MAY 2019 – TEAM B NAC CONSOLIDATION SCHEDULE –
Ultrasounds and Portables
| Dates* |
| Milestone – All Modalities |
| 5/1/2019 |
| Requirements/Requests due to the NAC |
| 5/14/2019 |
| Pre-Solicitation Notice posted to FBO |
| 5/21/2019 |
| Post requirements (RFQ) to FBO |
| 6/04/2019 |
| Deadline for Vendors to submit questions to NAC |
| 6/18/2019 |
| Deadline for NAC to respond to Vendor Questions |
| 7/02/2019 |
| Deadline for Vendor to submit quotes to NAC |
| 7/16/2019 |
| Deadline for Customers to receive vendor quotes via the shared drive |
| 8/20/2019 |
| Deadline for Customer to submit Best Value Selections |
| 9/24/2019 |
| Deadline for NAC to complete review of Selection Justifications |
| 10/29/2019 |
| Goal to award all Delivery Orders |
*Dates are estimates and are subject to change