36C10E19B0001-001.docx
DOCX document 146 KB Posted
- Attached to
- AMO/DROC, BLD 47 | St. Pete Federal contract opportunity
- Solicitation number
- 36C10E19B0001
About this file
36C10E19B0001 36C10E19B0001_1.docx
View the file
Other files for this federal contract opportunity
Show all 50
AMO/DROC, BLD 47 | St. Pete has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C10E19B0001
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6.
PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV.
8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that t ime. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government accepta nce after the date offers are due will not be considered and will be rejected.
VA
36C10E19B0001 X 04-03-2019 3176-000057 00101 Department of Veterans Affairs Veterans Benefits Administration Office of Acquisition 1800 G. Street N.W.
Washington DC 20006 Department of Veterans Affairs Veterans Benefits Administration
Scott Russell 336-251-0633 Contractor shall provide all manpower, tools , equipment, and material to renovate BLDG 47 in accordance with the SOW.
The contractor shall review existing conditions and address site constraints and uncertainties.
Construction shall be in accordance with OSHA, Federal, State and Local codes and/or requirements.
Construction Wage Determination for Pinellas County FL, is applicable.
This project is 100% set-side for CVE certified Service Disabled Veteran Owned Small Business' (SDVOSB) c apable of meeting the requirements set forth in this solicitation.
This requirement is a Total Service Disabled Veteran Owned Small Business (SDVOSB) Set-aside in accordancewith Public Law 109-461, Veterans First Program. Only offers from SDVOSB concerns that are registered and verified the Center for Verification and Evaluation (CVE) Vendor Information Pages (VIP) websiteat https://www.vip.vetbiz.gov/ of offers shall be considered for award. Offers from SDVOSB concerns that are not registered shall be rejected as non-responsive and shall not be considered for award.
NAICS Code: 236 Construction range of magnitude in accordance with VAAR 836.204 is estimated to be between $2,000,000 and $5,000,000.
Bid Bond, Payment Bond and Performance bonds are required for this project.
Certifi cate of Insurance indicating the contractor possesses the required General Liability and Workman's Compensation Insurance is required. The Contractor shall furnish a Certificate of Insurance at time of bid submission.
The site visit will be held on 24 April 2019 at 9:00 AM, EST. at:
VBA Regional Office 9500 Bay Pines BLVD.
St. Petersburg, FL 33708 All participants must RSVP by 12:00 AM EST on 24 April 2019 by contacting Scott Russell by email at scott.russell@va.gov
All questions pertaining to this solicitation or site visitshall be directed to Scott Russell at scott.russell@va.govAll Questions are due by 7:00 AM EST on 29 April 2019.
Questions will be collated and answered in the form of an amendment
X X 52.211-10 X See Pg. 43-44 05-07-2019 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMEN
DMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR
OR PERSON AUTHORIZED
31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to i ssuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
00101 Department of Veterans Affairs Veterans Benefits Administration Office of Acquisition 1800 G. Street N.W.
Washington DC 20006 All invoices must be emailed to:
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTS | 6 |
| B.1 PRICE/COST SCHEDULE | 6 |
| ITEM INFORMATION | 6 |
| SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK | 7 |
| C.1 STATEMENT OF WORK | 7 |
| SECTION D - PACKAGING AND MARKING | 8 |
| [For this Solicitation, there are NO clauses in this Section] | 8 |
| SECTION E - INSPECTION AND ACCEPTANCE | 9 |
| SECTION F - DELIVERIES OR PERFORMANCE | 10 |
| F.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) | 10 |
| F.2 DELIVERY SCHEDULE | 10 |
| SECTION G - CONTRACT ADMINISTRATION DATA | 11 |
| [For this Solicitation, there are NO clauses in this Section] | 11 |
| SECTION H - SPECIAL CONTRACT REQUIREMENTS | 12 |
| PART II - CONTRACT CLAUSES | 13 |
| SECTION I - CONTRACT CLAUSES | 13 |
| I.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 13 |
| I.2 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 15 |
| I.3 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008) | 15 |
| I.4 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018) | 16 |
| I.5 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (JUL 2002) | 18 |
| I.6 VAAR 852.236-74 INSPECTION OF CONSTRUCTION (JUL 2002) | 19 |
| I.7 VAAR 852.236-76 CORRESPONDENCE (APR 1984) | 19 |
| I.8 VAAR 852.236-77 REFERENCE TO "STANDARDS" (JUL 2002) | 20 |
| I.9 VAAR 852.236-78 GOVERNMENT SUPERVISION (APR 1984) | 20 |
| I.10 VAAR 852.236-79 DAILY REPORT OF WORKERS AND MATERIAL (APR 1984) | 20 |
| I.11 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 1984) | 20 |
| I.12 VAAR 852.236-84 SCHEDULE OF WORK PROGRESS (NOV 1984) | 21 |
