100_Percent_dwg_pdf.pdf

PDF 36 MB Posted

Attached to
Renovate Bldg 58 Basement and Infrastructure Project 542-15-203
Solicitation number
36C24418B0577
Issued by

About this file

100 Percent dwg pdf

View the file

Other files

File Type Posted
36C24418B0577-0003003.pdf PDF
36C24418B0577-0003004.pdf PDF
36C24418B0577-0003000.docx DOCX document
36C24418B0577-0003001.pdf PDF
36C24418B0577-0003006.pdf PDF
36C24418B0577-0003005.pdf PDF
36C24418B0577-0003002.pdf PDF
36C24418B0577-0001000.docx DOCX document
36C24418B0577.docx DOCX document
100_percent_Bid_Set_Specs_Combined.pdf PDF
36C24418B0577-000.docx DOCX document
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FIRE PROTECTION LEGEND

PIPING TO BE DEMOLISHED

PIPE TURNS UP

PIPE TURNS DOWN

CONTINUATION

TIE POINT INTO EXISTING

SHUT-OFF VALVE (BALL VALVE)

SPRINKLER PIPINGFP

CAPPED PIPE

INDICATING VALVE WITH TAMPER

SWITCH

FLOW SWITCH

LIGHT HAZARD - 0.10 GPM/1500 SQ. FT.

ORDINARY HAZARD GROUP 1 - 0.15 GPM/1500 SQ. FT.

ORDINARY HAZARD GROUP 2 - 0.20 GPM/1500 SQ. FT.

QUICK RELEASE, CONCEALED

HORIZONTAL SIDEWALL SPRINKLER

FM APPROVED QUICK RESPONSE,

UPRIGHT SPRINKLER

BACK FLOW PREVENTER

SHUT-OFF VALVE (GATE VALVE)

FS

SIGHT GLASS

Revisions: Date

Drawing Title:

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg. of

VA FORM 08-6231

# 58

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER:

ACG Project Number

17-113

FULLY SPRINKLERED

E

D C

B A

2 3 4 5 6 7

E D

C B

A

1 2 3 4 5 6 7

Date Checked Drawn

/2

/2

:5

:5

A

M

F-001

FIRE PROTECTION LEGEND,

ABBREVIATIONS, AND GENERAL NOTES

1 3SJP

JMN

RENOVATE BUILDING 58

BASEMENT &

INFRASTRUCTURE

COATESVILLE VAMC

COATESVILLE, PA 19320

17-113

04-27-18

542-15-203

100% CONSTRUCTION DOCUMENTS

1 THESE FIRE PROTECTION DRAWINGS ARE DIAGRAMMATIC IN NATURE. HOWEVER SPRINKLER HEAD TYPES AND APPROXIMATE LOCATIONS HAVE BEEN ESTABLISHED. THE FIRE PROTECTION LAYOUT INDICATED IS FOR REFERENCE ONLY. FINAL SYSTEM LAYOUT AND PIPE ROUTING

SHALL BE DETERMINED BY THE FIRE PROTECTION CONTRACTOR AND SHALL TAKE INTO CONSIDERATION THE BUILDING STRUCTURE, ARCHITECTURAL FEATURES AND SHALL BE COORDINATED WITH THE WORK OF OTHER TRADES. THE FIRE PROTECTION CONTRACTORS SHALL

PROVIDE WORKING DRAWINGS IN ACCORDANCE WITH NFPA 13 FOR REVIEW AND APPROVAL BY THE ENGINEER, ARCHITECT, AND COR.

2 COORDINATE FINAL SPRINKLER PLACEMENT AND PIPE ROUTING BETWEEN TRADES.

3 PLACE SPRINKLERS IN THE CENTER OF THE CEILING TILE IT IS SHOWN IN.

4 INSTALL VALVES IN A READILY ACCESSIBLE POSITION FOR OPERATION.

5 CONDUCT WORK IN ACCORDANCE WITH NFPA 13-2016, THE DEPARTMENT OF VETERANS AFFAIRS GUIDELINES, FIRE PROTECTION DESIGN

MANUAL 6TH EDITION, AND OTHER APPLICABLE CODES AND STANDARDS.

6 DESIGN OFFICE SPRINKLERS TO BE ORDINARY HAZARD QUICK RESPONSE SPRINKLERS WITH LIGHT HAZARD DENSITY OF 0.10 GPM/SQ. FT.

INITIAL DESIGN AREA BEFORE REDUCTION AS FOLLOWED BY NFPA 13 SHALL BE 1,500 SQ. FT.

7 DESIGN ELECTRICAL ROOM SPRINKLERS TO BE ORDINARY HAZARD QUICK RESPONSE SPRINKLERS, 0.15 GPM/SQ. FT. OVER THE ROOM OR

1,500 SQ. FT. BEFORE REDUCTION. USE THE LESSER OF THE TWO VALUES.

8 PROVIDE A COMPLETE AND WORKING WET PIPE SPRINKLER SYSTEM THAT IS IN COMPLIANCE WITH THE CONTRACT DOCUMENTS AND NFPA 13.

9 NOTIFIY THE COR AND OBTAIN APPROVAL PRIOR TO THE OPERATION (OPENING OR CLOSING) OF ANY VALVES CONTROLLING WATER TO THE

DOMESTIC OR FIRE SYSTEMS,

10 PROVIDE PIPING OFFSETS AS REQUIRED TO AVOID DUCTWORK, STRUCTURE, OTHER TRADES OR OTHER OBSTRUCTIONS.

11 INSTALL PIPING ABOVE CEILINGS IN AREAS WITH FINISHED CEILINGS. SPRINKLERS WILL BE RECESSED IN THESE AREAS. IN AREAS WITH EXPOSED STRUCTURE, PIPING SHALL BE EXPOSED AND PAINTED TO MATCH ADJACENT SURFACES.

12 DESIGN PIPING BY HYDRAULIC CALCULATION WITH THE AVAILABLE 2" MAIN DRAIN SUPPLY PRESSURE OF 50 PSI, 48 PSI RESIDUAL PRESSURE.

13 DESIGN KITCHEN, MAINTENANCE SHOP, AND STORAGE ROOM SPRINKLERS TO BE ORDINARY HAZARD GROUP 2 QUICK RESPONSE SPRINKLERS, 0.20 GPM/SQ. FT. OVER THE ROOM OR 1,500 SQ. FT. BEFORE REDUCTION. USE THE LESSER OF THE TWO VALUES.

FIRE PROTECTION GENERAL NOTES

4 4 4

4 4 4

4 4 4 4 4 4

1½1½

1½

1 1

1/4 1/4 1½

2½

½

2½

1 1

1 1

1 1

1 1

1 1

1 1

1 1 1

1 1

1 1

1 1

11 111/4

½

1 1

1 1

½

1 1 1

½

1½

1½

2½

½

½

½

½

½

½

½

½

½

TYPICAL FOR FLOOR

TYPICAL FOR FLOOR

TYPICAL FOR FLOOR

TYPICAL FOR FLOOR

TYPICAL FOR FLOOR

FS

FS

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

2.9 4.1 14.9 16.15.7 6.7 7.4 7.8 8.9 10.1 11.2 11.6 12.3 13.37.9 11.1

11.3

11.4

B

C

D

E

F

G G.2

H

K

L

M

G.3

J

H.6

H.8

G.7

A.8

B.8

C.9

N

ETR -

FDC

ETR - BUILDING

58 SPRINKLER

RISER

ETR - 4"

STANDPIPE

UP TO 1ST

FLOOR WITH

2-1/2" HOSE

VALVE

ETR - 4"

STANDPIPE

UP TO 1ST

FLOOR WITH

2-1/2" HOSE

VALVE

NSCOPE OUTLINE

KEY PLAN

# SHEET KEY NOTES:

Revisions: Date

Drawing Title:

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg. of

VA FORM 08-6231

# 58

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER:

ACG Project Number

17-113

SHEET NOTES:

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

FULLY SPRINKLERED

E

D C

B A

2 3 4 5 6 7

E D

C B

A

1 2 3 4 5 6 7

Date Checked Drawn

/2

/2

:5

:5

A

M

FD100

BASEMENT FIRE PROTECTION

DEMOLITION PLAN

2 3SJP

JMN

RENOVATE BUILDING 58

BASEMENT &

INFRASTRUCTURE

COATESVILLE VAMC

COATESVILLE, PA 19320

17-113

04-27-18

542-15-203

100% CONSTRUCTION DOCUMENTS

A CONTRACTOR SHALL FIRE STOP ALL

PENETRATIONS.

B REFER TO GI005 FOR PHASING PLANS. PROVIDE

TEMPORARY PIPING CONNECTIONS TO MAINTAIN

ACTIVE SPRINKLERS IN AREAS OUTSIDE OF THE

CURRRENT CONSTRUCTION PHASE.

SCALE: 1/8" = 1'-0"1

BASEMENT FIRE PROTECTION DEMOLITION PLAN

1 DEMOLISH FIRE PROTECTION PIPING, HANGERS,

SPRINKLER HEADS, AND SUPPORTS COMPLETE AS

INDICATED.

2 DEMOLISH FIRE HOSE CABINET AND BRANCH LINE TO

ISOLATION VALVE.

REF.

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

2.9 4.1 14.9 16.15.7 6.7 7.4 7.8 8.9 10.1 11.2 11.6 12.3 13.37.9 11.1

11.3

11.4

B

C

D

E

F

G G.2

H

K

L

M

G.3

J

H.6

H.8

G.7

A.8

B.8

C.9

N

DELIVERY

B11A

TUNNEL

WEST

T58-59

MEN

B09B

STAIR

B05

MECH.

B00-B3

TILE

STORAGE

B07B

TOILET

B08B

STAIR

B10

VEST.

B09

WOMEN

B09A

TESTING

B08A

BREAK

B08

LOCKSMITH

B07

VEST.

B02

CORRIDOR

B00-A

F.A.

B00-B2

STOR.

B04B

MAINT.

SHOP

B07A

ELEC

B03A

WAIT.

B04C

MEN

B02A

RECEP.

B04D

INT.

B04G

INT.

B04J

OFFICE

B04K

INT.

B04M

OFFICE

B04L

FOOD

PREP

B13

GIP

ROOM

B15

FLEX

OFF.

B01C

FLEX

OFF.

B01B

FLEX

OFF.

B01A

BREAK

B04H

TOILET

B04A

STOR

B12B

TUNNEL

EAST

T58-139

LOCKSMITH

STORAGE

B06

FOOD

SERVICE

STORAGE

B01

CORRIDOR

B00-B

OPEN

OFFICE

B03

IT

ROOM

B14A

EMS

B14

ELEVATOR

SERVICE

RM.

B15A

FOOD

PREP

B11

STOR

B12A

MED

STOR.

B04E

INT.

B04F

WOMEN

B02B

FOOD

PREP

B13A

CONF.

B03D

CORR.

B04

(TYP) 1

NSCOPE OUTLINE

KEY PLAN

# SHEET KEY NOTES:

Revisions: Date

Drawing Title:

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg. of

VA FORM 08-6231

# 58

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER:

ACG Project Number

17-113

SHEET NOTES:

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

FULLY SPRINKLERED

E

D C

B A

2 3 4 5 6 7

E D

C B

A

1 2 3 4 5 6 7

Date Checked Drawn

/2

/2

:5

:0

A

M

FP100

BASEMENT FIRE PROTECTION PLAN

3 3SJP

JMN

RENOVATE BUILDING 58

BASEMENT &

INFRASTRUCTURE

COATESVILLE VAMC

COATESVILLE, PA 19320

17-113

04-27-18

542-15-203

100% CONSTRUCTION DOCUMENTS

A CONTRACTOR SHALL FIRE STOP ALL

PENETRATIONS.

