36C24418R0071-002.pdf
PDF 9 MB Posted
- Solicitation number
- 36C24418R0071
About this file
36C24418R0071 Specifications.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24418R0071-00005000.docx | DOCX document | |
| 36C24418R0071-00005001.pdf | ||
| 36C24418R0071-00004001.pdf | ||
| 36C24418R0071-00004000.docx | DOCX document | |
| 36C24418R0071-00003000.docx | DOCX document | |
| 36C24418R0071-00002000.docx | DOCX document | |
| 36C24418R0071-00002001.pdf | ||
| 36C24418R0071-003.pdf | ||
| 36C24418R0071-005.pdf | ||
| 36C24418R0071-001.docx | DOCX document | |
| 36C24418R0071-006.pdf | ||
| 36C24418R0071-004.pdf | ||
| 36C24418R0071-007.pdf | ||
| 36C24418R0071-00001000.docx | DOCX document | |
| 36C24418R0071-000.docx | DOCX document |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Construction Bid Documents
SPECIFICATIONS
Steam and Condensate Main Replacement Oval 2
VA Project No. 542-10-101
VA Medical Center Coatesville, PA
Miller-Remick LLC 1010 Kings Highway South
Building Two – 2nd Floor Cherry Hill, New Jersey 08034
September 30. 2016
VA Medical Center, Coatesville, PA VA Project No. 542-10-101 Steam & Condensate Main Replacement Construction Bid Documents: 09/30/16
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-15 01 12 00 Photographs 01 33 23 Shop Drawings, Product Data, and Samples 07-15 01 35 26 Safety Requirements 10-14 01 45 29 Testing Laboratory Services 06-15 01 57 19 Temporary Environmental Controls 01-11 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 09-13
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 02-15
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 02-16
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 Firestopping 02-16 07 92 00 Joint Sealants 10-15
DIVISION 09 – FINISHES
09 91 00 Painting 05-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 09-15 22 05 12 General Motor Requirements for Plumbing Equipment 09-15 22 05 19 Meters and Gages for Plumbing Piping 09-15 22 05 23 General-Duty Valves for Plumbing Piping 09-15 22 07 11 Plumbing Insulation 09-15 22 11 00 Facility Water Distribution 09-15 22 11 23 Domestic Water Pumps 09-15 22 35 00 Domestic Water Heat Exchangers 09-15
00 01 10-2
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 02-15 23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment 11-10
23 07 11 HVAC and Boiler Plant Insulation 02-15 23 08 00 Commissioning of HVAC Systems 06-13 23 11 23 Facility Natural-Gas Piping 02-15 23 21 13 Hydronic Piping 09-12 23 21 23 Hydronic Pumps 02-15 23 22 13 Steam and Condensate Heating Piping 02-15 23 22 23 Steam Condensate Pumps 02-15 23 25 00 HVAC Water Treatment 02-15 23 55 33 Fuel Fired Unit Heaters
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 07-13 26 05 26 Grounding and Bonding for Electrical Systems 12-12 26 05 33 Raceway and Boxes for Electrical Systems 05-14 26 08 00 Commissioning of Electrical Systems 06-13 26 24 16 Panelboards 05-14 26 27 26 Wiring Devices 01-16 26 29 11 Motor Controllers 08-14 26 29 21 Enclosed Switches and Circuit Breakers 12-12 26 42 00 Cathodic Protection 12-12 26 51 00 Interior Lighting 08-14
DIVISION 31 – EARTHWORK
31 20 11 Earthwork (Short Form) 10-12
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 05-13
DIVISION 33 – UTILITIES
