Ralph Brennan Water Treatment Plant Storm Hardening & Resiliency Project

This Request for Qualifications (RFQ) is issued by the City of Daytona Beach, Florida, for progressive design-build services to harden and upgrade the Ralph Brennan Water Treatment Plant (WTP), the city's only potable water treatment facility serving over 100,000 customers. The project encompasses four primary components located at the WTP—electrical system replacement, lime softening basin expansion, finished storage expansion, and chlorine generation system conversion—plus an optional fifth component for distribution system hardening. The project addresses infrastructure vulnerabilities from extreme weather events, improves operational efficiency through replacement of obsolete equipment, and increases process reliability through system redundancy. The RFQ was released August 18, 2026, with a pre-proposal meeting on August 26, 2026, and a non-mandatory site visit on September 2, 2026, both at the WTP located at 3651 LPGA Boulevard, Daytona Beach, Florida. Questions and interpretation requests are due by September 15, 2026, at 5:00 p.m., with RFQ responses due September 22, 2026, at 2:00 p.m. Step 1 evaluation (Selection Committee Meeting) is scheduled for the week of October 5, 2026, followed by Step 2 interviews the week of October 26, 2026. Contract negotiations are anticipated to begin the week of November 2, 2026, with City Commission approval expected in February 2027. The anticipated final project completion date is July 2031, with a funding hard deadline of December 15, 2031.

The project is fully funded through the Supplemental Appropriation for Hurricanes Helene and Milton and Hawai'i Wildfires (SAHM) under Florida's Drinking Water State Revolving Fund (DWSRF) with a sponsor cap allocation of $35,139,169 and an additional $7,435,831 on the waiting list; additional funding may be sourced from the General SRF Program or other eligible grant programs. The project must comply with American Iron and Steel (AIS) and Davis-Bacon Wage Rate statutes; Build America Buy America (BABA) requirements may apply if supplemental federal funding is added. The designer must meet qualifications of professional services as defined in Florida Statutes 287.055(2), and the design-build team must meet qualifications as defined in Florida Statutes 287.055(5). A single master contract will be issued with multiple Guaranteed Maximum Price (GMP) submissions anticipated to procure long-lead items and address critical vulnerabilities sequentially. Evaluation will occur in two phases: Phase 1 assesses team qualifications (15%), collaborative delivery approach (20%), builder past performance (35%), and designer past performance (30%); Phase 2 (for shortlisted teams) evaluates team organization (20%), team member qualifications and experience (30%), and project understanding and delivery approach (50%). Design-build teams must demonstrate experience with water treatment facility projects of at least 15 million gallons per day permitted capacity, substantially completed within ten years of the RFP due date.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. INTRODUCTION

1.1. Summary

The City of Daytona Beach is hereby soliciting responses from qualified Design-Build Teams to provide progressive design build services for the design and construction of a hardening and upgrades project at the Ralph Brennan Water Treatment Plant (WTP).

The project consists of four individual components located at the WTP with a fifth component that covers the potable water distribution system. This project will address several key needs within the City’s only water treatment facility including hardening critical infrastructure and improving operational efficiency and reliability.

Ralph Brennan WTP

The Ralph Brennan WTP is the City’s only water treatment facility and provides potable water to over

100,000 customers located throughout the Cities of Daytona Beach and South Daytona and portions of

Daytona Beach Shores and unincorporated areas of Volusia County. The WTP was originally constructed in the mid-1970’s and was expanded in the mid-1980’s. Since that time, process specific improvements have taken place, but no plant-wide projects have occurred. The WTP is permitted as a lime softening treatment facility capable of treating up to 24 million gallons per day (MGD) of potable water. Given the age of the facility and being located within a coastal community, the facility is highly susceptible to impacts from extreme weather events such as hurricanes. Localized site flooding has occurred on-site during past hurricane events and wind-driven rain has rendered electrical components inoperable. In addition to the environmental vulnerabilities, various treatment components have been identified to have reliability concerns, including operational deficiencies and equipment obsolescence.

A complete Design Criteria Package is included with the RFQ and provides further details on the project and its individual components.

Project Funding

This project is fully funded by the Supplemental Appropriation for Hurricanes Helene and Milton and

Hawai'i Wildfires (SAHM) under the State of Florida's Drinking Water State Revolving Fund (DWSRF).

SAHM funding was eligible due to damage sustained and disruption of essential functions where there was potential impact to public health caused by Hurricane Milton. In June 2025, the City submitted a

Request for Inclusion (RFI) for funding related to damage sustained from Hurricane Milton and, in

November 2025, the City was placed on the SAHM Priority List for the Sponsor Cap amount of

$35,139,169, with an additional $7,435,831 placed on the waiting list. Depending on construction costs, the SAHM allocation may need to be supplemented with additional funding. While it is anticipated that any additional funding needed will come from the General SRF Program, the selected Design-Build Team will work with the City to identify and apply for other grant programs for which this project might be eligible for. Additionally, limited portions of the project will be funded directly by the City.

The following provisions will apply to this project given SRF funding:

• FDEP Supplementary Conditions have been included with the RFQ for reference as they will be applicable to the construction phase of this project.

Request For Proposal #2659RFQ Title: 2659RFQ - Ralph Brennan WTP Storm Hardening & Resiliency Project

• Given the project funding mechanisms, the entirety of this project will be required to comply with

American Iron and Steel (AIS) and Davis-Bacon Wage Rates statutes. Should the project be fully funded from the SAHM allocation, Build America Buy America (BABA) requirements will not apply to this project. However, if supplemental federal funding is added to this project, then BABA may become applicable. In that case, the Design-Build Team may be asked to provide cost analytics with BABA during creation of the guaranteed maximum price submissions (GMPs) to determine if a waiver is justified.

• The Designer on the selected Design-Build Team shall meet the qualifications of 'professional services' as defined in F.S. 287.055 (2).

• The Design-Build Team shall meet the qualifications of a 'design-build' team as defined in F.S.

287.055 (5).