B REFER TO GI005 FOR PHASING PLANS. PROVIDE

TEMPORARY PIPING CONNECTIONS TO MAINTAIN

ACTIVE SPRINKLERS IN AREAS OUTSIDE OF THE

CURRRENT CONSTRUCTION PHASE.

SCALE: 1/8" = 1'-0"1

BASEMENT FIRE PROTECTION NEW WORK

1 PROVIDE FIRE SPRINKLERS, FIRE PROTECTION PIPING,

HANGERS, AND SUPPORTS COMPLETE. PROVIDE

SPRINKLER HEADS IN MAINENANCE, MECHANICAL, AND

ELECTRICAL SPACES WITH SAFETY CAGES.

2 ORDINARY HAZARD

3 ORDINARY HAZARD GROUP 2

A/E ARCHITECT / ENGINEER

AD AREA DRAIN

AFF ABOVE FINISH FLOOR

AFG ABOVE FINISH GRADE

AG AIR GAP

AP ACCESS PANEL

AS AUTOMATIC SPRINKLER

ASD ADJUSTABLE SPEED DRIVE

ASD AUTOMATIC SPRINKLER DRAIN

ASHRAE AMERICAN SOCIETY HEATING,

REFRIGERATING, AIR CONDITIONING

ENGINEERS

ASME AMERICAN SOCIETY OF MECHANICAL

ENGINEERS

ASPE AMERICAN SOCIETY PLUMBING

ENGINEERS

ASR AUTOMATIC SPRINKLER RISER

AV ACID VENT

AW ACID WASTE

BFP REDUCED PRESSURE BACKFLOW

PREVENTER

BHP BREAK HORSEPOWER

BSP BLACK STEEL PIPE

BT BATHTUB

BTU BRITISH THERMAL UNIT

BTUH BRITISH THERMAL UNITS PER HOUR

C CELSIUS

CGA COMPRESSED GAS ASSOCIATION

CI CAST IRON

CO CLEANOUT

CS CLINICAL SINK

CV CONTROL VALVE

DCW DOMESTIC COLD WATER

DHW DOMESTIC HOT WATER

DHWR DOMESTIC HOT WATER RETURN

DHWS DOMESTIC HOT WATER SUPPLY

DI DEIONIZED WATER

DN DOWN

DOE DEPARTMENT OF ENERGY

DS DOWNSPOUT

DW DISHWASHER

DWG DRAWING

DWH DOMESTIC WATER HEATER

DWR DRINKING WATER RETURN

DWS DRINKING WATER SUPPLY

DWV DRAIN WASTE VENT

EL ELEVATION

EMCS ENERGY MONOSERRAT AND

CENTRAL SYSTEM

EPA ENVIRONMENTAL PROTECTION

AGENCY

EPACT ENERGY POLICY ACT

ESC ESCUTCHEON

ESH EMERGENCY SHOWER

ET EXPANSION TANK

EWC ELECTRIC WATER COOLER

EWH ELECTRIC WATER HEATER

EWS EYE WASH STATION

EX EXISTING

F FAHRENHEIT

FCO FLOOR CLEANOUT

FCW FILTERED COLD WATER

FD FLOOR DRAIN

FDC FIRE DEPARTMENT (HOSE)

CONNECTION

FM FLOW METER

FOP FUEL OIL PUMP

FOR FUEL OIL RETURN

FOS FUEL OIL SUPPLY

FOV FUEL OIL VENT

FS FLOOR SINK

FU FIXTURE UNITS

GAL GALLON

GCO GRADE CLEANOUTS

GPD GALLONS PER DAY

GPH GALLONS PER HOUR

GPM GALLONS PER MINUTE

GPR GAS PRESSURE REGULATOR

GRS GAS REGULATOR STATION

GT GREASE TRAP

GVTR GAS VENT THROUGH ROOF

GWH GAS FIRED WATER HEATER

N2 NITROGEN

N2O NITROUS OXIDE

NC NORMALLY CLOSED

NG NATURAL GAS

NIC NOT IN CONTRACT

NO NORMALLY OPEN

NOM NOMINAL

NPW NON POTABLE WATER

NTS NOT TO SCALE

02 OXYGEN

OC ON CENTER

OD OUTSIDE DIAMETER

OFD OVERFLOW DRAIN

OR OPERATING ROOM

OVFL OVERFLOW

PA PASCAL

PD PRESSURE DROP OR DIFFERENCE

PDI PLUMBING AND DRAINAGE INSTITUTE

PG PRESSURE GAUGE

PP PLUMBING PUMP

PPM PARTS PER MILLION

PRS PRESSURE REDUCING STATION

PRV PRESSURE REDUCING VALVE

PSI POUNDS PER SQUARE INCH

PSIA POUNDS PER SQUARE INCH

ATMOSPHERE

PSIG POUNDS PER SQUARE INCH GAUGE

PTRV PRESSURE TEMPERATURE RELIEF

VALVE

PW POTABLE WATER

RD ROOF DRAIN

RDL ROOF DRAIN LEADER

RL ROOF LEADER

RO REVERSE OSMOSIS

RWL RAIN WATER LEADER

SAN SANITARY SEWER

SCFM STANDARD CUBIC FOOT/MIN

SCW SOFTENED COLD WATER

SDMH STORM DRAIN MANHOLE

SP SUMP PUMP

SPR SPRINKLER LINE

SQFT SQUARE FOOT

SS STAINLESS STEEL

ST STORAGE TANK

SW STORM WATER

TCV TEMPERATURE CONTROL VALVE

TD TEMPERATURE DIFFERENCE

TD TRENCH DRAIN

TDH TOTAL DYNAMIC HEAD

TEMP TEMPERATURE

TMV THERMOSTATIC MIXING VALVE

TP TRAP PRIMER

TSTAT THERMOSTAT

TWR TEMPERED WATER RETURN

TWS TEMPERED WATER SUPPLY

TYP TYPICAL

UPC UNIFORM PLUMBING CODE

V VENT

VAC VACUUM

VB VACUUM BREAKER

VCO VACUUM CLEANER OUTLET

VP VACUUM PUMP

VS VENT STACK

VTR VENT THROUGH ROOF

W WASTE

WC WATER CLOSET

WCO WALL CLEANOUT

WG WATER GAUGE

WH WALL HYDRANT

WH WATER HEATER

WHA WATER HAMMER ARRESTOR

WL WATER LINE

WM WATER METER

WPD WATER PRESSURE DROP

WS WASTE STACK

YCO YARD CLEANOUT

YH YARD HYDRANT

H&CW HOT AND COLD WATER

HB HOSE BIBB

HD HUB DRAIN

HEX HEAT EXCHANGER

HP HORSEPOWER

HS HAND SINK

HST HOT WATER STORAGE TANK

(DOMESTIC)

HWB HOT WATER BOILER

HWCP HOT WATER CIRCULATING PUMP

HWP HOT WATER PUMP

HYD HYDRANT

ICW INDUSTRIAL COLD WATER

INV INVERT

IPC INTERNATIONAL PLUMBING CODE

IRW IRRIGATION WATER

IW INDIRECT WASTE

IWH INSTANTANEOUS WATER HEATER

IWR INDUSTRIAL WATER RETURN

IWS INDUSTRIAL WATER SUPPLY

KW KILOWATT

KWHR KILOWATT-HOUR

L/S LITER PER SECOND

LA LABORATORY AIR

LAV LAVATORY

LBS/HR POUNDS PER HOUR

LCW LABORATORY COLD WATER

LHW LABORATORY HOT WATER

LNG LIQUID NATURAL GAS

LOX LIQUID OXYGEN

LV LABORATORY VACUUM

LW LOW WATER

M METER

MA MEDICAL AIR

MAV MANUAL AIR VENT

MBH 1000 BTUH

MED MEDICAL

MER MECHANICAL EQUIPMENT ROOM

MH MANHOLE

MOU MEMORANDUM OF UNDERSTANDING

MSB MOP SERVICE BASIN

MV MEDICAL VACUUM

PLUMBING ABBREVIATIONS

V

SAN

PLUMBING LEGEND

GATE VALVE

GLOBE VALVE

GATE VALVE WITH 3/4" HOSE ADAPTER

CHECK VALVE

ANGLE GLOBE VALVE

BUTTERFLY VALVE

BALL VALVE

MODULATING CONTROL VALVE

BALANCING VALVE (CIRCUIT SETTER)

FE

DIRECTION OF PIPE PITCH (DOWN)

DIRECTION OF FLOW

ANCHOR

REDUCER OR INCREASER

ECCENTRIC REDUCER

TOP CONNECTION, 45° or 90°

BOTTOM CONNECTION, 45° OR 90°

SIDE CONNECTION

CAPPED OUTLET

RISE OR DROP IN PIPE

UNION

PIPE UP

PIPE DOWN

POINT OF CONNECTION BETWEEN NEW AND

EXISTING WORK

LIMIT OF DEMOLITION

WATER HAMMER ARRESTOR

FLOAT & THERMOSTATIC TRAP SET INCLUDING

PIPING ACCESSORIES

STRAINER

THERMOMETER

PRESSURE GAUGE

FLOW ELEMENT

TEMPERATURE SENSOR (AQUASTAT)

T

SANITARY SEWER PIPING

VENT PIPING

DOMESTIC COLD WATER PIPING

DOMESTIC HOT WATER PIPING

DOMESTIC HOT/COLD WATER RETURN

NON POTABLE

CONTINUATION

STORM WATER

SAN

SD

FIRE SUPPRESSIONFS

SANITARY SEWER PIPING (UNDER SLAB)

NATURAL GAS

COMPRESSED AIR

VACUUM

PIPING TO BE DEMOLISHED

OXYGEN

MV

MA

NG

O

PROJECT LIMITS OF WORK

MATCHLINE

PD104

PD103

WATER HAMMER ARRESTOR SCHEDULE

MARK FIXTURE UNIT RATING

A 1 - 10

B 11 - 32

C 33 - 60

D 61 - 113

E 114 - 154

F 155 - 330

1 CONFORM TO APPLICABLE LOCAL, STATE, NATIONAL CODES, AND VA STANDARDS.

2 INSTALL EQUIPMENT IN ACCORDANCE WITH MANUFACTURER'S WRITTEN RECOMMENDATIONS.

3 OBTAIN AND PAY FOR PERMITS, FEES, AND INSPECTIONS REQUIRED FOR THIS WORK.

4 PROVIDE NEW MATERIALS, EQUIPMENT AND PRODUCTS , OF A SUITABLE GRADE FOR THE PURPOSES INCORPORATED IN THE WORK.

5 SUBMIT PROPOSED EQUIPMENT DEVIATIONS THAT ARE SIMILAR BOTH IN QUALITY AND CAPACITY TO THE EQUIPMENT SPECIFIED. EQUIPMENT OR MATERIAL DEVIATIONS FROM

INDICATED CONTRACT REQUIREMENTS SHALL BE SUBJECT TO THE APPROVAL OF THE COR.

6 INSTALL EQUIPMENT AS INDICATED, ALLOWING FOR SUFFICIENT ACCESS AND CLEARANCE SPACE FOR EQUIPMENT MAINTENANCE, REPAIRS, AND REPLACEMENT.

7 PROVIDE FLUSH VALVE FIXTURES WITH PISTON TYPE WATER HAMMER ARRESTOR(S) SIZED ACCORDING TO MANUFACTURER'S RECOMMENDATIONS.

