3 - SOW_B801 RM101_4.9.24.pdf
PDF 121 KB Posted
- Attached to
- Repair Building 801, Room 101
- Solicitation number
- W50S97B240002
- Issued by
-
Department of the Army National Guard
About this file
This document is a Statement of Work (SOW) for the repair of Building 801, Room 101 at the 118th Wing Tennessee Air National Guard, Nashville International Airport. The contractor shall provide all management, tools, equipment, transportation, supervision, and labor necessary to repair the facilities as shown on the contract drawings and specifications. The key tasks include furnishing and installing gypsum board, wall insulation, ceiling tiles, rubber wall base, and carpet flooring; priming and painting; and electrical work. The performance period for this project is 90 calendar days, and the contractor must submit weekly activity reports and 4 new pictures to the Contracting Officer's Representative.
The related federal contract opportunity is a pre-solicitation for the Repair Building 801, Room 101 project, which will be issued as an Invitation for Bids. The contract is set aside 100% for Small Businesses under NAICS code 236220, with a construction magnitude between $25,000 and $100,000. The tentative solicitation issuance date is on-or-about 7 June 2024, with a pre-bid conference on-or-about 18 June 2024 and a bid opening on-or-about 10 July 2024. Interested offerors must be registered in the System for Award Management (SAM).
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
UNITED STATES AIR FORCE
118th Wing Tennessee Air National Guard
Berry Field Air National Guard Base, Nashville, TN
STATEMENT OF WORK
Bldg 801 Room 101 Repairs
BKTZ222004
8 April 2024
1.0 STATEMENT OF WORK
1.1. The contractor shall provide, unless otherwise noted, all management, tools, equipment, transportation, supervision, and labor necessary to repair the facilities as shown on contract drawings and specifications, Nashville, International Airport
(IAP) Repair building 801 (B801), room 101, Attachment 1 and 2, hereinafter referred to as "plans". Contractor shall perform all work in accordance with this Statement of Work (SOW) and the plans. Contractor shall coordinate all work with the Contracting Officer and Civil Engineer office and is subject to the work schedule as stated in this document. Upon completion, the facility must be complete and usable for the entire base populace.
1.2. These requirements, together with the technical specifications, standards, and drawings specified in the contract documents, cover the requirements for all work associated with Repair B801, room 101, Nashville IAP. The following section is a general description of the work involved:
1.3. Provide all material and services required to perform the following services as listed on plans:
1.3.1. Furnish, and install gypsum board with mudding, taping, and finishes
1.3.2. Furnish and install wall insulation
1.3.3. Match existing ceiling tile in areas tiles are missing. Furnish and Install tiles.
1.3.4. Furnish and install rubber wall base
1.3.5. Prime and paint areas shown in plans
1.3.6. Demolish, furnish, and install carpet in room as listed on plans. Carpet tiles are non-patterned loop 24” x 24” tiles with a nominal face weight of 20 oz. Samples to be provided for final selection per section 3.1.2 in plans.
1.3.7. Paint existing doors and frames in all areas being worked in plans. Paint corridor window frames to match in building
801.
1.3.8. Add/replace damaged/missing acoustic ceiling tile support bars and affix ceiling mounted electrical fixtures as listed on plans
1.3.9. Affix wall mounted electrical outlets and communication outlets.
1.4. Work shall be performed as shown on the plans and as described in this document.
1.4.1. Contractor will provide material for and perform all work to repair and replace damaged and missing interior walls, flooring, and insulation. Installation of interior walls, doors, base board, and flooring with associated connections and fittings. The contractor must submit dust/debris plan (see attached AF66) that describes measures to prevent the entrance of dust/debris in the areas where work is to be performed. Contractor must provide submittals of materials to the Civil
Engineer. (See Submittals Section Below.)
1.4.2. All materials shall meet or exceed all applicable referenced standards, local requirements, and conform to codes and ordinances of authorities having jurisdiction.
1.4.3. Prepare work site and ensure that dimensions are as indicated on shop drawings.
1.4.4. Coordinate with base authorities to obtain all passes required to enter the work site.
1.5. .INSTALLATION:
1.5.1. Installation shall meet or exceed all applicable federal, state and local requirements, referenced standards and conform to codes and ordinances of authorities having jurisdiction.
1.5.2. All equipment and material installations shall be in accordance with manufacturer’s published specifications and guidelines.
1.5.3. Contractor shall furnish all parts, assembly, and connections during construction.
1.6. EXECUTION
1.6.1. The performance period for this project is 90 calendar days.
1.6.2 FIELD QUALITY CONTROL: Contractor shall generate and send activity reports to the COR at james.bell.69@us.af.mil each week with a summary of work completed and 4 new pictures of completed work during the period of performance.
2.0 SPECIFICATIONS – B801 repairs: Contractor SHALL comply with the following items:
2.1. PART 1 – GENERAL
2.1.1. SUBMITTALS: Manufacturer's product literature, data, and warranty information. Contractor will provide three samples of carpet tile for final selection by Base Civil Engineer from manufacturer’s product catalog.
2.1.2. MATERIALS:
2.1.2.1. Gypsum Wall Board
2.1.2.2. Paint
2.1.2.3. Ceiling Tile
2.1.2.4. Ceiling Tile Support Bars
2.1.2.5. Carpet Flooring
2.1.2.6. Wall insulation
2.1.2.7. Associated fittings and connections
2.1.2.8. Supply additional 15% of carpet covering to COR for attic stock
File details come from the government source that posted it. Updated .