1.2. Background

Project Overview

The City of Daytona Beach (City) is undertaking the Ralph Brennan Water Treatment Plant (WTP)

Hardening and Upgrades Project. This project will address several key needs within the City’s only water treatment facility, including:

1. Harden critical infrastructure from extreme weather events.

2. Improve operational efficiency through the replacement of obsolete infrastructure and addressing condition concerns.

3. Increase process reliability through the addition of system redundancy.

This project consists of four (4) individual components located at the WTP as listed below in Table 1.

1.3. Contact Information

Purchasing Purchasing

Purchasing Agent

301 S. Ridgewood Ave.

Daytona Beach, FL 32114

Email: purchasing@daytonabeach.gov

Phone: (386) 671-8082

Department:

Utilities Department

1.4. Timeline

Release Project Date August 18, 2026

Pre-Proposal Meeting (Non-Mandatory) August 26, 2026, 10:00am

Join:

https://teams.microsoft.com/meet/285489183744

038?p=YgGIM7okhLcbiwTDck

Meeting ID: 285 489 183 744 038

Passcode: Ui9wf3MT

Dial in by phone

+1 312-667-7230,,296502825# United States, Chicago

Phone conference ID: 296 502 825# https://teams.microsoft.com/l/meetup-join/19%3ameeting_NmI4OWQ3ZDAtNjZiMS00ZjU xLTlmZjItZGU0OGNmNjFlNzgz%40thread.v2/0?cont ext=%7b%22Tid%22%3a%22112fe1e2-c356-4b5a-

885a-

669fa41090ef%22%2c%22Oid%22%3a%22c87eed1

5-230f-4ec1-9c22-f6810ed3a341%22%7d

Non-Mandatory Site Visit (Non-Mandatory)

(Non-Mandatory)

September 2, 2026, 10:00am

Please meet at Ralph Brennan Water Treatment

Plant

3651 LPGA Blvd.

Daytona Beach, FL 32124 mailto:purchasing@daytonabeach.gov tel:(386)671-8082 https://teams.microsoft.com/meet/285489183744038?p=YgGIM7okhLcbiwTDck https://teams.microsoft.com/meet/285489183744038?p=YgGIM7okhLcbiwTDck https://teams.microsoft.com/l/meetup-join/19%3ameeting_NmI4OWQ3ZDAtNjZiMS00ZjUxLTlmZjItZGU0OGNmNjFlNzgz%40thread.v2/0?context=%7b%22Tid%22%3a%22112fe1e2-c356-4b5a-885a-669fa41090ef%22%2c%22Oid%22%3a%22c87eed15-230f-4ec1-9c22-f6810ed3a341%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_NmI4OWQ3ZDAtNjZiMS00ZjUxLTlmZjItZGU0OGNmNjFlNzgz%40thread.v2/0?context=%7b%22Tid%22%3a%22112fe1e2-c356-4b5a-885a-669fa41090ef%22%2c%22Oid%22%3a%22c87eed15-230f-4ec1-9c22-f6810ed3a341%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_NmI4OWQ3ZDAtNjZiMS00ZjUxLTlmZjItZGU0OGNmNjFlNzgz%40thread.v2/0?context=%7b%22Tid%22%3a%22112fe1e2-c356-4b5a-885a-669fa41090ef%22%2c%22Oid%22%3a%22c87eed15-230f-4ec1-9c22-f6810ed3a341%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_NmI4OWQ3ZDAtNjZiMS00ZjUxLTlmZjItZGU0OGNmNjFlNzgz%40thread.v2/0?context=%7b%22Tid%22%3a%22112fe1e2-c356-4b5a-885a-669fa41090ef%22%2c%22Oid%22%3a%22c87eed15-230f-4ec1-9c22-f6810ed3a341%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_NmI4OWQ3ZDAtNjZiMS00ZjUxLTlmZjItZGU0OGNmNjFlNzgz%40thread.v2/0?context=%7b%22Tid%22%3a%22112fe1e2-c356-4b5a-885a-669fa41090ef%22%2c%22Oid%22%3a%22c87eed15-230f-4ec1-9c22-f6810ed3a341%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_NmI4OWQ3ZDAtNjZiMS00ZjUxLTlmZjItZGU0OGNmNjFlNzgz%40thread.v2/0?context=%7b%22Tid%22%3a%22112fe1e2-c356-4b5a-885a-669fa41090ef%22%2c%22Oid%22%3a%22c87eed15-230f-4ec1-9c22-f6810ed3a341%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_NmI4OWQ3ZDAtNjZiMS00ZjUxLTlmZjItZGU0OGNmNjFlNzgz%40thread.v2/0?context=%7b%22Tid%22%3a%22112fe1e2-c356-4b5a-885a-669fa41090ef%22%2c%22Oid%22%3a%22c87eed15-230f-4ec1-9c22-f6810ed3a341%22%7d

Question and Request for Interpretation

Submission Deadline

September 15, 2026, 5:00pm

RFQ Due Date/Open RFQs September 22, 2026, 2:00pm

Join:

https://teams.microsoft.com/meet/291735620298

998?p=zoenvLosEDzKd4Tl9c

Meeting ID: 291 735 620 298 998

Passcode: Fy3m63gq

Dial in by phone

+1 312-667-7230,,12022716# United States, Chicago

Phone conference ID: 120 227 16# https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDBmZjY2NTEtOGM3OC00N mVhLWJjMzItMmYwMDM0YTg4ZGRi%40thread.v2

/0?context=%7b%22Tid%22%3a%22112fe1e2-c356-4b5a-885a-

669fa41090ef%22%2c%22Oid%22%3a%22c87eed1

5-230f-4ec1-9c22-f6810ed3a341%22%7d

Step 1 Evaluation (Selection Committee

Meeting)

Week of October 5, 2026

Step 2 Evaluation (Interviews) Week of October 26, 2026

Begin Phase I Contract Negotiations Week of November 2, 2026

City Commission Approval/Notice February 2027

Anticipated Final Completion July 2031

Funding Hard Deadline (with final reimbursement submitted by January 31, 2032)

