260803 Request for Subcontractor Qualifications - IDOT Albia_Flatwork.pdf
PDF 614 KB Posted
- Attached to
- Request for Subcontractor Qualifications for Standard Bid Package -DOT Albia MG & Salt Structure
- Solicitation number
- 645-RFQ-2980-2027
- Issued by
- Marshall County, Iowa
About this file
This is a Request for Subcontractor Qualifications (RFQ) issued by Woodruff Construction, serving as Construction Manager at Risk (CMaR) for the Iowa Department of Transportation, for the Albia Maintenance Garage and Salt Structure project located at 1501 S C St, Albia, IA 52531. The project consists of site work and construction of a new salt storage building and a new maintenance facility of approximately 17,000 square feet on an existing operational DOT complex. Woodruff Construction is soliciting qualifications specifically for Bid Package No. A03.3 Concrete Flatwork. Statements of Qualifications (SOQs) are due on August 17, 2026, before 5:00 p.m. CST, submitted electronically to Precon@Woodruff.Build with the subject line "IDOT ALBIA [SUBCONTRACTOR_NAME] SOQ." Following evaluation, qualified contractors will be notified no less than thirteen days prior to the subcontractor bid letting on August 31, 2026. Subcontractor approval and award is anticipated for September 25, 2026. The project schedule indicates construction notice to proceed in September 2026, with substantial completion anticipated in April 2028 and final completion by May 31, 2028.
Responding firms bear all costs associated with SOQ preparation and delivery. The evaluation will follow Chapter 26A of Iowa Public Bidding Law on Guaranteed Maximum Price Contracts, applying objective prequalification criteria to determine qualified firms eligible to submit bids. Firms meeting prequalification standards will receive bid documents and be invited to submit proposals; those not meeting criteria will be notified of specific deficiencies. The RFQ requires submission of a two-page SOQ Form addressing firm profile and background, technical competence, personnel capacity, key personnel list, capability to perform, relevant project experience, insurance and bonding information, legal history, safety history, and project location familiarity. Subcontractors must demonstrate bonding capacity, OSHA compliance history, current EMR ratings, and may be required to secure performance and payment bonds. Woodruff Construction reserves the right to waive irregularities, cancel the RFQ, reject all proposals, or restart the process with modified criteria. Questions regarding the project should be directed to Will McAllister, Project Manager, at (319) 493-9788 or WILLM@Woodruff.Build.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1425402-event.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Subcontractor Qualifications
From: Woodruff Construction, Construction Manager at Risk (CMaR)
Project: IADOT Albia Maintenance Garage and Salt Structure Flatwork
Release Date: Monday, August 3rd, 2026
Woodruff Construction is soliciting subcontractor statements of qualifications “SOQs” on behalf of Iowa
Department of Transportation for its project described in this RFQ (the “Project”). This request invites firms to submit SOQ for the accomplishment of the items of work described below under the Project
Description and Scope of Work. SOQs shall be prepared and submitted in accordance with the requirements described in this RFQ.
Project Description and Scope of Work
Woodruff Construction invites you to submit your firm’s qualifications for subcontracted work for the below-described project(s):
• Project – Albia Salt Storage Building & Maintenance Building, 1501 S C St, Albia, IA 52531 o The project will be a new structure on the existing DOT site. The maintenance facility site where these buildings will be constructed will be a fully operational site and owner occupied during construction. The project consists of site work and construction of a new salt storage building on the existing Albia DOT complex, and a new Maintenance facility of approximately 17,000 SF to support the DOT's ongoing operations.
o The Construction Manager intends to issue the following scopes of work as individual subcontractor bid packages:
Bid Package No. Description
A03.3 Concrete Flatwork
Iowa DOT Background Info
The Iowa DOT has facilities across the state of Iowa and works to make Iowa lives better through transportation. The IDOT and Woodruff Construction are seeking sub-contractors for the above bid packages to submit qualifications.