33 51 00 Natural-Gas Distribution 10-11 33 63 00 Steam Energy Distribution 06-13
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWINGS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
GI-001 COVER SHEET AND DRAWING INDEX
G-002 CONSTRUCTION STAGING AND PIPE BASEMENT AND UPPER MER ACCESS
AREAS
CIVIL
C-001 CIVIL NOTES AND ABBREVIATIONS
C-101 CIVIL KEY SITE PLAN
C-501 CIVIL MISCELLANEOUS DETAILS No. 1
C-502 CIVIL MISCELLANEOUS DETAILS No. 2
SHEET 1 OF 4 SHEET INDEX
SHEET 2 OF 4 UTILITY LOCATION PLAN
SHEET 3 OF 4 UTILITY LOCATION PLAN
SHEET 4 OF 4 UTILITY LOCATION PLAN
STRUCTURAL
S-001 BUILDINGS 38, 39, 57, AND 58 MECH. ROOM STEEL MODIFICATIONS
GENERAL NOTES - STRUCTURAL
S-101 BUILDING 38 MECHANICAL ROOM PLAN - PLATFORM
S-102 BUILDING 39 MECHANICAL ROOM PLAN - PLATFORM
S-103 BUILDING 57 MECHANICAL ROOM PLAN - PLATFORM
S-104 BUILDING 58 MECHANICAL ROOM PLAN – STEEL FRAMING
S-301 BUILDING 38 MECH ROOM SECTION(S) - PLATFORM
S-302 BUILDING 39 MECH ROOM SECTION(S) - PLATFORM
S-303 BUILDING 57 MECH ROOM SECTION(S) - PLATFORM
S-304 BUILDING 58 MECH ROOM PLAN – STEEL FRAMING
S-501 B38, B39, B57, AND B58 MECHANICAL ROOMS SECTIONS AND
DETAILS, SHEET 1
S-502 B38, B39, B57, AND B58 MECHANICAL ROOMS SECTIONS AND
DETAILS, SHEET 2
00 01 15 - 2
MECHANICAL
M-001 MECHANICAL SYMBOLS, ABBREVIATIONS, AND NOTES
MS-101 MECHANICAL SITE KEY PIPING PLAN
MS-401 MECHANICAL SITE PARTIAL SITE PIPING PLAN AND PROFILE
MD-101 MECHANICAL DEMOLITION BUILDING 38, PIPE BASEMENT & SUB-
BASEMENT
MD-102 MECHANICAL DEMOLITION BUILDING 39, PIPE BASEMENT & SUB-
BASEMENT
MD-103 MECHANICAL DEMOLITION BUILDING 57, PIPE BASEMENT & SUB-
BASEMENT
MD-104 MECHANICAL DEMOLITION BUILDING 58, PIPE BASEMENT & SUB-
BASEMENT
MD-105 MECHANICAL DEMOLITION BUILDING 59, BASEMENT
MD-106 MECHANICAL DEMOLITION BUILDING 139, PIPE BASEMENT
MD-107 MECHANICAL DEMOLITION BUILDINGS 18, 36, AND 40
MD-108 MECHANICAL DEMOLITION CONNECTING CORRIDOR Nos. 1, 2, AND 3
MD-109 MECHANICAL DEMOLITION CONNECTING CORRIDORS Nos. 4 AND 5
MD-401 MECHANICAL DEMOLITION BUILDINGS 38, 39, AND 57, PIPE
BASEMENT MER ENLARGED PLANS
MD-402 MECHANICAL DEMOLITION BUILDINGS 58 AND 59, PIPE BASEMENT AND
BASEMENT MER ENLARGED PLANS
MD-403 MECHANICAL DEMOLITION BUILDING 139, PIPE BASEMENT AND BSMT
PENTHOUSE MER ENLARGED PLANS
MP-101 MECHANICAL PIPING BUILDING 38, PIPE BASEMENT, BASEMENT AND
SUB-BASEMENT – NEW WORK
MP-102 MECHANICAL PIPING BUILDING 39, PIPE BASEMENT AND SUB-
BASEMENT – NEW WORK
MP-103 MECHANICAL PIPING BUILDING 57, PIPE BASEMENT AND SUB-
BASEMENT – NEW WORK
MP-104 MECHANICAL PIPING BUILDING 58, PIPE BASEMENT AND SUB-
BASEMENT – NEW WORK
MP-105 MECHANICAL PIPING BUILDING 59, BASEMENT AND SUB-BASEMENT –
NEW WORK
MP-106 MECHANICAL PIPING BUILDING 139, PIPE BASEMENT, SUB-BASEMENT
AND PENTHOUSE – NEW WORK
MP-107 MECHANICAL PIPING BUILDINGS 36 & 40 – NEW WORK
MP-108 MECHANICAL PIPING CONNECTING CORRIDORS Nos. 1, 2, AND 3 –
NEW WORK
MP-109 MECHANICAL PIPING CONNECTING CORRIDORS Nos. 4 & 5 – NEW WORK
MP-301 MECHANICAL PIPING BUILDINGS 38, 39, 57, AND 58 MER SECTIONS
– NEW WORK
MP-302 MECHANICAL PIPING BLDGS 38, 39, 57, AND 58 EXTERIOR
ELEVATIONS – NEW WORK
00 01 15 - 3
MP-401 MECHANICAL PIPING BLDGS 38, 39, AND 57, PIPE BASEMENT MER
ENLARGED PLANS – NEW WORK
MP-402 MECHANICAL PIPING BLDGS 58 & 59, PIPE BASEMENT AND BASEMENT
