for MRI Upgrade Project 540-18-011 Federal contract opportunity
- Solicitation number
- 36C24519B0011
About this file
36C24519B0011 S02 MRI Upgrade Drawings.pdf
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSULTANTS:
Drawing Title
Approved: Project Director
Project Title:
Location:
Date: Checked: Drawn:
Drawing Number
Dwg. of
Building Number
Project Number
Office of Construction and Facilities Management
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
FULLY SPRINKLERED
A
B
C
D
E
F
209 SANDUSKY STREET
PITTSBURGH, PA 15212
PH: 412.287.7333
www.ae-works.com
AE WORKS PROJECT NUMBER:
ARCHITECTS/ENGINEERS:SEAL
6 " o n e e ig h th i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e h a lf i n c h o n e f o o t th re e i n c h e s o n e f o o t
209 SANDUSKY STREET
PITTSBURGH, PA 15212
PH: 412.287.7333
www.ae-works.com
AE WORKS PROJECT NUMBER:
BID DOCUMENTS
18030
HVAC UPGRADE FOR
MRI SUITE
LOUIS A. JOHNSON VA MEDICAL CENTER
CLARKSBURG, WEST VIRGINIA
540-18-011
CJC AC
G001 08/05/2019 161
COVER
HVAC UPGRADE FOR MRI SUITE
BUILDING 1
LOUIS A. JOHNSON VA MEDICAL CENTER
1 MEDICAL CENTER DRIVE
CLARKSBURG, WV 26301
PROJECT DIRECTORY
OWNER:
LOUIS A. JOHNSON VA MEDICAL CENTER
1 MEDICAL CENTER DRIVE
CLARKSBURG, WV 26301
(304) 623-3461
CONTACT: LARRY EAKLE
ARCHITECT/ENGINEER
AE WORKS
209 SANDUSKY STREET
PITTSBURGH, PA 15212
(412) 287-7333
CONTACT: CHRIS CHAMPAGNE, PE
DRAWING INDEX
SHEET # SHEET NAME
G001 COVER
G100 ICRA PLAN AND NOTES
M001 HVAC SYMBOLS, ABBREVIATIONS AND GENERAL NOTES
MD101 MRI SUITE HVAC DEMOLITION PLAN
M101 MRI SUITE HVAC NEW WORK PLAN
M102 HVAC ROOF PLAN
M501 HVAC DETAILS
M502 HVAC DETAILS
M601 HVAC CONTROLS
M701 HVAC SCHEDULES
E001 ELECTRICAL SYMBOLS AND ABBREVIATIONS
E101 MRI SUITE ELECTRICAL PLANS
E501 ELECTRICAL DETAILS AND SCHEDULES
S001 GENERAL NOTES
S100 PLANS AND DETAILS
S101 PLANS AND DETAILS II
SITE
SITE
NO REVISION DATE
H S
DUST CONTROL PLAN NOTES / DUST CONTROL PLAN HAZARD ASSESSMENT
PRIOR TO INITIATING WORK, CONTRACTOR AND COR WILL ACCESS THE SCOPE OF THE CONSTRUCTION
ACTIVITIES AND DETERMINE THE POTENTIAL RISK GROUPS INVOLVED BASED ON THE LOCATION OF ACTIVITIES
AND EXTENT AND DURATION OF THE WORK. LOW RISK GROUPS ARE CONSIDERED "OFFICE WORKERS", MEDIUM
RISK GROUPS ARE CONSIDERED ALL INPATIENT AND OUTPATIENT AREAS NOT IN THE HIGH RISK GROUP. HIGH
RISK GROUP DESIGNATION INCLUDES INPATIENT AREAS SUCH AS PEDIATRIC AND ADULT OPERATING/DELIVERY
ROOMS, CATH LABS, MYELO SUPPRESSION UNITS, ICUS, DIALYSIS, NURSERIES AS WELL AS CLINIC AREAS
(CLINICS ASSOCIATED WITH HEMATOLOGY, ONCOLOGY, PEDIATRIC INFECTION DISEASE, OR TRANSPLANT
SERVICES) AND SERVICE AREAS (CENTRAL PROCESSING, STERILE PROCESSING, FOOD PREP & SERVICE AREA
AND PHARMACIES. THE VAMC INFECTION CONTROL GROUP WILL CONFIRM AND APPROVE THE DESIGNATION
PROVIDED IN THIS SUBMITTED DUST CONTROL PLAN. VAMC IS ALSO RESPONSIBLE FOR ANY AND ALL INFECTION
CONTROL MEASURES DETERMINED AND ESTABLISHED BY VAMC POLICY, SUCH AS THE RELOCATION OF HIGH
RISK PATIENTS, APPROVING ALTERNATE TRAFFIC PATHS FOR CONSTRUCTION WORKERS OR ESTABLISH
ALTERNATE TRAFFIC PATTERNS FOR STAFF, PATIENTS AND VISITORS. THE PLAN SHOULD BE REVISED
ACCORDING TO SPECIFIC VAMC POLICIES OR CHANGING CONDITIONS AT THE SITE AS THEY MAY OCCUR.
INTERNAL DEMOLITION AND CONSTRUCTION ACTIVITIES DUST AND DEBRIS CONTROL
• BARRIER SYSTEMS: THE AREA SHOULD BE ISOLATED, AS THE PROJECT REQUIRES. SMALL, SHORT
DURATION PROJECTS GENERATING MINIMAL DUST MAY USE FIRE-RATED PLASTIC SHEETING, BUT
SHOULD BE SEALED AT FULL CEILING HEIGHT WITH AT LEAST 2-FOOT OVERLAPPING FLAPS FOR
ACCESS TO ENTRY. ANY DUST SHALL BE IMMEDIATELY CLEANED IF TRACKED OUTSIDE OF THE
CONSTRUCTION BARRIER. UPON COMPLETION OF THE CONSTRUCTION PROJECT DUST BARRIERS
SHALL BE REMOVED CAREFULLY TO MINIMIZE SPREADING OF DUST AND THE CONTRACTOR SHALL
HAVE TEMPORARY DUST PROTECTION IN PLACE BEFORE REMOVAL OF A PERMANENT BARRIER.
CONTRACTOR PERSONNEL SHALL MONITOR AND PERFORM BARRIER MAINTENANCE AND BE
EDUCATED TO NOTICE SIMPLE CLUES SUCH AS ACCUMULATIONS OF VISIBLE DUST EVIDENCED BY
FOOTPRINTS, OPENED DOORS/WINDOWS EVIDENCED BY PRESENCE OF INSECTS AND FLIES, WET
CEILING TILE, ETC.
• TRAFFIC CONTROL; DESIGNATED ENTRY AND EXIT PROCEDURES SHALL BE DEFINED. EGRESS PATHS
SHOULD BE FREE OF DEBRIS; DESIGNATED ELEVATORS SHOULD BE USED DURING SCHEDULED TIMES;
AND ONLY AUTHORIZED PERSONNEL SHOULD BE ALLOWED TO ENTER THE CONSTRUCTION ZONE.
SIGNAGE SHOULD DIRECT PEDESTRIAN TRAFFIC AWAY FROM THE CONSTRUCTION AREA AND
MATERIALS.
• DEMOLITION DEBRIS: DEBRIS SHOULD BE REMOVED IN CARTS WITH TIGHTLY FITTED COVERS, USING
DESIGNATED TRAFFIC ROUTES. EFFORTS SHOULD BE MADE TO MINIMIZE USE OF ELEVATORS WITH
AN EMPHASIS ON TRANSPORT DURING THE LOWEST PERIOD OF ACTIVITY. DEBRIS SHOULD BE
REMOVED DAILY AND AT TIMES SPECIFIED BY THE VAMC. IF CHUTES ARE USED TO DIRECT DEBRIS
OUTSIDE, HIGH EFFICIENCY PARTICULATE AIR (HEPA) FILTERED NEGATIVE AIR MACHINES SHOULD BE
USED, AND THE CHUTE OPENING SHOULD BE SEALED WHEN NOT IN USE. FILTERS SHOULD BE
BAGGED AND SEALED BEFORE BEING TRANSPORTED OUT OF THE CONSTRUCTION AREA. THE
CONTRACTOR SHALL NOT HAUL DEBRIS THROUGH PATIENT-CARE AREAS WITH PRIOR APPROVAL OF
THE VAMC.
• EXTERIOR WINDOWS: WINDOWS SHOULD BE SEALED TO MINIMIZE INFILTRATION FROM ANY ADJACENT
EXCAVATION DEBRIS.
• CEILINGS THAT ARE REMOVED/MODIFIED TO ALLOW CONSTRUCTION OF ICRA BARRIERS SHOULD BE
REINSTALLED TO PRE-CONSTRUCTION CONDITIONS.
VENTILATION AND ENVIRONMENTAL CONTROLS
• AIR SYSTEM FLOW: DETERMINE WHETHER THE CONSTRUCTION AREA USES FRESH/OUTSIDE OR RE-
CIRCULATED AIR; FILTERS SHOULD BE ADDED OR RETURN VENTS COVERED AS NEEDED WITH FILTER
MATERIAL OR PLASTIC. AIR MUST FLOW FROM CLEAN TO DIRTY AREAS.
• NEGATIVE AIR PRESSURE: THE AIR WITHIN THE CONSTRUCTION AREA MUST BE NEGATIVE WITH
RESPECT TO SURROUNDING AREAS AND WITH NO DISRUPTION OF AIR SYSTEMS OF ADJACENT AREAS.
USE OF THE NEGATIVE AIR PRESSURE SYSTEM WITHIN THE ENCLOSURE TO REMOVE DUST SHOULD
PASS AIR THROUGH AN INDUSTRIAL GRADE, PORTABLE HEPA FILTER CAPABLE OF FILTRATION RATES
OF 300-800 CUBIC FEET PER MINUTE (FT3//MIN), OR EXHAUST AIR DIRECTLY TO THE OUTSIDE IF
APPROVED BY VAMC. IF EXHAUST MUST BE TIED INTO A RE-CIRCULATED AIR SYSTEM, A PRE-FILTER
AND HEPA FILTER SHOULD BE USED BEFORE EXHAUST TO PREVENT CONTAMINATION OF THE DUCTS.
• ADJACENT AREAS: THE STATUS OF SEALED PENETRATIONS AND INTACT CEILING SHOULD BE VERIFIED
DAILY.
• AIR EXCHANGE RATES AND PRESSURE RELATIONSHIPS: VAMC AND/OR CONTRACTOR WILL VERIFY AND
MAINTAIN PROPER RATES IN CRITICAL AREAS NEAR CONSTRUCTION ACTIVITY AND ENSURE AIR IS NOT
BEING RE-CIRCULATED WITHOUT FILTRATION FROM THE CONSTRUCTION AREA ELSEWHERE. VAMC
WILL MAKE DETERMINATION ON PROVIDING FOR THE ACCOUNTABILITY AND FREQUENCY OF TESTING
AIR PRESSURE THROUGHOUT THE PROJECT.
