This document is a statement of objectives for a federal construction contract opportunity to provide power and communication at an East Range location at Fort Huachuca, Arizona. The scope of work includes installing approximately 500 feet of trenching for electrical and communication lines, a 400A electrical service entrance, a 10'x10' precast concrete communications shelter, four electrical pedestals, fiber optic cabling from an existing node building to the new shelter, and related electrical and communication infrastructure. Proposals are due by July 16, 2022 with award planned shortly thereafter. The contract will be a firm fixed price, lowest price technically acceptable award to a small business. The North American Industry Classification System code is 237130 and the wage determination is AZ20220023.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1.0 Project Background

STATEMENT OF OBJECTIVES

Work Order Number HIO21343-2J- East Range Provide Power and Communication Project Manager: Jason Curtis & Fredy Arevalo Date: May 25, 2022 HIO21343-2J. Provide Power and Communication. East Range Revision: 0

1.01 The East Range presently has no power and communications service for training units, and it is mainly worked for the Electronic Proving Ground (EPG) and their mission(s). DPTMS is requesting the installation of power and communication at the new training site. There is no available communication and electrical power in the area to support it. The project requires 400A, 3 phase, 120/208 V electrical service to provide electrical power to four 100A pedestal and to a communication Shelter. Additionally, the contractor will provide Fiber Optic Cable from building 86810 to East Range. This project will provide trenching for the 120/208V secondary line and communication. It will provide the 120/208V, 400A Service Entrance panel with breakers, 100A, 120/208V load panel breakers for each pedestal, a 10’x10’, standard height precast concrete building, communication materials and work. Fort Huachuca post power provider “Sulphur Spring Valley Electric Cooperative” (SSVEC) will provide and install power pole lines, transformer, and service entrance under a different task order.

2.0 Statement of Objectives

2.01 The contractor shall provide design/build services and furnish all labor, material, equipment, supervision, transportation, permits, fees, licenses necessary to “Provide Power and Communication”, located at Fort Huachuca, Arizona, unless specifically stated otherwise. A non-specific statement of work for this repair project is provided in Section 4.0 below. The contractor shall prepare a more detailed scope of work outlining their Contract Execution Overview, to include their technical approach, labor hours, materials/equipment, self-performance/sub-contractor, and tentative schedule. The contractor shall field verify the area of work before submitting their SOW and proposal. DA Pamphlet 385-1, NFPA-70, Installation Information Infrastructure Architecture (I3A), and pertinent UFC are referenced in this effort. The As-Built drawing (file #1 As-Built EPG fiber optic) for the existing communication manhole duct will be provide to the contractors in a compact disk (CD).

3.0 Proposal Requirements

3.01 Technical Approach. The contractor proposal technical approach section must address each of the line items listed in Section 4.0, Statement of Work. Language of this section must include a description of the steps and methods by which each item of the SOW will be completed. This description must adhere to the details outlined in pertinent UFC specifications, such that a clear understanding of the requirements can be demonstrated to a competent, qualified person. Prime contractor supervision, quality control and safety require more than one person, so indicate in the technical section more than one person will provide supervision, quality control and safety. One person can provide quality control and safety. The person providing supervision for a project cannot also be the onsite safety person for that project. A qualified Site Safety and Health Officer must be on post while any work is in progress under any award. The proposal must meet or exceed the acceptability standards.

3.02 Labor Hours. The contractor proposal labor hours section must give a detailed breakdown of labor hours, to include an estimated number of hours assigned to each trade or supervisory position, such that a clear understanding of the division of labor can be determined. In addition, the total number of hours estimated for the project should be listed.

3.03 Materials/Quantities/Equipment. The Contractor Proposal Materials, Quantities, and Equipment section must provide a clear and detailed list of all of the building materials and estimated quantities, as well as the equipment to be used in the execution of the project. These items must be presented in a bulleted list fashion such that a competent qualified person can understand what materials, estimated quantities, and equipment will be used during the execution phase of the project.

3.03.01 Materials shall include items such as chemicals or mechanical fasteners, hardware, devices, valves, piping, sealants, structural members, and all other permanently installed materials at the project location.

3.03.02 Equipment shall consist of all tools, machinery, motorized or engine driven equipment, and all other non-permanent items which will not be left on site. All best management practices (BMP), to protect against the introduction and /or movement of invasive species seed, shall be implemented and adhered to throughout this project. The government will provide specific requirements, on or prior to the site visit.