MER ENLARGED PLANS – NEW WORK
MP-403 MECHANICAL PIPING BLDG 139, PIPE BSMT AND PENTHOUSE MER
ENLARGED PLANS – NEW WORK
MP-501 MECHANICAL PIPING MISCELLANEOUS DETAILS No. 1
MP-502 MECHANICAL PIPING MISCELLANEOUS DETAILS No. 2
MP-503 MECHANICAL PIPING MISCELLANEOUS DETAILS No. 3
MP-504 MECHANICAL PIPING UNDERGROUND PRE-ENGINEERED PIPING SYSTEM
MISC. DETAILS
MP-505 MECHANICAL PIPING ABOVEGROUND PRE-ENGINEERED PIPING SYSTEM
MISC. DETAILS
MP-601 MECHANICAL PIPING PIPE MATERIAL SCHEDULE No.1
MP-602 MECHANICAL PIPING PIPE MATERIAL SCHEDULE No. 2
MP-603 MECHANICAL PIPING MISCELLANEOUS EQUIPMENT SCHEDULES No. 1
MP-604 MECHANICAL PIPING MISCELLANEOUS EQUIPMENT SCHEDULES No. 2
MP-605 MECHANICAL PIPING MISCELLANEOUS EQUIPMENT SCHEDULES No. 3
MP-606 MECHANICAL PIPING OVAL 2 SIMPLIFIED CONDENSATE SYSTEM FLOW
DIAGRAM
MP-607 MECHANICAL PIPING BLDGS 38, 39, AND 57 SIMPLIFIED STEAM AND
CONDENSATE SYSTEM FLOW DIAGRAM
MP-608 MECHANICAL PIPING BLDGS 58 AND 59 SIMPLIFIED STEAM AND
CONDENSATE SYSTEM FLOW DIAGRAM
MP-609 MECHANICAL PIPING BLDG 139 SIMPLIFIED STEAM AND CONDENSATE
SYSTEM FLOW DIAGRAM
MP-610 MECHANICAL PIPING BUILDING 39 SIMPLIFIED HOT WATER SYSTEM
FLOW DIAGRAM
PLUMBING
P-001 PLUMBING SYMBOLS, ABBREVIATIONS, AND NOTES
PD-401 PLUMBING DEMOLITION BUILDINGS 38, 39, AND 57 MER ENLARGED
PLANS
PD-402 PLUMBING DEMOLITION BUILDINGS 58, 59, AND 139 MER ENLARGED
PLANS
PL-401 PLUMBING NEW WORK BUILDINGS 38, 39, AND 57 MER ENLARGED
PLANS
PL-402 PLUMBING NEW WORK BUILDINGS 58, 59, AND 139 MER ENLARGED
PLANS
PL-501 PLUMBING MISCELLANEOUS FLOW DIAGRAMS
PL-601 PLUMBING MISCELLANEOUS EQUIPMENT
00 01 15 - 4
ELECTRICAL
E-001 ELECTRICAL SYMBOLS, ABBREVIATIONS, AND NOTES
E-002 ELECTRICAL GENERAL NOTES
ED-401 ELECTRICAL BUILDINGS 38, 39, AND 57 MER ENLARGED PLANS
DEMOLITION
ED-402 ELECTRICAL BUILDINGS 58 AND 59 MER ENLARGED PLANS DEMOLITION
ED-403 ELECTRICAL BUILDING 139 AND PENTHOUSE MER ENLARGED PLANS
DEMOLITION
EP-401 ELECTRICAL BUILDINGS 38, 39, AND 57 MER ENLARGED PLANS NEW
WORK
EP-402 ELECTRICAL BUILDINGS 58 AND 59 MER ENLARGED PLANS NEW WORK
EP-403 ELECTRICAL BUILDING 139 AND PENTHOUSE MER ENLARGED PLANS NEW
WORK
EP-404 ELECTRICAL BUILDINGS 36 AND 40 NEW WORK
E-501 ELECTRICAL SCHEDULES AND DETAILS
E-601 ELECTRICAL SINGLE LINE DIAGRAMS
- - - E N D - - -i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 RELATED SECTIONS
1.3 GENERAL INTENTION
1.4 STATEMENT OF BID ITEMS
1.5 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.6 CONSTRUCTION SECURITY REQUIREMENTS
1.7 OPERATIONS AND STORAGE AREAS
1.8 ALTERATIONS
1.9 DISPOSAL AND RETENTION
1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
1.11 RESTORATION
1.12 PROFESSIONAL SURVEYING SERVICES
1.13 LAYOUT OF WORK
1.14 AS-BUILT DRAWINGS
1.15 USE OF ROADWAYS
1.16 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.17 TEMPORARY TOILETS
1.18 AVAILIBILITY AND USE OF UTILITY SERVICES
1.19 TESTS
1.20 INSTRUCTIONS
1.21 PHOTOGRAPHIC DOCUMENTATION
1.22 HISTORIC PRESERVATION
01 00 00 - 1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 RELATED SPECIFICATIONS
A. Section 01 12 00, PHOTOGRAPHS.
1.3 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for The Steam and Condensate Main
Replacement project as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
Medical Center Contracting Officer’s Representative (COR).