8 PROVIDE SANITARY SEWER PIPING LOCATED BELOW FLOOR SLAB OR WITHIN WALLS UNLESS NOTED OTHERWISE. PROVIDE SANITARY VENT PIPING ABOVE THE CEILING OR WITHIN

WALLS UNLESS NOTED OTHERWISE.

9 SUPPORT PIPING SYSTEM AS REQUIRED BY LOCAL, STATE, AND NATIONAL CODES, SPECIFICATIONS, VA STANDARDS AND MANUFACTURER'S RECOMMENDATIONS.

10 FIRESTOP PIPING PENETRATIONS THROUGH NEW OR EXISTING WALLS OR FLOORS TO EQUAL THE RATING OF THE NEW OR EXISTING WALL OR FLOOR.

11 TEST PLUMBING SYSTEM AS REQUIRED PER LOCAL, STATE, AND NATIONAL CODES, AND VA STANDARDS.

12 COORDINATE PLUMBING EQUIPMENT INSTALLATION WITH OTHER CONTRACTING FIELDS.

13 DISINFECT THE DOMESTIC WATER SYSTEM IN ACCORDANCE WITH LOCAL, STATE, AND NATIONAL CODES, AND VA STANDARDS.

14 PROVIDE SHUT OFF VALVES AT BRANCH PIPING TO FIXTURES.

16 COORDINATE ANY PLUMBING SYSTEM SHUTDOWN WITH THE COR 1 WEEK IN ADVANCE.

17 PATCH, PAINT AND CLEAN SURFACES SUSTAINING DAMAGE ASSOCIATED WITH PLUMBING WORK.

18 SUBMIT BOUND SET OF OPERATING AND MAINTENANCE INSTRUCTIONS FOR EQUIPMENT AT COMPLETION OF PROJECT.

19 INSTALL ESCUTCHEONS IN PLACES WHERE PIPING PENETRATES A WALL IN AN EXPOSED LOCATION.

20 PIPES SHALL NOT BE ROUTED ABOVE TELECOM OR ELECTRICAL ROOMS.

PLUMBING GENERAL NOTES

Revisions: Date

Drawing Title:

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg. of

VA FORM 08-6231

# 58

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER:

ACG Project Number

17-113

FULLY SPRINKLERED

E

D C

B A

2 3 4 5 6 7

E D

C B

A

1 2 3 4 5 6 7

Date Checked Drawn

/2

/2

:5

:0

A

M

P-001

PLUMBING LEGEND, ABBREVIATIONS,

AND GENERAL NOTES

1 11SJP

JMN

RENOVATE BUILDING 58

BASEMENT &

INFRASTRUCTURE

COATESVILLE VAMC

COATESVILLE, PA 19320

17-113

04-27-18

542-15-203

100% CONSTRUCTION DOCUMENTS

2) SENSORS SHALL BE BATTERY POWERED.

NOTES

1) ADA BOTTOM OUTLET, BASE SHALL HAVE STRAIGHT SIDES AT FLOOR.

P-811 ICE MAKER BOX - - 1/2 - N/A N/A NO

P-808 WASHER WALL BOX 2 1.5 1/2 1/2 N/A N/A NO

P-707 EMERGENCY SHOWER/EYEWASH 2 1.5 3/4 3/4 N/A N/A NO

P-608 WATER COOLER 2 1-1/2 1/2 - N/A N/A N/A

P-524 KITCHEN SINK 2 1-1/2 1/2 1/2 N/A N/A N/A

P-521 LAUNDRY TUB 2 1-1/2 1/2 1/2 NO N/A NO

P-418 ADA LAVATORY 2 1-1/2 1/2 1/2 NO N/A YES

P-101 WATER CLOSET FLOOR MTD (NOTE 1) 4 2 1 - N/A N/A YES

IN IN IN IN

MARK DESCRIPTION

WASTE PIPE VENT PIPE COLD WATER HOT WATER

WRIST BLADE HANDLES FOOT PEDALCONTROL ELECTRIC SENSOR

PLUMBING FIXTURE SCHEDULE

C.O

1½"S.P

½"C.W

1¼"CW1¼"CW

3/4"H.W

3/4"H.W

½"H.W

3/4"H.W

½"H.W

"H .W

1½"S.P

"C

.W

"S .P

4"S.P6"S.P

½"C.W ½"H.W

½"H.W.R.C 1¼"H.W 2"C.W

2½"W.P

1"C.W 1"H.W

3"

5"W.P

4"S.P 3/4"C.W 3/4"H.W

½"H.W.R.C

3/4"H & C.W TO

CT-22 ON 1st FLOOR

¼"H.W.R.C 3/4"H.W

2"C.W

2"

3/4"

1½"C.W & 3/4"H.W

TO P-1 & P-66

ON 1st FLOOR

1½"C.W & 3/4"H.W

TO 1ST

3"F.D

6"S.P

2"W.P

DRAIN

2"

3"

3"

2"DRN & P-TRAP

2"W.P ABV.FLR.CONN

TO LAUNDRY CHUTE

3/4"C.W 3/4"H.W

½"H.W.R.C 1"H.W 1"C.W

5"S.P

3"

2"W.P-V.P

1½"V.P 2"V.P

1"C.W 1"H.W 1"

2"C.W & 1¼"H.W

3" 3"

3"D.S 3"D.S

C.O C.O

3/4"C.W3/4"C.W

3"

3"

2"

3/4"C.W 3/4"C.W

5" 2" C.O

2"

4"

C.O 6"

4"

3"

4"

4"

3"

C.O

C.O

C.O

C.O 3"

3"

5"

3"W.P

2"

2"

2"

5"

6"

C.O

3/4"

1¼" 1½"

½"

4"

1¼"

4"

4"

3/4" 1"

1½"C.W 3/4"H.W

3"

2"W.P

½"H.W.R.C 3/4"H.W

1"C.W

TO THERMOVALVE

& BARBERS LAV'S

3"W.P

C.O

C.O

C.O

4"

1½"

3/4"C.W

4"S.P 2½"C.W

TO W.C'S

5"

5"

2"V.P

½"C.W ½"H.W

2"W.P

3/4"C.W TO COOLER

3/8"PLUGGED TEE

2"W.P 2"V.P

3"S.P

½"H.W.R.C 1"H.W 1½"C.W

1¼"C.W

3/4"H.W TO TOILET

4"S.P

½"H.W.R.C 3/4"H.W 1¼"C.W

4"S.P 2"V.P 3"W.P-2"V.P

4"

4"S.P

½"H.W.R.C 1"H.W 1½"C.W

3/4"H.W 1½"C.W

C.O 2"W.P

½"H.W.R.C 1"H.W 1"C.W

3"W.P(C.I)

3"W.P(C.I)

3"W.P(C.I)

½"H.W.R.C 1"H.W 1"C.W

½"H.W.R.C 3/4"H.W 3/4"C.W

½"H.W.R.C 3/4"H.W 3/4"C.W

3/4"H.W 3/4"C.W

3"F.D

6"SANITARY SEWER

6"

C.O

4"

3"F.D

C.O

3"D.S3"D.S

C.O 3" 3"

3"

C.O

3/4"C.W3/4"C.W

3/4"C.W 3/4"C.W

2"

C.O 3"3"

C.O

3"

5"

4"4"

4"

4"

4"W.P-2"V.P(C.I) 4"S.P

2½"C.W TO W.C'S

2"W.P-V.P(C.I) 3/4"C.W 3/4"C.W

3/4"C.W

C.O

5"

5"

2"

3"

½"T.W.R.C ½"I.W

2"W.P

3/8"I.W

3/4"C.W

3"

3"

2"

C.O

4"

3/4" 1¼"

1½" 1" 1¼"

½"

3/4"

½"H.W.R.C 1¼"H.W 2"C.W

½"H.W.R.C 3/4"H.W 1"C.W

2"

2" 2"

2"W.P

4"

3"S.P

5"

4" 6"

4"

4"S.P

TO COOLER

TO D.F

C.O

½"H.W.R.C 3/4"H.W 3/4"C.W

1 1

FS

FS

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

2.9 4.1 14.9 16.15.7 6.7 7.4 7.8 8.9 10.1 11.2 11.6 12.3 13.37.9 11.1

11.3

11.4

B

C

D

E

F

G

G.2

H

K

L

M

G.3

J

H.6

H.8

G.7

A.8

B.8

C.9

N

DISHWASHER

SPRAY

SINK

NSCOPE OUTLINE

KEY PLAN

# SHEET KEY NOTES:

Revisions: Date

Drawing Title:

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg. of

VA FORM 08-6231

# 58

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER:

ACG Project Number

17-113

SHEET NOTES:

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

FULLY SPRINKLERED

E

D C

B A

2 3 4 5 6 7

E D

C B

A

1 2 3 4 5 6 7

Date Checked Drawn

/2

/2

:5

:0

A

M

PD100

BASEMENT PLUMBING DEMOLITION

PLAN

2 11SJP

JMN

RENOVATE BUILDING 58

BASEMENT &

INFRASTRUCTURE

COATESVILLE VAMC

COATESVILLE, PA 19320

17-113

04-27-18

542-15-203

100% CONSTRUCTION DOCUMENTS

1 DEMOLISH FIXTURE AND ALL ASSOCIATED PIPING TO

POINT INDICATED, INCLUDING BUT NOT LIMITED TO,

VENT, DRAIN, DOMESTIC COLD WATER, AND DOMESTIC

HOT WATER PIPING.

2 CAREFULLY REMOVE AND STORE PLUMBING FIXTURE

TO SUPPORT WALL FINISH WORK. ROUGH-IN IS

EXISTING TO REMAIN.

SCALE: 1/8" = 1'-0"1

BASEMENT PLUMBING DEMOLITION PLAN

A CONTRACTOR SHALL FIRE STOP ALL

PENETRATIONS.

B REFER TO GI005 FOR PHASING PLANS. PROVIDE

TEMPORARY PIPING CONNECTIONS TO MAINTAIN

ACTIVE SPRINKLERS IN AREAS OUTSIDE OF THE

CURRRENT CONSTRUCTION PHASE.

9 10 11

13 14 15 16 17 18

2.9 4.1 14.9 16.15.7 6.7 7.4 7.8 8.9 10.1 11.2 11.6 12.3 13.37.9 11.1

11.3

11.4

B

C

D

E

F

G G.2

H

K

L

M

G.3

J

H.6

H.8

G.7

A.8

B.8

C.9

N E

L E

C T

R

IC

C A

R T

P A

R K

IN

G

G A

S E

N G

IN

E

C A

R T

P A

R K

IN

G

ELECTRIC CART

CHARGING STATION

PREFAB. CONC.

WHEEL STOP

STRIPING

S L O

P E

:2

M

A X

NEW CONC. RAMP

NEW CONC. LANDING

STEEL HANDRAILS

EXISTING SIDEWALK TO REMAIN

NEW ASPHALT

PAVING AND BASE

EXISTING CONCRETE SIDEWALK

ALIGN

NEW CONC. SIDEWALK

NEW CONCRETE

RETAINING WALL

STEEL GUARDRAIL

NEW CONC.

RETAINING WALL

NEW STEEL GUARDRAIL

NEW STEEL HANDRAIL

NEW CONC. STAIR

D O

W N

NEW LANDING TO MATCH

EXISTING LEVEL OF

EXISTING LANDING

SIDEWALK TO ALIGN

WITH LEVEL OF

EXISTING SIDEWALK

A R

E A

O F

L

IG

H T

W E

L L

SLOPE 1:20 MAX.

AREA OF NEW CONCRETE SIDEWALK

BAR GRATING

TOP OF GRATING

CONC.

SIDEWALK -

ALIGN W/ ADJ.