3.03.03 The contractor must list estimated quantities for the materials.

3.04 Tentative Schedule. The Contractor Proposal Tentative Schedule section must provide a detailed estimate of all activities to be conducted during the project period of performance. Scheduled actions must be listed in a logical order to demonstrate a clear timeline of the proposed project activities.

4.0 Statement of Work

The following list is not detailed in scope; the contractor shall provide a more specific scope of work:

4.01 Dig approximately 500 feet length, 3 feet deep trench to install PVC conduit for low voltage (LV) cable and communication line from the pre-cast concrete building to each pedestal (4 total). See Fig #1 and #2.

4.02 The contractor shall provide select backfill (pipe bedding material), warning tape, and compaction to the specifications of the Fort Huachuca post power provider (SSVEC) and all other required codes. All best management practices (BMP), to protect against the introduction and /or movement of invasive species seed, shall be implemented and adhered to throughout this project. The government will provide specific requirements, on or prior to the site visit. See Fig #3 and File #2 (2017 SSVEC Service Entrance Requirement) in the CD.

4.03 Install 4” PVC conduit for the 400A, 3 phase, 120/208V Service Entrance (SE). Fort Huachuca post power provider (SSVEC) will provide and install the conductors. The location of the SE will be 20 to 30 feet away from the pole transformers. The Government will provide all necessary 4” PVC conduits as required.

4.04 Provide and install 400A, 3 phase, 120/208V Service Entrance (SE); include meter base, current transformer-can, disconnect switch, pedestal, and associated parts. The SE pedestal shall be near or adjunct to the precast building. Fort Huachuca post power provider (SSVEC) will provide the meter and current transformers. See Fig #4

4.05 Provide and install a 400A, 3 phase, 120/208V panelboard inside the communication shelter. The panelboard shall have four (4) 100A, 3 pole breakers to feed each pedestal. Also, provide four (4) 20A breakers (one per wall), one (1) 20A breaker for light fixture and HVAC evaporator, and one breaker necessary for the HVAC compressor. The contractor shall provide conduit, conductors, and any associated parts necessary to connect the 400A panelboard.

4.06 Build a 14’x14’ base to place a 10’x10’, standard height precast concrete building. The base material shall be aggregate base course (ABC), 6” thick over grade, and wet compacted.

4.07 Provide a 10’x10’standard height precast concrete building for communication shelter. The precast building shall have one single door, insulated for communication purposes, with light, and cooling system per UFC 3-580-01-2016_c1 specification. The Communication shelter shall be located at the perimeter of 150’x150’ between two pedestals. See Fig #1 and #2.

4.08 The communication shelter shall have one 20A outlet per wall with dedicate circuit and cooling system. The cooling system should be 1 TON split unit type.

4.09 Provide and install 4 pedestal NEMA 3R Load Center with 100 amp, 3 phase main breaker with at least 12 spaces for circuit breakers distribution. Each pedestal will be located in the corner of the 150’x150’ square. See Fig #1.

4.010 Provide and install 4 x 20A dedicated 120V outlet with weatherproof covers in each pedestal.

4.011 Provide and install 1x30A dedicated 208V outlet with weatherproof covers in each pedestal.

4.012 Provide and install PVC conduits and communication boxes with weatherproof covers to support communication outlet (dual RJ45 wall jacks); 5 wires (CAT 6) in each pedestal. Install 20 Outlet: Dual RJ45 wall jacks unto the five pedestals located on East Range from the new Communications Hut. The Government will provide all necessary PVC conduits as required (4” and 1 ½” schedule 40 Rigid PVC nonmetallic conduit are available). See Fig #5.

4.013 Provide and install 1 ½” PVC conduits for low voltage (LV) cable. The Government will provide all necessary 1 ½” conduits as required.

4.014 Storage areas and lay down yards shall be returned to the existing stable state, which may require some rehabilitation of the land, like re-seeding with native grass mixture. Re-seed all disturbed areas. Re-seeding will include the areas disturbed by Fort Huachuca post power provider (SSVEC) work.

4.015 The contractor shall utilize to the maximum extent possible the existing pathways which include underground conduits, Manholes, and Pull boxes. It is approximately 18,784 feet from building 86810 (A NODE) to Manhole #8. See Fig. #6 and #7.

4.016 Excavation of approximately 10,523 feet (from EPG MH #8 to the 10’x10’ precast building) of trench to install 4” schedule 40 PVC conduit duct bank system with manholes and Pull boxes. See Fig #7 and #8.

