9000 Gallon Tank.pdf
PDF 893 KB Posted
- Attached to
- Y1DA-- REPLACE OXYGEN TANK | 630-22-116 Federal contract opportunity
- Solicitation number
- 36C24222R0033
About this file
This solicitation is for a design-build project to replace an oxygen tank at a Department of Veterans Affairs medical center in Manhattan, New York. Key requirements include providing all labor, materials, tools and equipment for design and construction of a new 9000 gallon oxygen tank, including drawings, specifications, construction estimates and site preparation. The design-build team will be responsible for architectural, engineering and construction services, with a completion deadline of 120 days from notice to proceed. The team must make ten site visits during construction and submit various design packages, shop drawings and as-built documentation for review and approval by the VA.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24222R0033 0003.docx | DOCX document | |
| 36C24222R0033 0002.docx | DOCX document | |
| KBA OXYGEN TANK 6000 Gals.pdf | ||
| 36C24222R0033 0001.docx | DOCX document | |
| 36C24222R0033_1.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VHANYNSituJ Text Box Project No. 630-22-116 Project Title. Replace Oxygen Tank DWGs are reference ONLY. Contractor to verify field conditions
DWG NO. REV
SCALE SHEETFILE NAME
DRAWN
ENGINEER
DATE TITLE
APPD.
DESIGN
SAFETY
OPERATIONS
REF. NO.
REVISION DESCRIPTION DATE BY OPS SFTY. DGN. ENG.REV.
NONE 1 OF 1
B
AIR
PRODUCTS
PRELIM
INARY DRAWING
NOT FOR CONSTRUCTIO
N
THIS DRAWING IS THE PROPERTY OF AIR PRODUCTS AND CHEMICALS INC.
AND MUST BE ACCOUNTED FOR AND RETURNED TO THE COMPANY.
INFORMATION HEREON IS CONFIDENTIAL AND MUST NOT BE COPIED,
REPRODUCED, DUPLICATED, DISCLOSED TO OTHERS IN WHOLE OR IN
PART, SENT OUTSIDE THE COMPANY WITHOUT PROPER AUTHORIZATION,
OR USED OTHER THAN FOR THE INTENDED PURPOSE FOR WHICH
IT IS DISCLOSED.
CONFIDENTIAL
Oxygen Foundation 9000 GallonTank
Ss > 0.25 & <=0.30
BOTTOM MAT
TOP MAT #3 REBAR
GRADE
TANK MAT FOUNDATION
SECTION "A" (TANK)
1" CHAMFER
(EXPOSED EDGES)
STONE BASE
(SEE NOTES
B & D4)
WELL COMPACTED EARTH
@ 12" EACH WAY
SEE TABLE
S E
E
#3 BARS
@ 12" CTRS.
#4 @ 12"
HORIZONTAL
(WITH FROST WALLS)
2-#4 HORIZ.,
CONT. 4 SIDES
F R
O S
T D
E P
T H
V A
R
IE
S
IF
R
E Q
U
IR
E D
T
O L
O C
A L
T A
N K
S S
L A
B O
N
M
IN
S
T O
N E
B A
S E
(TANK FND. ONLY)
T A
B L
E
FOUNDATION NOTES:
A. DESIGN BASIS:
1. Presumed Max. Allow. Soil Bearing - 1500 psf
2. Design Wind Velocity = 120 mph
3. Occupancy Category III
4. Site Class "D"; Max. S = 0.40 (See Table);
Importance Factor = 1.25; Max. F = 1.60 (See Table)
5. Exposure Category "C"; Wind Directionality
Factor = 0.95; Height and Exposure Adjustment
Factor = 1.04; Press. Coefficient = 0.90; Gust
Effect Factor = 0.85; Force Coefficient = 0.80
B. STONE BASE
Crusher run, 3 8" nominal, 5% max. passing
#4 sieve, 1% max. passing #200 sieve (95%
C. CONCRETE
1. Concrete Properties:
a. Transit-mixed per ASTM C-94
b. Minimum Compressive Strength - 4,000 psi / 28 days
c. Minimum Flexural Strength - 550 psi
d. Slump - 4"
e. Air Entrainment - 5%. Admixture per
ASTM C-260
Proctor Compaction).
2. Primary Reinforcement:
Deformed steel rebar, per ASTM
A-615 Grade 60
3. Secondary Reinforcement (If Shown)
a. Preferred Alternate - Synthetic fiber, Fibermesh I (1.5 lb/CY) or Nurlon
b. Acceptable Substitute - Welded wire fabric per ASTM A-185, D. CONSTRUCTION
1. Excavate to required depths.
2. Compact the exposed sub-base to 95% per ASTM D-1557.
3. If compaction cannot be achieved, stop construction and contact APCI.
4. Lay stone base in max. 9-inch lifts, compacting each lift to 75% per ASTM
D-2047. Use 6" base for a flat pad no frost walls.
5. Set froms and chamfer strips. Place and brace re-bar and ancor bolts. Allow min.
3 inches concrete cover for re-bar.
6. Carefully place concrete.
MECHANICALLY VIBRATE.