CONC.

SIDEWALK

CONC. RAMP

NO PARKING

6"6"

6"6"

10"10"

10"10"

10"10"

REFER TO PP200 FOR CONTINUATION.

REFER TO PP200 FOR CONTINUATION.

ETR

ETR

ETR

E T

R

S T

O R

M B

E L O

W

ETR STORM MANHOLE 11' DEEP.

6"6" 6"6"

6"6"

6"6"

NSCOPE OUTLINE

KEY PLAN

# SHEET KEY NOTES:

Revisions: Date

Drawing Title:

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg. of

VA FORM 08-6231

# 58

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER:

ACG Project Number

17-113

SHEET NOTES:

FULLY SPRINKLERED

E

D C

B A

2 3 4 5 6 7

E D

C B

A

1 2 3 4 5 6 7

Date Checked Drawn

/2

/2

:5

:2

A

M

PS100

PLUMBING SITE PLAN

3 11SJP

JMN

RENOVATE BUILDING 58

BASEMENT &

INFRASTRUCTURE

COATESVILLE VAMC

COATESVILLE, PA 19320

17-113

04-27-18

542-15-203

100% CONSTRUCTION DOCUMENTS

SCALE: 1/8" = 1'-0"1

COURTYARD GRADE

1 PROVIDE SITE STORM WATER PIPING. TRENCH,

BACKFILL, GRADE, AND SEED TO MATCH EXISTING

ADJACENT CONDITIONS.

2 PROVIDE CONCRETE CATCH BASIN AND STORM

GRATE.

3 PROVIDE SITE STORM WATER MANHOLE. EXCAVATE,

BACKFILL, GRADE, AND SEED TO MATCH EXISTING

ADJACENT CONDITIONS.

4 PROVIDE TRENCH DRAIN.

5 PROVIDE PERFORATED FRENCH DRAIN AND SEDIMENT

WRAP.

1 2

3 4 5 6 7 8 9 10 11 12

13 14 15 16 17 18

2.9 4.1 14.9 16.15.7 6.7 7.4 7.8 8.9 10.1 11.2 11.6 12.3 13.37.9 11.1

14.1 4.9

A

B

C

D

F

G G.2

H

K

L

M

G.3

J

H.6

H.8

G.7

A.8

B.8

C.9

N

E

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

2.9 4.1 14.9 16.15.7 6.7 7.4 7.8 8.9 10.1 11.2 11.6 12.3 13.37.9 11.1

11.3

11.4

B

C

D

E

F

G G.2

H

K

L

M

G.3

J

H.6

H.8

G.7

N

DELIVERY

B11A

TUNNEL

WEST

T58-59

MEN

B09B

STAIR

B05

MECH.

B00-B3

TILE

STORAGE

B07B

TOILET

B08B

STAIR

B10

VEST.

B09

WOMEN

B09A

TESTING

B08A

BREAK

B08

LOCKSMITH

B07

VEST.

B02

CORRIDOR

B00-A

F.A.

B00-B2

STOR.

B04B

MAINT.

SHOP

B07A

ELEC

B03A

WAIT.

B04C

MEN

B02A

RECEP.

B04D

INT.

B04G

INT.

B04J

OFFICE

B04K

INT.

B04M

OFFICE

B04L

FOOD

PREP

B13

GIP

ROOM

B15

FLEX

OFF.

B01C

FLEX

OFF.

B01BFLEX

OFF.

B01A

BREAK

B04H

TOILET

B04A

STOR

B12B

TUNNEL

EAST

T58-139

LOCKSMITH

STORAGE

B06

FOOD

SERVICE

STORAGE

B01

CORRIDOR

B00-B

OPEN

OFFICE

B03

IT

ROOM

B14A

EMS

B14

ELEVATOR

SERVICE

RM.

B15A

FOOD

PREP

B11

STOR

B12A

MED

STOR.

B04E

INT.

B04F

WOMEN

B02B

FOOD

PREP

B13A

CONF.

B03D

CORR.

B04

1 1

P-808

P-707

P-811

P-524

P-418 P-418

P-418

P-101

P-101

P-521

P-418P-524

P-811

P-418

P-101

P-101

1"1"

3/ 4"

3/ 4"

3/ 4"

3/ 4"

1/

4"

1/ 4"

3/ 4"

3/ 4"

2"2"

1P-101

P-608

DISHWASHER

SPRAY

SINK

NSCOPE OUTLINE

KEY PLAN

# SHEET KEY NOTES:

Revisions: Date

Drawing Title:

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg. of

VA FORM 08-6231

# 58

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER:

ACG Project Number

17-113

SHEET NOTES:

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

FULLY SPRINKLERED

E

D C

B A

2 3 4 5 6 7

E D

C B

A

1 2 3 4 5 6 7

Date Checked Drawn

/2

/2

:5

:1

A

M

PP100

BASEMENT DOMESTIC WATER PLAN

4 11SJP

JMN

RENOVATE BUILDING 58

BASEMENT &

INFRASTRUCTURE

COATESVILLE VAMC

COATESVILLE, PA 19320

17-113

04-27-18

542-15-203

100% CONSTRUCTION DOCUMENTS

1 PROVIDE FIXTURE, PIPING, HANGERS, AND SUPPORTS

COMPLETE.

3 CLEAN AND REINSTALL EXISTING FIXTURE. CONNECT

FIXTURE TO EXISTING ROUGH-IN.

4 PROVIDE TRAP PRIMER. WORK IN THE BASEMENT PIPE

SPACE SHALL BE CONSIDERED AS CONFINED SPACE

ENTRY. PP100

5 PROVIDE DUMP VALVE WITH TIMER.

A SLEEVE ALL PENETRATIONS, FIRESTOP OR SEAL

AS REQUIRED.

B ALL PIPING SHALL BE CONCEALED IN THE PLENUM

SPACE OR WALLS UNLESS NOTED OTHERWISE.

C REFER TO ARCHITECTURAL PLANS FOR RATED

WALL LOCATIONS.

D ALL HANGER SUPPORTS SHALL BE INSTALLED

VERTICALLY AND UPRIGHT.

E ALL PIPES SHALL BE INSTALLED PARALLEL AND

PERPENDICULAR TO BUILDING UNLESS

OTHERWISE INDICATED.

SCALE: 1/8" = 1'-0"1

BASEMENT DOMESTIC WATER PLAN

2 3 4 5

12 13 14 15 16 17 18

5.7 6.7 7.4 7.8 8.9 10.1 11.2 11.6 12.3 13.37.9 11.1

D

E

F

G G.2

K

G.3

J

3/4"3/4"

1/ 2"

1/ 2"

1/ 2"

1/ 2"

# SHEET KEY NOTES:

Revisions: Date

Drawing Title:

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg. of

VA FORM 08-6231

# 58

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER:

ACG Project Number

17-113

SHEET NOTES:

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

FULLY SPRINKLERED

E

D C

B A

2 3 4 5 6 7

E D

C B

A

1 2 3 4 5 6 7

Date Checked Drawn

/2

/2

:5

:1

A

M

PP101

ATTIC DOMESTIC WATER PLAN

5 11SJP

JMN

RENOVATE BUILDING 58

BASEMENT &

INFRASTRUCTURE

COATESVILLE VAMC

COATESVILLE, PA 19320

17-113

04-27-18

542-15-203

100% CONSTRUCTION DOCUMENTSSCALE: 1/8" = 1'-0"1

ATTIC DOMESTIC WATER PLAN

1 CONNECT TO EXISTING 3/4" DCW IN ACCESSIBLE

SECOND FLOOR PIPE CHASE AND ROUTE TO ATTIC.

2 CONNECT TO CLEAN STEAM GENERATOR. REFER TO

DRAWING MH401.

3 PROVIDE ZERO TDS FILTER. INSTALL OVER AN

INDUSTRY STANDARD WATER HEATER DRAIN PAN.

PROVIDE 3/4" COPPER DRAIN TO NEAREST FLOOR

DRAIN.

4 PROVIDE BACKFLOW PREVENTOR.

A CONTRACTOR SHALL FIRE STOP ALL

PENETRATIONS.

B REFER TO GI005 FOR PHASING PLANS. PROVIDE

TEMPORARY PIPING CONNECTIONS TO MAINTAIN

ACTIVE SPRINKLERS IN AREAS OUTSIDE OF THE

CURRRENT CONSTRUCTION PHASE.

FS

FS

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

2.9 4.1 14.9 16.15.7 6.7 7.4 7.8 8.9 10.1 11.2 11.6 12.3 13.37.9 11.1

11.3

11.4

B

C

D

E

F

G G.2

H

K

L

M

G.3

J

H.6

H.8

G.7

A.8

B.8

C.9

N

P-808

P-707

P-811

P-524

P-418

P-418

P-418

P-101

P-101

P-521

P-418

P-524

P-811

P-418

P-101

P-101

5"5"

4"4"

5"5" 5"5"

5"5"

3"3" 4"4" 4"4"4"4"

2"2"

2"2"

2"2"

6"6"

6"6"

6"6"

6"6" 6"6"

4"4"

4"4"

6"6"

P-418

P-418

P-101

5"5"

P-608

REFER TO PS100 FOR CONTINUATION

REFER TO

PS100 FOR

CONTINUATION

6"6"

CO

CO

NSCOPE OUTLINE

KEY PLAN

# SHEET KEY NOTES:

Revisions: Date

Drawing Title:

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg. of

VA FORM 08-6231

# 58

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER:

ACG Project Number

17-113

SHEET NOTES:

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

FULLY SPRINKLERED

E

D C

B A

2 3 4 5 6 7

E D

C B

A

1 2 3 4 5 6 7

Date Checked Drawn

/2

/2

:5

:1

A

M

PP200

PLUMBING BASEMENT SANITARY PLAN

6 11SJP

JMN

RENOVATE BUILDING 58

BASEMENT &

INFRASTRUCTURE

COATESVILLE VAMC

COATESVILLE, PA 19320

17-113

04-27-18

542-15-203

100% CONSTRUCTION DOCUMENTSSCALE: 1/8" = 1'-0"1

BASEMENT SANITARY PLAN

1 PROVIDE PIPING, HANGERS, AND SUPPORTS

COMPLETE. WORK IN THE BASEMENT PIPE SPACE

SHALL BE CONSIDERED AS CONFINED SPACE ENTRY.

2 CONNECT FIXTURE TO EXISTING ROUGH-IN.

3 PROVIDE RAIN LEADER PIPING, HANGERS, AND

SUPPORTS COMPLETE IN CRAWL SPACE.

A SLEEVE ALL PENETRATIONS, FIRESTOP OR SEAL

AS REQUIRED.

B ALL PIPING SHALL BE CONCEALED IN THE PLENUM

SPACE OR WALLS UNLESS NOTED OTHERWISE.

C REFER TO ARCHITECTURAL PLANS FOR RATED

WALL LOCATIONS.

D ALL HANGER SUPPORTS SHALL BE INSTALLED

VERTICALLY AND UPRIGHT.

E ALL PIPES SHALL BE INSTALLED PARALLEL AND

PERPENDICULAR TO BUILDING UNLESS

OTHERWISE INDICATED.