Subcontractor Solicitation Schedule
Subcontractor RFQ Issued August 3rd, 2026
Qualification Statements Due August 17th, 2026
Issuance of Contract Documents for Bid
Proposals for qualified contractors
August 17th, 2026
Subcontractor Bid Letting August 31st, 2026
Subcontractor Approval/Award (Anticipated) September 25th, 2026
Response Format:
• Please fill out the attached two-page Statement of Qualifications (SoQ) Form
• Incomplete or illegible forms may be grounds for disqualification
• Sections included in the SoQ Form are as follows:
o Firm Profile & Background o Technical Competence o Capacity of Personnel o List of Key Personnel o Capability to Perform o List of Relevant Projects o Insurance & Bonding
Information o Legal History o Safety History o Availability To and Familiarity with the Location of the Project o Certification by an officer of the company
Contact and Due Date
Please submit an electronic PDF copy through email or digital file share.
Date Qualifications Due: Before 5:00p.m. CST on August 17th, 2026
Qualifications Statements to: Woodruff Construction
Precon@Woodruff.Build
Subject: “IDOT ALBIA [SUBCONTRACTOR_NAME] SOQ”.
RFQ responses that are incomplete or are received after 5:00 p.m. local time on August 17th, 2026, will not be considered and will be returned unopened. Email subject and electronic file shall be clearly marked
“IDOT ALBIA (Company Name) SOQ”.
Woodruff Construction reserves the right to waive any deficiencies or irregularities in any RFQ responses and to determine if qualified firms are allowed to submit a proposal in the best interest and value of the
Owner.
Please direct all project-specific questions to the Woodruff Construction Project Manager:
Attn: Will McAllister
501 Greenfield Dr.
Tiffin, IA 52340
Cell: (319) 493-9788
Email: WILLM@Woodruff.Build mailto:Precon@Woodruff.Build mailto:WILLM@Woodruff.Build
Evaluation Criteria
As the Construction Manager at Risk (CMaR), Woodruff Construction will collect Subcontractor
Qualification Statements and, following Chapter 26A of Iowa Public Bidding Law on Guaranteed
Maximum Price Contracts, apply objective prequalification criteria to evaluate them.
• All firms who meet the objective prequalification criteria as a qualified firm shall be allowed to submit a bid for the relevant trade contract work and materials package
• Upon determining which firms meet the prequalification criteria, Woodruff Construction will notify all firms who responded to the request for qualifications whether they successfully meet the prequalification criteria and will include a list of all firms who were deemed to have successfully met the prequalification criteria.
• Notification will be given no less than thirteen days prior to the subcontractor bids being due.
• Subcontractors who failed to meet the prequalification standards shall also be provided with information regarding which prequalification criteria were not met.
Following evaluation, Woodruff Construction will notify all respondents of the results. All qualified firms will be asked to submit a bid proposal.
OTHER INFORMATION
Responding firms will bear all costs for preparation & delivery of the response to this RFQ.
The Owner and Construction Manager reserve certain rights, including, but not limited to, the following:
1. Cancel the entire RFQ
2. Reject all proposals
3. Cancel the entire RFQ process and restart with modified criteria
4. Remedy technical errors in the RFQ process
5. Appoint evaluation committees to review qualifications and proposals
6. Seek assistance of outside technical experts in evaluation
7. Issue subsequent requests for proposals
8. Waive informalities and irregularities in the RFQ or subsequent RFP process https://www.legis.iowa.gov/docs/code/26A.pdf
Subcontractor Statement of Qualification Form
Project: Date:
Response Format:
• Please fill out the Subcontractor Statement of Qualifications Form that follows this section in its entirety.
• Incomplete or illegible forms may be grounds for disqualification.
Seeking Prequalification for the following work:
Please list which bid packages/trades your firm anticipates submitting a proposal bid for:
Note: Combined bids for multiple packages may be allowed for this project. Note that individual bids will still be required for any and all packages that are bid as a combined package to avoid gaps and/or overlap in bid coverage.
Do you anticipate bidding two or more packages as a combined bid package (Yes/No):
Firm Profile and Background:
Company Name:
Address 1 Address 2 Website:
Contact Person/Title:
Contact Email:
Contact Phone #:
Type of Organization
(LLC, Sole Proprietor, Corporation, etc.)
Number of Years in Business:
State of Iowa Contractor #:
Est. Value of Contract Work Completed in Previous 3 Years:
Year :
Year :
Year :
Qualifications:
Technical Competence
Does your company have an orientation program for new employees? (Yes/No):
Does your company have a training program or provide continuing education to your employees? (Yes/No):
Does your company have a written quality control plan that provides guidelines, best practices, and checklists (Yes/No):
used on all projects?