• MANOMETERS SHOULD BE LOCATED ON ICRA PARTITION DOOR AND ON THE NON-CONSTRUCTION SIDE
OF THE PARTITION.
INFECTION CONTROL RISK ASSESSMENT FOR CONSTRUCTION
1. CLEAN WORK UPON COMPLETION OF TASK
1. WIPE WORK SURFACES WITH DISINFECTANT.
2. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY COVERED CONTAINERS.
3. WET MOP &/OR VACUUM BEFORE LEAVING WORK AREA.
4. REMOVE ISOLATION OF HVAC SYSTEM IN AREA WHERE WORK IS BEING PERFORMED.
1. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT IS INSPECTED BY
SAFETY MANAGEMENT & INFECTION CONTROL & THOROUGHLY CLEANED BY ENVIRONMENTAL
MANAGEMENT.
2. REMOVE BARRIER MATERIALS CAREFULLY TO MINIMIZE SPREADING OF DIRT & DEBRIS
ASSOCIATED WITH CONSTRUCTION.
3. VACUUM WORK AREA WITH HEPA-FILTERED VACUUMS.
4. WET MOP WITH DISINFECTANT.
5. REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.
1. REMOVE BARRIER MATERIALS CAREFULLY TO MINIMIZE SPREADING OF DIRT & DEBRIS
ASSOCIATED WITH CONSTRUCTION.
2. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY COVERED CONTAINERS.
3. COVER TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING UNLESS SOLID LID.
4. VACUUM WORK AREA WITH HEPA-FILTERED VACUUMS.
5. WET MOP WITH DISINFECTANT.
6. REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.
CLASS I - UPON COMPLETION OF PROJECTS
CLASS II - UPON COMPLETION OF PROJECTS
CLASS III - UPON COMPLETION OF PROJECTS
CLASS IV - UPON COMPLETION OF PROJECTS
(TO BE COMPLETED BY CONTRACTOR AND COR, THEN SIGNED BY INFECTION CONTROL NURSE)
CONTRACTOR'S SIGNATURE AND DATE
COR SIGNATURE AND DATE
LIGHT GRAY HATCH INDICATES
TYPES AND CLASSES SELECTED
FOR THIS RENOVATION
STEP #1: SELECT ACTIVITY TYPE BELOW:
CONSTRUCTION ACTIVITY TYPES:
TYPE A
INSPECTION AND NON-INVASIVE ACTIVITIES
INCLUDES, BUT NOT LIMITED TO:
• REMOVAL OF CEILING TILES FOR VISUAL INSPECTION LIMITED TO 1 TILE
PER 50 SQUARE FEET.
• PAINTING (BUT NOT SANDING)
• WALL COVERING
• ELECTRICAL TRIM WORK
• MINOR PLUMBING
• ACTIVITIES WHICH DO NOT GENERATE DUST OR REQUIRE CUTTING OF
WALLS OR ACCESS TO CEILINGS OTHER THAN FOR VISUAL INSPECTION
TYPE B
SMALL SCALE, SHORT DURATION (less than 1 day) ACTIVITIES WHICH CREATE
MINIMAL DUST
INCLUDES, BUT NOT LIMITED TO:
• INSTALLATION OF TELEPHONE AND COMPUTER CABLING
• ACCESS TO CHASE SPACES
• CUTTING OF WALLS OR CEILING WHERE DUST MIGRATION CAN BE
CONTROLLED
TYPE C
WORK THAT GENERATES A MODERATE TO HIGH LEVEL OF DUST OR REQUIRES
DEMOLITION OR REMOVAL OF ANY FIXED BUILDING COMPONENTS OR
ASSEMBLIES
INCLUDES, BUT NOT LIMITED TO:
• SANDING OF WALLS FOR PAINTING OR WALL COVERING
• REMOVAL OF FLOOR COVERING, CEILING TILES AND CASEWORK
• NEW WALL CONSTRUCTION
• MINOR DUCT WORK OR ELECTRICAL WORK ABOVE CEILINGS
• MAJOR CABLING ACTIVITIES
• ANY ACTIVITY WHICH CANNOT BE COMPLETED WITHIN A SINGLE WORK
SHIFT
TYPE D
MAJOR DEMOLITION AND CONSTRUCTION PROJECTS
INCLUDES, BUT NOT LIMITED TO:
• ACTIVITIES THAT REQUIRE CONSECUTIVE WORK SHIFTS.
• REQUIRES HEAVY DEMOLITION OR REMOVAL OF A COMPLETE HVAC
SYSTEM.
• NEW CONSTRUCTION
IS IT LIKELY THE CONTRACTOR'S STAFF WILL BE PLACED AT RISK FOR INFECTION
WITH TUBERCULOSIS? YES / NO
IS IT LIKELY THERE WILL BE PHYSICAL DISRUPTION OF THE WATER
SYSTEM/LINES DURING ACTIVITY? YES / NO
STEP #2: SELECT RISK GROUP BELOW AND MARK BOTTOM OF COLUMN
A) INFECTION CONTROL RISK GROUPS
GROUP 1 - LOW: OFFICE AREAS:
GROUP 2 - MEDIUM: CARDIOLOGY, ECHOCARDIOGRAPHY, ENDOSCOPY, NUCLEAR
MEDICINE, PHYSICAL THERAPY, RADIOLOGY/MRI, RESPIRATORY THERAPY
GROUP 3 - HIGH RISK: CCU, EMERGENCY ROOM, LABORATORIES, OUTPATIENT
SURGERY, PHARMACY, POST ANESTHESIA CARE UNIT, SURGICAL UNITS
GROUP 4 - HIGHEST RISK: ANY AREA CARING FOR IMMUNOCOMPROMISED
PATIENTS, CARDIAC CATH LAB, CENTRAL SUPPLY, INTENSIVE CARE UNITS,
MEDICAL UNITS, NEGATIVE AIRFLOW ROOMS, ONCOLOGY, OPERATING ROOMS
STEP #3: DETERMINE CLASS OF PRECAUTIONS USING MATRIX BELOW:
CONSTRUCTION ACTIVITY / INFECTION CONTROL MATRIX TO DETERMINE CLASS
** ICN MUST BE CONSULTED WHEN THE ASSESSMENT INDICATES THAT CLASS II,
III, IV PRECAUTIONS ARE REQUIRED.
RISK LEVEL TYPE 'A' TYPE 'B' TYPE 'C' TYPE 'D'
GROUP 1 I II II III / IV
GROUP 2 I II III IV
GROUP 3 I II III / IV IV
GROUP 4 II III / IV III / IV IV
CONSTRUCTION TYPE:
C
RISK GROUP:
LOW
RISK ASSESSMENT:
II
ELECTRICAL
YES
POTABLE WATER
NO
HVAC
YES
MEDICAL VACUUM
NO
SEWER
YES
PROJECTED UTILITY OUTAGES IMPACTING INFECTION CONTROL
STEP #4: COMPLETE THE INFECTION CONTROL CONSTRUCTION PERMIT:
1. EXECUTE WORK BY METHOD TO MINIMIZE RAISING DUST FROM CONSTRUCTION OPERATIONS
2. IMMEDIATELY REPLACE A CEILING TILE DISPLACED FOR VISUAL INSPECTION
1. PROVIDE ACTIVE MEANS TO PREVENT AIRBORNE DUST FROM DISPERSING INTO
ATMOSPHERE.
2. WATER MIST WORK SURFACES TO CONTROL DUST WHILE CUTTING
3. SEAL UNUSED DOORS WITH DUCT TAPE
4. BLOCK OFF AND SEAL AIR VENTS.
5. PLACE DUST MAT AT ENTRANCE AND EXIT OF WORK AREA.
6. REMOVE OR ISOLATE HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.
1. REMOVE OR ISOLATE HVAC SYSTEM IN AREA WHERE WORK IS BEING DONE TO PREVENT
CONTAMINATION OF DUCT SYSTEM.
2. COMPLETE ALL CRITICAL BARRIERS, I.E. SHEETROCK, PLYWOOD, PLASTIC, TO SEAL AREA
FROM NON-WORK AREA OR IMPLEMENT CONTROL CUBE METHOD (CART WITH PLASTIC
COVERING & SEALED CONNECTION TO WORK SITE WITH HEPA VACUUM FOR VACUUMING PRIOR
TO EXIT) BEFORE CONSTRUCTION BEGINS.
3. MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORK SITE UTILIZING HEPA-EQUIPPED AIR
FILTRATION UNITS.
4. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORTATION IN TIGHTLY COVERED
CONTAINERS.
5. COVER TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING UNLESS SOLID LID IS USED.
1. ISOLATE HVAC SYSTEM IN AREA WHERE WORK IS BEING DONE TO PREVENT CONTAMINATION
OF DUCT SYSTEM.
2. COMPLETE ALL CRITICAL BARRIERS, I.E., SHEETROCK, PLYWOOD, PLASTIC, TO SEAL AREA
FROM NON-WORK AREA OR IMPLEMENT CONTROL CUBE METHOD (CART WITH PLASTIC
COVERING & SEALED CONNECTION TO WORK SITE WITH HEPA VACUUM FOR VACUUMING PRIOR
TO EXIT) BEFORE CONSTRUCTION BEGINS.
3. MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORK SITE UTILIZING HEPA-EQUIPPED AIR
FILTRATION UNITS.
4. SEAL HOLES, PIPES, CONDUITS AND PUNCTURES APPROPRIATELY.
5. CONSTRUCT ANTEROOM AND REQUIRE ALL PERSONNEL TO PASS THROUGH THIS ROOM SO
THEY CAN BE VACUUMED USING A HEPA VACUUM CLEANER BEFORE LEAVING WORK SITE; OR
THE CAN WEAR CLOTH OR PAPER COVERALLS THAT ARE REMOVED EACH TIME THEY LEAVE
THE WORK SITE.
6. ALL PERSONNEL ENTERING THE WORK SITE ARE REQUIRED TO WEAR SHOE COVERS. SHOE
COVERS MUST BE CHANGED EACH TIME THE WORKER EXITS THE WORK AREA.
7. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT IS INSPECTED BY
SAFETY MANAGEMENT & INFECTION CONTROL & THOROUGHLY CLEANED BY ENVIRONMENTAL
MANAGEMENT.
CLASS I - DURING CONSTRUCTION PROJECT
CLASS II - DURING CONSTRUCTION PROJECT
CLASS III - DURING CONSTRUCTION PROJECT
CLASS IV - DURING CONSTRUCTION PROJECT
INFECTION CONTROL NURSE'S SIGNATURE AND DATE
D
17 16 15 11
SOILED UTILITY
TOILET
MED RM
CLEAN UTILITY
OBSERVATION
STAIR
TEL
ELEC
G100
HC BATHROOM
102IV START RM
FOYER
CONTROL RM
EXAM RM
EQUIP RM
1 LAYER 5/8" TYPE-X G.W.B.
INSULATION - SEE SPECIFICATIONS
5/8" G.W.B.