2 3 4 5 6 7 8 9 10 11

5.7 6.7 7.4 7.8 8.9 10.1 11.27.9 11.1

11.4

B

C

D

E

F

G G.2

A.8

B.8

C.9

AC-1

3/ 4"

3/ 4" 3/4"3/4" 3/4"3/4"

3 UP TO

BASEMENT

LEVEL

NSCOPE OUTLINE

KEY PLAN

# SHEET KEY NOTES:

Revisions: Date

Drawing Title:

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg. of

VA FORM 08-6231

# 58

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER:

ACG Project Number

17-113

SHEET NOTES:

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

FULLY SPRINKLERED

E

D C

B A

2 3 4 5 6 7

E D

C B

A

1 2 3 4 5 6 7

Date Checked Drawn

/2

/2

:5

:1

A

M

PP300

PLUMBING SUB-BASEMENT

COMPRESSED AIR PLAN

7 11SJP

JMN

RENOVATE BUILDING 58

BASEMENT &

INFRASTRUCTURE

COATESVILLE VAMC

COATESVILLE, PA 19320

17-113

04-27-18

542-15-203

100% CONSTRUCTION DOCUMENTS

SCALE: 1/8" = 1'-0"1

SUBBASEMENT COMPRESSED AIR PLAN

2 PROVIDE ROUTINE MAINTENANCE.

3 PROVIDE PIPING, HANGERS, AND SUPPORTS

COMPLETE.

A SLEEVE ALL PENETRATIONS, FIRESTOP OR SEAL

AS REQUIRED.

B ALL PIPING SHALL BE CONCEALED IN THE PLENUM

SPACE OR WALLS UNLESS NOTED OTHERWISE.

C REFER TO ARCHITECTURAL PLANS FOR RATED

WALL LOCATIONS.

D ALL HANGER SUPPORTS SHALL BE INSTALLED

VERTICALLY AND UPRIGHT.

E ALL PIPES SHALL BE INSTALLED PARALLEL AND

FS

FS

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

2.9 4.1 14.9 16.15.7 6.7 7.4 7.8 8.9 10.1 11.2 11.6 12.3 13.37.9 11.1

11.3

B

C

D

E

F

G G.2

H

K

L

M

G.3

J

H.6

H.8

G.7

A.8

B.8

C.9

N

1/2"1/2"

1/2"1/2"

1/2"1/2" 1/2"1/2"

3/ 4"

3/ 4"

3/ 4"

3/ 4"

DOWN TO

SUB-

BASEMENT

NSCOPE OUTLINE

KEY PLAN

# SHEET KEY NOTES:

Revisions: Date

Drawing Title:

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg. of

VA FORM 08-6231

# 58

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER:

ACG Project Number

17-113

SHEET NOTES:

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

FULLY SPRINKLERED

E

D C

B A

2 3 4 5 6 7

E D

C B

A

1 2 3 4 5 6 7

Date Checked Drawn

/2

/2

:5

:2

A

M

PP301

PLUMBING BASEMENT COMPRESSED

AIR PLAN

8 11SJP

JMN

RENOVATE BUILDING 58

BASEMENT &

INFRASTRUCTURE

COATESVILLE VAMC

COATESVILLE, PA 19320

17-113

04-27-18

542-15-203

100% CONSTRUCTION DOCUMENTS

SCALE: 1/8" = 1'-0"1

BASEMENT COMPRESSED AIR PLAN

1 PROVIDE WALL MOUNTED COMPRESSED AIR HOSE

REEL. MOUNT PER MANUFACTURER'S

RECOMMENDATIONS. PROVIDE AIR FILTER.

2 PROVIDE PIPING, HANGERS, AND SUPPORTS

COMPLETE.

3 PROVIDE END OF RUN BLOW DOWN WITH 3/4 BALL

VALVE APPROXIMATELY 5'-0" AFF"

A SLEEVE ALL PENETRATIONS, FIRESTOP OR SEAL

AS REQUIRED.

B ALL PIPING SHALL BE CONCEALED IN THE PLENUM

SPACE OR WALLS UNLESS NOTED OTHERWISE.

C REFER TO ARCHITECTURAL PLANS FOR RATED

WALL LOCATIONS.

D ALL HANGER SUPPORTS SHALL BE INSTALLED

VERTICALLY AND UPRIGHT.

E ALL PIPES SHALL BE INSTALLED PARALLEL AND

FINISHED FLOOR

FINISHED WALL

VACUUM

BREAKER TUBE

GRAB BAR, SEE

ARCH.

DRAWINGS

[8 m m

[4 m m

F O

R F

IX

T

U R

E H

E

IG

H T

S S

E E

A R

C H

IT

E

C T

U R

A L

D R

A W

IN

G

S

ELECTRONIC

SENSOR

OVERRIDE

BUTTON

MINIMUM 16 GAGE GALVANIZED

STEEL PLATE 12"x48" [300x1200mm] MIN. SECURED TO

A MIN. 4 STUDS PER LAVATORY

TYP. 1/8" 1/4"

TYP. [3mm] [6mm]

1/4" [6mm] MOLLY BOLT HOLLOW WALL ANCHOR

(1 EA. SIDE OF LAV)

PLAN

NOTE:

1. AT LAVS WITH FOOT PEDAL CONTROLS

PROVIDE AN ADDITIONAL 16 GAGE GALVANIZED

STEEL PLATE 12"x16" [300sx600mm] SECURED TO

A MINIMUM OF 2 STUDS PER FOOT PEDAL

2. PROVIDE 20 GAGE STUDS WHEN

HEIGHT EXCEEDS 12'-0" [3600mm]

STEEL WALL PLATE

WALL ANCHOR

STUDS

STEEL HANGER BY LAV MFGR

AA

FOR FIXTURE

HEIGHT SEE

ARCHITECTURAL

DRAWINGS

MIN. 5 1/4"

[131mm] GALV/

MACHINE BOLTS

WELDED TO PLATE

MIN. (3) 1/4"

[6mm] MACHINE

BOLTS W/ DOUBLE

LOCK NUTS ON

BACK SIDE

SECTION A

[9 m m

T O

F L O

O R

V A

R

IE

S

1/8" NPT PORT SEAL WITH

BRASS HEX HEAD PLUG USING

TEFLON TAPE (2 PL.)

FAUCET SEE

SPECIFICATIONS

LAMINAR FLOW

CONTROL DEVICE

OFFSET

WASTE

TRAP

PARALLEL

TO WALL

FINISHED

FLOOR

ESCUTCHEON

LOOSE

KEY STOP

F O

R F

IX

T

U R

E H

E

IG

H T

S S

E E

A R

C H

IT

E

C T

U R

A L D

R A

W

IN

G S

8"

/4

QUICK CLOSING

VALVE

WATER HAMMER ARRESTOR

ISOLATION VALVE

OUTLET

PROVIDE MEANS OF

ACCESS FOR SERVICING

#4 HOOPS

AND #4

VERTICAL

AT 18"

#4 AT 12" O/C EACH WAY

NOTE 4

5"

MIN

PRECAST

CONCRETE

(TYP)

12" MIN

CONCRETE

COLLAR

TRACER

WIRE (ST-

G30GEN-3)

1" MIN

MORTAR

CONCRETE FILL

9'-0" SQUARE FOR 6'-0" MANHOLE

8"

BARREL SECTIONS AS

NECESSARY

6'-0" MIN4-1/8"

MIN

6"

MIN

3" OR 6" GRADE

RINGS AS REQUIRED.

12" MAX HEIGHT

MASTIC SEAL

SIDE WALK SURFACE

OVER CONCRETE

COLLAR

GROUT

DUCTILE IRON FRAME

AND COVER SUITABLE

FOR TRAFFIC

DETAIL KEYED NOTES

1) TERMINATE ALL PIPING AT LEAST 3" INTO MANHOLE.

2) CLEAN ALL JOINTS AND INSTALL SEALING GASKETS.

3) GROUT WATER STOP (TYP)

4) TEST STATION WITH 6" CONCRETE COLLAR.

5)MASTIC AND/OR GROUT FOR WATER TIGHT SEAL AND

THE PREVENTION OF DISPLACEMENTOFG RINGS AND

COVER.

NOTE 5

NOTE 2

NOTE 1

NOTE 3

Revisions: Date

Drawing Title:

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg. of

VA FORM 08-6231

# 58

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER:

ACG Project Number

17-113

FULLY SPRINKLERED

E

D C

B A

2 3 4 5 6 7

E D

C B

A

1 2 3 4 5 6 7

Date Checked Drawn

/2

/2

:5

:2

A

M

PP501

PLUMBING DETAILS

9 11SJP

JMN

RENOVATE BUILDING 58

BASEMENT &

INFRASTRUCTURE

COATESVILLE VAMC

COATESVILLE, PA 19320

17-113

04-27-18

542-15-203

100% CONSTRUCTION DOCUMENTS

SCALE: N.T.S.2

WATER CLOSET DETAIL-SENSOR OPERATED

SCALE: N.T.S.1

LAVATORY MOUNTING DETAIL

SCALE: N.T.S.4

DUAL PORT SHUT-OFF VALVE WITH LOCKING HANDLE

SCALE: N.T.S.3

TYPICAL WHEELCHAIR LAVATORY DETAIL

SCALE: N.T.S.5

WATER HAMMER ARRESTOR DETAIL

SCALE: N.T.S.6

MANHOLE DETAIL

2"2"

2"2"

1 1/2"1 1/2"

2"2"

2"2"

4"4" 4"4"

4"4"

4"4" 4"4"

3"3"

2"2"

5"5"

3"3"

5"5"

2"2"

5"5"

2"2"

4"4" 4"4"

4"4"

2"2"

1 1/2"1 1/2"

2"2"

1 1/2"1 1/2" 4"4"

4"4"

4"4"

5"5"

2"2"

2"2"

2"2" 2"2"

2"2"

4"4"

1/

2 "

1/ 2 "

2"2"

1 1/2"1 1/2"

1 1/2"1 1/2"

2"2" 4"4"

4"4"

4"4"

2"2"

2"2"

1 1/2"1 1/2"

2"2"

1 1/2"1 1/2"4"4"

4"4"

4"4"

2"2"

2"2"

2"2"

4"4"

4"4"

4"4"

4"4"

4"4" 2"2"

1 1/2"1 1/2"

1 1/2"1 1/2"

4"4"

2"2"

6"6"

6"6"

6"6"

2"2"

6"6"

6"6"

4" FD

wco co

Revisions: Date

Drawing Title:

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg. of

VA FORM 08-6231

# 58

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER:

ACG Project Number

17-113

FULLY SPRINKLERED

E

D C

B A

2 3 4 5 6 7

E D

C B

A

1 2 3 4 5 6 7

Date Checked Drawn

/2

/2

:5

:2

A

M

PP901

SANITARY RISERS

10 11SJP

JMN

RENOVATE BUILDING 58

BASEMENT &

INFRASTRUCTURE

COATESVILLE VAMC

COATESVILLE, PA 19320

17-113

04-27-18

542-15-203

100% CONSTRUCTION DOCUMENTS

SCALE:1

SANITARY ISOMETRIC 1 SCALE:2

SANITARY ISOMETRIC 2

SCALE:3

SANITARY ISOMETRIC 3

1"1" 1/ 2"

1/ 2"

3/4"3/4"

1 1/4"1 1/4"

1"1"

1/2"1/2"

3/4"3/4" 1"1"

1/2"1/2" 1"1"

1/ 2"

1/ 2"

1/ 2"

1/ 2"

1/ 2"

1/ 2"

P-811

1/2"1/2"

1"1"

1"1"

1/2"1/2"

1"1"

1/ 2"

1/ 2"

1/ 2"

1/ 2"

1"1"

1/2"1/2"

1/2"1/2"

1/ 2"

1/ 2" 3/

4" 3/

4"

1/

2"

1/ 2"

1"1"

1/ 2"

1/ 2"

1/ 2"

1/ 2"

1"1"

1/2"1/2"

3/4"3/4"

1 1/2"1 1/2"

3/4"3/4"