Does your company employ Building Information Model (BIM model personnel) or subcontract this service? (Yes/No):
Capacity of Personnel
Does your company have the resources (personnel, financial, or other) to successfully complete this project? (Yes/No):
Do your trade workers have the capability and technical competence to successfully complete this project (Yes/No):
Does your company have the experience to successfully complete this project? (Yes/No):
List of Key Personnel (Add additional pages and resumes if possible)
Employee Name Title/Position Years in
Trade
Special Qualifications or Trade Certifications
Capability to Perform
1. How many full-time employees does your company have? Part Time?
2. What is your firm’s average project contract value over the past 3 years?
3. What is your firm’s largest single contract value over the past 3 years?
4. What is your firm’s backlog for the next 12 months?
(Attach Backlog Report if Available)
Subcontractor Statement of Qualification Form (Continued)
List five relevant projects similar in size and scope to this project your company has recently completed
Project Name Owner, Architect, or Engineer Reference (Name, Title, and Contact Info)
Contract
Amount
Year
Completed
Insurance and Bonding:
Can your company secure the level of insurance typically required for a public project such as this? (Yes/No):
Can your company secure a bid bond or a performance & payment bond for this project, if required? (Yes/No):
What is the name of your bonding company?
What is your single project bonding capacity?
What is your aggregate bonding capacity?
If possible, add a letter from your bonding company as an attachment to this document assuring your company’s ability to bond the project
Legal:
In the past five years, has your company failed to complete any contracted work? (Yes/No):
In the past five years, has your company filed for bankruptcy or insolvency? (Yes/No):
In the past five years, has any company officer, partner, or principal been convicted of a crime? (Yes/No):
In the past ten years, has your company operated under any other names or tax identification numbers? (Yes/No):
In the past ten years, has there been any judgements, claims, arbitrations, proceedings against your company? (Yes/No):
If yes, please describe the nature and outcome. Attach a separate document if necessary:
Safety:
Does your company comply with State and Federal Safety Regulations? (Yes/No):
Does your company have an internal safety program/manual? (Yes/No): If yes, please attach copy
Does your company have a Safety Officer? (Yes/No): If Yes, Full or Part Time?
In the past three years, has your company had any OSHA citations? (Yes/No): Attach 3 Year OSHA 300A Forms
If yes, please describe the nature of the citation(s):
What is your EMR Rating for the most recent three years?
Year Year Year
Availability To and Familiarity With the Location of the Project:
Approximately what percentage of your company’s work has been performed within a 60 mile radius of the project site: %
What is the distance (in miles) between the contact office that will be serving this project and the project site? miles
Certification:
The undersigned states that they have carefully examined all the information provided and representations made in this Statement of
Qualifications and certifies, to the best of their knowledge, that this State of Qualifications is entirely complete, true, and accurate.