METAL STUDS @16" O.C.
BASE - SEE FINISH
SCHEDULE FOR TYPE
TRACK RUNNER
FLOOR SLAB
S E
E S
C H
E D
U
LE
P A
R T
IT
IO
N W
ID
T
H
FIRESTOPPING SEALANT - SEE SPECIFICATIONS
DECK OR
STRUCTURE
ABOVE
NOTE:
1. FOR EXISTING PARTITIONS USED AS ICRA BARRIERS, THE
CONTRACTOR SHALL COMPLETE THE FOLLOWING:
· MODIFY EXISTING PARTITION TO A ONE-HOUR RATED ICRA BARRIER
· EXTEND PARTITION TO FLOOR DECK WITH 5/8” G.W.B. ON EACH SIDE
· FINISH WALL PARTITION AS DIRECTED BY UL RATING REQUIREMENTS
· INFILL EXISTING OPENINGS WITH 5/8” G.W.B ON EACH SIDE
· PROVIDE FIRESTOPPING AT ALL EXISTING PENETRATIONS
2. PROVIDE 45 MINUTE RATED DOOR TO ACCESS CONSTRUCTION AREA
AT ALL NEW AND EXISTING ICRA BARRIERS
3. THE CONTRACTOR SHALL NOT BLOCK SPRINKLER PROTECTION ON
THE VA-OCCUPIED SIDE OF THE ICRA BARRIER.
EXISTING CEILING
EXISTING METAL STUD PARTITION TO
STRUCTURE ABOVE. IF DRYWALL IS NOT
AS SHOWN, CONTRACTOR TO ADD
DRYWALL AND SEAL AT TOP OF WALL AS
SHOWN ON ICRA BARRIER WALL TYPE.
EXISTING HOLLOW
METAL DOOR ASSEMBLY
NEW ICRA BARRIER FLUSH WITH
SOFFIT. INSTALL PER ICRA BARRIER
WALL TYPE ON THIS SHEET. ADD
SHEET PLASTIC AND ZIPPER ACCESS
DOOR AS REQUIRED FOR ROOM
ACCESS. CONTRACTOR MUST
MAINTAIN ICRA CONTROL AT ALL
TIMES. DEPTH OF THE CONTAINMENT
AREA AS NEEDED TO MEET CLASS IV
REQUIREMENTS.
CONSULTANTS:
Drawing Title
Approved: Project Director
Project Title:
Location:
Date: Checked: Drawn:
Drawing Number
Dwg. of
Building Number
Project Number
Office of Construction and Facilities Management
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
FULLY SPRINKLERED
A
B
C
D
E
F
209 SANDUSKY STREET
PITTSBURGH, PA 15212
PH: 412.287.7333
www.ae-works.com
AE WORKS PROJECT NUMBER:
ARCHITECTS/ENGINEERS:SEAL
6 " o n e e ig h th i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e h a lf i n c h o n e f o o t th re e i n c h e s o n e f o o t
209 SANDUSKY STREET
PITTSBURGH, PA 15212
PH: 412.287.7333
www.ae-works.com
AE WORKS PROJECT NUMBER:
BID DOCUMENTS
18030
HVAC UPGRADE FOR
MRI SUITE
LOUIS A. JOHNSON VA MEDICAL CENTER
CLARKSBURG, WEST VIRGINIA
540-18-011
CJC SB
G100 08/05/2019 162
ICRA PLAN AND NOTES
NORTH
PROJECT
TRUE NORTH = 81
1/4" = 1'-0"
LEVEL 1 OVERALL HVAC PLAN
NOT TO SCALE
ICRA BARRIER WALL TYPE
ICRA KEYNOTES
KEYNOTE DESCRIPTION
1 ICRA BARRIER FLUSH WITH SOFFIT ABOVE. SEE SECTION ON THIS SHEET.
2 COVER OPENING IN BARRIER WITH SHEET PLASTIC WITH ACCESS ZIPPER.
NOT TO SCALE
BARRIER SECTION
CO2
CO
H
HS
NO2
S
TH
TS
T
MS
CHWS
HWR
HWS
(E)
CHWR CHILLED WATER RETURN
CHILLED WATER SUPPLY
HEATING WATER RETURN
HEATING WATER SUPPLY
RL
RS
REFRIGERANT-LIQUID
REFRIGERANT-SUCTION
2"
HVAC PIPING SYMBOLS
KEYNOTE
CONTINUATION SYMBOL
NUMBER OF SHEET WHERE DETAIL APPEARS
NUMBER OF DETAIL ON SHEET
REVISION NUMBER - SHOWN ON PLANS
GENERAL HVAC SYMBOLS
ROOM NAME AND NUMBER
POINT WHERE NEW CONNECTS TO EXISTING
EXISTING PIPE TAG
ITEM TO BE DEMOLISHED
AREA NOT IN CONTRACT
PIPING BEING DEMOLISHED
ABOVE GROUND PIPING
PIPE SIZE TAG (DIAMETER)
BELOW GROUND PIPING
PIPE INVERT ELEVATION TAG
PIPE SLOPE TAG
* NOTE *
ALL OF GENERAL NOTES ON THIS SHEET ARE TO BE APPLIED TO ALL OTHER DRAWINGS IN
THIS SET. THE SYMBOLS AND ABBREVIATIONS SHOWN ON THIS SHEET MAY OR MAY NOT
BE USED IN THIS SET OF DRAWINGS.
Room
INVERT: -10' - 1"
1/8" / 12" SLOPE
16"x8"
16"/8"
(E)
F
S
M
B
D
C
16"Ø
E/A
O/A
T/A
L/A
R/A
S/A
EXHAUST AIR
OUTSIDE AIR
RELIEF AIR
RETURN AIR
SUPPLY AIR
TRANSFER AIR
GRILLES, REGISTERS & DIFFUSERS TAG
CFM
THROW-150FPM/ 100FPM/ 50FPM
NECK SIZE / MODULE SIZE
EXISTING DUCT TAG
OVAL DUCT SIZE TAG (WIDTH / HEIGHT)
SQUARE DUCT SIZE TAG (WIDTH x HEIGHT)
HVAC SYMBOLS
RECTANGULAR SUPPLY/OUTSIDE AIR DUCT RISE
RECTANGULAR RETURN/TRANSFER AIR DUCT RISE
MECHANICAL EQUIPMENT TAGS
ROUND DUCT SIZE TAG (DIAMETER)
LINEAR DIFFUSER TAG
CFM
TYPE (SEE SCHEDULE) NUMBER OF SLOTS /
ACTIVE SLOT LENGTH (PLENUM
LENGTH) /
NECK SIZE
DUCT BEING DEMOLISHED
ELEVATION (CENTER OF FACE)
ROUND SUPPLY/OUTSIDE AIR DUCT RISE
ROUND RETURN/TRANSFER AIR DUCT RISE
RECTANGULAR EXHAUST/RELIEF AIR DUCT RISE
ROUND EXHAUST/RELIEF AIR DUCT RISE
DROP
DROP
DROP
DROP
DROP
DROP
GE/A GREASE EXHAUST AIR
SE/A SMOKE EXHAUST AIR
EQUIPMENT BY OTHERS
(REFER TO OTHER DISCIPLINE
FOR ADDITIONAL
INFORMATION)
EXISTING EQUIPMENT
TO REMAIN
FLUE EXHAUST GAS FLUE
C/A COMBUSTION AIR
S-O/A CONDITIONED OUTSIDE AIR
VAV-XX
10' - 0"
(E)VAV-XX
VAV-XX
Ø ROUND
ABV ABOVE
AC AIR CONDITIONING
AD AREA DRAIN
ADD ADDENDUM
AFF ABOVE FINISHED FLOOR
AFUE ANNUAL FUEL UTILIZATION EFFICIENCY
ALT ALTERNATE
AP ACCESS PANEL
ARCH ARCHITECT/ARCHITECTURAL
BFF BELOW FINISHED FLOOR
BLW BELOW
BTU BRITISH THERMAL UNITS
BTUH BRITISH THERMAL UNITS PER HOUR
CAP CAPACITY
CB CATCH BASIN
CFM CUBIC FEET PER MINUTE
CLG CEILING
CO CLEAN OUT
CW COLD WATER
D DEGREE
DB DRY BULB
DIA DIAMETER
DN DOWN
DW DISTILLED WATER
EA EACH
EAT ENTERING AIR TEMPERATURE
ELEC ELECTRICAL
EQUIP EQUIPMENT
EWC ELECTRIC WATER COOLER
EWT ENTERING WATER TEMPERATURE
E/A EXHAUST AIR
EXIST EXISTING
F DEGREES FAHRENHEIT
FCO FLOOR CLEAN OUT
FD FLOOR DRAIN
FD FIRE DAMPER
FDV FIRE DEPARTMENT VALVE
FL FLOOR
FO FUEL OIL
FOV FUEL OIL VENT
FOR FUEL OIL RETURN
FOS FUEL OIL SUPPLY
FPM FEET PER MINUTE
FS FLOOR SINK
FT FOOT/FEET
FTR FIN TUBE RADIATION
GAL GALLON
GC GENERAL CONTRACTOR
GPM GALLONS PER MINUTE
GW GREASE WASTE
HB HOSE BIB
HP HORSE POWER
HTG HEATING
HTR HEATER
HW HOT WATER
HYD HYDRANT
ID INDIRECT
IN INCH
INV INVERT
LB POUND
LB/HR POUNDS PER HOUR
LAT LEAVING AIR TEMPERATURE
LP LOW PRESSURE
LPG LIQUEFIED PETROLEUM GAS
LVR LOUVER
LWT LEAVING WATER TEMPERATURE
M/A MIXED AIR
MAX MAXIMUM
MBH ONE THOUSAND BTU PER HOUR
MCF ONE THOUSAND CUBIC FEET
MD MOTORIZED DAMPER
MECH MECHANICAL
MFR MANUFACTURER
MIN MINIMUM
MISC MISCELLANEOUS
MTR MOTOR
MU/A MAKE-UP/AIR
NC NOISE CRITERIA
NC NORMALLY CLOSED
NIC NOT IN CONTRACT
NO NUMBER
NO NORMALLY OPEN
NTS NOT TO SCALE
O OXYGEN
O/A OUTSIDE AIR
ORD OVERFLOW ROOF DRAIN
PD PRESSURE DROP
PIV POST INDICATOR VALVE
PLBG PLUMBING
PRESS PRESSURE
PRV PRESSURE REDUCING VALVE
PSI POUNDS PER SQUARE INCH
PSIG POUNDS PER SQUARE INCH GAUGE
PWR POWER
R DUCT RISER
R/A RETURN AIR
RCP RADIANT CEILING PANEL
RD ROOF DRAIN
REC RECESSED
RED REDUCER
RH RELATIVE HUMIDITY
RL/A RELIEF AIR
RM ROOM
RPM REVOLUTIONS PER MINUTE