2"2"

1/ 2"

1/ 2"

1/ 2"

1/ 2"

1/ 2"

1/ 2"

3/4"3/4"

2"2"

2"2"

1/2"1/2"

1/2"1/2"

1/ 2"

1/ 2"

1/ 2"

1/ 2"

1/2"1/2"

1/2"1/2"

1"1" 2"2"

3/4"3/4"

2"2"

1/2"1/2"

1/2"1/2"

P-521

P-808 P-707

Revisions: Date

Drawing Title:

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg. of

VA FORM 08-6231

# 58

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER:

ACG Project Number

17-113

FULLY SPRINKLERED

E

D C

B A

2 3 4 5 6 7

E D

C B

A

1 2 3 4 5 6 7

Date Checked Drawn

/2

/2

:5

:2

A

M

PP902

DOMESTIC WATER RISERS

11 11SJP

JMN

RENOVATE BUILDING 58

BASEMENT &

INFRASTRUCTURE

COATESVILLE VAMC

COATESVILLE, PA 19320

17-113

04-27-18

542-15-203

100% CONSTRUCTION DOCUMENTS

SCALE:1

DOMESTIC WATER ISOMETRIC 1

SCALE:2

DOMESTIC WATER ISOMETRIC 2

SCALE:3

DOMESTIC WATER ISOMETRIC 3

A/E ARCHITECT / ENGINEER

AAHX AIR TO AIR HEAT EXCHANGER

AB AIR BLENDER

AAV AUTOMATIC AIR VENT

ACC AIR-COOLED CONDENSER

ACCH AIR-COOLED CHILLER

ACCU AIR-COOLED CONDENSING UNIT

ACU AIR CONDITIONING UNIT

ACD AUTOMATIC CONTROL DAMPER,

MODULATING

ACD-TP AUTOMATIC CONTROL DAMPER,TWO

POSITION

AD ACCESS DOOR

AF AFTER FILTER

AFCV AIR FLOW CONTROL VALVE

AFF ABOVE FINISHED FLOOR

AFMD AIR FLOW MEASURING DEVICE

AFW AIR FOIL WHEEL (FAN)

AHU AIR-HANDLING UNIT

AMP AMPERGE

AP ACCESS PANEL

APD AIR PRESSURE DROP

ARI AIR CONDITIONING AND REFRIGERATION

INSTITUTE

AS AIR SEPARATOR

ASME AMERICAN SOCIETY OF MECHANICAL

ENGINEERS

AW AIR WASHER

AXF AXIAL FLOW

B BOILER

BD BUTTERFLY DAMPER

BDD BACKDRAFT DAMPER

BDR BASE BOARD RADIATOR

BFP BACKFLOW PREVENTER

BFT BOILER PLANT FIRE TUBE

BHP BRAKE HORSEPOWER

BHW HOT WATER HEATING BOILER

BHX BOILER BLOWDOWN HEAT EXCHANGER

BIW BACKWARD INCLINED WHEEL (FAN)

BSC BIOLOGICAL SAFETY CABINETS

BT BUFFER TANK

BTU BRITISH THERMAL UNIT

BTUH BRITISH THERMAL UNIT PER HOUR

C CENTIGRADE (CELCIUS)

CC COOLING COIL

CCD COOLING COIL CONDENSATE DRAIN

CENT CENTRIFICAL

CFH CUBIC FEET PER HOUR

CFM CUBIC FEET PER MINUTE

CFT CUBIC FEET

CFP CHEMICAL FEED PUMP

CH CHILLER

CHWP CHILLED WATER PUMP

CHW CHILLER WATER

CHWR CHILLED WATER RETURN

CHWS CHILLED WATER SUPPLY

CI CAST IRON

CM CARBON MONOXIDE

CM CUBIC METER

CM/S CUBIC METER PER SECOND

CO CLEAN OUT

CO2 CARBON DIOXODE

COMP COMPRESSOR UNIT

COP COEFFICIENT OF PERFORMANCE

CP CONDENSATE PUMP

CU CONDENSING UNIT

CUH CABINET UNIT HEATER

CV CONSTANT VOLUME

CW COLD WATER (POTABLE)

CHWCC CHILLED WATER COOLING COIL

D CONDENSATE DRAIN

D-1 OUTDOOR AIR DAMPER

D-2 RETURN AIR DAMPER

D-3 RELIEF AIR DAMPER

D-4 ECONOMIZER OUTDOOR AIR DAMPER

dB DECIBELS Db DRY-BULB TEMPERATURE

DDC DIRECT DIGITAL CONTROLS

DEG DEGREE

DF DIFFUSER

DIA DIAMETER

DIW DEIONIZED WATER

DP DEW POINT TEMPERATURE

DP DIFFUSER PLATE

DPA DIFFERENTIAL PRESSURE ASSEMBLY

DPS DIFFERENTIAL PRESSURE SENSOR

DX DIRECT EXPANSION

DXCC DIRECT EXPANSION COOLING COIL

EA EXHAUST AIR

EAT ENTERING AIR TEMPERATURE

ECC ENGINEERING CONTROL CENTER

EER ENERGY EFFICIENCY RATIO

EF EXHAUST FAN

EG EXHAUST GRILLE

EGS EMERGENCY GAS SHUTOFF

EH EXHAUST HOOD

EJ EXPANSION JOINT

EMD END OF MAIN DRIP (STEAM)

ENT ENTERING

ESP EXTERNAL STATIC PRESSURE

EWT ENTERING WATER TEMPERATURE

EX. EXISTING

F FAHRENHEIT

F&T FLOAT AND THERMOSTATIC

F/SDPR COMBINATION FIRE SMOKE DAMPER

FA FREE AREA

FC FLEXIBLE CONNECTION

FCU FAN COIL UNIT (4 PIPE)

FCW FORWARD CURVED WHEEL (FAN)

FD FLOOR DRAIN

FD FIRE DAMPER

FF FINAL FILTER

FM FLOW METER

FPM FEET PER MINUTE

FPS FEET PER SECOND

FRP FIBER REINFORCED POLYESTER

FS FLOW SWITCH

FSTAT FREEZESTAT

FT FEET

FT-LB FOOT-POUND

FTR FIN TUBE RADIATION

FV FACE VELOCITY

GA GAUGE

GAL GALLONS

GH GRAVITY HOOD

GPD GALLONS PER DAY

GPH GALLONS PER HOUR

GPM GALLONS PER MINUTE

GS GALVANIZED STEEL

H HUMIDIFER

H&CW HOT & COLD WATER

HAC HOUSEKEEPING AID CLOSET

HB HOSE BIBB

HC HEATING COIL

HD HEAD

HD HOOD

HHW HEATING HOT WATER

HHWC HEATING HOT WATER COIL

HHWP HEATING HOT WATER PUMP

HHWR HEATING HOT WATER RETURN

HHWS HEATING HOT WATER SUPPLY

HOA HAND/OFF/AUTOMATIC

HP HEAT PUMP

HP HORSEPOWER

HPDT HIGH PRESSURE DRIP TRAP

HPR HIGH PRESSURE RETURN (STEAM

CONDENSATE)

HPS HIGH PRESSURE SUPPLY (STEAM)

HRC HEAT RECOVERY COIL

HRD HEAT RECOVERY DEVICE

HRP HYDRONIC RADIANT (CEILING) PANEL

HRW HEAT RECOVERY WHEEL

HSTAT HUMIDISTAT

HUM HUMIDIFIER UNIT MOUNTED

HVU HEATING AND VENTILATING UNIT

HW HOT WATER

HWC HOT WATER COIL

HWUH HOT WATER UNIT HEATER

HX HEAT EXCHANGER

Hz HERTZ

I/O INPUT/OUTPUT

IAQ INDOOR AIR QUALITY

IBT INVERTED BUCKET TRAP

ICF IN-LINE CENTRIFUGAL FAN

ICU INTENSIVE CARE UNIT

ID INSIDE DIAMETER

IFB INTEGRAL FACE AND BYPASS

IN INCHES

IN HG INCHES OF MERCURY

IN WC INCH WATER COLUMN

IN WG INCH WATER GAUGE

IN-LB INCH-POUND

IPLV INTERGRATED PART LOAD VALUE

IRH INTRARED HEATER

IS INSECT SCREEN

IV INLET VANES

kg KILOGRAM kg/HR KILOGRAM PER HOUR kPa KILOPASCAL kW KILOWATT kWh KILOWATT HOUR

L LITER

L/s LITERS PER SECOND

LAT LEAVING AIR TEMPERATURE

LBS/HR POUNDS PER HOUR

LF LINEAR FOOT (FEET)

LH LATENT HEAT

LPR LOW PRESSURE RETURN (STEAM

CONDENSATE)

LPS LOW PRESSURE SUPPLY (STEAM)

LSD LINEAR SLOT DIFFUSER

LTCP LOCAL TEMPERATURE CONTROL

PANEL

LVG LEAVING

LVR LOUVER

LWT LEAVING WATER TEMPERATURE

M METER, SI UNIT

M/s METERS PER SECOND (OR

METERS/SECOND)

MA MIXED AIR

MAT MIXED AIR TEMPERATURE

MAV MANUAL AIR VENT

MAX MAXIMUM

MB MIXING BOX

MBH 1000 BTUH

MCA MINIMUM BRANCH CIRCUIT AMPACITY

MER MECHANICAL EQUIPMENT ROOM

MERV MINIMUM EFFICIENCY REPORTING VALUE

MHP MOTOR HORSEPOWER

MIN MINIMUM

MM MILLIMETER

MOV MOTOR OPERATED VALVE

MPR MEDIUM PRESSURE RETURN (STEAM

CONDENSATE)

MPS MEDIUM PRESSURE SUPPLY (STEAM)

MTD MEAN TEMPERATURE DIFFERENCE

MVD MANUAL VOLUME DAMPER

NA NOT APPLICABLE

NC NOISE CRITERIA

NC NORMALLY CLOSED

NO NORMALLY OPEN

NOAA NATIONAL OCEANIC & ATMOSPHERIC

ADMINISTRATION

NOM NOMINAL

NPLV NON-STANDARD PART LOAD VALUE

NPSH NET POSITIVE SUCTION HEAD

NTS NOT TO SCALE

OA OUTSIDE AIR

OAI OUTSIDE AIR INTAKE

OD OUTSIDE DIAMETER

OR OPERATING ROOM

OSA OUTSIDE SUPPLY AIR (CONDITIONED)

P PUMP

PC PUMPED CONDENSATE

PCF POUNDS PER CUBIC FOOT (FEET)

PD PRESSURE DROP

PF PRE-FILTER

PG PRESSURE GAGE

PHC PREHEAT COIL

PHCP PREHEAT COIL PUMP

PPM PARTS PER MILLION

PRV PRESSURE REGULATING VALVE

PSI POUNDS PER SQUARE INCH

PSIA POUNDS PER SQUARE INCH –

ABSOLUTE

PSIG POUNDS PER SQUARE INCH – GAGE

PSS PRIMARY SECONDARY SYSTEM

PSV PRESSURE SAFETY VALVE

R/E RETURN OR EXHAUST

RA RETURN AIR

RAT RETURN AIR TEMPERATURE

RDS ROOM DATA SHEETS

REA RELIEF AIR

RF RETURN FAN

RG RETURN GRILLE

RH RELATIVE HUMIDITY

RHC REHEAT COIL

RL REFRIGERANT LIQUID LINE

RLA RUN LOAD AMPERE

RPM REVOLUTIONS PER MINUTE

RS REFRIGERANT SUCTION

RTU ROOF TOP UNIT

RV RELIEF VALVE

SA SUPPLY AIR

SAD SOUND ATTENUATING DEVICE

SAT SUPPLY AIR TEMPERATURE

SC SHADING COEFFICIENT

SCFM STANDARD CUBIC FEET PER MINUTE

SCR SILICON CONTROLLED RECTIFIER

SD SMOKE DETECTOR

SD SUPPLY AIR DIFFUSER

SDPR SMOKE DAMPER

SDR SMOKE DAMPER (RETURN)