December 15, 2031 https://teams.microsoft.com/meet/291735620298998?p=zoenvLosEDzKd4Tl9c https://teams.microsoft.com/meet/291735620298998?p=zoenvLosEDzKd4Tl9c https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDBmZjY2NTEtOGM3OC00NmVhLWJjMzItMmYwMDM0YTg4ZGRi%40thread.v2/0?context=%7b%22Tid%22%3a%22112fe1e2-c356-4b5a-885a-669fa41090ef%22%2c%22Oid%22%3a%22c87eed15-230f-4ec1-9c22-f6810ed3a341%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDBmZjY2NTEtOGM3OC00NmVhLWJjMzItMmYwMDM0YTg4ZGRi%40thread.v2/0?context=%7b%22Tid%22%3a%22112fe1e2-c356-4b5a-885a-669fa41090ef%22%2c%22Oid%22%3a%22c87eed15-230f-4ec1-9c22-f6810ed3a341%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDBmZjY2NTEtOGM3OC00NmVhLWJjMzItMmYwMDM0YTg4ZGRi%40thread.v2/0?context=%7b%22Tid%22%3a%22112fe1e2-c356-4b5a-885a-669fa41090ef%22%2c%22Oid%22%3a%22c87eed15-230f-4ec1-9c22-f6810ed3a341%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDBmZjY2NTEtOGM3OC00NmVhLWJjMzItMmYwMDM0YTg4ZGRi%40thread.v2/0?context=%7b%22Tid%22%3a%22112fe1e2-c356-4b5a-885a-669fa41090ef%22%2c%22Oid%22%3a%22c87eed15-230f-4ec1-9c22-f6810ed3a341%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDBmZjY2NTEtOGM3OC00NmVhLWJjMzItMmYwMDM0YTg4ZGRi%40thread.v2/0?context=%7b%22Tid%22%3a%22112fe1e2-c356-4b5a-885a-669fa41090ef%22%2c%22Oid%22%3a%22c87eed15-230f-4ec1-9c22-f6810ed3a341%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDBmZjY2NTEtOGM3OC00NmVhLWJjMzItMmYwMDM0YTg4ZGRi%40thread.v2/0?context=%7b%22Tid%22%3a%22112fe1e2-c356-4b5a-885a-669fa41090ef%22%2c%22Oid%22%3a%22c87eed15-230f-4ec1-9c22-f6810ed3a341%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDBmZjY2NTEtOGM3OC00NmVhLWJjMzItMmYwMDM0YTg4ZGRi%40thread.v2/0?context=%7b%22Tid%22%3a%22112fe1e2-c356-4b5a-885a-669fa41090ef%22%2c%22Oid%22%3a%22c87eed15-230f-4ec1-9c22-f6810ed3a341%22%7d

2. DEFINITIONS

THESE TERMS ARE STANDARD FOR ALL SOLICITATIONS ISSUED BY THE CITY OF DAYTONA BEACH. THE CITY

MAY DELETE, SUPERSEDE, OR MODIFY ANY OF THESE FOR A PARTICULAR SOLICITATION BY USE OF SPECIAL

PROVISIONS.

Certain terms used herein will have the following meanings. Note some defined terms are not relevant to this

Solicitation:

Addenda means written or graphic instruments issued prior to the end of the Offer Phase which clarify, correct, or change the Solicitation documents or Contract documents. Also means Addendum.

Bid means Solicitation Submission, or Proposal, submitted by a Bidder on the prescribed forms setting forth the prices for the work to be performed, and in the case of a Request for Proposals, the credentials, qualifications, and proposed project approach.

Bidder one who submits a response to a Solicitation; also means Proposer or Respondent.

City means The City of Daytona Beach, unless the context indicates otherwise, includes the City’s officers, employees, and agents.

Commodities means the supplies, materials, goods, merchandise, food, equipment, or other personal property, excluding real property, that the Bidder will be obligated to provide the City under any resulting Contract.

References to commodities shall mean goods.

Contract means the form Contract, if any, required by the City in order to integrate all terms and conditions therein, provided by the City for the Bidder’s execution and includes 1) the Solicitation documents 2) the Offer

Package, 3) the Resolution or Ordinance 4) all Purchase Orders issued pursuant to the Solicitation documents

5) all amendments that may after the date of award be executed by the Bidder and the City 6) any addenda 7) any other Solicitation Documents. Also means an Agreement to purchase Goods or Services or both, regardless of whether the agreement is reduced to a single written document.

Electronic Signature means the original signature transmitted and received via electronic transmission of a scanned document, (e.g., PDF or similar format) and are true and valid signatures for all purposes hereunder and shall bind the parties to the same extent as that of an original signature. Any such electronic counterpart shall be of sufficient quality to be legible either electronically or when printed as hardcopy. The City shall determine legibility and acceptability for public record purposes.

Florida Prompt Payment Act means F.S. §§ 255.0705—255.078, as amended from time to time.

Goods means the supplies, materials, commodities, merchandise, food, equipment, or other personal property, excluding real property, that the Bidder will be obligated to provide the City under any resulting

Contract. References to Goods shall mean Commodities.

Local Vendor means a person or business entity which has maintained a permanent place of business with full-time employees within the city limits for a minimum of six months prior to the date Offers were received for the purchase or Contract at issue, which generally provides from such permanent place of business the kinds of Goods or Services solicited, and which at the time of the Solicitation fully complies with state and local laws, including City zoning and licensing ordinances.

Notice of Intent to Award (NOI) means a written notice given by the City stating that staff is recommending award to the listed Proposer. It includes instructions for completing and submitting any Contract that accompanies the NOI.

Offer means Solicitation Submission, Bid, or Proposal, submitted by a Bidder on the prescribed forms setting forth the prices for the work to be performed, and in the case of a Request for Proposals, the credentials, qualifications, and proposed project approach.