Submitted by (Signature)
Printed Name & Title
Company Name
Date
2025 2026 2027 2028
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
DOT Albia Master Schedule
Procurement
Trade Packages, Front End & Estimation
Develop Trade Packages
Project Kickoff Meeting
Early Project Solicitation
Early Estimates / Budgetary
GMP Budgetary Estimate & Owner Evaluation
Design Optimization
DOT Drawing & Specs Revisions
Constructability Review
4. Procurement
6. Outage Work Integration Plan
7. Quality Management Plan
3. Site Logistics, Security, and Safety Plan
Maintenance Garage Bid Package Invites/RFP
Send out Requests for Qualifications
Receive SOQs
Evaluate SOQs
Review Qualified contractors w/ Owner
Publish Bid Documents & Send to Qualified Contractors
Subcontractor Bid Preparation
Subcontractor Bid Review
RFQ Flatwork
Notify & Send Bid Docs
Bid Time
Flatwork GMP Prep
Present Flatwork GMP to Owner
Amendment Excecution
GMP Preparation & Execution
Prepare GMP Documents & Admendment to Contract
Internal GMP Review
Review GMP with Owner
Amendment Excecution
Today: 03 Aug
# Activity Start Duration End Progress
0 01/15/26 620 days 05/31/28 18.89%DOT Albia Master Schedule
1 01/15/26 194 days 10/13/26 100.00%Procurement
2 01/15/26 100 days 06/03/26 100.00%Trade Packages, Front End …
3 01/15/26 10 days 01/28/26 100.00%Develop Trade Packages
4 01/21/26 0 days 01/21/26 100.00%Project Kickoff Meeting
5 01/29/26 5 days 02/04/26 100.00%Early Project Solicitation
6 02/02/26 15 days 02/20/26 100.00%Early Estimates / Budgetary
7 02/24/26 0 days 02/24/26 100.00%GMP Budgetary Estimate & O…
8 02/25/26 10 days 03/10/26 100.00%Design Optimization
9 03/11/26 61 days 06/03/26 100.00%DOT Drawing & Specs Revisio…
10 03/11/26 20 days 04/07/26 100.00%Constructability Review
11 03/11/26 20 days 04/07/26 100.00%4. Procurement
12 03/11/26 20 days 04/07/26 100.00%6. Outage Work Integration Pl…
13 03/11/26 20 days 04/07/26 100.00%7. Quality Management Plan
14 03/11/26 20 days 04/07/26 100.00%3. Site Logistics, Security, an…
15 05/05/26 115 days 10/13/26 100.00%Maintenance Garage Bid Pa…
16 05/05/26 0 days 05/05/26 100.00%Send out Requests for Qualifi…
17 05/06/26 15 days 05/26/26 100.00%Receive SOQs
18 05/27/26 5 days 06/02/26 100.00%Evaluate SOQs
19 06/02/26 0 days 06/02/26 100.00%Review Qualified contractors …
20 06/03/26 0 days 06/03/26 100.00%Publish Bid Documents & Sen…
21 06/04/26 25 days 07/08/26 100.00%Subcontractor Bid Preparation
22 07/09/26 5 days 07/15/26 100.00%Subcontractor Bid Review
23 08/03/26 10 days 08/14/26 0.00%RFQ Flatwork
24 08/14/26 0 days 08/14/26 0.00%Notify & Send Bid Docs
25 08/17/26 10 days 08/28/26 0.00%Bid Time
26 08/31/26 1 day 08/31/26 0.00%Flatwork GMP Prep
27 09/01/26 1 day 09/01/26 0.00%Present Flatwork GMP to Owner
28 09/02/26 30 days 10/13/26 0.00%Amendment Excecution
29 07/08/26 43 days 09/04/26 54.55%GMP Preparation & Execution
30 07/08/26 6 days 07/15/26 100.00%Prepare GMP Documents & Ad…
31 07/15/26 1 day 07/15/26 100.00%Internal GMP Review
32 07/20/26 0 days 07/20/26 100.00%Review GMP with Owner
33 07/20/26 35 days 09/04/26 0.00%Amendment Excecution
25-141 IDOT CMaR Albia
Main Schedule - Together
2025 2026 2027 2028
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
# Activity Start Duration End Progress
General
Parent Activity
Child Activity
Activity Baseline
Milestone Baseline
Milestone
(+# days) Delay
Links
Critical Path
Critical
Non Critical
Printed on: 08/03/26
Page: 1/3
Submittal Activity
Subcontracts & POs