| I.13 VAAR 852.236-85 SUPPLEMENTARY LABOR STANDARDS PROVISIONS (APR 1984) | 21 |
| I.14 VAAR 852.236-86 WORKER'S COMPENSATION (JAN 2008) | 22 |
| I.15 VAAR 852.236-87 ACCIDENT PREVENTION (SEP 1993) | 22 |
| I.16 VAAR 852.236-88 CONTRACT CHANGES--SUPPLEMENT (JUL 2002) | 22 |
| I.17 VAAR 852.236-91 SPECIAL NOTES (JUL 2002) | 24 |
| I.18 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 25 |
| I.19 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (JUL 2018) | 25 |
| I.20 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 26 |
| I.21 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013) | 27 |
| I.22 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (OCT 2015) | 28 |
| I.23 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUL 2014) | 29 |
| I.24 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010) | 29 |
| I.25 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014) | 31 |
| I.26 SUPPLEMENTAL INSURANCE REQUIREMENTS | 33 |
| I.27 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2016)(DEVIATION) | 34 |
| I.28 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 35 |
| I.29 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 35 |
| I.30 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (JUL 2002) | 37 |
| I.31 VAAR 852.236-89 BUY AMERICAN ACT (JAN 2008) | 37 |
| PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS | 38 |
| SECTION J - LIST OF ATTACHMENTS | 38 |
| PART IV - REPRESENTATIONS AND INSTRUCTIONS | 39 |
| SECTION K - REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS | 39 |
| K.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (OCT 2018) | 39 |
| K.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 42 |
| K.3 52.209-13 VIOLATION OF ARMS CONTROLS TREATIES OR AGREEMENTS—CERTIFICATION (JUN 2018) | 43 |
| SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS | 46 |
| BIDDER INFORMATION / INSTRUCTIONS | 46 |
| L.1 52.214-31 FACSIMILE BIDS (DEC 1989) | 47 |
| L.2 52.216-1 TYPE OF CONTRACT (APR 1984) | 48 |
| L.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 48 |
| L.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 49 |
| L.5 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) ALTERNATE I (MAY 2014) | 50 |
| L.6 52.228-1 BID GUARANTEE (SEP 1996) | 51 |
| L.7 52.233-2 SERVICE OF PROTEST (SEP 2006) | 51 |
| L.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 52 |
| L.9 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 52 |
| L.10 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018) | 52 |
| L.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 53 |
| L.12 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE (JAN 2008) | 53 |
| SECTION M - EVALUATION FACTORS FOR AWARD | 54 |
| M.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 54 |
| STATEMENT OF WORK | 55 |
SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTS
B.1 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1.00 |
| EA |
| __________________ |
| __________________ |
The Contractor shall provide all management, labor, tools, supplies, and resources necessary for the complete renovation of the office space in accordance with the Specifications, Drawings and Statement of Work.
| 0.00 |
| JB |
| __________________ |
| __________________ |
ALTERNATE NO.1: Omit renovations of the 2nd floor not including above ceiling work required for the 3rd floor.
| 1.00 |
| LT |
| __________________ |
| __________________ |
The Contractor shall provide all management, labor, tools, supplies, and resources necessary for the provision and installation of the furniture for the office space in accordance with the Specifications, Drawings and Statement of Work.
| GRAND TOTAL |
| __________________ |
36C10E19B0001 Section B
Page 1 of Page 1 of
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 STATEMENT OF WORK
36C10E19B0001 Section C The statement of work is included as an attachment.
Page 1 of Page 1 of
SECTION D - PACKAGING AND MARKING
[For this Solicitation, there are NO clauses in this Section] 36C10E19B0001 Section D
Page 1 of Page 1 of
SECTION E - INSPECTION AND ACCEPTANCE
36C10E19B0001 Section E
Page 1 of Page 1 of
| FAR Number |
| Title |
| Date |
| 52.246-12 |
| INSPECTION OF CONSTRUCTION |
| AUG 1996 |
SECTION F - DELIVERIES OR PERFORMANCE
| FAR Number |
| Title |
| Date |
| 52.242-14 |
| SUSPENSION OF WORK |
| APR 1984 |
F.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 180 days after receipt of award. The time stated for completion shall include final cleanup of the premises.
(End of Clause)
F.2 DELIVERY SCHEDULE
| ITEM NUMBER |
| QUANTITY |
| DELIVERY DATE |
| 0001 |
| SHIP TO: |
| 9500 Bay Pines BLVD |
Saint Petersburg, FL 33708
USA
1.00
| MARK FOR: |
| Dennis Ecord |
(727) 319-5800 x 6705 dennis.ecord@va.gov
| 0002 |
| SHIP TO: |
| 9500 Bay Pines BLVD |
Saint Petersburg, FL 33708
USA
0.00
| MARK FOR: |
| Dennis Ecord |
| 0003 |
| SHIP TO: |
| 9500 Bay Pines BLVD |
Saint Petersburg, FL 33708
USA
| 1.00 |
| 180 Days ARO |
| MARK FOR: |
| Dennis Ecord |
36C10E19B0001 Section F
Page 1 of
SECTION G - CONTRACT ADMINISTRATION DATA