Platform means OpenGov, the software currently used by the City. All communications regarding this

Solicitation will be posted at www.codb.us/841/purchasing through the Public Solicitations link. Bidders MUST submit Offers through the Platform. The Platform is utilized by the City and the Bidders to: 1) Allow Bidders to register and manage their company records, 2) Post and issue City Solicitation packages for Bidders from inception to award of a Solicitation, 3) Allow Bidders to submit an Offer Package online, electronically, through the Platform, 4) Allow Bidders to view all public record documents related to an online Solicitation.

Pricing Sheet means the area within the Platform where Bidders will provide their pricing response for the

Solicitation. Also known as Bid Schedule.

Proposal means Solicitation Submission, or Bid, submitted by a Bidder on the prescribed forms setting forth the prices for the work to be performed, and in the case of a Request for Proposals, the credentials, qualifications, and proposed project approach.

Proposer means one who submits a response to a Solicitation; also means Bidder or Respondent

Purchase Order means a written document to an awarded Proposer formalizing the terms and conditions of a proposed transaction.

Respondent one who submits a response to a Solicitation; also means Proposer or Bidder.

Responsible refers to a Proposer that has the necessary skills, ability, capacity, and capability to perform the work required under a Solicitation and is otherwise eligible for award.

Responsive means conforming in all respects to the Solicitation Package, except minor irregularities.

Services means a Proposer's ability to comply with promised delivery dates, specifications, and technical assistance. Also means the furnishing of labor, time, or other form of effort.

Solicitation means the group or collection of information that constitutes detailing the requirements and requesting responses or submittals from eligible Proposers. The information may be in the form of electronic documents, files, and information contained in data fields in the Platform.

Solicitation Deadline means the specific date a time that a Solicitation is due. No Offers will be accepted after this time.

Tabulation Sheet means the opening results of a Solicitation. The Proposer's name, City, and Offer Price will be recorded for Invitations to Bid.

Vendor means Contractor, Consultant, Respondent, Supplier or Proposer to whom the Contract is awarded.

3. SCOPE OF WORK

3.1. SCOPE

List of Potential Design Build Services

The following list provides guidance on tasks that are anticipated to be included in the Design Builder’s work. Additional items may be identified during contract negotiations. Services may include, but are not limited to:

• Grant funding identification and support services

• Selection of component and system locations

• Evaluation of equipment/processes

• Creation of Facilities Plan in accordance with SRF requirements for both SAHM and base-SRF programs

• Support services to ensure compliance with SAHM and base-SRF programs

• Public utility studies, surveys and coordination

• Subsurface utility location and engineering

• Geotechnical engineering and testing

• Survey of existing conditions

• Validation of project site conditions

• Engineering Design

• Project scheduling (design and construction)

• Hydraulic evaluation of proposed improvements

• Coordination and installation of Owner-provided Equipment

• Cost estimating and reporting

• Preliminary and Final development of Guaranteed Maximum Price

• Value engineering

• Lifecycle cost analysis

• Coordination with outside agencies for easements/permitted crossings

• Scheduling of design, construction, and logistics

• Regulatory permitting

• CEI services

• FDEP SRF Administration Services

• Davis-Bacon Wage Determination/Interviews/Tracking

• Maintaining AIS/BABA compliance, as applicable

• Right of way acquisition

• Construction of selected improvements

• System start-up and testing

• Maintenance of plant operations

• Training in the operations of the improvements

• Inspection and closeout

• Commissioning

• Operation and Maintenance manuals

• Warranty bonds (if any)

• Extended warranty period

• As-Built documentation

3.2. PROJECT COMPONENTS

Project Components

The project components are listed below with a brief description of the work. Additional details are provided in the Design Criteria Package including project background, project objectives, and supporting documentation.

• Ralph Brennan WTP - Electrical System Replacement: Replacement/upgrade of the electrical system at the Brennan WTP with focus on hardening and resiliency against storm impacts.

• Ralph Brennan WTP - Lime Softening Basin Expansion: Evaluation and construction of additional lime softening capacity, including necessary improvements to existing lime silos and ancillary lime handling facilities, as needed, with focus on hardening and resiliency against storm impacts.

• Ralph Brennan WTP - Finished Storage Expansion: Sizing and addition of on-site finished water storage tank and improvements to transfer pump system.

• Ralph Brennan WTP – Chlorine Generation System: Conversion of bulk chlorine storage system to on-site hypo generation system, to include storage tank and building improvements as necessary.

• Ralph Brennan WTP – Distribution System Hardening: Evaluation of distribution system to provide scenarios and improvements needed to ensure adequate pressure and redundancy during storm impacts. This project component is being included, but will only be moved forward if additional funding is identified.

3.3. Non-Mandatory Site Visit Schedule

There is a non-mandatory site visit scheduled for Wednesday, September 2, 2026, at 10:00am.

Please meet at the Ralph Brennan Water Treatment Plant

Address:

3651 LPGA Blvd.

Daytona Beach, FL 32124

4. SPECIAL PROVISIONS

4.1. E-VERIFY

E-Verify. - The Proposer (and its subcontractors) have an obligation to utilize the U.S. Department of

Homeland Security’s (DHS) E-Verify system for all newly hired employees. By executing this Contract, the

Proposer certifies that it is registered with, and uses, the E-Verify system for all newly hired employees.

The Contractor must obtain an affidavit from its subcontractors in accordance with paragraph (2)(b) of section 448.095, F.S., and maintain a copy of such affidavit for the duration of the Contract.

This section serves as notice to the Proposer regarding the requirements of section 448.095, F.S., specifically sub-paragraph (2)(c)1, and the City’s obligation to terminate the contract if it has a good faith belief that the Proposer has knowingly violated section 448.09(1), F.S. If terminated for such reason, the

Proposer will not be eligible for award of a public contract for at least one year after the date of such termination. The City reserves the right to order the immediate termination of any contract between the

Proposer and a subcontractor performing work on its behalf should the City develop a good faith belief that the subcontractor has knowingly violated section 448.095(1), F.S.