RW RAIN WATER
SF SQUARE FOOT
S/A SUPPLY AIR
SAN SANITARY
SF SQUARE FOOT
SD SMOKE DAMPER
SM SURFACE MOUNT
SP STANDPIPE
SP STATIC PRESSURE
STM STEAM
T THERMOSTAT
TD TEMPERATURE DROP
TDR TRENCH DRAIN
TEMP TEMPERATURE
TYP TYPICAL
UG UNDERGROUND
VAC VACUUM
V VENT
VAV VARIABLE AIR VOLUME
VENT VENTILATION
VTR VENT THROUGH ROOF
W WASTE
WB WET BULB
WCO WALL CLEAN OUT
WH WALL HYDRANT
ABBREVIATIONS
AC AIR CONDITIONING UNIT
ACC AIR COOLED CONDENSER
ACCU AIR COOLING CONDENSING UNIT
AHU AIR HANDLING UNIT
AS AIR SEPARATOR
B BOILER
CH CHILLER
CT COOLING TOWER
CUH CABINET UNIT HEATER
CWP CONDENSER WATER PUMP
CHWP CHILLED WATER PUMP
DBP DOMESTIC WATER BOOSTER PUMP
DC DUCT MOUNTED COIL
DCP DOMESTIC WATER CIRCULATING PUMP
EF EXHAUST FAN
EDC ELECTRIC DUCT COIL
ET EXPANSION TANK
EWH ELECTRIC WATER HEATER
FCU FAN COIL UNIT
FP FIRE PUMP
GI GREASE INTERCEPTOR
GRV GRAVITY ROOF VENTILATOR
HWP HEATING WATER PUMP
HX HEAT EXCHANGER
HRU HEAT RECOVERY UNIT
PRV POWER ROOF VENTILATOR
RE RETURN/EXHAUST FAN
RTU ROOFTOP UNIT
SEP SEWAGE EJECTOR PUMP
SF SUPPLY FAN
SP SUMP PUMP
UH UNIT HEATER
WH WATER HEATER
EQUIPMENT ABBREVIATIONS
48"x2 1/2"
8" / 24x24
12" / ---
LINEAR BAR GRILLE
LINEAR SLOT DIFFUSER
PERFORATED DIFFUSER
WITH DEFLECTORS
ROUND DIFFUSER WITH
ADJUSTABLE PATTERNS
LOUVERED DOUBLE
DEFLECTION GRILLE
12"x10" / ---
TYPE (SEE SCHEDULE)
10" / 24x24 H-5/7/1422
3-CONE DIFFUSER
THROW PATTERN
MAX NC RATING
1 / 4' - 0" / 8"
8' - 0" AFF
1 / 4' - 0" / 8"
18' - 0"
1 / 4' - 0" / 8"
SECTION TOTAL TRACK LENGTH
12"x10" / 24x12
LOUVERED GRILLE
12"x10" / 24x24
EGGCRATE RETURN
GRILLE
BOTTOM OF EQUIPMENT
ELEVATION
505 lb
RTU-XX
RTU-XX
3.0 ton
115000 Btu/h
115 CFH
RTU-XX
Htg: 3.7 GPM
VAV-XX
HEATING COIL
FLOW
OPERATING WEIGHT
NOT INCLUDING CURB
FUEL INPUT
GAS PIPE FLOW
NOMINAL COOLING
CAPACITY
VAV BOX
ROOFTOP UNIT
DATA DEVICE TAGS
DAMPER TAGS
VAV-XX
RTU-XX
EQUIPMENT ID
SYMBOL
BBB
INLET COLLAR DAMPER
MANUAL BALANCING DAMPER
BACKDRAFT DAMPER
COMBINATION FIRE/SMOKE
DAMPER
FIRE DAMPER
SMOKE DAMPER
MOTORIZED DAMPER
SENSOR
MANUAL SWITCH
THERMOSTAT
TEMPERATURE SENSOR
TEMPERATURE & HUMIDITY SENSOR
HUMIDITY SENSOR
NITROGEN DIOXIDE SENSOR
CARBON MONOXIDE SENSOR
CARBON DIOXIDE SENSOR
HUMIDISTAT
CD CONDENSATE DRAIN LINE
CONSULTANTS:
Drawing Title
Approved: Project Director
Project Title:
Location:
Date: Checked: Drawn:
Drawing Number
Dwg. of
Building Number
Project Number
Office of Construction and Facilities Management
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
FULLY SPRINKLERED
A
B
C
D
E
F
209 SANDUSKY STREET
PITTSBURGH, PA 15212
PH: 412.287.7333
www.ae-works.com
AE WORKS PROJECT NUMBER:
ARCHITECTS/ENGINEERS:SEAL
6 " o n e e ig h th i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e h a lf i n c h o n e f o o t th re e i n c h e s o n e f o o t
209 SANDUSKY STREET
PITTSBURGH, PA 15212
PH: 412.287.7333
www.ae-works.com
AE WORKS PROJECT NUMBER:
BID DOCUMENTS
18030
HVAC UPGRADE FOR
MRI SUITE
LOUIS A. JOHNSON VA MEDICAL CENTER
CLARKSBURG, WEST VIRGINIA
540-18-011
CJC AC
M001 08/05/2019 163
HVAC SYMBOLS, ABBREVIATIONS AND
GENERAL NOTES
HVAC GENERAL NOTES
40 UNLESS OTHERWISE NOTED, ALL PIPING AND DUCTWORK IF OVERHEAD, TIGHT TO UNDERSIDE
OF STRUCTURE OR SLAB, WITH SPACE FOR INSULATION.
41 PROVIDE CHAINWHEEL OPERATORS FOR ALL EXPOSED VALVES MOUNTED GREATER THAN 8'-0"
ABOVE FINISHED FLOOR LEVEL. CHAIN SHALL EXTEND UNOBSTRUCTED TO 7'-0" ABOVE FLOOR
LEVEL.
42 ALL PIPING AND DUCTWORK SHALL CLEAR DOORS, WINDOWS, EQUIPMENT CLEARANCES,
MAINTENANCE REQUIREMENTS, CODE SETBACKS, ETC. TO ASSURE PROPER OPERATION,
INSPECTION AND MAINTENANCE.
43 ALL VALVES SHALL BE ADJUSTED FOR SMOOTH AND EASY OPERATION.
44 PROVIDE ALL 90 DEGREE SQUARE ELBOWS WITH DOUBLE RADIUS TURNING VANES UNLESS
OTHERWISE INDICATED OR SPECIFIED. PROVIDE ACCESS DOORS UPSTREAM OF ALL ELBOWS
CONTAINING TURNING VANES.
45 ALL DUCTS SHALL BE BONDED ACROSS FLEXIBLE CONNECTIONS WITH FLEXIBLE COPPER
GROUNDING STRAPS. GROUNDING STRAPS SHALL BE BOLTED OR SOLDERED TO BOTH THE
EQUIPMENT AND THE DUCT.
46 ALL EQUIPMENT SUBMITTALS AND SHOP DRAWINGS REQUIRED BY THE SPECIFICATIONS SHALL
BE APPROVED BY THE ENGINEER PRIOR TO PURCHASE, FABRICATION AND INSTALLATION.
47 ALL HEATING DEVICES AND SURFACES WITH ELEVATED TEMPERATURES WHICH CAN BE
ACCESSED OR COME IN CONTACT WITH OWNER PERSONNEL SHALL BE PROTECTED,
INSULATED, OR CONTROLLED TO REMAIN BELOW 120º F.
48 PROVIDE MANUAL VOLUME DAMPERS IN ALL RUN-OUTS TO DIFFUSERS, BRANCH TAKE-OFFS
FROM MAIN SUPPLY DUCT, AND IN ALL OTHER AREAS REQUIRED TO PROVIDE PROPER SYSTEM
AIRFLOW BALANCING.
HVAC GENERAL NOTES
1 NOT ALL SYMBOLS ARE NECESSARILY USED.
2 COORDINATE FINAL LOCATIONS OF DIFFUSERS AND GRILLES WITH ARCHITECTURAL
REFLECTED CEILING PLANS.
3 DRAWINGS ARE DIAGRAMMATIC. CONTRACTOR TO FIELD VERIFY DUCT AND PIPE ROUTING AND
COORDINATE INTERFERENCE BETWEEN TRADES PRIOR TO INSTALLATION.
4 ROOF OPENINGS, FLASHING, AND COUNTER FLASHING BY CONTRACTOR. LOCATION OF
OPENINGS BY CONTRACTOR.
5 DUCTWORK TO BE INSTALLED TIGHT TO UNDERSIDE OF STRUCTURE ABOVE UNLESS NOTED
OTHERWISE.
6 PROVIDE ALL MATERIALS, EQUIPMENT AND PERFORM ALL LABOR REQUIRED TO INSTALL
COMPLETE AND OPERABLE MECHANICAL SYSTEMS AS INDICATED ON THE DRAWINGS, AS
SPECIFIED AND AS REQUIRED BY CODE.
7 CONTRACT DOCUMENT DRAWINGS FOR MECHANICAL WORK ARE DIAGRAMMATIC AND ARE
INTENDED TO CONVEY SCOPE AND GENERAL ARRANGEMENT ONLY. CONTRACTOR SHALL BE
RESPONSIBLE TO FIELD SURVEY ACTUAL SITE CONDITIONS AND ACCOMODATE ACTUAL SITE
CONDITIONS AS PART OF SCOPE OF WORK AT NO COST TO OWNER.
8 INSTALL ALL MECHANICAL EQUIPMENT AND APPURTENANCES IN ACCORDANCE WITH
MANUFACTURER'S RECOMMENDATIONS, CONTRACT DOCUMENTS, APPLICABLE BUILDING,
STATE AND LOCAL CODES, SEISMIC REQUIREMENTS, ENERGY CODES AND INSURANCE
UNDERWRITER REQUIREMENTS.
9 COORDINATE CONSTRUCTION OF ALL MECHANICAL WORK WITH ARCHITECTURAL,
STRUCTURAL, CIVIL AND ELECTRICAL WORK, ETC. SHOWN ON OTHER CONTRACT DOCUMENT
DRAWINGS.
10 MAINTAIN A MINIMUM OF 6'-8" CLEARANCE TO UNDERSIDE OF PIPES, DUCTS, CONDUITS,
SUSPENDED EQUIPMENT, SUPPORTS, ETC., THROUGHOUT ACCESS ROUTES IN MECHANICAL
ROOMS.
11 ALL TESTS SHALL BE COMPLETED AND ACCEPTED BY THE INSPECTOR BEFORE ANY
MECHANICAL EQUIPMENT OR PIPING INSULATION IS APPLIED.