[For this Solicitation, there are NO clauses in this Section] 36C10E19B0001 Section G
Page 1 of Page 1 of
SECTION H - SPECIAL CONTRACT REQUIREMENTS
36C10E19B0001 Section H
PART II - CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES
I.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/
(End of Clause)
| FAR Number |
| Title |
| Date |
| 52.202-1 |
| DEFINITIONS |
| NOV 2013 |
| 52.203-3 |
| GRATUITIES |
| APR 1984 |
| 52.203-5 |
| COVENANT AGAINST CONTINGENT FEES |
| MAY 2014 |
| 52.203-6 |
| RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT |
| SEP 2006 |
| 52.203-7 |
| ANTI-KICKBACK PROCEDURES |
| MAY 2014 |
| 52.203-8 |
| CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY |
| MAY 2014 |
| 52.203-10 |
| PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY |
| MAY 2014 |
| 52.203-12 |
| LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS |
| OCT 2010 |
| 52.203-17 |
| CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS |
| APR 2014 |
| 52.203-19 |
| PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS OR STATEMENTS |
| JAN 2017 |
| 52.204-4 |
| PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER |
| MAY 2011 |
| 52.204-9 |
| PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL |
| JAN 2011 |
| 52.204-10 |
| REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS |
| OCT 2018 |
| 52.204-13 |
| SYSTEM FOR AWARD MANAGEMENT MAINTENANCE |
| OCT 2018 |
| 52.204-14 |
| SERVICE CONTRACT REPORTING REQUIREMENTS |
| OCT 2016 |
| 52.204-18 |
| COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE |
| JUL 2016 |
| 52.209-6 |
| PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT |
| OCT 2015 |
| 52.209-10 |
| PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS |
| NOV 2015 |
| 52.211-6 |
| BRAND NAME OR EQUAL |
| AUG 1999 |
| 52.214-26 |
| AUDIT AND RECORDS—SEALED BIDDING |
| OCT 2010 |
| 52.214-27 |
| PRICE REDUCTION FOR DEFECTIVE CERTIFIED COST OR PRICING DATA—MODIFICATIONS—SEALED BIDDING |
| AUG 2011 |
| 52.214-28 |
| SUBCONTRACTOR CERTIFIED COST OR PRICING DATA—MODIFICATIONS—SEALED BIDDING |
| OCT 2010 |
| 52.214-29 |
| ORDER OF PRECEDENCE—SEALED BIDDING |
| JAN 1986 |
| 52.219-8 |
| UTILIZATION OF SMALL BUSINESS CONCERNS |
| OCT 2018 |
| 52.222-3 |
| CONVICT LABOR |
| JUN 2003 |
| 52.222-4 |
| CONTRACT WORK HOURS AND SAFETY STANDARDS—OVERTIME COMPENSATION |
| MAY 2018 |
| 52.222-6 |
| CONSTRUCTION WAGE RATE REQUIREMENTS |
| AUG 2018 |
| 52.222-7 |
| WITHHOLDING OF FUNDS |
| MAY 2014 |
| 52.222-8 |
| PAYROLLS AND BASIC RECORDS |
| AUG 2018 |
| 52.222-9 |
| APPRENTICES AND TRAINEES |
| JUL 2005 |
| 52.222-10 |
| COMPLIANCE WITH COPELAND ACT REQUIREMENTS |
| FEB 1988 |
| 52.222-11 |
| SUBCONTRACTS (LABOR STANDARDS) |
| MAY 2014 |
| 52.222-12 |
| CONTRACT TERMINATION—DEBARMENT |
| MAY 2014 |
| 52.222-13 |
| COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND RELATED REGULATIONS |
| MAY 2014 |
| 52.222-14 |
| DISPUTES CONCERNING LABOR STANDARDS |
| FEB 1988 |
| 52.222-15 |
| CERTIFICATION OF ELIGIBILITY |
| MAY 2014 |
| 52.222-21 |
| PROHIBITION OF SEGREGATED FACILITIES |
| APR 2015 |
| 52.222-26 |
| EQUAL OPPORTUNITY |
| SEP 2016 |
| 52.222-27 |
| AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION |
| APR 2015 |
| 52.222-37 |
| EMPLOYMENT REPORTS ON VETERANS |
| FEB 2016 |
| 52.222-50 |
| COMBATING TRAFFICKING IN PERSONS |
| JAN 2019 |
| 52.222-54 |
| EMPLOYMENT ELIGIBILITY VERIFICATION |
| OCT 2015 |
| 52.222-55 |
| MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 |
| DEC 2015 |
| 52.222-62 |
| PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 |
| JAN 2017 |
| 52.223-5 |
| POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION |
| MAY 2011 |
| 52.223-6 |
| DRUG-FREE WORKPLACE |
| MAY 2001 |
| 52.223-18 |
| ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING |
| AUG 2011 |
| 52.223-21 |
| FOAMS |
| JUN 2016 |
| 52.225-13 |
| RESTRICTIONS ON CERTAIN FOREIGN PURCHASES |
| JUN 2008 |
| 52.227-1 |
| AUTHORIZATION AND CONSENT |
| DEC 2007 |
| 52.227-2 |
| NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT |
| DEC 2007 |
| 52.227-4 |
| PATENT INDEMNITY—CONSTRUCTION CONTRACTS |
| DEC 2007 |
| 52.228-2 |
| ADDITIONAL BOND SECURITY |
| OCT 1997 |
| 52.228-5 |
| INSURANCE—WORK ON A GOVERNMENT INSTALLATION |
| JAN 1997 |
| 52.228-11 |
| PLEDGES OF ASSETS |
| AUG 2018 |
| 52.228-12 |
| PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS |
| MAY 2014 |
| 52.228-14 |
| IRREVOCABLE LETTER OF CREDIT |
| NOV 2014 |
| 52.228-15 |
| PERFORMANCE AND PAYMENT BONDS—CONSTRUCTION |
| OCT 2010 |
| 52.229-3 |
| FEDERAL, STATE, AND LOCAL TAXES |
| FEB 2013 |
| 52.232-5 |
| PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS |
| MAY 2014 |
| 52.232-17 |
| INTEREST |
| MAY 2014 |
| 52.232-23 |
| ASSIGNMENT OF CLAIMS |
| MAY 2014 |
| 52.232-27 |
| PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS |
| JAN 2017 |
| 52.232-33 |
| PAYMENT BY ELECTRONIC FUNDS TRANSFER—SYSTEM FOR AWARD MANAGEMENT |
| OCT 2018 |
| 52.232-39 |
| UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS |
| JUN 2013 |