4.2. RESTRICTIONS, PROHIBITIONS

A. A person or affiliate who has been placed on the Convicted Vendor List following a conviction for a public entity crime may not submit a Proposal to provide any goods or services to a public entity; may not submit a Proposal on a contract with a public entity for the construction or repair of a public building or public work; may not submit a Proposal on leases of real property to a public entity; may not be awarded or perform work as a Contractor, Supplier, subcontractor or Consultant under a contract with any public entity; and may not transact business with any public entity in excess of the threshold amount provided in Section 287.017, Florida Statutes, for

CATEGORY TWO for a period of 36 months from the date of being placed on the Convicted

Vendor List.

B. In accordance with Section 287.134, Florida Statutes, an entity or affiliate who has been placed on the Discriminatory Vendor List, kept by the Florida Department of Management Services, may not submit a Proposal to provide goods or services to a public entity; may not submit Proposal with a public entity for the construction or repair of a public building or public work; may not submit proposals on leases of real property to a public entity; may not be awarded or perform work as a contractor, supplier, subcontractor or consultant under a contract with any public entity; and may not transact business with any public entity.

C. An entity or affiliate who has had its Certificate of Qualification suspended, revoked, denied or have further been determined by the Department to be a non-responsible Contractor may not submit a Proposal or perform work for the construction or repair of a public building or public work on a contract with the Recipient.

D. No funds received pursuant to this Agreement may be expended for lobbying the Florida

Legislature, judicial branch or any state agency.

4.3. FDEP SRF SUPPLEMENTARY CONDITIONS

FDEPs Supplementary Conditions for formally advertised construction procurement will apply to this project given the SRF funding associated with it. The latest version of this document is attached to this advertisement for reference.

4.4. CONTRACT ARRANGEMENT

A single contract will be issued for this project; however, it is anticipated that multiple GMPs will be issued to help procure long lead items, address the most critical vulnerabilities first, and ensure the project schedule is maintained. During the design phase of the project, the Design-Build Team will work with the City to determine the appropriate number and delineation of GMPs. The design phase at which the GMPs will be developed will be negotiated with the selected Design-Build Team, but Final GMPs will be developed no later than 90% design. The GMP process will involve an open-book breakdown of overall cost and will require the Design-Build Team to competitively bid the individual construction packages, which will be identified during design based on maximizing competition. The Design-Builder will be permitted to self-perform construction packages subject to being identified as the successful low bidder in accordance with the Contract documents.

5. GENERAL CONDITIONS

THIS IS NOT A BID. This is a Request for Qualifications issued in accordance with The City of Daytona Beach

Code Chapter 30, Division 3, “Source Selection and Contract Formation”. The Request for Qualifications specifies the product(s) or services needed and lists the criteria upon which the Proposals will be evaluated. When received, Qualifications will be reviewed and ranked in order, beginning with the one deemed most advantageous to the City. Negotiations will commence with the selected Proposer(s). Upon completion of satisfactory negotiations, the Contract negotiated as the best will be recommended to the

City Commission. A copy of Chapter 30 may be obtained upon request.

5.1. ELECTRONIC PLATFORM

To ensure consideration of your Proposal, please follow these instructions.

The City will only accept online Proposals for this Solicitation through the Platform accessible through

Opengov, the City's online procurement Platform. All solicitations can be accessed through the City’s website: www.codb.us/841/Purchasing under the link to “Public Solicitation”, then by selecting the proper solicitation.

No other forms of online Proposals will be accepted. All Proposals not in compliance with the conditions specified herein are subject to rejection.

Interested Proposers shall contact OpenGov Procurement Support related to any inquiries related to the software. Proposers may contact Support via the blue chat bubble in the bottom right corner of an

OpenGov Procurement webpage or can reach out via email at procurement-support@opengov.com or via phone at (855) 680-4747.

5.2. REQUESTS FOR INTERPRETATIONS

If the Proposer is in doubt as to the meaning of any of the Solicitation Documents or other Exhibits included in this Solicitation, the Proposer may submit a question through the Platform. Such requests must be received by the deadline communicated in the Timeline in the INTRODUCTION in order to be considered. The City is not obligated to respond to such requests.

5.3. ADDENDA TO SOLICITATION DOCUMENTS

Prior to Solicitation opening, the City may, on the City’s own initiative or in response to a request for clarification, furnish Addenda, or answer questions via the Platform for additions or alterations to the

Solicitation Documents previously supplied by the City. In addition, the City may by Addendum extend the date scheduled for Solicitation opening. The Purchasing representative will make reasonable efforts through the Platform to notify all potential Suppliers of the issuance of an Addendum. The City’s

Purchasing web site address is www.codb.us/841/Purchasing; Addenda may be found under the “Public

Solicitations” link.

Any clarification or interpretation issued by the City in the form of a written Addendum will be deemed to be a part of the Solicitation Documents. No oral clarification or interpretation will be binding. However, the Proposer is solely responsible for ensuring that the Proposal submitted reflects all such

Addenda/Questions and Answers.

5.4. EXECUTION OF OFFER

The City will only accept Offers online through the Platform. No paper Offers will be accepted.

All electronic files uploaded must be in a common format accessible by software programs the City uses.

Those common formats are generally described as Microsoft Word (.doc or .docx), Microsoft Excel (.xls or

.xlsx), Microsoft Power Point (.ppt or pptx), or Adobe Portable Document Format (.pdf.). Bidders will not secure, password protect or lock uploaded files; the City must be able to open and view the contents of the file. Bidders will not disable or restrict the ability of the City to print the contents of an uploaded file.

Scanned documents or images must be of sufficient quality, no less than 150 dpi, to allow for reading or https://procurement.opengov.com/portal/codb/projects/282087/document?section=2721411 interpreting the words, drawings, images or sketches. The City may disqualify any Offer that does not meet the criteria stated in this paragraph.

5.5. WITHDRAWAL OF OFFERS

The Proposer may withdraw their submission and resubmit anytime until the specified opening date and time, (i.e., the end of the Offer Phase). Once the Offer Phase has ended the City will be able to view the submissions and begin the evaluation of all Proposals received.