Salt Storage Precast Submittal
Salt Storage Post Frame Submittals
Precast T Lead Times
MB Precast Submittals
Salt Structure Post Frame Building Lead Time
MB Precast Lead Times
Construction
Notice to Proceed
Mobilize
Mass Sitework
Brine Tank Structure (Tied to MB)
Footings & Foundations
SOG
MEP
Set Tanks and Plumb (By Owner)
Demo Existing Brine Structure
Salt Structure
Earthwork & Utilities
Foundations, Posts & Bollards
Install Woodframe
Install Granular Fill
Install Siding
Precast Barrier Install
Concrete Flatwork
Joint and Paint Barriers
Punch
Maintenance Building
Demo Misc Buildings around Site
Earthwork & Utilities
Demo Existing Salt Hoop 50/50 Buildings
Footings & Foundations
Precast Walls
34 09/07/26 131 days 03/08/27 0.00%Submittal Activity
35 09/07/26 10 days 09/18/26 0.00%Subcontracts & POs
36 09/21/26 10 days 10/02/26 0.00%Salt Storage Precast Submittal
37 09/21/26 10 days 10/02/26 0.00%Salt Storage Post Frame Submit…
38 09/21/26 10 days 10/02/26 0.00%Precast T Lead Times
39 09/21/26 60 days 12/11/26 0.00%MB Precast Submittals
40 10/05/26 30 days 11/13/26 0.00%Salt Structure Post Frame Buildi…
41 12/15/26 60 days 03/08/27 0.00%MB Precast Lead Times
42 09/08/26 451 days 05/31/28 0.00%Construction
43 09/08/26 0 days 09/08/26 0.00%Notice to Proceed
44 09/14/26 2 days 09/15/26 0.00%Mobilize
45 09/21/26 210 days 07/09/27 0.00%Mass Sitework
46 10/12/26 391 days 04/10/28 0.00%Brine Tank Structure (Tied t…
47 10/12/26 12 days 10/27/26 0.00%Footings & Foundations
48 10/28/26 5 days 11/03/26 0.00%SOG
49 09/27/27 15 days 10/15/27 0.00%MEP
50 03/28/28 5 days 04/03/28 0.00%Set Tanks and Plumb (By Ow…
51 04/04/28 5 days 04/10/28 0.00%Demo Existing Brine Structure
52 11/16/26 115 days 04/23/27 0.00%Salt Structure
53 11/16/26 20 days 12/11/26 0.00%Earthwork & Utilities
54 11/16/26 10 days 11/27/26 0.00%Foundations, Posts & Bollards
55 11/30/26 15 days 12/18/26 0.00%Install Woodframe
56 12/14/26 7 days 12/22/26 0.00%Install Granular Fill
57 12/21/26 15 days 01/08/27 0.00%Install Siding
58 12/23/26 5 days 12/29/26 0.00%Precast Barrier Install
59 03/29/27 10 days 04/09/27 0.00%Concrete Flatwork
60 04/12/27 5 days 04/16/27 0.00%Joint and Paint Barriers
61 04/19/27 5 days 04/23/27 0.00%Punch
62 04/12/27 266 days 04/17/28 0.00%Maintenance Building
63 04/12/27 10 days 04/23/27 0.00%Demo Misc Buildings around …
64 04/12/27 30 days 05/21/27 0.00%Earthwork & Utilities
65 04/26/27 5 days 04/30/27 0.00%Demo Existing Salt Hoop 50/…
66 05/10/27 20 days 06/04/27 0.00%Footings & Foundations
67 06/07/27 15 days 06/25/27 0.00%Precast Walls
25-141 IDOT CMaR Albia
Main Schedule - Together
2025 2026 2027 2028
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
# Activity Start Duration End Progress
General
Parent Activity
Child Activity
Activity Baseline
Milestone Baseline
Milestone
(+# days) Delay
Links
Critical Path
Critical
Non Critical
Page: 2/3
Steel Roof Structure
Roofing
Underground MEP
Interior SOG
Masonry Walls
OH Doors
Exterior Concrete Flatwork
Mezzanine Construction
MEP Rough Ins
Doors
Sprinkler Install
Painting
Ceilings
Finish MEP
Bridge Crane
Flooring
Misc Metals
Bathroom Specialties
Owner FFE & Move In substantial
Substantial Completion
Punchlist
Final Completion
68 06/28/27 30 days 08/06/27 0.00%Steel Roof Structure
69 08/09/27 20 days 09/03/27 0.00%Roofing
70 09/06/27 15 days 09/24/27 0.00%Underground MEP
71 09/27/27 16 days 10/18/27 0.00%Interior SOG
72 10/19/27 20 days 11/15/27 0.00%Masonry Walls
73 10/19/27 15 days 11/08/27 0.00%OH Doors