| 52.232-40 |
| PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS |
| DEC 2013 |
| 52.233-1 |
| DISPUTES |
| MAY 2014 |
| 52.233-3 |
| PROTEST AFTER AWARD |
| AUG 1996 |
| 52.233-4 |
| APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM |
| OCT 2004 |
| 52.236-2 |
| DIFFERING SITE CONDITIONS |
| APR 1984 |
| 52.236-3 |
| SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK |
| APR 1984 |
| $ |
| 52.236-5 |
| MATERIAL AND WORKMANSHIP |
| APR 1984 |
| 52.236-6 |
| SUPERINTENDENCE BY THE CONTRACTOR |
| APR 1984 |
| 52.236-7 |
| PERMITS AND RESPONSIBILITIES |
| NOV 1991 |
| 52.236-8 |
| OTHER CONTRACTS |
| APR 1984 |
| 52.236-9 |
| PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS |
| APR 1984 |
| 52.236-10 |
| OPERATIONS AND STORAGE AREAS |
| APR 1984 |
| 52.236-11 |
| USE AND POSSESSION PRIOR TO COMPLETION |
| APR 1984 |
| 52.236-12 |
| CLEANING UP |
| APR 1984 |
| 52.236-13 |
| ACCIDENT PREVENTION |
| NOV 1991 |
| 52.236-14 |
| AVAILABILITY AND USE OF UTILITY SERVICES |
| APR 1984 |
| 52.236-15 |
| SCHEDULES FOR CONSTRUCTION CONTRACTS |
| APR 1984 |
| 52.236-17 |
| LAYOUT OF WORK |
| APR 1984 |
| 52.236-21 |
| SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION |
| FEB 1997 |
| 52.236-26 |
| PRECONSTRUCTION CONFERENCE |
| FEB 1995 |
| 52.242-13 |
| BANKRUPTCY |
| JUL 1995 |
| 52.243-4 |
| CHANGES |
| JUN 2007 |
| 52.244-6 |
| SUBCONTRACTS FOR COMMERCIAL ITEMS |
| JAN 2019 |
| 52.246-21 |
| WARRANTY OF CONSTRUCTION |
| MAR 1994 |
| 52.248-3 |
| VALUE ENGINEERING—CONSTRUCTION |
| OCT 2015 |
| 52.249-2 |
| TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED PRICE) ALTERNATE I (SEPT 1996) |
| APR 2012 |
| 52.249-10 |
| DEFAULT (FIXED-PRICE CONSTRUCTION) |
| APR 1984 |
| 52.253-1 |
| COMPUTER GENERATED FORMS |
| JAN 1991 |
I.2 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)
The Contractor shall not make reference in its commercial advertising to Department of Veterans Affairs contracts in a manner that states or implies the Department of Veterans Affairs approves or endorses the Contractor’s products or services or considers the Contractor’s products or services superior to other products or services.
(End of Clause)
I.3 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)
When net changes in original contract price affect the premium of a Corporate Surety Bond by $5 or more, the Government, in determining the basis for final settlement, will provide for bond premium adjustment computed at the rate shown in the bond.
(End of Clause) I.4 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018) The clause FAR 52.232–5, Payments Under Fixed-Price Construction Contracts, is implemented as follows:
(a) Retainage.
(1) The Contracting Officer may retain funds—
(i) Where performance under the contract has been determined to be deficient or the Contractor has performed in an unsatisfactory manner in the past; or
(ii) As the contract nears completion, to ensure that deficiencies will be corrected and that completion is timely.
(2) Examples of deficient performance justifying a retention of funds include, but are not restricted to, the following—
(i) Unsatisfactory progress as determined by the Contracting Officer;
(ii) Failure to meet schedule in Schedule of Work Progress;
(iii) Failure to present submittals in a timely manner; or
(iv) Failure to comply in good faith with approved subcontracting plans, certifications, or contract requirements.
(3) Any level of retention shall not exceed 10 percent either where there is determined to be unsatisfactory performance, or when the retainage is to ensure satisfactory completion. Retained amounts shall be paid promptly upon completion of all contract requirements, but nothing contained in this paragraph (a)(3) shall be construed as limiting the Contracting Officer’s right to withhold funds under other provisions of the contract or in accordance with the general law and regulations regarding the administration of Government contracts.
(b) The Contractor shall submit a schedule of cost to the Contracting Officer for approval within 30 calendar days after date of receipt of notice to proceed. Such schedule will be signed and submitted in triplicate. The approved cost schedule will be one of the bases for determining progress payments to the Contractor for work completed. This schedule shall show cost by the work activity/event for each building or unit of the contract, as instructed by the resident engineer.
(1) The work activities/events shall be subdivided into as many sub-activities/events as are necessary to cover all component parts of the contract work.
(2) Costs as shown on this schedule must be true costs and the resident engineer may require the Contractor to submit the original estimate sheets or other information to substantiate the detailed makeup of the schedule.
(3) The sums of the sub-activities/events, as applied to each work activity/event, shall equal the total cost of such work activity/event. The total cost of all work activities/events shall equal the contract price.