Mere negligence on the part of the Proposer in preparing the Offer does not constitute a right to withdraw the Proposal after opening.

5.6. OPENING DATE

The opening of Proposals will be scheduled at the date and time specified by the Solicitation, or as changed by Addenda or response that the City may issue. At opening, the City will open and record the Proposals so long as they are proper and have been timely submitted. In recording the Proposals, the City will state the name of the Proposer. The Tabulation Sheet will be created on the Platform by the Purchasing representative. The Proposer is solely responsible to ensure that the Proposal is submitted online prior to the end of the Offer Phase. Late Submissions will not be accepted.

5.7. GENERAL REVIEW PROCEDURES

The Purchasing Code, Chapter 30, Code of the City of Daytona Beach, sets forth the general review procedures for competitive sealed Offers. Under the Purchasing Code, the City Manager is required to evaluate and rank Responsive Proposals in accordance with the criteria identified in the Solicitation.

Before submitting a recommendation for final action on this Solicitation to the City Commission, the City

Manager is authorized to “shortlist’ and negotiate with one or more of the Proposers who submitted the highest ranked Proposals. As part of these negotiations, the City Manager may request revised Offers from shortlisted Proposers.

The City Manager has adopted a policy delegating the task of initially ranking Responsive Offers to a

Selection Committee. The Selection Committee may require personal interviews with Proposers before submitting its recommendations to the City Manager.

5.8. REJECTION OF OFFERS

The City reserves the right to reject any or all Proposals in whole or in part and to award by items, parts of items, or by any aggregate group of items specified. The City also reserves the right to waive technical defect when in its judgment the best interests of the City thereby will be served.

5.9. AWARD

The award will be made by the City to the Proposer most qualified and offering the best value to the City, which will be determined by evaluation of Proposals using the evaluation criteria contained in the

Solicitation, and in accordance with applicable rules and regulations governing the purchase and Contract adopted and established by the City, and the State of Florida.

5.10. SELECTION PROCESS

For the purpose of selecting the most qualified Proposal, the City will use a competitive selection process as set forth in pertinent City and State procurement requirements. The procedure will involve the following steps:

A. The City will advertise and email notice of formal Requests for Proposals to interested Proposers.

The City’s Selection Committee will review, rank, and shortlist all Proposals received by the established deadline for submission. Oral presentations by the short-listed Proposers to clarify their Offers may be required. These presentations will serve to explain implementation techniques integral to the written Proposal. Subsequent to the receipt of Proposals, the City may schedule a time for each requested oral presentation at a place convenient to the City.

B. The City’s Selection Committee will then rank each Proposal and prepare a recommendation for approval by the City Manager. Upon receipt of the City Manager’s approval, the City’s Project

Manager shall negotiate a contract with the highest ranked Proposer(s) approved by the City

Manager. Should the Project Manager be unable to negotiate a satisfactory contract with the any of the shortlisted Proposers, the City Manager, or designee, shall terminate such negotiations with any or all of the shortlisted Proposers and begin negotiations with remaining Proposers based on ranking, until negotiations are successful or this Solicitation is cancelled.

C. The City Commission has the sole authority to bind the City to the terms and conditions of a contract that has been approved in a public meeting of the City Commission. The City

Commission reserves the right to modify or reject any contract for the acquisition of goods and/or services submitted to it for consideration.

5.11. LICENSES, PERMITS, AND FEES

All Proposals submitted shall include in the price the cost of any business or professional licenses, permits or fees required by the City and any agency having jurisdiction over the Services solicited through this

Request for Proposal.

5.12. PATENT INFRINGEMENT

By submission of a Proposal, the Proposer certifies that the Services to be furnished will not infringe any valid patent, copyright, or trademark and the successful Proposer shall, at his/her own expense, defend any and all actions or suits charging such infringement and hold the City harmless in case of any such infringements.

5.13. TAXES

All Proposals shall be exclusive of federal taxes. Tax exemption certificates will be furnished upon request.

5.14. FLORIDA PUBLIC RECORDS LAW

Sealed Offers received by the City pursuant to the Request for Proposals will be temporarily exempt from disclosure in accordance with Florida’s Public Records Laws. F.S. §119, states that Offers are not public record for 30 days from the date of the opening of the Offers or the date a Notice of Intent to Award is posted, whichever is first. Thereafter, all Offers will be open for a personal inspection by any person pursuant to Public Records Law.

If the Proposer believes that the Offer or any portion thereof is permanently exempt from disclosure under the public records laws, the Proposer must state the grounds for this position in CAPITAL LETTERS in a certified letter addressed to the Purchasing Agent and received at least 3 days prior to the Offer opening. The Proposer will be contacted prior to the opening of the Offer and a determination will be made as to whether or not it is exempt prior to opening. If a determination is made that it is not exempt from disclosure, the Proposer may in writing request the return of the sealed Proposal.

5.15. QUALIFYING PROPOSERS

Prior to awarding of Offer, the City may require submission by Proposer of complete financial statement and questionnaire describing Proposer’s financial ability and experience in performance of similar work.

5.16. RULES AND REGULATIONS

All work performed under this agreement shall be in strict compliance with local, State and Federal laws, rules and regulations. Proposer shall assume all liability for fines and penalties assessed by the authorities for any infractions.

5.17. NO COSTS

The City of Daytona Beach bears no responsibility for any costs incurred in the preparation of the

Proposal.

5.18. INTERNET/WEB SERVICES

For the purposes of this paragraph, any Services or products offered to the public via the internet or online must comply with WCAG 2.0 AA in order to be deemed ADA compliant. The City will provide Contractor with prompt written notice with respect to any ADA deficiencies of which the City is aware and Contractor will promptly correct such deficiencies. If the County, the Department of Justice, or other governmental entity tasked with the enforcement of the ADA ("Enforcement Agency") notes any deficiency in the facilities, practices, services, or operations of the Contractor furnished or provided in connection with this

Agreement, Contractor shall, at no additional charge or cost to the City, immediately cure any such deficiencies without delay to the satisfaction of such Enforcement Agency. Contractor further agrees that it shall, to the extent permitted by law, indemnify, defend, and hold harmless the City against any and all claims, sanctions, or penalties assessed against the City, which claims, sanctions, or penalties arise or otherwise result from the Contractor's failure to comply with the ADA or WCAG 2.0 AA, for online or internet services or products.