C. Offices of Miller-Remick LLC, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer.
D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.4 STATEMENT OF BID ITEM(S)
A. ITEM I, The Steam and Condensate Main Replacement – Oval 2 project is for the removal and replacement of condensate piping routed throughout the Oval 2 interconnecting pipe tunnels, pipe basements and basements of buildings 38, 39, 57, 58, 59, 139. A portion of the condensate piping is direct buried underground from building 58 to 59. This project also includes removal and replacement of associated equipment and the decentralization of the steam system and addition of natural gas and gas fired equipment at buildings 36 and 40. This project includes but is not limited to the following:
1. The contractor is responsible to locate and identify any public or private underground utility. For public utilities, contractors must contact the Pennsylvania Public Utility Commission 'PA One Call' at
01 00 00 - 2
1-800-692-7380. The contractor is responsible to verify the location of all public utilities and all private utilities that may be exposed or could be impacted by the work and are within and adjacent to any excavations or underground work. The contractor shall enlist the assistance of the COR or appointed facility personnel to obtain their opinion as to the locations of underground utilities that may exist within the construction area and that may or may not be presented in the contract documents.
2. Shut down of the steam system must be minimized. The contractor shall plan and coordinate all required steam shut-downs with the
COR. Steam shut-downs are generally limited to 8-hours maximum.
Contractors shall develop a phasing plan using the existing steam valves; steam (exceed system pressure and temperature) rated hoses and new valves and fabricated pipe spools to achieve this objective.
Phasing plan subject to final approval by the VA. Final approved phasing plan shall not be grounds for a change order.
3. The existing domestic hot water systems in buildings 38, 39, 57, 58, 59 and 139 are being modified and will be affected during construction. The contractor shall provide temporary domestic hot water generating equipment and piping to provide domestic hot water during periods that the building domestic hot water equipment is not providing hot water to the building distribution system, other than scheduled shut-downs.
4. It is the intent of this project that all work will be accomplished and completed during warm seasons (approximately May 1 through
October 1) when building heating is not required. If construction extends beyond this, the Contractor will be required to provide temporary building heat as required to meet the heating demand, at no additional cost to the government.
5. All pipe basements are considered confined spaces. All contractors shall be OSHA trained and provide all required safety equipment and monitors for confine space entry.
a. All contractors entering any confined space shall request hot work and confined space permits from the Coatesville VA facility.
b. Contractors shall provide temporary lighting for pipe basement and tunnels.
01 00 00 - 3
c. Contractors shall provide the required OSHA ventilation rates when working in any areas considered confined spaces.
i. All confined spaces shall be purged with ventilation air for
30 minutes before contractor entry.
ii. To minimize dust into the buildings, contractors shall provide ventilation by means of exhaust fans for the pipe basements due to the existing dirt floors.
6. Upper access to the building sub-basement mechanical rooms shall be made utilizing existing windows and exterior wall openings at ventilation louvers locations. All ventilation louvers, fans and ductwork removed for such purposes shall be reinstalled and exterior walls sealed and made weathertight.
7. Prior to demolition, the contractor shall ensure that all existing vent registers located in the interconnecting corridors are in the closed position to prevent construction dust from migrating into occupied spaces.
8. Main access to the building pipe basements shall be made using the existing staired entryways at building 57 and 58. Lower access to the pipe basements can be also made utilizing existing the pipe basement windows at these buildings.
9. Access to the sub-basement mechanical rooms shall be made using the existing staired entryways from ground level.
10. Contractor shall perform the following pre-demolition and construction testing and surveys of the following existing conditions:
a. Perform a survey of the existing steam system located in the pipe tunnels to determine usage of all steam and condensate pipe branches. Document, submit and verify findings with the VA COR prior to demolition.
b. Perform testing of the affected hydronic systems to document pre-construction and post construction temperatures, flow rates and pressures. The results of the testing shall be documented in report formats and submitted to the VA COR and
A/E. Note: All post construction system values shall not show a negative impact on the post-construction system.
c. Perform functionality tests on the affected pneumatics and HVAC controls to evaluate and assess the systems
01 00 00 - 4 prior to construction. The results of these tests shall be presented and discussed with the VA COR.
i. The intent of this project is not to alter the existing control system other than replacing non-performing control valves with similar new valves or replacing existing electrical/control panels.