(4) Insurance and similar items shall be prorated and included in the cost of each branch of the work.
(5) The cost schedule shall include separate cost information for the systems listed in the table in this paragraph (b)(5). The percentages listed in the following table are proportions of the cost listed in the Contractor’s cost schedule and identify, for payment purposes, the value of the work to adjust, correct and test systems after the material has been installed. Payment of the listed percentages will be made only after the Contractor has demonstrated that each of the systems is substantially complete and operates as required by the contract.
VALUE OF ADJUSTING, CORRECTING, AND TESTING SYSTEM
| System |
| Percent |
| Pneumatic tube system………………………………………………………………………………. |
| 10 |
| Incinerators (medical waste and trash)……………………………………………………….. |
| 5 |
| Sewage treatment plant equipment……………………………………………………………. |
| 5 |
| Water treatment plant equipment……………………………………………………………… |
| 5 |
| Washers (dish, cage, glass, etc.)………………………………………………………………….. |
| 5 |
| Sterilizing equipment……………………………………………………………………………….…. |
| 5 |
| Water distilling equipment…………………………………………………………………………. |
| 5 |
| Prefab temperature rooms (cold, constant temperature)………………………….. |
| 5 |
| Entire air-conditioning system (Specified under 600 Sections)…………………… |
| 5 |
| Entire boiler plant system (Specified under 700 Sections)………………………….. |
| 5 |
| General supply conveyors…………………………………………………………………………… |
| 10 |
| Food service conveyors………………………………………………………………………….…… |
| 10 |
| Pneumatic soiled linen and trash system…………………………………………………… |
| 10 |
| Elevators and dumbwaiters………………………………………………………………………… |
| 10 |
| Materials transport system…………………………………………………………………………. |
| 10 |
| Engine-generator system……………………………………………………………………………. |
| 5 |
| Primary switchgear……………………………………………………………………………………… |
| 5 |
| Secondary switchgear………………………………………………………………………………….. |
| 5 |
| Fire alarm system………………………………………………………………………………………… |
| 5 |
| Nurse call system………………………………………………………………………………………… |
| 5 |
| Intercom system………………………………………………………………………………………….. |
| 5 |
| Radio system……………………………………………………………………………………………….. |
| 5 |
| TV (entertainment) system………………………………………………………………………… |
| 5 |
(c) In addition to this cost schedule, the Contractor shall submit such unit costs as may be specifically requested. The unit costs shall be those used by the Contractor in preparing its bid and will not be binding as pertaining to any contract changes.
(d) The Contracting Officer will consider for monthly progress payments material and/or equipment procured by the Contractor and stored on the construction site, as space is available, or at a local approved location off the site, under such terms and conditions as the Contracting Officer approves, including but not limited to the following—
(1) The materials or equipment are in accordance with the contract requirements and/or approved samples and shop drawings;
(2) The materials and/or equipment are approved by the resident engineer;
(3) The materials and/or equipment are stored separately and are readily available for inspection and inventory by the resident engineer;
(4) The materials and/or equipment are protected against weather, theft and other hazards and are not subjected to deterioration; and
(5) The Contractor obtains the concurrence of its surety for off-site storage.
(e) The Government reserves the right to withhold payment until samples, shop drawings, engineer’s certificates, additional bonds, payrolls, weekly statements of compliance, proof of title, nondiscrimination compliance reports, or any other requirements of this contract, have been submitted to the satisfaction of the Contracting Officer.
(f) The Contracting Officer will notify the Contractor in writing within 10 calendar-days of exercising retainage against any payment in accordance with FAR clause 52.232–5(e). The notice shall disclose the amount of the retainage in value and percent retained from the payment, and provide explanation for the retainage.
(End of Clause)
I.5 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (JUL 2002)
The clause entitled "Performance of Work by the Contractor" in FAR 52.236-1 is supplemented as follows:
(a) Contract work accomplished on the site by laborers, mechanics, and foremen/forewomen on the contractor's payroll and under his/her direct supervision shall be included in establishing the percent of work to be performed by the contractor. Cost of material and equipment installed by such labor may be included. The work by the contractor's executive, supervisory and clerical forces shall be excluded in establishing compliance with the requirements of this clause.
(b) The contractor shall submit, simultaneously with the schedule of costs required by the Payments Under Fixed-Price Construction Contracts clause of the contract, a statement designating the branch or branches of contract work to be performed with his/her forces. The approved schedule of costs will be used in determining the value of a branch or branches, or portions thereof, of the work for the purpose of this article.
(c) If, during the progress of work hereunder, the contractor requests a change in the branch or branches of the work to be performed by his/her forces and the contracting officer determines it to be in the best interest of the Government, the contracting officer may, at his/her discretion, authorize a change in such branch or branches of said work. Nothing contained herein shall permit a reduction in the percentage of work to be performed by the contractor with his/her forces, it being expressly understood that this is a contract requirement without right or privilege of reduction.
(d) In the event the contractor fails or refuses to meet the requirement of the FAR clause at 52.236-1, it is expressly agreed that the contract price will be reduced by 15 percent of the value of that portion of the percentage requirement that is accomplished by others. For the purpose of this clause, it is agreed that 15 percent is an acceptable estimate of the contractor's overhead and profit, or mark-up, on that portion of the work which the contractor fails or refuses to perform, with his/her own forces, in accordance with the FAR clause at 52.236-1.