5.19. DRUG FREE WORKPLACE

The selected Proposer must provide the Drug Free Workplace Form in accordance with Florida Statute

287.087, prior to Contract award.

5.20. PROHIBITION OF LOBBYING

Except for negotiations authorized by the City Purchasing Code, the Consultants Competitive Negotiations

Act, or other state or federal law, lobbying by the Proposer, or the Proposer’s principals, officers, employees, attorneys, or other agents, is strictly prohibited during the Blackout Period. Lobbying in violation of this section may cause the Offer to be rejected. “Lobbying” means influencing or attempting to influence action or non-action in connection with this Solicitation or the Offer, through direct or indirect oral or written communication with the Mayor, any member of the City Commission, the City Manager, or any other City employee.

The following activities are not within the definition of “lobbying,” and are permitted: requests for clarification submitted to the Purchasing Agent in accordance with this Solicitation, discussions with the

Selection Committee as part of the selection process, the submission of additional information in response to a request by the City and addressing the City Commission during the City Commission meeting at which the Contract is awarded, or all Offers are rejected.

The Blackout Period begins on the date that this Solicitation is issued and ends when the Contract is awarded or all Offers are rejected.

6. INDEMNIFICATION & INSURANCE REQUIREMENTS

6.1. Indemnification

The Design Builder shall indemnify and hold harmless the City of Daytona Beach, and its officers and employees, from liabilities, damages, losses, and costs, including, but not limited to, reasonable attorneys’ fees, to the extent caused by the negligence, recklessness, or intentional wrongful conduct of the design builder professional and other persons employed or utilized by the design builder professional in the performance of the contract. This indemnification agreement is separate and apart from, and in no way limited by, any insurance provided pursuant to this agreement or otherwise.

6.2. Insurance

Insurance.

DESIGN BUILDER will provide and maintain at DESIGN BUILDER’s own expense, at a minimum, insurance of the kinds of coverage and in the amounts set forth in this Section. All such insurance will be primary and non-contributory with the CITY’s own insurance. In the event any request for the performance of services presents exposures to the CITY not covered by the requirements set forth below, the CITY reserves the right to add insurance requirements that will cover such an exposure. Unless specifically waived hereafter in writing by the

CITY, DESIGN BUILDER agrees that the insurer(s) shall waive its rights of subrogation, if any, against the CITY on the listed insurance coverages in this section.

(a) Coverage and Amounts.

(1) Workers Compensation Insurance as required by Florida Statutes, Chapter 440 (and any other applicable federal laws), Workers’ Compensation Insurance, for all employees of DESIGN BUILDER, employed at the site of the service or in any way connected with the work, which is the subject of this service. The insurance required by this provision will comply fully with the Florida Workers’ Compensation Law and include

Employers’ Liability Insurance with limits of not less than $500,000 per occurrence. Any associated or subsidiary company involved in the service must be named in the Workers’ Compensation coverage.

(2) Liability Insurance, including:

(i) Commercial General Liability coverage for operations, independent contractors, products-completed operations, broad form property damage, and personal injury on an "occurrence" basis insuring

DESIGN BUILDER and any other interests, including but not limited to any associated or subsidiary companies involved in the work; and

(ii) Automobile Liability Insurance, which will insure claims for damages because of bodily injury or death of any person or property damage arising out of the ownership, maintenance, or use of any motor vehicle used by the DESIGN BUILDER in the performance of this Contract.

The limit of liability for each policy will be a combined single limit for bodily injury and property damage of no less than $1,000,000 per occurrence. If insurance is provided with a general aggregate, then the aggregate will be in an amount of no less than $2,000,000, project specific. The Risk Manager may authorize lower liability limits for the automobile policy only, at the Risk Manager’s sole discretion.

THE COMMERCIAL GENERAL LIABILITY INSURANCE POLICY WILL NAME THE CITY AS AN ADDITIONAL INSURED.

DESIGN BUILDER’s Commercial General Liability insurance policy shall provide coverage to DESIGN BUILDER, and CITY when required to be named as an additional insured either by endorsement or pursuant to a blanket additional insured endorsement, for those sources of liability which would be covered by the latest edition of the standard Commercial General Liability Coverage Form (ISO Form CG 00 01) without the attachment of any endorsements excluding or limiting coverage for Products/Completed Operations, Independent contractors, Property of CITY in DESIGN BUILDER’s Care, Custody or Control or Property of CITY on which contracted operations are being performed, Explosion, Collapse or Underground hazards (XCU Coverage, Contractual

Liability or Separation of Insureds). When CITY is added as additional insured by endorsement, ISO

Endorsements CG 20 10 and CG 20 37 or their equivalent shall be used to provide such Additional Insured status.

(iii) Umbrella Liability Insurance in the amount of $5,000,000 per occurrence/aggregate that is no more restrictive in coverage than all underlying coverages described above. The CITY SHALL BE NAMED AS

ADDITIONAL INSURED.

(iv) Professional Liability Insurance, insuring DESIGN BUILDER and other interests, including, but not limited to, any associated or subsidiary companies involved in the work, for errors or omissions in the performance of design professional services to be rendered pursuant to this Contract. The limit of liability will be no less than $2,000,000, per occurrence. (Professional Liability coverage will be provided on an Occurrence

Form or a Claims Made Form with a retroactive date equal to at least the first date of this agreement and with a three-year reporting tail beyond the annual expiration date of the policy).