11. Contractor shall submit a fixed price cost for the testing of ten
(10) steam drip pocket assemblies, adjacent piping and steam main traps (See Drawing MS-101).
a. The existing 6” & 8” steam main routed throughout Oval 2 was installed with ten (10) drip legs and trap stations.
Contractor shall perform a steam trap survey of all existing steam main traps with the results shown in a steam trap assessment report presented to the VA COR.
b. Contractor shall perform nondestructive testing using radiography on all 6” and 8” steam drip legs, including tees
(or elbows), pipe and caps and 10 foot section of adjacent piping to evaluate pipe anomaly threats (i.e. external and internal pipe corrosion and stress corrosion cracking etc.).
All results of these tests shall be presented to the VA COR in a detailed assessment report.
12. Contractor shall remove each existing steam trap assembly and provide new float and thermostatic steam trap station with a valved bypass for traps that are tested inadequate (Reference Bid Item No.
11, and Alternate No. 2. Note: All steam trap assemblies shall be provided in accordance with VA CAD Detail No. SD232111-01.DWG (See
Drawing MS-101).
13. Contractor shall remove and replace steam main drip pockets that are tested inadequate (Reference Bid Item No. 11). Provide a unit price deduct for each drip pocket assembly determined by the COR to be existing-to-remain. Contractor shall provide new, fully insulated and jacketed 6” and 8” drip leg assemblies and a portion of the adjacent piping which shall include the following:
a. 6” & 8” Steam Main Drip Pockets.
Note: All steam line drip pockets shall be 18” from bottom of horizontal steam main to bottom of pipe cap and be fabricated
01 00 00 - 5 in accordance with VA CAD Detail No. SD232111-01.DWG (See
Drawing G-002).
i. 6” and 8x6x8” tee, butt weld, carbon steel, schedule 40
ii. 6” cap, butt weld, carbon steel, schedule 40
iii. 6” schedule 40, carbon steel, ASTM A53 or 106
iv. Weldolet, Sockolet or Threadolet branch connections for trap piping and drain.
v. 3/4" drain valve and schedule 80 carbon steel pipe.
b. 6” Steam Main
i. 10 feet of 6” schedule 40, carbon steel, ASTM A53 or 106
c. 8” Steam Main
i. 10 feet of 8” schedule 40, carbon steel, ASTM A53 or 106
d. Insulation is addressed in Bid Item 37.
14. Remove existing condensate (medium pressure return (MPR), low pressure return (LPR), pumped condensate (PC), vacuum return (VR) piping, fittings, valves and appurtenances, which are routed throughout the pipe basements and pipe tunnels within Oval 2
(buildings 38, 39, 57, 58, 59, 139 and interconnecting pipe tunnels). Remove condensate branch piping, fittings, valves and appurtenance to points of disconnect.
15. Remove the denoted existing electric and steam pressure power pumps located within buildings 38, 39, 57, 58, 59 and 139. Cut and remove steam and condensate piping, fittings, valves and appurtenances from equipment to points of disconnect.
16. Remove domestic hot water generating equipment, equipment stands and hot water recirculation pumps located within buildings 38, 39, 57, 58, 59 and 139. Cut and remove steam, condensate, potable water, domestic hot water and hot water recirculation piping, fittings, valves and appurtenances from equipment to points of disconnects.
17. Remove existing steam to water shell and tube heat exchangers located within building 38, 39, 57, 58, 59 and 139. Remove steam, condensate, and hot water supply and return piping, fittings, valves, control valves and appurtenances from heat exchangers to points of disconnects. Temporarily cap all disconnected pneumatic control tubing for reconnection to new equipment and valves.
18. Remove the denoted existing hydronic heating water pumps and inertia pads located within building 39. Remove hot water supply and return
01 00 00 - 6 piping, fittings, valves and appurtenances from pumps to points of disconnect.
19. Remove the hydronic heating and chilled water system expansion tanks located within buildings 38, *39, 57 and 58. Remove associated piping from expansion tanks to points of disconnect.
20. Remove the denoted existing steam pressure reducing valves and/or stations located within buildings 38, 39, 57, 58, 59 and 139. *The existing chilled water expansion tank located in building 39 shall remain.
21. Remove existing chilled and hydronic heating water piping, fittings, valves and appurtenances located in building 39 for access to new platform. Provide new rerouted chilled and hydronic heating piping, fittings, valves and appurtenances.