12 LOCATE ALL TEMPERATURE, PRESSURE AND FLOW MEASURING DEVICES IN ACCESSIBLE
LOCATIONS WITH STRAIGHT SECTION OF PIPE OR DUCT UPSTREAM AND DOWNSTREAM, AS
RECOMMENDED BY THE MANUFACTURER FOR ACCURACY.
13 TESTING ADJUSTING AND BALANCING (TAB) AGENCY SHALL BE A MEMBER OF THE ASSOCIATED
AIR BALANCING COUNCIL (AABC) OR THE NATIONAL ENVIRONMENTAL BALANCING BUREAU
(NEBB). TAB FIRM SHALL HAVE A MINIMUM OF 5 YEARS EXPERIENCE ON SIMILAR PROJECTS.
PERFORM TAB IN ACCORDANCE WITH THE REQUIREMENTS OF THE TAB PROCEDURAL
STANDARD RECOMMENDED BY THE TAB TRADE ASSOCIATION THAT APPROVED THE TAB FIRM'S
QUALIFICATIONS.
14 WHERE TWO OR MORE ITEMS OF THE SAME TYPE OF EQUIPMENT ARE REQUIRED, THE
PRODUCTS OF A SINGLE MANUFACTURER SHALL BE USED.
15 COORDINATE ALL FINAL EQUIPMENT CONNECTIONS WITH THE MANUFACTURERS' CERTIFIED
DRAWINGS. COORDINATE AND PROVIDE ALL DUCTWORK AND PIPING TRANSITIONS REQUIRED
FOR FINAL EQUIPMENT CONNECTIONS TO FURNISHED EQUIPMENT. FIELD VERIFY AND
COORDINATE ALL DUCTWORK AND PIPING DIMENSIONS BEFORE FABRICATION.
16 ALL CONTROL WIRE AND CONDUIT SHALL COMPLY WITH THE NATIONAL ELECTRIC CODE,
DIVISION 26 OF THE SPECIFICATIONS, ALL LOCAL CODES, AND OWNER'S INSURANCE
UNDERWRITER REQUIREMENTS.
17 THE LOCATIONS AND SIZES OF ALL ITEMS SHOWN ON THE DRAWINGS OR CALLED FOR IN THE
SPECIFICATIONS THAT ARE NOT DEFINITELY FIXED BY DIMENSIONS ARE APPROXIMATE ONLY.
THE EXACT LOCATIONS AND SIZES NECESSARY TO SECURE THE BEST CONDITIONS AND
RESULTS SHALL BE DETERMINED BY THE PROJECT SITE CONDITIONS AND SHALL HAVE THE
APPROVAL OF THE ENGINEER BEFORE BEING INSTALLED. DO NOT SCALE DRAWINGS.
18 PLAN DRAWINGS AND SECTIONS CUTS WHICH SPECIFICALLY IDENTIFY SERVICE ROUTE
OFFSETS, ELEVATION CHANGES, OBSTRUCTIONS, ACCESS DOORS, BALANCING DEVICES, ETC.
ARE SHOWN FOR CLARITY WHERE SPECIFIC KNOWN CONDITIONS EXIST. CONTRACTOR SHALL
COORDINATE EQUIPMENT, DUCTWORK, AND PIPING ROUTINGS WITH ALL OTHER TRADES.
REQUIREMENTS NOT SPECIFICALLY IDENTIFIED SHALL NOT BE INTERPRETED AS EXCLUSION
FROM CONTRACTOR'S SCOPE OF WORK. CONTRACTOR SHALL BE RESPONSIBLE FOR ACTUAL
SITE CONDITIONS AND SHALL INCLUDE SUCH CONDITIONS IN SCOPE OF WORK AT NO
ADDITIONAL COST TO THE OWNER.
19 ALL MISCELLANEOUS STEEL REQUIRED TO ENSURE PROPER INSTALLATION AND SUPPORT OF
MECHANICAL WORK AS SHOWN IN DETAILS FOR PIPING, DUCTWORK AND EQUIPMENT (UNLESS
OTHERWISE NOTED) SHALL BE FURNISHED AND INSTALLED BY THE CONTRACTOR AT NO
ADDITIONAL COST TO THE OWNER.
20 ALL EQUIPMENT, PIPING, DUCTWORK, ETC., SHALL BE SUPPORTED AS DETAILED, SPECIFIED
AND AS REQUIRED TO PROVIDE A VIBRATION FREE INSTALLATION.
21 ALL OPENINGS IN FIRE RATED WALLS AND SMOKE PARTITIONS DUE TO DUCTWORK, PIPING, CONDUIT, ETC., SHALL BE FIRE STOPPED WITH APPROVED FIRESTOPPING MATERIALS.
22 REFER TO TYPICAL DETAILS FOR DUCTWORK, PIPING AND EQUIPMENT INSTALLATION.
23 UNLESS OTHERWISE SHOWN, LOCATE ALL ROOM THERMOSTATS WITH TOP AT 48" ABOVE
FINISHED FLOOR IN ACCORDANCE WITH ADA REQUIREMENTS. NOTIFY THE ENGINEER OF ANY
ROOMS WHERE THE ABOVE LOCATION CAN NOT BE MAINTAINED OR WHERE THERE IS A
QUESTION ON LOCATION. COORDINATE FINAL LOCATIONS WITH OWNER.
24 LOCATE ALL MECHANICAL EQUIPMENT (VAV BOXES, CABINET HEATERS, UNIT HEATERS, ETC.,)
FOR UNOBSTRUCTED ACCESS TO UNIT ACCESS PANELS, FILTERS, CONTROLS AND VALVING.
DO NOT LOCATE FAN POWERED VAV BOXES ABOVE LIGHTING FIXTURES.
25 PROVIDE FLEXIBLE CONNECTIONS IN ALL DUCTWORK SYSTEMS (SUPPLY, RETURN AND
EXHAUST) CONNECTED TO FANS AND OTHER EQUIPMENT WHICH REQUIRE VIBRATION
ISOLATION. FLEXIBLE CONNECTIONS SHALL BE PROVIDED AT THE POINT OF CONNECTION TO
THE EQUIPMENT UNLESS OTHERWISE INDICATED.
26 ALL LOUVERS SHALL BE FURNISHED AND INSTALLED BY THE CONTRACTOR (UNLESS
OTHERWISE NOTED). CONTRACTOR SHALL COORDINATE SIZES, LOCATIONS, AND
CONNECTIONS. CONNECTIONS TO LOUVERS SHALL BE FURNISHED AND INSTALLED BY
CONTRACTOR.
27 PROVIDE AN AIR VENT AT THE HIGH POINT OF EACH DROP IN HYDRONIC WATER PIPING
SYSTEMS. ALL PIPING SHALL SLOPE TO LOW POINTS. PROVIDE HOSE END DRAIN VALVES AT
THE BOTTOM OF ALL RISERS AND LOW POINTS.
28 INSTALL PIPING SO THAT ALL VALVES, STRAINERS, UNIONS, TRAPS, FLANGES AND OTHER
APPURTENANCES REQUIRING ACCESS ARE ACCESSIBLE.
29 ALL ISOLATION VALVES SHALL BE IN LOCATION AND ELEVATION WHICH ALLOWS FOR
EQUIPMENT AND BRANCH PIPING REMOVAL, WHILE MAINTAINING SERVICE UPSTREAM OF THE
ISOLATION VALVE.
30 ALL BALANCING VALVES AND ISOLATION VALVES USED TO ADJUST FLOW RATES SHALL BE
PROVIDED WITH POSITIONS INDICATORS AND MAXIMUM ADJUSTABLE STOPS (MEMORY STOPS).
31 ALL ISOLATION VALVES (EXCEPT CONTROL VALVES), STRAINERS, AND PIPING SPECIALTIES
SHALL BE FULL LINE SIZE BEFORE REDUCING SIZE TO MAKE CONNECTIONS TO EQUIPMENT
AND CONTROLS.
32 MECHANICAL JOINTS SUCH AS UNIONS, FLANGES, OR THREADED FITTINGS SHALL BE
INSTALLED AT EACH EQUIPMENT CONNECTION, IN BYPASSES, AT FLOOR PENETRATIONS, AT
CONTROL DEVICES, AND IN LONG PIPE RUNS (100 FEET OR MORE) TO PERMIT DISASSEMBLY
FOR ALTERATION AND REPAIRS.
33 MEASURE, CUT AND INSTALL PIPE LENGTH ACCURATELY TO MINIMALIZE MISALIGNMENT.
INSTALL ALL PIPING WITHOUT FORCING OR SPRINGING.
34 PROVIDE FLEXIBLE CONNECTIONS IN ALL PIPING SYSTEMS CONNECTED TO PUMPS AND OTHER
EQUIPMENT WHICH REQUIRE VIBRATION ISOLATION (EXCEPT WATER COILS). FLEXIBLE
CONNECTIONS SHALL BE PROVIDED AS CLOSE TO THE EQUIPMENT AS POSSIBLE OR AS
INDICATED ON THE DRAWINGS.
35 PROVIDE VIBRATION INSULATION FOR ALL MECHANICAL EQUIPMENT TO PREVENT VIBRATION
TRANSMISSION TO BUILDING STRUCTURE.
36 CONCRETE HOUSEKEEPING PADS SHALL BE FURNISHED AND INSTALLED BY THE GENERAL
CONTRACTOR. MECHANICAL CONTRACTOR SHALL PROVIDE EQUIPMENT WEIGHTS, SIZES AND
LOCATION TO GENERAL CONTRACTOR. MINIMUM CONCRETE PAD THICKNESS SHALL BE IN
ACCORDANCE WITH STRUCTURAL DETAILS. PAD SHALL EXTEND BEYOND THE EQUIPMENT
FOOTPRINT A MINIMUM OF 6 INCHES ON EACH SIDE.
37 ALL DUCTWORK, PIPING, AND EQUIPMENT SUPPORTED FROM STRUCTURAL STEEL SHALL BE
COORDINATED WITH GENERAL CONTRACTOR. ALL ATTACHEMENTS TO STEEL MEMBERS, BAR
JOISTS, TRUSSES, OR JOIST GIRDERS SHALL BE APPROVED BY STRUCTURAL ENGINEER.
WELDING TO STRUCTURAL MEMBERS SHALL NOT BE PERMITTED.
38 MECHANICAL EQUIPMENT, DUCTWORK, AND PIPING SHALL NOT BE SUPPORTED FROM ROOF OR
DECK ASSEMBLY. SUPPORTS SHALL ATTACH TO STRUCTURAL MEMBERS. COORDINATE WITH
STRUCTURAL DRAWINGS.
39 PROVIDE MANUFACTURER'S MATCHING ROOF CURBS FOR ALL ROOF MOUNTING EQUIPMENT.
COORDINATE ACTUAL ROOF PITCH AND CONSTRUCTION DETAILS WITH CONTRACTOR.