SDS SMOKE DAMPER (SUPPLY)

SEN SENSIBLE HEAT

SF SUPPLY FAN

SH STEAM HUMIDIFIER

SHC STEAM HEATING COIL

SI SQUARE INCHES

SP STATIC PRESSURE

SP GR SPECIFIC GRAVITY

SPD SUPPLY PROCESS AND DISTRIBUTION

SPRV STEAM PRESSURE REDUCING VALVE

SPS STATIC PRESSURE SENSOR

SQ FT SQUARE FOOT (FEET)

SR SUPPLY AIR REGISTER

SS STAINLESS STEEL

SSR SOLID SEPARATOR

ST STEAM TRAP

SV STEAM SAFETY VALVE

SVS STEAM VENT SILENCER

T & PCV TEMPERATURE AND PRESSURE

CONTROL VALVE

TAB TESTING, ADJUSTING, BALANCE

TD TEMPERATURE DIFFERENCE

TDH TOTAL DYNAMIC HEAD

TDS TOTAL DISSOLVED SOLIDS

TP TRAP

TSP TOTAL STATIC PRESSURE

TSTAT THERMOSTAT

TU TERMINAL UNIT

UC UNDER CUT

UH UNIT HEATER

UL UNDERWRITERS LABORATORY

V VALVE

VAF VANE-AXIAL FAN

VAV VARIABLE AIR VOLUME

VD VOLUME DAMPER (MANUAL OPPOSED

BLADE)

VFD VARIABLE FREQUENCY DRIVE

VHA VETERANS HEALTH ADMINISTRATION

VI VIBRATION ISOLATOR

VP VACUUM PUMP

VPS VARIABLE PRIMARY SYSTEM

VR VACUUM (STEAM CONDENSATE) RETURN

VSD VARIABLE SPEED DRIVE

VUH VERTICAL UNIT HEATER

W WATTS

Wb WET-BULB (TEMPERATURE)

WFCV WATER FLOW CONTROL VALVE

WFM WATER FLOWMETER

WFMD WATER FLOW MEASURING DEVICE

WG WATER GAGE

WPD WATER SIDE PRESSURE DROP

XT EXPANSION TANK

YR YEAR

MECHANICAL ABBREVIATIONS

T

CO2 CARBON DIOXIDE

THERMOSTAT

SUPPLY DIFFUSER

RETURN DIFFUSER/GRILLE

EXHAUST GRILLE

ROUND FLEX DUCT

EG-88 2000 DIFFUSER TAG | DIFFUSER CFM

LINEAR SLOT DIFFUSER

BALANCING DAMPER

(RECTANGULAR)

BALANCING DAMPER

(ROUND)

FIRE DAMPER

SMOKE DAMPER

D

R INCLINED RISE, IN DIRECTION

OF AIRFLOW

INCLINED DROP, IN DIRECTION

OF AIRFLOW

CONNECT NEW DUCT

TO EXISTING

LIMIT OF DEMOLITION

VANED ELBOW (PROVIDE ALL

SQUARE OR RECTANGULAR

ELBOWS WITH VANES EVEN IF

SYMBOL IS MISSING)

STANDARD RADIUS ELBOW

(LONG RADIUS)

10x8 NEW DUCT (INSIDE DIMENSIONS:

WIDTH X DEPTH)

EXISTING DUCT TO REMAIN

EXISTING DUCT TO BE

DEMOLISHED

DUCT TRANSITION

SIDE MOUNTED GRILLE

SUPPLY

RETURN45°

45°

DN

DN

UP

UP

DNUP

STANDARD BRANCH SUPPLY OR

RETURN, NO SPLITTER (45° TAP)

SUPPLY DUCT (UP & DOWN)

EXHAUST DUCT (UP & DOWN)

RETURN DUCT (UP & DOWN)

MECHANICAL LEGEND

HPS

LPS

LPR

CHWS

CHWR

HIGH PRESSURE STEAM PIPING

(60 PSI)

LOW PRESSURE STEAM PIPING

(15 PSI AND BELOW)

LOW PRESSURE STEAM

CONDENSATE RETURN

CHILLED WATER SUPPLY PIPING

CHILLED WATER RETURN PIPING

PIPE UP

PIPE DOWN

BOTTOM CONNECTION

TOP CONNECTION

CAPPED OUTLET

GLOBE VALVE

GATE VALVE

BALL VALVE

STEAM SAFETY VALVE

PRESSURE REGULATING VALVE

WYE STRAINER VALVE

BALANCING VALVE

MOTORIZED CONTROL VALVE

STEAM TRAPCOND CONDENSATE DRAIN LINE

HPR HIGH PRESSURE STEAM

CONDENSATE RETURN

HHWS

HHWR

HEATING HOT WATER SUPPLY PIPING

HEATING HOT WATER RETURN PIPING

RLS REFRIGERANT LINE SET (LIQUID

AND SUCTION)

CONNECT TO EXISTING PIPE

LIMITS OF DEMOLITION

INLINE CENTRIFUGAL PUMP

TANGENTIAL AIR SEPARATOR

EXPANSION TANK

WALL-MOUNTED INDOOR

SPLIT-SYSTEM

SPLIT-SYSTEM CONDENSING UNIT

UTILITY SET EXHAUST FAN

STEAM PRESSURE

REDUCING STATION

DRAIN VALVE

TEST PLUG

SUPPLY

TERMINAL UNIT SUPPLY DUCT

BRANCH (CONICAL TAP)

TERMINAL UNIT

CHECK VALVE

MECHANICAL GENERAL NOTES

1 CONFORM TO APPLICABLE LOCAL, STATE, AND NATIONAL CODES AND APPLICABLE VA STANDARDS.

2 INSTALL EQUIPMENT IN ACCORDANCE WITH MANUFACTURER'S WRITTEN RECOMMENDATIONS.

3 OBTAIN AND PAY FOR PERMITS, FEES, AND INSPECTIONS REQUIRED FOR THIS WORK.

4 PROVIDE NEW MATERIALS, EQUIPMENT AND PRODUCTS INCORPORATED IN THE WORK, OF A SUITABLE GRADE FOR THE PURPOSES INTENDED.

5 PROVIDE STANDARD PRODUCTS OF THE VARIOUS MANUFACTURERS EXCEPT WHERE SPECIAL CONSTRUCTION OR PERFORMANCE FEATURES ARE REQUIRED.

6 EQUIPMENT OR MATERIAL DEVIATIONS FROM INDICATED CONTRACT REQUIREMENTS SHALL BE SUBJECT TO THE APPROVAL OF THE COR. SUBMIT PROPOSED EQUIPMENT DEVIATIONS THAT ARE SIMILAR BOTH IN QUALITY AND CAPACITY TO THAT EQUIPMENT SPECIFIED, AS SOLELY DETERMINED BY THE COR.

7 PROVIDE MECHANICAL EQUIPMENT THAT IS LISTED AND LABELED BY UNDERWRITERS LABORATORIES (U.L.).

8 INSTALL EQUIPMENT AS INDICATED, ALLOWING FOR SUFFICIENT ACCESS AND CLEARANCE SPACE FOR EQUIPMENT MAINTENANCE, REPAIRS, AND REPLACEMENT.

9 INSTALL EQUIPMENT WITH PROPER CLEARANCES FOR REQUIRED PIPING AND ELECTRICAL SERVICES AND CONNECTIONS. INSTALL EQUIPMENT WITH REQUIRED ACCESS AND CLEARANCES IN ACCORDANCE WITH MANUFACTURER'S WRITTEN RECOMMENDATIONS AND APPLICABLE CODES AND STANDARDS.

10 COORDINATE LOCATION, INSTALLATION, AND ROUTING OF DUCTWORK, PIPING, AND EQUIPMENT WITH WORK OF OTHER TRADES.

11 PROVIDE SUPPORT FOR MECHANICAL EQUIPMENT. COORDINATE SUPPORT LOCATIONS WITH OTHER TRADES PRIOR TO INSTALLATION.

12 PROVIDE POWER CONNECTIONS TO EQUIPMENT PROVIDED UNDER THIS CONTRACT AS WORK OF DIVISION 26.

13 PROVIDE CONTROL WIRING FOR MECHANICAL EQUIPMENT AS WORK OF DIVISION 26.

14 COORDINATE AND DETERMINE EXACT ROUTING OF DUCTWORK AND PIPING IN THE FIELD. DUCTWORK AND PIPING LAYOUTS AND LOCATIONS ARE SCHEMATIC. DO NOT SCALE THESE

DRAWINGS.

15 VERIFY DIMENSIONS IN FIELD BY ACTUAL MEASUREMENT AND OBSERVATION BEFORE ORDERING OR FABRICATING DUCTWORK, PIPING OR EQUIPMENT.

16 NOTIFY COR REGARDING DISCREPANCIES BETWEEN CONTRACT DOCUMENTS AND EXISTING CONDITIONS OR DIMENSIONS BEFORE PERFORMING WORK. FAILURE TO VERIFY AND REPORT SHALL CONSTITUTE CONTRACTOR'S ACCEPTANCE OF EXISTING CONDITIONS AS FIT FOR THE PROPER EXECUTION OF THE WORK.

17 REFER TO ARCHITECTURAL DRAWINGS FOR FINAL LOCATION OF CEILING INSTALLED EQUIPMENT.

18 INSTALL DUCTWORK AND PIPING AS HIGH AS POSSIBLE AND AS CLOSE AS POSSIBLE TO BUILDING WALLS, CEILING AND FLOOR AND ROOF STRUCTURE. PROVIDE OFFSETS, FITTINGS, AND DIMENSIONAL TRANSITIONS NOT SHOWN BUT REQUIRED TO MAINTAIN MINIMUM CLEAR SPACE TO BUILDING SURFACES.

19 PATCH, PAINT AND CLEAN SURFACES SUSTAINING DAMAGE ASSOCIATED WITH MECHANICAL WORK OF THIS CONTRACT.

20 SUBMIT BOUND SET OF OPERATING AND MAINTENANCE INSTRUCTIONS FOR EQUIPMENT AT COMPLETION OF PROJECT.

21 INSTALL ESCUTCHEONS IN PLACES WHERE PIPING PENETRATES A WALL IN AN EXPOSED LOCATION.

22 REVIEW DRAWINGS, INCLUDING SCHEDULES AND DETAILS, PRIOR TO BEGINNING MECHANICAL SYSTEM INSTALLATION. RESOLVE CONFLICTS WITH THE COR.

23 INSTALL PIPING INDICATED TO BE EXPOSED AND PIPING IN EQUIPMENT ROOMS AND SERVICE AREAS AT RIGHT ANGLES OR PARALLEL TO BUILDING WALLS. DIAGONAL RUNS ARE NOT

ACCEPTABLE UNLESS SPECIFICALLY INDICATED OTHERWISE.