22. Remove denoted existing steam main isolation valves.
23. Remove existing motor control centers located within building 39 and building 57.
24. Contractor is responsible for providing all pipe through exterior/interior wall, floor and roof penetrations necessary for the installation of this project. Unless noted otherwise, all pipe through wall penetrations must be sleeved.
a. All pipe penetrations through fire-rated exterior and interior walls must be provided with a UL-tested and approved assembly while maintaining the integrity of the wall's fire-resistance rating(s). All pipe penetrations through exterior walls must be properly sealed and made weather-tight.
b. All pipe through exterior wall and roof penetrations shall be sleeved and made weather-tight.
c. All pipe through building through wall penetrations shall be un-sleeved and made water-tight using link-seal modular seals with stainless steel hardware.
25. Provide new low pressure return (LPR), medium pressure return (MPR) and pumped condensate (PC) piping, fittings, and valves. All MPR &
PC piping routed throughout the pipe basements and interconnecting pipe tunnels throughout Oval 2 (buildings 38, 39, 57, 58, 59, 139 and pipe tunnels) shall be provided with aboveground pre-engineered/pre-insulated and jacketed piping. Provide new condensate
01 00 00 - 7 branch piping, fittings, valves and appurtenances from points of reconnection to condensate main.
a. All new medium pressure return (MPR), low pressure return (LPR) and pumped condensate (PC) piping above ¾” and routed throughout the building pipe basements and interconnecting pipe tunnels shall be a pre-insulated/pre-engineered piping system as specified in the project contract documents.
26. Provide new direct buried pre-insulated/pre-engineered pumped condensate pipe from building 58 to building 59.
27. Provide new electric condensate pumps for building heating and process in buildings 38, 39, 57, 58, 59 and 139.
28. Provide new vented flash tanks and supports in buildings 38, 39, 57, 58, 59 and 139.
29. Provide a new vented receiver in building 59.
30. Provide new domestic hot water generating equipment, supports
(building 59) and domestic hot water master mixing valves within buildings 38, 39, 57, 58, 59 and 139. Basis of design domestic water heating equipment was specified for replacement “in-kind” in buildings 59 and 139. Provide new steam, condensate, potable water, domestic hot water and hot water recirculation piping, fittings, valves, hot water recirculation circulators and appurtenances from points of reconnection to domestic water heating equipment.
31. Provide new steam to water shell and tube heat exchangers located within building 38, 39, 57, 58, 59 and 139. All basis of design equipment was specified for replacement “in-kind”. Provide new steam, condensate, and hot water supply and return piping, fittings, valves and appurtenances from points of reconnection to heat exchangers.
32. Provide new hydronic heating water pumps and inertia pads located in building 39. Provide new hot water piping, fittings, valves and appurtenances from points of reconnection to pumps.
33. Provide new hydronic heating and chilled water system expansion tanks in buildings 38, 39, 57 and 58. Provide new piping, fittings and appurtenances from points of reconnection to expansion tanks.
34. Provide new steam pressure reducing valves and/or stations located in buildings 38, 39, 57, 58, 59 and 139.
01 00 00 - 8
35. Provide new chilled and hydronic heating water piping, fittings, valves and appurtenances located in building 39.
36. Provide new steam main isolation valves, gaskets and bolt sets.
a. All existing 6” and 8” medium pressure steam main isolation valves located in Oval 2 shall be removed and provided with new valves.
37. All existing 6” and 8” medium pressure steam (MPS shall be reinsulated and jacketed.
a. All existing MPS pipe shall be insulated with four (4) layers of Aspen Aerogel Pyrogel XT-E 10mm thick blanket insulation (basis of design), total installed thickness 40mm. Each layer of insulation shall be secured with stainless steel bands, placed
18" on center and jacketed with a pvc jacket.
38. Provide new elevated structural steel equipment racks, access platforms and ladders in buildings 38, 39 and 57.
39. Provide new structural steel racks for heat exchangers.
40. All steel to be galvanized with the following exception: Guard rails and ladders shall be painted safety yellow. See structural drawings.
41. Provide new pump motor starters in buildings 39 and 57.
42. The existing mechanical equipment is currently being served by existing motor control panel ‘MCP-39A’ (208Y/120V, 3ph, 4w, 225A) locally mounted in sub-basement. MCP-39A will be removed and replaced with a new circuit breaker panel ‘MP-39A’ (208Y/120V, 3ph, 4w, 225A) in new location to avoid new mechanical construction of sub-basement. Existing equipment circuited to existing panel, that is to remain, will be re-circuited to new panel and provided with new starter/disconnects sized accordingly.