PROVIDE SLOPED CURBS PER MANUFACTURER'S RECOMMENDATIONS. CONTRACTOR SHALL
INSTALL ROOF CURBS AND FLASHING PER ROOFING MANUFACTURER'S INSTALLATION
REQUIREMENTS.
Title Sheet Revision
AHU-1
M101
D
17 16 15
EXISTING
SKYLIGHT
EXISTING ROOF DRAIN
EXISTING
REMOTE
CONDENSING
UNIT
EXISTING ROOF HATCH
EXISTING MRI CHILLER
D
(E)EF-1
(E)EF2
17 16 15
(E)EF
(E)EF
(E)EF
(E)CU-1
CONSULTANTS:
Drawing Title
Approved: Project Director
Project Title:
Location:
Date: Checked: Drawn:
Drawing Number
Dwg. of
Building Number
Project Number
Office of Construction and Facilities Management
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
FULLY SPRINKLERED
A
B
C
D
E
F
209 SANDUSKY STREET
PITTSBURGH, PA 15212
PH: 412.287.7333
www.ae-works.com
AE WORKS PROJECT NUMBER:
ARCHITECTS/ENGINEERS:SEAL
6 " o n e e ig h th i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e h a lf i n c h o n e f o o t th re e i n c h e s o n e f o o t
209 SANDUSKY STREET
PITTSBURGH, PA 15212
PH: 412.287.7333
www.ae-works.com
AE WORKS PROJECT NUMBER:
BID DOCUMENTS
18030
HVAC UPGRADE FOR
MRI SUITE
LOUIS A. JOHNSON VA MEDICAL CENTER
CLARKSBURG, WEST VIRGINIA
540-18-011
CJC AC
MD101
08/05/2019 164
MRI SUITE HVAC DEMOLITION PLAN
HVAC FLOOR PLAN DEMOLITION KEYNOTES
1 REMOVE ALL HVAC DUCTWORK AND GRILLES IN THIS ROOM SERVING THIS ROOM.
2 DEMOLISH EXISTING AIR HANDLING UNIT AND ASSOCIATED DUCTWORK.
3 DEMOLISH EXISTING OA INTAKE HOOD AND ASSOCIATED DUCTWORK.
4 DEMOLISH EXISTING EXHAUST DUCTWORK UP TO ROOF.
5 REMOVE EXISTING EXHAUST FAN AND ASSOCIATED DUCTWORK.
6 EXISTING EXHAUST FAN TO BE DEMOLISHED AND REPLACED WITH NEW EXHAUST FAN IN
SAME LOCATION. PREPARE ROOF FOR NEW, LARGER OPENING.
7 EXISTING EXHAUST DUCTWORK TO BE DEMOLISHED. PREPARE ROOF FOR NEW, LARGER
OPENING.
8 EXISTING EXHAUST FAN TO BE DEMOLISHED AND REPLACED WITH NEW EXHAUST FAN IN
SAME LOCATION. STRUCTURAL SUPPORT RAILS TO REMAIN FOR NEW EXHAUST FAN EF-2.
9 EXISTING CONDENSING UNIT TO BE DEMOLISHED AND REPLACED WITH NEW CU-1 IN SAME
LOCATION.
10 EXISTING INTAKE HOOD TO BE DEMOLISHED AND REPLACED WITH NEW INTAKE HOOD IN
SAME LOCATION. PREPARE ROOF FOR NEW, LARGER OPENING.
NORTH
PROJECT
TRUE NORTH = 81
1/4" = 1'-0"
HVAC DEMOLITION PLAN
HVAC GENERAL DEMOLITION NOTES
1 REFER TO FACILITY'S INFECTION CONTROL AND RISK ASSESSMENT (ICRA) FOR ADDITIONAL
REQUIREMENTS.
2 CAP RETURN AIR DUCTS TO CONTRUSTION ZONE TO PREVENT RETURN FROM CONSTRUCTION
ZONE. MINIMIZE SUPPLY AI RPROVICDED TO CONSTRUCTION ZONE.
3 EXISTING SYSTEMS TO REMAIN IN SERVICE UNLESS OTHERWISE NOTED.
4 REFER TO DRAWINGS M101 AND M102 FOR INFORMATION FOR NEW EQUIPMENT.
1/4" = 1'-0"
HVAC DEMOLITION ROOF PLAN
T
T
T
T
H S
T
14"Ø S/A
22"x16" S/A
34"x18" S/A
18"x12" S/A
10"x10" S/A
12"x12" S/A
22"x18" R/A
12"x10" R/A
"x
S /A
"Ø
R /A
12"x12" E/A
10"Ø E/A
8" x6
E
/A
10"Ø S/A
8"Ø S/A
"x
E /A
14"x14" / 24x24
835RG5
14"x14" / 24x24
835RG5
12"x10" / 24x24
500EG-4
8"x6" / 24x24
150EG-2
14"x14" / 24x24
830RG5
12"x8" / 24x24
350EG-3
14"x6" / 24x24
300EG-3
14" / 24x24
625SD5
10" / 24x24
350SD3
10" / 24x24
350SD3
6" / 24x24
100SD1
M101
AHU-1
EQUIP RM
EXAM RM
CONTROL RM
HC BATHROOM
IV START RM
FOYER
14" / 24x24
625SD5
D
H-1
28"x20" R/A
"Ø
E /A
10" / 24x24
250CD3
"x
S /A
RHC-5
RHC-4
"x
8" S
/A
RHC-3
10" / 24x24
250CD3
RHC-2
10"Ø S/A
10"Ø S/A
14"Ø S/A
14" / 24x24
625SD5
14" / 24x24
625SD5
M101
RHC-1
M101
16 15
28"x20" S/A
30"x20" E/A
6 7
24"x14" / ---
1400RR1
D
H-1
AHU-1
1 1/4" CW
1/
4" C
W
EQUIP RM
17 16
RO-1
6"6"
X = DUCT DEPTH AS
INDICATED ON PLAN
AIR FLOWX
X+3"
X
12x12 ACCESS PANEL
MOUNT ON SIDE OF DUCT
OPPOSITE OF HUMIDIFIER
AIR FLOW SWITCH -
INTERLOCK WITH HUMIDIFIER
3'-0"
DRAIN
VALVE
HUMIDIFIER DISPERSION TUBE
STAINLESS STEEL DUCT SECTION
SOLDER DRAIN PAN WATER TIGHT
HIGH LIMIT
HUMIDISTAT
10' - 0"
MIN. FROM
HUMIDIFIER
AIR GAP FITTING
PIPE TO FLOOR
DRAIN W/ FUNNEL
CONDENSATE
DRAIN
HUMIDIFIER
UNION
CW MAKE-UP
SHUT-OFF VALVE
SUPPLY
DUCT
PITCH TO
HUMIDIFIER
DRAIN TEEMANIFOLD
WATER OUTLET
TO RO-1
MIN. 4'-0"
OFF FLOORBALL VALVE
UNION
WALL PIPE SUPPORT
WALL PIPE
SUPPORT
WATER INLET
AIR GAP
DRAIN
STRAINER
REDUCED PRESSURE
BACKFLOW PREVENTER
1" TO NEAREST
FLOOR DRAIN
Level 1 0' - 0"
AHU-1
Level 1 0' - 0"
AHU-1
H-1
Level 1 0' - 0"
AHU-1
CONSULTANTS:
Drawing Title
Approved: Project Director
Project Title:
Location:
Date: Checked: Drawn:
Drawing Number
Dwg. of
Building Number
Project Number
Office of Construction and Facilities Management
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
FULLY SPRINKLERED
A
B
C
D
E
F
209 SANDUSKY STREET
PITTSBURGH, PA 15212
PH: 412.287.7333
www.ae-works.com
AE WORKS PROJECT NUMBER:
ARCHITECTS/ENGINEERS:SEAL
6 " o n e e ig h th i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e h a lf i n c h o n e f o o t th re e i n c h e s o n e f o o t
209 SANDUSKY STREET
PITTSBURGH, PA 15212
PH: 412.287.7333
www.ae-works.com
AE WORKS PROJECT NUMBER:
BID DOCUMENTS
18030
HVAC UPGRADE FOR
MRI SUITE
LOUIS A. JOHNSON VA MEDICAL CENTER
CLARKSBURG, WEST VIRGINIA
540-18-011
CJC AC
M101 08/05/2019 165
MRI SUITE HVAC NEW WORK PLAN
NORTH
PROJECT
TRUE NORTH = 81
HVAC GENERAL NEW WORK NOTES
1 REFER TO FACILITY'S INFECTION CONTROL AND RISK ASSESSMENT
(ICRA) FOR ADDITIONAL REQUIREMENTS.
2 ALL WORK SHALL BE SCHEDULED AND COORDINATED JOINTLY WITH
LOUIS A. JOHNSON VAMC. A DETAILED JOB TIMELINE SHALL BE
ESTABLISHED AND SUBMITTED FOR REVIEW AND APPROVAL.
3 COORDINATE ALL WAVE GUIDE FILTER REQUIREMENTS AT RF
PENETRATIONS WITH RF SHIELD VENDOR AND MRI EQUIPMENT VENDOR.
EXISTING RF SHIELD VENDOR IS BRADEN SHIELDING SYSTEMS – (918)
624-2888. THERE IS A FUTURE PROJECT THAT REPLACES THE MRI
EQUIPMENT. THE PROJECT IS TITLED “AVANTO FIT UPGRADE (MRI
ROOM)” 540-18-011NAC. CONTRACTOR TO COORDINATE WITH COR
BEFORE CONSTRUCTION NOTICE TO PROCEED TO OBTAIN DRAWINGS
FOR THAT PROJECT TO COORDINATE WITH THIS PROJECT.
4 CONTRACTOR TO HAVE THE RF SHIELD TESTED PRIOR TO
CONSTRUCTION AND AT THE END OF CONSTRUCTION. CONTRACTOR TO
REPAIR RF SHIELD AS REQUIRED TO PASS TEST PER BRADEN SHIELDING
SYSTEM REQUIREMENTS
5 ALL DUCTWORK, FASTENERS, HANGERS, AND APPURTENANCES WITHIN
THE RF SHIELD SHALL BE NON-FERROUS.
6 CONTRACTOR TO PROVIDE REMOTE OPERATORS FOR ALL MANUAL
VOLUME DAMPERS LOCATED ABOVE GYPSUM BOARD CEILINGS.
7 RUNOUT BRANCH TO DUCTWORK TO SUPPLY DIFFUSERS, AND EXHAUST
GRILLES TO BE THE SAME SIZE AS THE NECK SIZE ON THE AIR DEVICE
UNLESS NOTED OTHERWISE.
8 MAINTAIN 6" MINIMUM CLEARANCE FROM RATED WALLS AND HVAC
EQUIPMENT.