(3) Builders’ Risk: DESIGN BUILDER shall purchase Builders’ Risk insurance for the Work on an “all risk” basis, including without limitation, insurance against the perils of flood, fire, earthquake, theft, vandalism, malicious mischief, collapse, water damage, stored materials, materials in transit, windstorm, falsework, testing and startup, temporary building and debris removal on a completed value basis insuring the Work, and all equipment and materials to be incorporated into the Work, for the benefit of the CITY, the DESIGN BUILDER and Subcontractors at every tier as their interests may appear. The CITY the DESIGN BUILDER and any

Subcontractor insured therein waive all rights against each other for damages caused by fire and other perils to the extent covered by the insurance obtained pursuant to this paragraph.

(b) Subcontractors’ Insurance. Each of DESIGN BUILDER’s subcontractors will be required to provide insurance in substantially similar form to the insurance required of DESIGN BUILDER above based on services provided.

(c) Proof of Insurance. DESIGN BUILDER will furnish proof of insurance acceptable to the CITY prior to or at the time of execution of this Contract. DESIGN BUILDER will not commence work until all proof of all required insurance has been filed with and approved by the CITY. DESIGN BUILDER will furnish such proof in the form of certificates of insurance which will clearly outline all hazards covered as itemized above, the amounts of insurance applicable to each hazard, and the expiration dates. The certificates will also contain the following language as to cancellation:

“In the event of cancellation of this policy by the insurer or any insured, this Company will give not less than

30 days advance written notice to:

Risk Manager

The CITY of Daytona Beach

P.O. Box 2451

Daytona Beach, Florida 32115-2451”

If requested by the CITY, DESIGN BUILDER will furnish copies of the insurance contracts to support the certificates of insurance and the copies of said insurance must be acceptable to the CITY.

(d) Cancellation; Replacement Required. DESIGN BUILDER will file replacement certificates 30 days prior to expiration or termination of the required insurance occurring prior to the acceptance of the work by the CITY.

If a required policy is canceled without DESIGN BUILDER’s prior knowledge DESIGN BUILDER will immediately notify the CITY immediately upon becoming aware that a required insurance coverage has been canceled for any reason, and promptly replace the canceled policy. The CITY expressly reserves the right to replace the canceled policy at DESIGN BUILDER’S expense if DESIGN BUILDER fails to do so.

(e) Termination of Insurance. DESIGN BUILDER may not cancel the insurance required by this Contract until the work is completed, accepted by the CITY and DESIGN BUILDER has received written notification from the Risk

Management Division of the CITY that DESIGN BUILDER may cancel the insurance required by this Contract and the date upon which the insurance may be canceled. The Risk Management Division of the CITY will provide such written notification at the request of DESIGN BUILDER if the request is made no earlier than two weeks before the work is to be completed.

(f) Liabilities Unaffected. DESIGN BUILDER’s liabilities under this Contract will survive and not be terminated, reduced or otherwise limited by any expiration or termination of insurance coverages. Similarly, DESIGN

BUILDER’s liabilities under this Contract will not be limited by the existence of any exclusions or limitations in insurance coverages, or by DESIGN BUILDER’S failure to obtain insurance coverage.

DESIGN BUILDER will not be relieved from responsibility to provide required insurance by any failure of the

CITY to demand such coverage, or by CITY’s approval of a policy submitted by DESIGN BUILDER that does not meet the requirements of this Contract.

Notices. Unless otherwise expressly agreed herein, all notices, requests, and demands to or upon the Parties will be delivered by hand, delivered by a courier service, provided to a nationally recognized delivery service for overnight delivery, or by U.S. mail, postage prepaid by registered or certified mail, return receipt requested, to the addresses set forth herein.

7. EVALUATION CRITERIA

The proposed evaluation is an initial process to elicit a short list of Proposers; with the contract awarded not necessarily to the consultant of least cost, but rather to the consultant with the best combination of attributes (i.e., qualifications and experience, technical approach, and cost), based upon the evaluation factors specifically established for this solicitation.

The weighted evaluation criteria in the EVALUATION CRITERIA will be used to evaluate Offers and develop a recommendation to the City Manager. Each criterion will be scored between 0 and 5; 0=non-responsive

1=poor, 2=below average, 3=average, 4=above average, 5=excellent. Scores will be multiplied by the criterion weight for a weighted score; weighted scores will be totaled for the weighted total score.

Proposal Evaluation Criteria and Submittal Information

The evaluation of qualified Design-Build Teams will be conducted in two phases by the Selection

Committee. The Selection Committee consists of following individuals: Chief Financial Officer/Designee, City Engineer, Utilities Director/Designee, Ralph Brennan WTP Superintendent/Designee, Utilities

Sustainability and Resiliency Officer/Designee. Phase 1 will include the submission of written Proposals.

These responses will be evaluated by the Selection Committee, who will then short-list the highest ranked Design-Build Teams, with a minimum of three (3) Teams being short-listed. The short-listed

Teams will move on to Phase 2, which includes an Interview/Presentation to be heard an evaluated by the Selection Committee. At the conclusion of Phase 2, the Selection Committee will make a recommendation of the most qualified Team for the City Manager’s approval. The evaluation criteria for each step of the process are outlined below. For the purposes of the written response, the Design-Build

Team will be referred to as the “Team”.

When asked to supply information for the corporate entities, only information regarding the Designer(s) and Builder(s) is needed. No information needs to be submitted for subconsultants or trades, unless specifically asked for.

If short-listed for interviews, and to aid the Selection Committee, please submit an Organizational

Chart and resumes at least three (3) days prior to the interview. Each resume will be limited to 1 page and should be provided for the Key Team Members identified below. Up to six (6) additional resumes may be submitted for individuals of the Teams choosing. Additionally, short-listed Teams should bring printed copies of their presentation at the time of the interview.

Please note that scores from Phase 1 and Phase 2 will NOT be combined when deciding the most qualified Team.

7.1. Phase 1

No. Evaluation Criteria Scoring Method Weight (Points)

1. Qualifications of Team (3 pages)

Provide an introduction of the Team/Team composition, including an Organizational Chart, and provide information regarding the Team’s qualifications as they relate to water…

This is the start of the file's text. The full file is on GovTribe.