43. The existing mechanical equipment is currently being served by existing motor control panel ‘MCP-57A’ (208Y/120V, 3ph, 4w, 225A) locally mounted in sub-basement room. MCP-57A will be removed and replaced with a new circuit breaker panel ‘MP-57A’ (208Y/120V, 3ph, 4w, 225A) in new location to avoid new mechanical construction of sub-basement. Existing equipment circuited to existing panel, that is to remain, will be re-circuited to new panel and provided with new starter/disconnects sized accordingly.
01 00 00 - 9
44. Provide new 208V, 3ph electrical circuiting from existing local ‘MCP’ panel as required for new duplex condensate pump package in buildings 38, 58, 59 and 139.
45. Provide new 208V, 3ph electrical circuiting from new local ‘MP’ panel as required for new duplex condensate pump package in buildings 39 and 57.
46. Provide new 120V, 1ph circuit from local power panel for new domestic water heater control panel circuit in buildings 38, 39, 57, 58, 59 and 139.
47. Provide new 120V, 1ph circuit from local power panel for new domestic water re-circulation pump in buildings 38, 39, 57, 58, 59 and 139. The pumps will be reconnected to their respective electrical service source when possible. The existing conductors and conduit will be reused wherever possible.
48. Electrical Contractor shall be responsible for disconnecting existing control circuits from NEMA starters in existing ‘MCP-39A’ and ‘MCP-57A’ motor control panels. Retain control circuit wiring from local LTCP control panels for equipment that is to remain as indicated on electrical single line diagrams. Extend and modify existing control circuits for reconnection to new NEMA starters located next to replacement ‘MP’ panels.
49. Remove and cap the steam and condensate branch piping to buildings 36 and 40 within the basement of building 18.
50. Contractor shall coordinate the installation of natural gas service to buildings 36 and 40. Coordinate with the COR and the gas utility
(PECO). The utility shall supply gas service, regulator and meter at street side of building 40.
51. Provide underground natural gas piping, fittings, valves and appurtenances from PECO meter/regulator (building 40) to building
36.
52. Provide natural gas piping, vented, gas fired unit heaters and electric unit heater in building 36.
53. Provide venting of unit heaters in building 36.
54. Provide natural gas piping, gas fired, vented cabinet heater in building 40.
55. Provide natural gas piping, fittings, valves and appurtenances from PECO meter/regulator to cabinet heater in building 40.
01 00 00 - 10
56. Provide venting of unit heaters in building 40.
57. Saw-cut and remove existing concrete walkway(s), curb(s) and asphalt drives as necessary for the installation of the new underground natural gas and condensate piping systems.
58. Provide new sections of concrete walkway(s), curb(s) and asphalt drives to replace those sections.
59. Replacement of existing trees, shrubs, plantings, etc. damaged by the Work. Landscape and seed areas disturbed during construction.
Restore site grades, grass areas, site road and walkway surfaces, and signage to pre-construction conditions.
60. Contractor shall repair all existing architectural either damaged or altered during demolition and construction.
61. Contractor shall test adjust & balance the completed system. All balancing work shall be done under the direct supervision of an AABC or NEBB-qualified supervisor who shall certify the results.
62. Contractor is responsible for all cleaning, hydrotesting, and coordination of inspections of the new piping systems in accordance with the project documents and all applicable codes.
63. Removal and disposal of all construction debris including concrete, asphalt, etc. that is being replaced by the new natural gas and condensate piping system or removed to construct the work.
B. ALTERNATE NO.1:
Contractor shall provide a deduct cost for the removal of these items from their base bid. Each item shall be shown as a separate deduct cost.
1. Item 1A: Delete the replacement of insulation around existing 6” and 8” MPS pipe located above-floor in Building 59. Instead, patch and repair existing mineral wool insulation and scrim to match existing intact insulation. For bid purposes, use 15% of total lengths of existing insulation requiring patches and repairs.
2. Item 1B: Delete the replacement of insulation around 50% of existing 6” and 8” MPS pipe located in crawl spaces. For the existing-to-remain mineral wool insulation (covering 50% of the MPS in the crawl spaces), spot patch as required Instead, patch and repair existing mineral wool insulation and scrim to match existing intact insulation and provide a PVC jacket around the entire length of this existing-to-remain insulation of 6” and 8” MPS. For bid purposes, 01 00 00 - 11 use forty (40) 2-foot sections requiring patches and repairs. The existing-to-remain insulation is to be repaired and jacketed prior to demolition.