7. Slab to be poured level. Provide a rough broom surface finish.
8. Keep concrete moist. Cure per ACI-301 for seven days.
(1 lb/CY)
6 x 6 - W2.9 x W2.9
Note: Prior to setting reinforcing and/or pouring, the Contractor shall secure the services of a soils testing laboratory to field test and confirm a minimum soil bearing capacity of 1500 psf s a
6. Dimensions shown are for a single piece of equipment.
Refer to Layout Drawing for actual dimensions.
NOTE: All Foundation Design and Details conform to the 2012 International Building Code (IBC) and the complimentrary ASCE 7-10 requirements for Seismic, Wind and Snow Loading Conditions
ASSUMED AVERAGE 9,000 GAL LIN/LOX
TANK ANCHOR BOLT LAYOUT
THREE (3) 14"± X 16" ± BASE
PLATES 1-1/2" THK W/ ONE (1)
1-1/2"Ø BOLT HOLES EACH
/4
/8
/2
/4
R4'-9"±
R4'-0 1/2"±
TANK ANCHORAGE SPECIFICATION (See Manufacturer's Tank Drawings for Baseplate & Bolt Circle Details):
1) 9,000-Gallon LIN/LOX Tank: Use total of Six (6) or Three (3) -1-1/4"Ø Hilti HAS-B7 Threaded Steel Rods per tank (i.e. two or one bolt per base plate) having a minimum embedment depth as indicated on this drawing at the table below using Hilti HIT-HY-200 Epoxy Anchoring System. Note: Where tank baseplates have holes larger than 1-1/2"Ø, provide 4"x4"x3/4" pre-drilled (1-1/2"Ø) "Dock Washer" plates to cover oversized anchor holes. Spot weld to base plates. Provide sufficient exposed threaded rods for baseplate thickness, washers, nuts, and overrun.
(Hammer drill anchor hole in fresh concrete; Core drill only where and if interference with rebar is encountered)
>0.25 & <0.30 1.55 18"
#6 BARS @
9" CTRS. E.W.
12" FOR 2
15" FOR 1
S S
Fa
MAT
THK.
BOT.
REINF.
ANCHOR
DEPTH
MAT REINFORCING FOR 9,000 GALLON
LIQUID OXYGEN & NITROGEN TANKS
Note: The above indicated mat foundation parameters are applicable to LOX and LIN tanks only, and for S values of 0.40 or less.S All other 9,000 gallon tank applications to be individually analyzed.
TRAILER APRON
GRADE
SECTION "C"
STONE BASE
(SEE NOTES
B & D4)
1" CHAMFER
(4 SIDES)
FIBRECRETE OR
CONCRETE WITH
WWF (SEE NOTE C3)
SEE
NOTE
C3B
SEE LAYOUT PLAN FOR DIMENSIONS
C
L R
1'-4"
GRADE
PROTECTIVE POST - DTL. "B"
6" PIPE, CS SCH 40, FILLED
W/ CONCRETE, CENTERED
ON SONOTUBE, PRIMED AND
PAINTED SAFETY YELLOW
W/ YELLOW PLASTIC SLEEVE
R E
C E
S S
EQUIPT. MAT
SECTION "D"
CONTRACTION JOINT
SILICONE CAULK,
2" MIN. DEPTH; AS
MANUFACTURED BY
GE OR DOW CORNING3/16"
(MIN.)
M
IN
TANK MAT
SIDE SIDE
DISCONTINUE
REBAR ACROSS
JOINT LOCATION
R E
C E
S S
BLDG. FND.
SECTION "F"
EXPANSION JOINT
SILICONE CAULK, 1" MIN.
DEPTH; AS MANUFACTURED
BY GE OR DOW CORNING
BITUMINOUS FIBER
EXPANSION JOINT PER
ASTM D-1751, FULL
DEPTH OF CONCRETE
1/2"
(MIN.)
TRAILER APRON
OR VAPORIZER FND
M
IN
OR TANK FND.
OR EQUIVALENT SYSTEM
VHANYNSituJ
Project No. 630-22-116 Project Title. Replace Oxygen Tank DWGs are reference ONLY. Contractor to verify field conditions
Project No. 630-22-116 Project Title. Replace Oxygen Tank DWGs are reference ONLY. Contractor to verify field conditions
Project No. 630-22-116 Project Title. Replace Oxygen Tank DWGs are reference ONLY. Contractor to verify field conditions
Project No. 630-22-116 Project Title. Replace Oxygen Tank DWGs are reference ONLY. Contractor to verify field conditions
Project No. 630-22-116 Project Title. Replace Oxygen Tank DWGs are reference ONLY. Contractor to verify field conditions
| 150M-400-1369 Tank Dims |
| 9000 gal PL-ATM-Foundation |
| VAI806FL12 DRAWING 50250400 REVISION 0 3-10-21 to Current |
| VAI836FL12 DRAWING 50250404 REVISION 0 3-10-21 TO CURRENT |
| VS 9000 OD and Dims drawing |
File details come from the government source that posted it. Updated .