This solicitation seeks bids for site preparation work to replace a CT scan at the Philadelphia VA Medical Center. The Department of Veterans Affairs requires renovations including floor replacement, new finishes, wall changes, and revisions to HVAC, electrical and plumbing systems. Drawings and specifications are included in the solicitation package available on SAM.gov as of February 9, 2021. Bids are due on March 17, 2021. The award will be a firm fixed-price contract for work expected to take 220 calendar days to complete. Only verified Service-Disabled Veteran-Owned Small Businesses are eligible to bid on this set-aside opportunity.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Abstract of Offers 3-24-2021.pdf | ||
| 36C24421B0007 0004.docx | DOCX document | |
| 36C24421B0007 0003.docx | DOCX document | |
| 36C24421B0007 0002.docx | DOCX document | |
| Site Visit Sign-in Sheet 02.16.2021.pdf | ||
| Bid Sheet.docx | DOCX document | |
| Calculation of Self Performed Work.pdf | ||
| 21717 CT SCAN SPECS - VOL 2.pdf | ||
| Equipment Rerence Drawings 1-14-2021.pdf | ||
| CT Scan Bid Set R1 - Stamped - Drawings - Dated 1-11-2021.pdf | ||
| 21717 CT SCAN SPECS - VOL 1 .pdf | ||
| 36C24421B0007_2.docx | DOCX document |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:
Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 02-22-2021 642-21-1-526-0003
642-CSI-118
00244 Department of Veterans Affairs Network Contracting Office 4 Philadelphia PA 19104 00244 Department of Veterans Affairs Network Contracting Office 4 Philadelphia PA 19104 To all Offerors/Bidders
36C24421B0007 02-09-2021
X X X
THE PURPOSE OF AMENDMENT 0001 IS HEREBY ISSUED TO RESPOND TO REQUEST FOR
INFORMATION (RFI'S), INCLUDE THE BID SHEET AND
POST THE SITE VISIT SIGN-IN SHEET (ATTACHED).
BID DUE DATE REMAINS UNCHANGED OF MARCH 17, 2021 AT 1:00PM LOCAL TIME.
PLEASE RETURN A SIGNED COPY OF THIS AMENDMENT WITH YOUR BID.
ALL
OTHER TERMS AND CONDITIONS REMAIN THE SAME.
MAUREEN JACKSON
CONTRACT SPECIALIST
Amendment 0001 36C24421B0007
QUESTIONS & ANSWERS
1. CONSIDERING THERE IS A LEAD LINED CEILING IN THE CT ROOM, IT WOULD BE IDEAL FOR COORDINATION IF THE GENERAL CONTRACTOR (OR OTHERS) INCLUDED THE STRUCTURAL STEEL WORK IN THEIR SCOPE OF WORK. OUR PRICE WOULD BE REDUCED IF WE ARE SIMPLY MOUNTING OUR LIFT RAILS TO STRUT (PROVIDED BY OTHERS) AT THE CEILING LEVEL. CAN YOU COMMENT ON WHETHER THE GC IS PROVIDING THE STRUCTURAL STEEL IN THEIR SCOPE?
ANSWER: YES, THE STRUCTURAL STEEL IS IN THE GENERAL CONTRACTOR’S SCOPE OF WORK.
2. REQUEST TO CONFIRM THE BID DEDUCTS.
ANSWER: THERE IS ONE (1) BID DEDUCT, DEDUCT ALTERNATE #1 - REMOVE WALL BASE AND EXISTING FLOOR FINISHES. DO NOT DISTURB EXISTING LEAD SHIELDING. PATCH ANY DAMAGED LEAD SHIELDING (ALLOW FOR 10 PATCHES AT 2'x2') IN PREPARATION FOR NEW FLOOR FINISHES.
3. WHEN IS THE LAST DAY FOR RFIS
ANSWER: 1 WEEK PRIOR TO BID DUE DATE – MARCH 10, 2021.
“BID OPENING REMAINS MARCH 17, 2021 AT 1PM LOCAL TIME”
NOTE
FAILURE TO ACKNOWLEDGE AMENDMENTS MAY BE CAUSE FOR REJECTION OF OFFERS.