C. ALTERNATE NO. 2:
Contractor shall provide a deduct unit cost for the removal of each of these items from their base bid. Each item shall be shown as a separate deduct cost.
1. Item 2A: Contractor shall submit cost for providing removal of existing steam trap assembly and providing a new float and thermostatic steam trap station with a valved bypass. Note: All steam trap assemblies shall be provided in accordance with VA CAD
Detail No. SD232111-01.DWG.
2. Item 2B: Contractor shall submit unit price cost for the removal and replacement of steam main drip pockets. Contractor shall provide new, fully insulated and jacketed 6” and 8” drip leg assembly and a portion of the adjacent piping which shall include the following:
a. 6” & 8” Steam Main Drip Pockets.
Note: All steam line drip pockets shall be 18” from bottom of horizontal steam main to bottom of pipe cap and be fabricated in accordance with VA CAD Detail No. SD232111-01.DWG.
i. 6” and 8x6x8” tee, butt weld, carbon steel, schedule 40
ii. 6” cap, butt weld, carbon steel, schedule 40
iii. 6” schedule 40, carbon steel, ASTM A53 or 106
iv. Weldolet, Sockolet or Threadolet branch connections for trap piping and drain.
v. 3/4" drain valve and schedule 80 carbon steel pipe.
b. 6” Steam Main
i. 10 feet of 6” schedule 40, carbon steel, ASTM A53 or 106
c. 8” Steam Main
i. 10 feet of 8” schedule 40, carbon steel, ASTM A53 or 106
d. Insulation is addressed in Bid Item 37.
D. ALTERNATE NO. 3 (Reference Sketch SK-608A):
Contractor shall provide Add Alternate cost for the following:
1. Item 3A: In addition to equipment and valve replacements, replace all of the condensate piping in Building 59 Service Room
(Mechanical Room B10) and the steam piping from the 8-inch main
01 00 00 - 12 to the heat exchangers (HX), and in doing so, raising the new HX, adding flash tanks and reconfiguring the steam and condensate piping to facilitate effective drainage. Reference flow diagram and thumbnail sketches on reference sketch SK-608A. The add alternate cost shall include only the additional materials and labor for the additional work. Do not include Base Bid work in the price. Include:
a. Equipment supports to raise domestic water heat exchanger package approximately 27 inches additional,
b. Remove and reorient the steam inlet strainer for the packaged domestic water HX, so that the strainer is mounted horizontally and on its side within the steam pipe,
c. Equipment supports and housekeeping pad to raise heating water HX approximately 18 inches additional.
d. Reconfigure steam supplies for proper flow at PRV and TCV.
e. Revise existing vertical heating water supply and return, and domestic hot and cold water at elevated heat exchangers.
Relocate isolation valves, (2) DDC temperature sensors and (3) thermometers associated with the HX.
f. Provide new drain valve and revise approximately 12 inches of 3/4-inch piping at bottom of heating water air separator to allow space for the HX steam supply to be run higher.
g. Provide flash tanks 59-FT-2 and -3 and vent the flash tanks to the outside.
h. Provide insulation as specified.
1.5 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.6 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
01 00 00 - 13
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the COR for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
01 00 00 - 14
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. Separate permits shall be issued for General Contractor and
Contractor’s employees for parking in designated areas only.
1.7 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways
01 00 00 - 15 constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
(FAR 52.236-10)
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workmen are subject to rules of Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence
01 00 00 - 16 of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
I. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
To insure such executions, Contractor shall furnish the COR with a schedule of approximate phasing and dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing and dates to insure accomplishment of this work in successive phases mutually agreeable to COR and Contractor.
J. Buildings 38, 39, 57, 58, 59, 139 will be occupied during performance of work.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to VA personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access. Coordinate alteration work in
01 00 00 - 17 areas occupied by Department of Veterans Affairs so that Medical
Center operations will continue during the construction period.
I. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.
Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm
(one inch) above grade. Remove the fence when directed by COR.
J. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance.
K. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, and condensate pipes, they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS and 28 05 11, REQUIREMENTS FOR
ELECTRONIC SAFETY AND SECURITY INSTALLATIONS for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least
01 00 00 - 18 inconvenience to operations of Medical Cemetery. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
M. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
N. Coordinate the work for this contract with other construction operations as directed by the COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF
ROADWAYS.
1.8 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a signed report to the
Contracting Officer. This report shall list by rooms and spaces:
01 00 00 - 19
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and the COR.
B. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
C. Protection: Provide the following protective measures:
1. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
2. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.9 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
01 00 00 - 20
1. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
2. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract.
B. The Contractor shall protect from damage all existing improvements and utilities at or…