(End of Clause)
I.6 VAAR 852.236-74 INSPECTION OF CONSTRUCTION (JUL 2002)
The clause entitled "Inspection of Construction" in FAR 52.246-12 is supplemented as follows:
(a) Inspection of materials and articles furnished under this contract will be made at the site by the resident engineer, unless otherwise provided for in the specifications.
(b) Final inspection will not be made until the contract work is ready for beneficial use or occupancy. The contractor shall notify the contracting officer, through the resident engineer, fifteen (15) days prior to the date on which the work will be ready for final inspection.
(End of Clause)
I.7 VAAR 852.236-76 CORRESPONDENCE (APR 1984)
All correspondence relative to this contract shall bear Specification Number, Project Number, Department of Veterans Affairs Contract Number, title of project and name of facility.
(End of Clause)
I.8 VAAR 852.236-77 REFERENCE TO "STANDARDS" (JUL 2002)
Any materials, equipment, or workmanship specified by references to number, symbol, or title of any specific Federal, Industry or Government Agency Standard Specification shall comply with all applicable provisions of such standard specifications, except as limited to type, class or grade, or modified in contract specifications. Reference to "Standards" referred to in the contract specifications, except as modified, shall have full force and effect as though printed in detail in specifications.
(End of Clause)
I.9 VAAR 852.236-78 GOVERNMENT SUPERVISION (APR 1984)
(a) The work will be under the direction of the Department of Veterans Affairs contracting officer, who may designate another VA employee to act as resident engineer at the construction site.
(b) Except as provided below, the resident engineer's directions will not conflict with or change contract requirements.
(c) Within the limits of any specific authority delegated by the contracting officer, the resident engineer may, by written direction, make changes in the work. The contractor shall be advised of the extent of such authority prior to execution of any work under the contract.
(End of Clause)
I.10 VAAR 852.236-79 DAILY REPORT OF WORKERS AND MATERIAL (APR 1984)
The contractor shall furnish to the resident engineer each day a consolidated report for the preceding work day in which is shown the number of laborers, mechanics, foremen/forewomen and pieces of heavy equipment used or employed by the contractor and subcontractors. The report shall bear the name of the firm, the branch of work which they perform such as concrete, plastering, masonry, plumbing, sheet metal work, etc. The report shall give a breakdown of employees by crafts, location where employed, and work performed. The report shall also list materials delivered to the site on the date covered by the report.
(End of Clause)
I.11 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 1984)
(a) Nothing contained in this contract shall be construed as creating any contractual relationship between any subcontractor and the Government. Divisions or sections of specifications are not intended to control the contractor in dividing work among subcontractors, or to limit work performed by any trade.
(b) The contractor shall be responsible to the Government for acts and omissions of his/her own employees, and of the subcontractors and their employees. The contractor shall also be responsible for coordination of the work of the trades, subcontractors, and material suppliers.
(c) The Government or its representatives will not undertake to settle any differences between the contractor and subcontractors or between subcontractors.
(d) The Government reserves the right to refuse to permit employment on the work or require dismissal from the work of any subcontractor who, by reason of previous unsatisfactory work on Department of Veterans Affairs projects or for any other reason, is considered by the contracting officer to be incompetent or otherwise objectionable.
(End of Clause)
I.12 VAAR 852.236-84 SCHEDULE OF WORK PROGRESS (NOV 1984)
(a) The contractor shall submit with the schedule of costs, a progress schedule that indicates the anticipated installation of work versus the elapsed contract time, for the approval of the contracting officer. The progress schedule time shall be represented in the form of a bar graph with the contract time plotted along the horizontal axis. The starting date of the schedule shall be the date the contractor receives the "Notice to Proceed." The ending date shall be the original contract completion date. At a minimum, both dates shall be indicated on the progress schedule. The specific item of work, i.e., "Excavation", "Floor Tile", "Finish Carpentry", etc., should be plotted along the vertical axis and indicated by a line or bar at which time(s) during the contract this work is scheduled to take place. The schedule shall be submitted in triplicate and signed by the contractor.
(b) The actual percent completion will be based on the value of installed work divided by the current contract amount. The actual completion percentage will be indicated on the monthly progress report.
(c) The progress schedule will be revised when individual or cumulative time extensions of 15 calendar days or more are granted for any reason. The revised schedule should indicate the new contract completion date and should reflect any changes to the installation time(s) of the items of work affected.
(d) The revised progress schedule will be used for reporting future scheduled percentage completion.
(End of Clause)
I.13 VAAR 852.236-85 SUPPLEMENTARY LABOR STANDARDS PROVISIONS (APR 1984)
(a) The wage determination decision of the Secretary of Labor is set forth in section GR, General Requirements, of this contract. It is the result of a study of wage conditions in the locality and establishes the minimum hourly rates of wages and fringe benefits for the described classes of labor in accordance with applicable law. No increase in the contract price will be allowed or authorized because of payment of wage rates in excess of those listed.
(b) The contractor shall submit the required copies of payrolls to the contracting officer through the resident engineer or engineer officer, when acting in that capacity. Department of Labor Form WH- 347, Payroll, available from the Superintendent of Documents, Government Printing Office, Washington, DC 20402, may be used for this purpose. If, however, the contractor or subcontractor elects to use an individually composed payroll form, it shall contain the same information shown on Form WH-347, and in addition be accompanied by Department of Labor Form WH-348, Statement of Compliance, or any other form containing the exact wording of this form.
