36C24222Q0599 0001.docx

DOCX document 19 KB Posted

Attached to
Y1DA--526-22-207 - AHU's Coil Replacement Federal contract opportunity
Solicitation number
36C24222Q0599
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--526-22-207 - AHU's Coil Replacement, newest first.
File Type Posted
Site Visit Sign in Sheet.pdf PDF
StartUpChecklist.docx DOCX document
A-1_100-H158 Schedules.pdf PDF
A-1_100-H156 Schedules.pdf PDF
A-1_100-H155 Schedules.pdf PDF
36C24222Q0599_1.docx DOCX document
A-1_CHW Coil Replacement GF Research Redline 1.pdf PDF
A-1_100-H157 Schedules 2F 3B CHW Cooling Coil.pdf PDF
A-1_100-H113 2F Mechanical Service Bay Plans.pdf PDF
A-1_100-HVAC Schedules.pdf PDF
A-1_100-H32 3rd Floor Plan-Area-B.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 526-22-3-636-0367 526-22-207 36C242 Department of Veterans Affairs Network Contracting Office 2 Saint Albans VA Medical Center 179-00 Linden Blvd, Room D-202 Jamaica

NY

10425 36C242 Department of Veterans Affairs Saint Albans VA Medical Center Network Contracting Office 2 179-00 Linden Blvd, Room D-202 Jamaica

NY

10425 To all Offerors/Bidders

36C24222Q0599 04-22-2022

X X X

X Amendment 0001 to Solicitation 36C24222Q0599, Project 526-22-207 - AHU's Coil Replacement at James J. Peters VAMC. The purpose of this modification is to respond to inquiries received by the Contracting Officer.

SEE CONTINUATION PAGE FOR DETAILS.

1. The RFP shows four (4) coils but there are really five (5) coils found during last week’s site visit. Are all five being replaced?

Answer: Yes, all five coils are to be replaced. The SOW was updated to demonstrate the new coil count.

1. Expedited fabrication charges were requested. 10 days fabrication?

Answer: The POP is to complete all work 45 days from Notice to proceed. The contractor shall determine the appropriate amount of expedited time needed to support his schedule.

1. For AHU-1, are we insulating piping that is not insulated currently? The RFP says replace any damaged insulation. It doesn’t specify “missing” insulation.

Answer: The contractor shall replace only the missing sections of the insulation. New insulation shall match existing or close and equal to performance.

1. The RFP does not bring attention replacing coil drip pans. Is there anything to be done to the current drip pans? Sealing, etc.?

Answer: Drip pans for cooling coils is standard and shall be included part of the system. Please ensure to include this with the newly installed cooling coils.

1. Area 2F, AHU-15 – the scope calls to replace 1 of 2 coils in the AHU. Is the coil to be replaced the top or bottom coil? Replacing one coil may involve completely removing the other, especially if the bottom coil is to be replaced.

Answer: All five coils are to be replaced. The SOW was updated to demonstrate the new coil count.

1. The scope calls for vibration checks, and coil pressure drop testing. Please clarify if this is to be performed by a certified third-party testing and balancing contractor?

Answer: Vibration checks are specific to ensuring contractor did not cause the blower fan out of alignment or specifications. Pressure drop test can be demonstrated with the newly installed gauges. Contractor will be in charge for ensuring flow is present in the new coil.

1. Can you please provide the “StartUpChecklist” document – it was not provided with the rest of the solicitation documents, or we were unable to find it.

Answer: See attachment StartUpChecklist

1. AHU-1 GF piping is partially insulated with ½” ArmaFlex and partially uninsulated above an adjacent AHU. Please specify the insulation type for replacement insulation.

Answer: The contractor shall replace only the missing sections of the insulation. New insulation shall match existing or close and equal to performance.

1. Coils are available with lead time options that have considerable and differing associated costs. For example, a 10-day, 25-day or 45-day lead time may be available. Please give guidance as to the desired lead time for coil production.

Answer: The POP is to complete all work 45 days from Notice to proceed. The contractor shall determine the appropriate amount of expedited time needed to support his schedule.

See attached document: Site Visit Sign in Sheet.

See attached document: StartUpChecklist.

File details come from the government source that posted it. Updated .