74 10/19/27 30 days 11/29/27 0.00%Exterior Concrete Flatwork
75 11/16/27 20 days 12/13/27 0.00%Mezzanine Construction
76 12/14/27 35 days 01/31/28 0.00%MEP Rough Ins
77 12/14/27 15 days 01/03/28 0.00%Doors
78 12/21/27 15 days 01/10/28 0.00%Sprinkler Install
79 02/01/28 15 days 02/21/28 0.00%Painting
80 02/22/28 5 days 02/28/28 0.00%Ceilings
81 02/22/28 30 days 04/03/28 0.00%Finish MEP
82 02/22/28 15 days 03/13/28 0.00%Bridge Crane
83 02/29/28 10 days 03/13/28 0.00%Flooring
84 03/14/28 10 days 03/27/28 0.00%Misc Metals
85 04/04/28 10 days 04/17/28 0.00%Bathroom Specialties
86 04/11/28 5 days 04/17/28 0.00%Owner FFE & Move In
87 04/17/28 0 days 04/17/28 0.00%substantial
88 04/18/28 1 day 04/18/28 0.00%Substantial Completion
89 04/19/28 30 days 05/30/28 0.00%Punchlist
90 05/31/28 1 day 05/31/28 0.00%Final Completion
25-141 IDOT CMaR Albia
Main Schedule - Together
2025 2026 2027 2028
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
# Activity Start Duration End Progress
General
Parent Activity
Child Activity
Activity Baseline
Milestone Baseline
Milestone
(+# days) Delay
Links
Critical Path
Critical
Non Critical
Page: 3/3
| Project: |
| Bid Packages: |
| Combined Bid Packages?: |
| Years in Business: |
| Address 1: |
| Address 2: |
| State of Iowa Contract #: |
| Website: |
| Contact Person/Title: |
| Contact Email: |
| Contact Phone: |
| Est. Revenue Value 1: |
| Organization Type: |
| Est. Revenue Value 2: |
| Est. Revenue Value 3: |
| Orientation Program?: |
| Training Program?: |
| Q/C Program?: |
| BIM Personnel?: |
| Resources?: |
| Capability and Technical Competence: |
| Experience?: |
| Employee Title 1: |
| Years in Trade 1: |
| Special Quals 1: |
| Employee Title 2: |
| Years in Trade 2: |
| Special Quals 2: |
| Employee Name 3: |
| Employee Title 3: |
| Years in Trade 3: |
| Special Quals 3: |
| Employee Name 4: |
| Employee Title 4: |
| Years in Trade 4: |
| Special Quals 4: |
| Employee Name 5: |
| Employee Title 5: |
| Years in Trade 5: |
| Special Quals 5: |
| Full Time Employees: |
| Part Time? (1): |
| Part Time? (2): |
| Part Time? (3): |
| 12 month Backlog: |
| Project Name 1: |
| Project Reference 1: |
| Project Amount 1: |
| Project Comp 1: |
| Project Name 2: |
| Project Reference 2: |
| Project Amount 2: |
| Project Comp 2: |
| Project Name 3: |
| Project Reference 3: |
| Project Amount 3: |
| Project Comp 3: |
| Project Name 4: |
| Project Reference 4: |
| Project Amount 4: |
| Project Comp 4: |
| Project Name 5: |
| Project Reference 5: |
| Project Amount 5: |
| Project Comp 5: |
| Insurance?: |
| Bond?: |
| Bond Company?: |
| Single Project Bonding Capacity: |
| Aggregate Bonding Capacity: |
| Failure to complete work?: |
| Bankruptcy?: |
| Crime Conviction?: |
| Other Names/Tax ID: |
| Litigation: |
| Litigation Line 1: |
| Litigation Line 2: |
| Litigation Line 3: |
| State/Federal Regulations?: |
| Internal Safety Program: |
| Safety Officer?: |
| Safety Full/Part Time?: |
| OSHA Citations?: |
| OSHA Line 1: |
| OSHA Line 2: |
| OSHA Line 3: |
| EMR Rating 1: |
| EMR Rating 2: |
| EMR Rating 3: |
| Certification: Printed Name & Title: |
| EMR Rating 1 Year: |
| EMR Rating 2 Year: |
| EMR Rating 3 Year: |
| % Work within 60 Miles: |
| Distance to Site: |
| Revenue Year 1: |
| Revenue Year 2: |
| Revenue Year 3: |
| Company Name: |
| Employee Name 1: |
| Date: |
| Certification: Company Name: |
| Certification: Date: |
| Employee Name 2: |
File details come from the government source that posted it. Updated .