(End of Clause)
I.14 VAAR 852.236-86 WORKER'S COMPENSATION (JAN 2008)
Public Law 107-217 (40 U.S.C. 3172) authorizes the constituted authority of States to apply their workers compensation laws to all lands and premises owned or held by the United States.
(End of Clause)
I.15 VAAR 852.236-87 ACCIDENT PREVENTION (SEP 1993)
The Resident Engineer on all assigned construction projects, or other Department of Veterans Affairs employee if designated in writing by the Contracting Officer, shall serve as Safety Officer and as such has authority, on behalf of the Contracting Officer, to monitor and enforce Contractor compliance with FAR 52.236-13, Accident Prevention. However, only the Contracting Officer may issue an order to stop all or part of the work while requiring satisfactory or corrective action to be taken by the Contractor.
(End of Clause)
I.16 VAAR 852.236-88 CONTRACT CHANGES--SUPPLEMENT (JUL 2002)
The clauses entitled “Changes” in FAR 52.243-4 and “Differing Site Conditions” in FAR 52.236-2 are supplemented as follows:
(a) Paragraphs (a)(1) through (a)(4) apply to proposed contract changes costing over $500,000.
(1) When requested by the contracting officer, the contractor shall submit proposals for changes in work to the resident engineer. Proposals, to be submitted as expeditiously as possible but within 30 calendar days after receipt of request, shall be in legible form, original and two copies, with an itemized breakdown that will include material, quantities, unit prices, labor costs (separated into trades), construction equipment, etc. (Labor costs are to be identified with specific material placed or operation performed.) The contractor must obtain and furnish with a proposal an itemized breakdown as described above, signed by each subcontractor participating in the change regardless of tier. When certified cost or pricing data are required under FAR Subpart 15.403, the cost or pricing data shall be submitted in accordance with FAR 15.403-5.
(2) When the necessity to proceed with a change does not allow sufficient time to negotiate a modification or because of failure to reach an agreement, the contracting officer may issue a change order instructing the contractor to proceed on the basis of a tentative price based on the best estimate available at the time, with the firm price to be determined later. Furthermore, when the change order is issued, the contractor shall submit a proposal, which includes the information required by paragraph (a)(1), for cost of changes in work within 30 calendar days.
(3) The contracting officer will consider issuing a settlement by determination to the contract if the contractor's proposal required by paragraphs (a)(1) or (a)(2) of this clause is not received within 30 calendar days or if agreement has not been reached.
(4) Bond premium adjustment, consequent upon changes ordered, will be made as elsewhere specified at the time of final settlement under the contract and will not be included in the individual change.
(b) Paragraphs (b)(1) through (b)(11) apply to proposed contract changes costing $500,000 or less:
(1) When requested by the contracting officer, the contractor shall submit proposals for changes in work to the resident engineer. Proposals, to be submitted as expeditiously as possible but within 30 calendar days after receipt of request, shall be in legible form, original and two copies, with an itemized breakdown that will include material, quantities, unit prices, labor costs (separated into trades), construction equipment, etc. (Labor costs are to be identified with specific material placed or operation performed.) The contractor must obtain and furnish with a proposal an itemized breakdown as described above, signed by each subcontractor participating in the change regardless of tier. When certified cost or pricing data or information other than cost or pricing data are required under FAR 15.403, the data shall be submitted in accordance with FAR 15.403-5. No itemized breakdown will be required for proposals amounting to less than $1,000.
(2) When the necessity to proceed with a change does not allow sufficient time to negotiate a modification or because of failure to reach an agreement, the contracting officer may issue a change order instructing the contractor to proceed on the basis of a tentative price based on the best estimate available at the time, with the firm price to be determined later. Furthermore, when the change order is issued, the contractor shall submit within 30 calendar days, a proposal that includes the information required by paragraph (b)(1) for the cost of the changes in work.
(3) The contracting officer will consider issuing a settlement by determination to the contract if the contractor's proposal required by paragraphs (b)(1) or (b)(2) of this clause is not received within 30 calendar days, or if agreement has not been reached.
(4) Allowances not to exceed 10 percent each for overhead and profit for the party performing the work will be based on the value of labor, material, and use of construction equipment required to accomplish the change. As the value of the change increases, a declining scale will be used in negotiating the percentage of overhead and profit. Allowable percentages on changes will not exceed the following: 10 percent overhead and 10 percent profit on the first $20,000; 7-1/2 percent overhead and 7-1/2 percent profit on the next $30,000; 5 percent overhead and 5 percent profit on balance over $50,000. Profit shall be computed by multiplying the profit percentage by the sum of the direct costs and computed overhead costs.
(5) The prime contractor's or upper-tier subcontractor's fee on work performed by lower-tier subcontractors will be based on the net increased cost to the prime contractor or upper-tier subcontractor, as applicable. Allowable fee on changes will not exceed the following: 10 percent fee on the first $20,000; 7-1/2 percent fee on the next $30,000; and 5 percent fee on balance over $50,000.
(6) Not more than four percentages, none of which exceed the percentages shown above, will be allowed regardless of the number of tiers of subcontractors.
(7) Where the contractor's or subcontractor's portion of a change involves credit items, such items must be deducted prior to adding overhead and profit for the party performing the work. The contractor's fee is limited to the net increase to contractor of subcontractors' portions cost computed in accordance herewith.