9 ALL DUCTWORK TO BE LOW PRESSURE (3") PRESSURE CLASS.
10 NOTE: THE CRAWLSPACE BELOW EQUIP RM 106 IS LABELED A
“CONFINED SPACE”. CONTRACTOR TO FOLLOWING VA’S PROCEDURE
FOR WORKING IN A CONFINED SPACE AND COORDINATE WITH COR.
11 NO ONSITE WORK CAN BEGIN UNTIL ALL SUBMITTALS HAVE BEEN
RECEIVED AND APPROVED BY THE AE AND VA.
1/2" = 1'-0"
MRI SUITE HVAC NEW WORK PLAN
HVAC KEYNOTES
1 INSTALL WALL MOUNTED, REMOTE DIGITAL READOUT FOR
TEMPERATURE AND HUMIDITY LEVELS OF EXAM ROOM 105 INSIDE OF
EQUIPMENT ROOM 106. THIS PANEL IS INTENDED FOR LOUIS A.
JOHNSON STAFF TO VIEW. UNIT STATUS MUST BE DISPLAYED.
PANEL MUST BE CONNECTED TO AND REPORT TO EXISTING BAS
SYSTEM/CENTRAL ENGINEERING CONTROL CENTER (ECC).
2 INSTALL A DIGITAL TEMPERATURE SENSOR AT THIS LOCATION.
3 INSTALL A HUMIDITY SENSOR AT THIS LOCATION.
4 INSTALL A DIGITAL PRESSURE SENSOR AT THIS LOCATION.
5 INSTALL DUCT MOUNTED, SHORT ABSORPTION MANIFOLD
CONNECTED TO STEAM HUMIDIFIER H-1 AT THIS LOCATION. REFER
TO DETAIL ON DRAWING.
6 IF INDIVIDUAL SUPPLY, RETURN, AND EXHAUST BRANCH DUCTS
PENETRATE RF SHIELD CONTRACTOR TO PROVIDE WAVE GUIDE
FILTER. COORDINATE WITH RF SHIELD VENDOR.
7 ALL DUCTWORK, SUPPORTS, HANGERS AND FASTENERS IN EXAM
ROOM 105 SHALL BE OF NON-FERROUS CONSTRUCTION.
8 PROVIDE WAVEGUIDE FILTER AT THE INDICATED LOCATION WHERE
DUCTWORK PENETRATES RF SHIELD. COORDINATE WITH RF SHIELD
VENDOR.
9 12“x12” UP TO EF-1 ON ROOF. TRANSITION AS REQUIRED.
10 26“x24” EXHAUST UP TO DUCTWORK ON ROOF.
11 28“x20” UP TO IH-1 ON ROOF. TRANSITION AS REQUIRED.
12 SIDEWALL SUPPLY GRILLE SS-1 DOWNSTREAM OF RHC-1.
CONTRACTOR TO BALANCE TO 1,400 CFM.
13 CONTRACTOR TO RELOCATE EXISTING BAS CONTROL PANELS AS
NEEDED TO COORDINATE WITH RELOCATED ELECTRICAL PANELS.
14 MOTORIZED DAMPER. DAMPER FULLY OPEN DURING NORMAL
OPERATION. IN ECONOMIZER MODE THE DAMPER FULLY SHUTS AND
ALL RETURN AIR IS EXHAUSTED BY EF-2.
15 1-1/4” CONDENSATE DRAIN FROM AHU-1 DOWN TO CRAWLSPACE
BELOW. CONNECT TO SAME PIPE THAT EXISTING AHU’S
CONDENSATE DRAIN CONNECTED TO.
16 1-1/4” DOMESTIC WATER SUPPLY PIPE DIVIDES INTO (2) ½” NPT PIPES
DOWN TO H-1. CONTRACTOR TO COORDINATE EXACT PIPE SIZE AND
TERMINATION LOCATION WITH INSTALLED HUMIDIFIER.
17 3” DRAIN PIPE DOWN FROM HUMIDIFIER TO CRAWLSPACE. DRAIN
PIPE CONNECTS TO HUMIDIFIER AT (2) LOCATIONS. CONTRACTOR TO
COORDINATE EXACT PIPE SIZE AND DISCHARGE LOCATION WITH
INSTALLED HUMIDIFIER. CONNECT TO SAME DRAIN PIPE THAT
EXISTING AHU’S CONDENSATE DRAIN CONNECTED TO IN
CRAWLSPACE.
18 1-1/4” DOMESTIC WATER SUPPLY PIPE DOWN TO RO-1. CONTRACTOR
TO COORDINATE EXACT PIPE SIZE AND TERMINATION LOCATION WITH
INSTALLED REVERSE OSMOSIS SYSTEM. PROVIDE BACKFLOW
PREVENTER ON SUPPLY PIPE PER “BACKFLOW PREVENTER” DETAIL
ON THIS DRAWING.
19 1” DRAIN PIPE DOWN FROM RO-1, ROUTE HORIZONTALLY INTO
EQUIPMENT ROOM 106 AND THEN DOWN TO CRAWLSPACE.
CONTRACTOR TO COORDINATE EXACT PIPE SIZE AND DISCHARGE
LOCATION WITH INSTALLED REVERSE OSMOSIS SYSTEM. CONNECT
TO SAME DRAIN PIPE THAT EXISTING AHU’S CONDENSATE DRAIN
CONNECTED TO IN CRAWLSPACE.
20 INSTALL AN AUDIBLE AND VISUAL ALARM FOR HUMIDITY AND
TEMPERATURE LEVELS OUTSIDE NORMAL OPERATING CONDITIONS
OF AHU/HUMIDIFIER. REPORT GENERAL ALARM TO BAS.
21 LOCATION OF NEW SMOKE DETECTOR AND DAMPER TO BE
CONNECTED TO AHU-1. REFER TO DRAWING M601 FOR ADDITIONAL
INFORMATION.
22 RE-ROUTE EXISTING 4” PVC ROOF DRAIN AS NEEDED TO
ACCOMMODATE NEW DUCTWORK.
1/4" = 1'-0"
LEVEL 1 MRI SUITE HVAC PIPING PLAN
NOT TO SCALE
HUMIDIFIER (H-1) DRAIN PAN DETAIL - DUCT MOUNTED
NOT TO SCALE
HUMIDIFIER (H-1) PIPING DETAIL - ELECTRIC
NOT TO SCALE
BACKFLOW PREVENTER DETAIL
1/4" = 1'-0"
EQUIP RM 106 SECTION LOOKING NORTH
1/4" = 1'-0"
EQUIP RM 106 SECTION LOOKING NORTH 2
1/4" = 1'-0"
EQUIP RM 106 SECTION LOOKING EAST
EXISTING ROOF DRAIN
EXISTING ROOF HATCH
EXISTING MRI CHILLER
D
17 16 15
EF-2
IH-1
26"x24" L/A
CU-1
(E)EF
(E)EF
(E)EF
EF-1
CONSULTANTS:
Drawing Title
Approved: Project Director
Project Title:
Location:
Date: Checked: Drawn:
Drawing Number
Dwg. of
Building Number
Project Number
Office of Construction and Facilities Management
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
FULLY SPRINKLERED
A
B
C
D
E
F
209 SANDUSKY STREET
PITTSBURGH, PA 15212
PH: 412.287.7333
www.ae-works.com
AE WORKS PROJECT NUMBER:
ARCHITECTS/ENGINEERS:SEAL
6 " o n e e ig h th i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e h a lf i n c h o n e f o o t th re e i n c h e s o n e f o o t
209 SANDUSKY STREET
PITTSBURGH, PA 15212
PH: 412.287.7333
www.ae-works.com
AE WORKS PROJECT NUMBER:
BID DOCUMENTS
18030
HVAC UPGRADE FOR
MRI SUITE
LOUIS A. JOHNSON VA MEDICAL CENTER
CLARKSBURG, WEST VIRGINIA
540-18-011
CJC AC
M102 08/05/2019 166
HVAC ROOF PLAN
NORTH
PROJECT
TRUE NORTH = 81
1/4" = 1'-0"
ROOF PLAN
HVAC KEYNOTES
1 NEW EXHAUST FAN EF-1. MODIFY ROOF OPENING FOR LARGER DUCT THAN EXISTING.
2 NEW EXHAUST DUCT DOWN. MODIFY ROOF OPENING FOR LARGER DUCT THAN EXISTING.
3 NEW EXHAUST FAN EF-2.
4 NEW CONDENSING UNIT NEW CU-1. ROUTE NEW REFRIGERANT PIPING FROM NEW CU-1 TO
NEW AHU-1 FOLLOWING SAME PATH AS EXISTING REFRIGERANT PIPING. SIZE
REFRIGERANT PIPING PER MANUFACTURER’S RECOMMENDATIONS.
5 NEW INTAKE HOOD IH-1. MODIFY ROOF OPENING FOR LARGER DUCT THAN EXISTING.
HVAC GENERAL NEW WORK NOTES
1 REFER TO FACILITY'S INFECTION CONTROL AND RISK ASSESSMENT (ICRA) FOR ADDITIONAL
REQUIREMENTS.
2 ALL WORK SHALL BE SCHEDULED AND COORDINATED JOINTLY WITH LOUIS A. JOHNSON VAMC.
A DETAILED JOB TIMELINE SHALL BE ESTABLISHED AND SUBMITTED FOR REVIEW AND
APPROVAL.
3 ALL STRUCTURAL AND MISCELLANEOUS STEEL REQUIRED TO SUPPORT AND ANCHOR HVAC
EQUIPMENT ON THE ROOF AND STRUCTURAL AND MISCELLANEOUS STEEL REQUIRED FOR ANY
ROOF PENETRATIONS BEYOND WHAT IS INDICATED ON THE STRUCTURAL DRAWINGS IS THE
RESPONSIBILITY OF THE CONTRACTOR. THIS INCLUDES EQUIPMENT SHOWN AS BASIS OF
DESIGN ON THE CONTRACT DOCUMENTS, EQUIVALENT EQUIPMENT, OR EQUIPMENT ACCEPTED
FROM ALTERNATE MANUFACTURERS.
4 COORDINATE WITH ROOF MANUFACTURER TO MAINTAIN ANY APPLICABLE WARRANTY.
SUPPORT
SADDLE FROM
STRUCTURE
FLEXIBLE DUCT SIZE
SAME AS DIFFUSER
INLET: 5'-0" MAX LENGTH
12"
CEILING
VOLUME DAMPER W/
LOCKING QUAD
LOCKING QUAD
SHEET METAL
SADDLE
CONICAL OUTLET
BRANCH DUCT
USE RIGID ELBOWS
FOR CHANGE OF
DIRECTION GREATER
THAN 45º
[300mm]
SEE SPECIFICATIONS FOR
CLAMPS AND SEALANT (TYP.)