24 INSTALL PIPING FREE OF SAGS AND BENDS.

25 INSTALL PIPING TO ALLOW APPLICATION OF INSULATION.

26 PIPING SHALL NOT BE ROUTED OVER TELECOM OR ELECTRICAL CLOSETS/ROOMS.

27 PREPARE DRAWINGS SHOWING MECHANICAL SYSTEMS AND EQUIPMENT FOR COORDINATION WITH WORK OF OTHER DIVISIONS AND WORK BY THE GOVERNMENT.

a. INCLUDE PLAN VIEWS, SECTIONS, AND ELEVATIONS, AS REQUIRED, TO FULLY COORDINATE NEW WORK WITH ITSELF AND EXISTING CONDITIONS.

b. DRAWINGS SHALL SHOW, BUT NOT BE LIMITED TO, DUCTWORK, AIR DISTRIBUTION, MECHANICAL EQUIPMENT, MECHANICAL PIPING, FIRE PROTECTION PIPING, PLUMBING PIPING, CABLE TRAYS, LIGHTING FIXTURES, CEILING GRID AND HEIGHT, BEAMS AND JOISTS (WITH ELEVATIONS MARKED), ELECTRICAL CONDUIT LARGER THAN 2 INCHES IN DIAMETER AND

OTHER CEILING MOUNT DEVICES OR EQUIPMENT THAT PROTRUDE INTO THE CEILING CAVITY.

c. CONSULT WITH COR FOR GUIDANCE AND MAKE CORRECTIONS IN ACCORDANCE WITH DIRECTIONS GIVEN WHERE THERE ARE OUTSTANDING ISSUES THAT CANNOT BE RESOLVED.

d. DO NOT BEGIN FABRICATION OR PLACE EQUIPMENT ORDERS UNTIL COORDINATION DRAWINGS HAVE BEEN APPROVED.

e. INSTALLATION COMMENCED PRIOR TO COORDINATION DRAWING APPROVAL IS TAKEN AT THE CONTRACTORS OWN RISK. MODIFY, MOVE, OR RECONFIGURE WORK LACKING

COORDINATION.

HVAC DESIGN DATA

DESIGN CONDITIONS

SUMMER WINTER LOWEST AVERAGE

ANNUAL DEWPOINTDRY BULB WET BULB % HUMIDITY TEMP DEWPOINT % HUMIDITY

OUTDOOR DESIGN CONDITIONS 86.0 °F 77.0 °F 67 15.0 °F 13.0 °F 64 3

CORRIDOR 75.0 °F 65.3 °F 60 70.0 °F 50.0 °F 20 28

ELECTRICAL AND OIT 75.0 °F 65.3 °F 60 70.0 °F 50.0 °F 20 28

STORAGE 75.0 °F 65.3 °F 60 70.0 °F 50.0 °F 20 28

MAINTENANCE 75.0 °F 65.3 °F 60 68.0 °F 50.0 °F 20 28

LOCKER ROOM 75.0 °F 65.3 °F 60 70.0 °F 50.0 °F 20 28

LOUNGE 75.0 °F 65.3 °F 60 70.0 °F 50.0 °F 20 28

KITCHEN PRODUCTION 78.0 °F 65.3 °F 60 70.0 °F 50.0 °F 20 28

TOILETS 75.0 °F 65.3 °F 60 70.0 °F 50.0 °F 20 28

DEDUCT ALTERNATES

1 NONE

NOTES:

1. ELECTRICAL EQUIPMENT ROOMS WITHOUT INTERNAL HEAT GAIN HAVE NO TEMPERATURE REQUIREMENTS. ELECTRICAL EQUIPMENT ROOMS WITH

HEAT GAIN ARE REQUIRED TO BE 86 SUMMER/40 WINTER, BUT HAVE BEEN DESIGNED TO ADJACENT SPACE TEMPERATURES DUE TO THEIR SMALL

SIZE.

Revisions: Date

Drawing Title:

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg. of

VA FORM 08-6231

# 58

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER: ACG Project Number 17-113

FULLY SPRINKLERED

E

D C

B A

2 3 4 5 6 7

E D

C B

A

1 2 3 4 5 6 7

Date Checked Drawn

4/

/2

2:

:4

P

M

M-001

MECHANICAL LEGEND, ABBREVIATIONS,

AND GENERAL NOTES

1 12SJP

SWR

RENOVATE BUILDING 58

BASEMENT &

INFRASTRUCTURE

COATESVILLE VAMC

COATESVILLE, PA 19320

17-113

04/27/2018

542-15-203

100% BID DOCUMENTS

F

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

2.9 4.1 14.9 16.15.7 6.7 7.4 7.8 8.9 10.1 11.2 11.6 12.3 13.37.9 11.1

14.14.9

A

B

C

D

F

G

G.2

H

K

L

M

G.3

J

H.6

H.8

G.7

A.8

B.8

C.9

N

4 (TYP)

(TYP)

5 (TYP)

ETR DISHWASHER

EXHAUST FAN AND

DUCTWORK.

24x1018x814x8

16x10

20x10 x1 x8

24x12 x1

36x12 x1

30x12

9x

8x4

8x6 x4 x6

24x10 16x6 x8 x6 x1 x8 x4

14x8 14x6

16x612 x6

12x6 x6

8x

8x6

8x4

8x4 30x12

16x416x4

16x4 16x4

16x416x4

MH201

MH201 1

MH201

MH201 5

MH201

MH201 7MH20112

MH201 6

MH201

MH201

OUTLINED WORK TAKES

PLACE IN PIPE BASEMENT

MH201

MH201

MD101

MH201

12x6 12x6 15

ETR FIRE DAMPER

ETR FIRE DAMPER

ETR FIRE DAMPER

ETR FIRE DAMPER

ETR FIRE DAMPER

ETR FIRE DAMPER

8x6

10x6 8x6 10x6 10x6 10x6

8x68x68x6

10x8 10x8

8x6

8x4

8x6

8x4

12x4

16x4

12x12

50x10

ETR RISER

HHWS / HHWR 1 1/4"

CHWS / CHWR 1 1/4"

D 1"

ETR RISER

HHWS / HHWR 1"

CHWS / CHWR 1 1/4"

D 1"

ETR RISER

HHWS / HHWR 1 1/4"

CHWS / CHWR 1 1/4"

D 1"

ETR RISER

HHWS / HHWR 1"

CHWS / CHWR 1"

D 1"

ETR RISER

HHWS / HHWR 1"

CHWS / CHWR 1 1/4"

D 1"

ETR RISER

HHWS / HHWR 1"

CHWS / CHWR 1 1/4"

D 1"

ETR RISER

HHWS / HHWR 1"

CHWS / CHWR 1"

D 1"

ETR RISER

HHWS / HHWR 1 1/4"

CHWS / CHWR 1 1/4"

D 1"

ETR RISER

HHWS / HHWR 3/4"

CHWS / CHWR 3/4"

D 1"

ETR RISER

HHWS / HHWR 1"

CHWS / CHWR 1"

D 1"

ETR RISER

HHWS / HHWR 3/4"

CHWS / CHWR 1"

D 1"

ETR RISER

HHWS / HHWR 1"

CHWS / CHWR 1 1/4"

D 1"

ETR RISER

HHWS / HHWR 1"

CHWS / CHWR 3/4"

D 1"

ETR RISER

HHWS / HHWR 3/4"

CHWS / CHWR 1"

D 1"

ETR RISER

HHWS / HHWR 1"

CHWS / CHWR 1"

D 1"

ETR RISER

HHWS / HHWR 1"

CHWS / CHWR 1 1/4"

D 1"

ETR RISER

HHWS / HHWR 1 1/4"

CHWS / CHWR 1 1/4"

D 1"

ETR RISER

HHWS / HHWR 1 1/4"

CHWS / CHWR 3/4"

D 1"

ETR RISER

HHWS / HHWR 1"

CHWS / CHWR 1"

D 1"

ETR RISER

HHWS / HHWR 3/4"

CHWS / CHWR 3/4"

D 1"

ETR RISER

HHWS / HHWR 1"

CHWS / CHWR 1 1/4"

D 1 1/4"

ETR RISER

HHWS / HHWR 1"

CHWS / CHWR 1"

D 1"

ETR RISER

HHWS / HHWR 1"

CHWS / CHWR 1"

D 1"

ETR RISER

HHWS / HHWR 3/4"

CHWS / CHWR 3/4"

D 1"

ETR RISER

HHWS / HHWR 1 1/2"

CHWS / CHWR 1 1/2"

D 1 1/2"

ETR RISER

HHWS / HHWR 1 1/4"

CHWS / CHWR 1 1/4"

D 1"

ETR RISER

HHWS / HHWR 1 1/4"

CHWS / CHWR 1 1/4"

D 1"

ETR RISER

HHWS / HHWR 3/4"

CHWS / CHWR 1"

D 1"

ETR RISER

HHWS / HHWR 1 1/2"

CHWS / CHWR 1"

D 1"

ETR RISER

HHWS / HHWR 1 1/4"

CHWS / CHWR 1 1/4"

D 1"

ETR RISER

HHWS / HHWR 3/4"

CHWS / CHWR 3/4"

D 1"

ETR RISER

HHWS / HHWR 1"

CHWS / CHWR 1 1/4"

D 1"

ETR RISER

HHWS / HHWR 1"

CHWS / CHWR 1"

D 1"

ETR RISER

HHWS / HHWR 1 1/4"

CHWS / CHWR 1 1/4"

D 1"

ETR RISER

HHWS / HHWR 3/4"

CHWS / CHWR 3/4"

D 1"

MH101

MH101

9 10

A.8

3/4" LPR

2" LPR

2" LPS

3/4" LPS

ETR

ETR

ETR

ETR

NSCOPE OUTLINE

KEY PLAN

# SHEET KEY NOTES:

Revisions: Date

Drawing Title:

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg. of

VA FORM 08-6231

# 58

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER: ACG Project Number 17-113

SHEET NOTES:

FULLY SPRINKLERED

E

D C

B A

2 3 4 5 6 7

E D

C B

A

1 2 3 4 5 6 7

Date Checked Drawn

4/

/2

2:

:5

P

M

MD101

BASEMENT MECHANICAL DEMOLITION

PLAN

2 12SJP

SWR

RENOVATE BUILDING 58

BASEMENT &

INFRASTRUCTURE

COATESVILLE VAMC

COATESVILLE, PA 19320

17-113

04/27/2018

542-15-203

100% BID DOCUMENTS

SCALE: 1/8" = 1'-0"1 BASEMENT MECHANICAL DEMOLITION PLAN

1 DEMOLISH FLOOR MOUNTED FCU. DEMOLISH 3/4" HOT WATER AND

3/4" CHILLED WATER PIPING AND INSULATION TO ETR RISER AND

CAP. TYPICAL FLOOR MOUNTED FCU PICTURED ON 1/MH201.

2 DEMOLISH DUCTWORK, HANGERS, INSULATION, AND SUPPORTS

COMPLETE. DEMOLISH DUCTWORK TO UNDERSIDE OF DECK

ABOVE AND PROVIDE TEMPORARY DUCT CAP.

3 DEMOLISH DUCTWORK, HANGERS, AND SUPPORTS COMPLETE TO

FLOOR LEVEL. PICTURED ON 4/MH201.

4 DEMOLISH CEILING MOUNTED FCU, HANGERS, SUPPORTS, PIPING,

AND INSULATION COMPLETE. DEMOLISH HOT WATER AND CHILLED

WATER TO ETR RISER AND CAP.

5 DEMOLISH STEAM RADIATOR PIPING AND INSULATION COMPLETE.

DEMOLISH PIPING FLUSH TO FLOOR AND CAP.

6 DEMOLISH EXHAUST FAN, LOUVER, AND SUPPORTS COMPLETE.

PICTURED ON MH201.

7 DEMOLISH OUTSIDE AIR LOUVER AND SUPPORTS COMPLETE.

PICTURED ON MH201.

8 DEMOLISH…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it.