(8) Where a change involves credit items only, a proper measure of the amount of downward adjustment in the contract price is the reasonable cost to the contractor if he/she had performed the deleted work. A reasonable allowance for overhead and profit are properly includable as part of the downward adjustment for a deductive change. The amount of such allowance is subject to negotiation.
(9) Cost of Federal Old Age Benefit (Social Security) tax and of Worker's Compensation and Public Liability insurance appertaining to changes are allowable. While no percentage will be allowed thereon for overhead or profit, prime contractor's fee will be allowed on such items in subcontractors' proposals.
(10) Overhead and contractor's fee percentages shall be considered to include insurance other than mentioned herein, field and office supervisors and assistants, security police, use of small tools, incidental job burdens, and general home office expenses and no separate allowance will be made therefore. Assistants to office supervisors include all clerical, stenographic and general office help. Incidental job burdens include, but are not necessarily limited to, office equipment and supplies, temporary toilets, telephone and conformance to OSHA requirements. Items such as, but not necessarily limited to, review and coordination, estimating and expediting relative to contract changes are associated with field and office supervision and are considered to be included in the contractor's overhead and/or fee percentage.
(11) Bond premium adjustment, consequent upon changes ordered, will be made as elsewhere specified at the time of final settlement under the contract and will not be included in the individual change.
(End of Clause)
I.17 VAAR 852.236-91 SPECIAL NOTES (JUL 2002)
(a) Signing of the bid shall be deemed to be a representation by the bidder that:
(1) Bidder is a construction contractor who owns, operates, or maintains a place of business, regularly engaged in construction, alteration, or repair of buildings, structures, and communications facilities, or other engineering projects, including furnishing and installing of necessary equipment; or
(2) If newly entering into a construction activity, bidder has made all necessary arrangements for personnel, construction equipment, and required licenses to perform construction work; and
(3) Upon request, prior to award, bidder will promptly furnish to the Government a statement of facts in detail as to bidder's previous experience (including recent and current contracts), organization (including company officers), technical qualifications, financial resources and facilities available to perform the contemplated work.
(b) Unless otherwise provided in this contract, where the use of optional materials or construction is permitted, the same standard of workmanship, fabrication and installation shall be required irrespective of which option is selected. The contractor shall make any change or adjustment in connecting work or otherwise necessitated by the use of such optional material or construction, without additional cost to the Government.
(c) When approval is given for a system component having functional or physical characteristics different from those indicated or specified, it is the responsibility of the contractor to furnish and install related components with characteristics and capacities compatible with the approved substitute component as required for systems to function as noted on drawings and specifications. There shall be no additional cost to the Government.
(d) In some instances it may have been impracticable to detail all items in specifications or on drawings because of variances in manufacturers' methods of achieving specified results. In such instances the contractor will be required to furnish all labor, materials, drawings, services and connections necessary to produce systems or equipment which are completely installed, functional, and ready for operation by facility personnel in accordance with their intended use.
(e) Claims by the contractor for delay attributed to unusually severe weather must be supported by climatological data covering the period and the same period for the 10 preceding years. When the weather in question exceeds in intensity or frequency the 10-year average, the excess experienced shall be considered "unusually severe." Comparison shall be on a monthly basis. Whether or not unusually severe weather in fact delays the work will depend upon the effect of weather on the branches of work being performed during the time under consideration.
(End of Clause) I.18 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) The Contractor's representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
(End of Clause) I.19 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (JUL 2018)
(a) Definitions. As used in this clause—Covered article means any hardware, software, or service that—
(1) Is developed or provided by a covered entity;
(2) Includes any hardware, software, or service developed or provided in whole or in part by a covered entity; or
(3) Contains components using any hardware or software developed in whole or in part by a covered entity.
Covered entity means—
(1) Kaspersky Lab;
(2) Any successor entity to Kaspersky Lab;
(3) Any entity that controls, is controlled by, or is under common control with Kaspersky Lab; or
(4) Any entity of which Kaspersky Lab has a majority ownership.
(b) Prohibition. Section 1634 of Division A of the National Defense Authorization Act for Fiscal Year 2018 (Pub. L. 115–91) prohibits Government use of any covered article. The Contractor is prohibited from—
(1) Providing any covered article that the Government will use on or after October 1, 2018; and
(2) Using any covered article on or after October 1, 2018, in the development of data or deliverables first produced in the performance of the contract.
(c) Reporting requirement. (1) In the event the Contractor identifies a covered article provided to the Government during contract performance, or the Contractor is notified of such by a subcontractor at any tier or any other source, the Contractor shall report, in writing, to the Contracting Officer or, in the case of the Department of Defense, to the website at https://dibnet.dod.mil. For indefinite delivery contracts, the Contractor shall report to the Contracting Officer for the indefinite delivery contract and the Contracting Officer(s) for any affected order or, in the case of the Department of Defense, identify both the indefinite delivery contract and any affected orders in the report provided at https://dibnet.dod.mil.
(2) The Contractor shall report the following information pursuant to paragraph (c)(1) of this clause:
(i) Within 1 business day from the date of such identification or notification: The contract number; the order number(s), if applicable; supplier name; brand; model number (Original Equipment Manufacturer (OEM) number, manufacturer part number, or wholesaler number); item description; and any readily available information about mitigation actions undertaken or recommended.
(ii) Within 10 business days of submitting the report pursuant to paragraph (c)(1) of this clause: Any further available information about mitigation actions undertaken or recommended.