NOTE:
THE USE OF FLEXIBLE AIR DUCT CONNECTORS ARE NOT
PERMITTED FOR THE DEDICATED AHU SERVING THE SURGICAL SUITE.
TYPICAL
DIFFUSER OR
REGISTER IN
LAY-IN CLG.
THERMAL INSULATION
SEE SPECIFICATIONS
NOTE:
1. UNLESS OTHERWISE INDICATED ON PLANS, MAXIMUM ANGLES SHOWN SHALL APPLY.
BRANCH DUCT TAKE-OFF PLAN VIEW
W
1/4 W
OR 4" MIN.
MAIN SUPPLY
DUCT
PROVIDE VOLUME DAMPER
A
IR
F
LO
W
AIR
FLOW
SUPPLY REGISTER TAKE-OFF PLAN VIEW
AIR
FLOW
AIR
FLOW
VOLUME EXTRACTOR; ADJUSTABLE
FROM FULLY CLOSED POSITION TO CFM
NOTED ON FLOOR PLANS
ADJUSTABLE
METAL ROD OR
LINKAGE
TOP REGISTER
MAIN
SUPPLY
DUCT
SEE FLOOR PLAN FOR
SPLIT DIMENSION
MAIN
SUPPLY
DUCT
TURNING VANES
AIR
FLOW
AIR
FLOW
A
IR
F
LO
W
PROVIDE
VOLUME
DAMPER
AIR SPLIT DUCT TAKE-OFF PLAN VIEW
SUPPLY REGISTER OR
BRANCH DUCT
NOTES:
1. DELETE INSULATION STAND-OFF ON DUCTWORK WITHOUT EXTERIOR INSULATION.
2. DETAIL SHOWS SINGLE BLADE DAMPER. DAMPER INSTALLATION SHALL BE SIMILAR FOR
MULTI-BLADE DAMPERS & ROUND DAMPERS.
SIDE ELEVATION SECTION
HANDLE WITH
LOCKING
QUADRANT
INSIDE END BEARING
1/8"CLEARANCE ALL
AROUND
DAMPER BLADE
INSULATION STAND-
OFF
DUCT
INSULATION SEE
SPECIFICATION
STIFFEN BLADE
AS REQUIRED
OUTSIDE END BEARING
1/2" ROUND ROD PIN
LAY-IN CEILING DIFFUSER INSTALLATION
GYP BOARD CEILING DIFFUSER INSTALLATION
FOR GYPSUM BOARD CEILING INSTALLATION, LOCATE
VOLUME DAMPER IMMEDIATELY UPSTREAM OF DIFFUSER
DROP OR AT TAP COLLAR. SUCH THAT VOLUME DAMPER AT
TAP CAN BE ACCESSED FROM DIFFUSER OPENING IN CLG.
D D
BRANCH DUCTCLOSED END OF
BRANCH DUCT
OBD
DIFFUSER
FLEXIBLE DUCTWORK
TAP COLLAR
CEILING
GYP-BOARD
FRAME
VOLUME DAMPER
AIR FLOW
USE CONICAL TAP WHERE DUCT SIZE &
ELEVATION PERMITS, OTHERWISE USE
CYLINDRICAL TAP
CLOSED END OF
BRANCH DUCT
OBD
DIFFUSER
FLEXIBLE DUCTWORK
TAP COLLAR
USE CONICAL TAP WHERE DUCT SIZE &
ELEVATION PERMITS, OTHERWISE USE
CYLINDRICAL TAP
BRANCH DUCT
VOLUME DAMPER
NOTE:
1. ALL FLEXIBLE DUCTWORK SHALL BE UL-181 CLASS 1 RATED.
LAY-IN FRAME
CEILING
D D D D
VOLUME DAMPER
AIR FLOW
24" MAX
UNLESS FOOT STRAP IS
PLACED UNDER A BOTTOM
REINFORCEMENT
SCREWS
1" MIN.
STRAP HANGERS LOAD RATED
FASTENERS
HANGER
BAND OF SAME SIZE AS
HANGER STRAP
36" DIA.
MAX.
24" DIA.
MAX.
LOWER HANGER ATTACHMENTS
TRAPEZE HANGERS
L
HANGERS MUST NOT
DEFORM DUCT SHAPE
HANGER RODS
OR STRAPS
BAND ONE HALF-ROUND MAY BE
USED IF DUCT IS MAINTAINED.
W
2" 2"
ROD
UPPER ATTACHMENT DEVICES
STRAP HANGER OR
HANGER ROD (NOT
SHOWN)
EXPANSION SHIELD
CONCRETE ANCHOR
NOTE: NOT PERMITTED IN
METAL ROOF DECK.
WASHER
METAL DECK
CONCRETE
FLOOR SLAB
NOTE:
EXPANSION SHIELD ANCHORS ARE PERMITTED IN SHEAR
ONLY. DO NOT INSTALL VERTICALLY.
FRICTION CLAMP OR
CADDY CLAMP
NUT & BOLT
STRAP HANGER OR
ALL THREAD ROD
HANGER ROD
RETAINING CLIP
6aC - CLAMP W/ RETAINING CLIP
6bC - CLAMP W/ LOCK NUT(OPTIONAL)
STRAP
HANGER
WASHER MAY BE OMITTED
WITH 100 LB. MAX. LOAD ON
22 GA STRAP WHEN
FOLDED.
BENT ALL THREAD
HANGER ROD
SLOT IN DECK
HANGER STRAP
BOLT, PIN OR SCREW
PENETRATION
NOTE:
1.
2.
3.
4.
5.
ACCESS DOORS SHALL BE GASKETED AND HINGED TO OPEN
AGAINST FAN OPERATING PRESSURE TO PREVENT AIR LEAKAGE.
MINIMUM ACCESS DOOR WIDTH SHALL BE 24" [600mm].
ACCESS DOOR HEIGHT SHALL BE DETERMINED BY UNIT CASING
BUT NOT TO EXCEED 6'-0" [1800mm].
ACCESS DOORS ON FAN SUCTION SHALL OPEN OUTWARD.
ACCESS DOORS ON FAN DISCHARGE SIZE SHALL OPEN INWARD.
14 15 1613121110987654321
AIR INTAKE FOR MISSION
CRITICAL FACILITIES, SEE
VA STANDARD DETAILS.
RETURN AIR INTAKE.
MIN CLEARANCE - 36"
COIL PULL DISTANCE
AIR HANDLING UNIT ITEM
MIN OA
TWO BEDS OF
FILTERS VAV
MIN OA THREE BEDS
OF FILTERS CV
100% OA
TWO BEDS
OF FILTERS CV
100% OA
THREE BEDS OF
FILTERS CV
* MIXING BOX 1 YES YES NO NO
* BLENDER SECTION 2 YES YES NO NO
PRE-FILTERS (SIDE
ACCESS)
3 YES YES YES YES
INSPECTION
SECTION, SMALL
4 YES YES YES YES
AFTER FILTER (SIDE
ACCESS)
5 YES YES YES YES
ACCESS SECTION,
MED-LARGE
6 YES YES YES YES
* HEAT RECOVERY COIL 7 NO NO YES YES
ACCESS SECTION,
MED-LARGE
8 NO NO YES YES
* PRE-HEAT COIL 9 YES YES YES YES
INSPECTION
SECTION,SMALL
10 YES YES YES YES
HUMIDIFIER 11 YES YES YES YES
COOLING COIL 12 YES YES YES YES
FAN 13 YES YES YES YES
* DIFFUSER PLATE 14 NO NO NO YES
ACCESS
SECTION,MED-LARGE
15 NO NO YES YES
* HEPA FILTER 16 NO NO NO YES
DISCHARGE PLENUM
(VERTICAL)
17 YES YES YES YES
* AS REQUIRED
ACCESS DOOR
NOTE 3
SUPPLY
STEAM HUMIDIFIER
42" MAX
ACCESS DOOR
NOTE 3
NOTE 1
AIR HANDLING UNIT
NOTE 3
ROUTE TO
FLOOR SINK
3'-0" 3'-0"
NOTES:
1. TRANSITION WELDED STAINLESS STEEL 3' UPSTREAM OF HUMIDIFIER AND 3'
DOWNSTREAM OF HUMIDIFIER.
2. INTEGRAL STAINLESS STEEL DRAIN PAN SLOPE FROM ALL DIRECTIONS TO DRAIN
CONNECTION. SLOPE 0.125" PER 1'-0".
3. PROVIDE MIN. 18" WIDE ACCESS DOOR DIRECTLY UPSTREAM AND DOWNSTREAM OF
HUMIDIFIER.
NOTES:
1. LATCHES SHALL BE OF THE WEDGE TYPE TO CLOSE DOORS TIGHTLY.
2. HINGES ON THE ACCESS DOORS SHALL HAVE NON-CORROSIVE PINS.
3. SEE SMACNA 2005, FIGURE 9-15
ACCESS DOOR
ACCESS PANEL
SECTION "B-B"
SECTION "A-A"
INSULATION
GASKET
DUCT
INSULATION
"A"
"A"
HANDLE INSIDE
NEOPRENE GASKET
CASING
FLEXIBLE WASHER
FACTORY FABRICATED
LATCH/HANDLE
1-1/2" MIN.
INSULATION
"B" "B"
NOTES:
1. THE INTERIOR SURFACE OF ALL RADIUS ELBOWS SHALL BE MADE ROUND.
2. ALL STANDARD RADIUS ELBOWS CAN BE SUBSTITUTED WITH SHORT RADIUS ELBOWS.
ALL SHORT RADIUS ELBOWS SHALL HAVE VANES. VANES SHALL BE CONSTRUCTED,
SUPPORTED AND FASTENED AS RECOMMENDED BY SMACNA.
3. FOR R < 1-1/2 W, VANES SHALL BE USED.
R SHALL
EQUAL OR
BE
GREATER
THAN W.
W
R
STANDARD RADIUS OR
LONG RADIUS ELBOW
R SHALL
EQUAL OR
BE
GREATER
THAN 1/3W.
R SHALL
EQUAL OR
BE
GREATER
THAN 1/6W.
SHORT RADIUS ELBOW
WITH ONE VANE
SHORT RADIUS ELBOW
WITH TWO VANES
W W
2/3 W
1/2 W
VANE
VANER
R
1/
W
1/6 W
1/
W
W
W1
NOTES:
1. ALL VANE ELBOWS SHALL BE CONSTRUCTED AND INSTALLED AS
DETAILED BY SMACNA.
2. WHEN W1 DOES NOT EQUAL W2, VANE SHALL BE SINGLE THICKNESS
VANE TYPE REGARDLESS OF W DIMENSION.
3. ALL SINGLE THICKNESS VANES SHALL HAVE A 2" RADIUS, 1 1/2"
MAXIMUM SPACE BETWEEN VANES AND A 3/4" TRAILING EDGE.
4. WHEN W EQUALS W2 AND W1…