4.017 Backfill and compact over duct system.

4.018 Pull Maxcel Fabric Innerduct and Fiber Optics Cable through duct bank, manholes and pull boxes.

4.019 Install risers and building entry pathways as required. Install relay racks and patch panels as required.

4.020 Fusion splicing and testing of fiber optics cable as required.

4.021 The Government will provide all necessary 4” schedule 40 Rigid PVC nonmetallic conduits.

4.022 Install, secure, test, document, migrate, and cutover a turn-key solution to install four (4) twenty-four (24) strands Fiber Optic Cable from building 86810 (A NODE) to Communications Hut located on East Range. See Fig #8.

4.023 The Government will provide all necessary 4x24 strand Fiber Optic Cable for the project, approximately 4x29,500 feet. See Fig #9 and #10.

4.024 The Contractor is responsible for testing all government furnished Fiber Optic Cable and ensuring it is acceptable prior to installing it. See file #3, I3A (Technical Criteria for the Installation Information Infrastructure Architecture) and file #4, UFC 3-580-01-2016_c1 (Telecommunications Interior Infrastructure Planning and Design) in the CD.

4.025 The contractor shall employ best practices to furnish, install, secure, test, document, migrate, and cutover a turn-key solution in accordance with the I3A and all references and specifications found within the UFC 3-580-01-2016_c1, and NFPA 70. See file #3 (I3A) and file #4 (UFC 3-580-01-2016_c1) in the CD.

4.026 The contractor will be required to have the Registered Communications Distribution Designer (RCDD). Certification.

4.027 Damage/Repair: The contractor shall immediately repair and/or replace all facilities and/or equipment damaged by the contractor and/or their subcontractors due to contractor negligence. All areas affected shall be returned to their original condition and operational status within a reasonable time before the completion of the project.

4.028 Slack: The contractor shall provide enough slack in the cabling IAW I3A section 2.4.1.1 a minimum of 10ft of slack.

4.029 Grounding and Bonding: Equipment installed as part of this effort, identified on the project drawings shall be grounded and comply with I3A and UFC. See file #3 (I3A) and file #4 (UFC 3-580-01-2016_c1) in the CD.

4.030 Fiber Optics Patch Panels: Utilize patch panel connectors and couplers of the same type and configuration as used elsewhere in the system. Utilize duplex LC connectors on 19-inch (475 mm) rack mounted panels, unless otherwise directed. Provide a 3-foot (1-meter) slack loop of fiber within each panel and include strain relief for cables within the panel. Provide proper termination, splice storage, routing, radius limiting, cable fastening, storage, and cross-connection in all patch panels. Install fiber optic patch panels in the same rack or in the rack immediately adjacent to the LAN equipment in order to minimize patch cord lengths. Provide a minimum spare capacity of 25 percent.

4.031 In existing facilities, other connector types may be used to match the current infrastructure, with the approval of the telecommunications manager.

4.032 Aerial Cable: Aerial cable plant systems are not a preferred solution but may be used as specified in the design package. Exceptions may include range cables or other long runs through undeveloped areas; locations where underground systems cannot be installed; or locations where compliance with local mandates is required. The desired or required reliability (i.e., “five nines” or 99.999% reliability) of some communications systems may preclude the use of aerial pathways. Aerial pathways and spaces may consist of poles, messenger wire, anchoring guy wires, splice closures, and terminals.

4.033 Messenger Strand: The smallest messenger strand used for all new installations shall be 6.6 m. A 2.2-m strand shall be used only as an extension of existing 2.2-m strands. Fiber optic cable shall be installed on its own messenger. Copper and fiber cables shall not be lashed on the same messenger without U.S. Government approval.

4.034 Testing Inside and Outside Plant: The contractor shall perform testing. The contractor shall record the results and provide the results to the Government PM upon completion but no later than five (5) business days after completion of the test. All installed telecommunication cable and hardware shall PASS 100%.

5.0 Schedule

5.01 Notice to Proceed (NTP) shall be issued no later than 10 calendar days after the award and project shall be 100% complete and ready for final inspection no later than 150 working days after the NTP.

5.02 The contractor’s proposed schedule shall be submitted with the proposal. A revised schedule shall be submitted at the time of the preconstruction conference for approval. The schedule shall be in the form of a progress chart of suitable scale to indicate the percentage of work scheduled for completion at any given date during the period. The schedule shall take into consideration anticipated adverse weather that could preclude progress, long-lead equipment or materials critical to the completion of the project, review periods for submittal items requiring Government review and approval, air quality control permitting process and other events and milestones as necessary.

6.0 Occupancy

6.01 The area included in the scope of this contract will not be occupied. The contractor will schedule and perform work under this contract in coordination with DPW, NEC, and SSVEC.

7.0 Material, Standards, Codes, Regulations, and Workmanship (FAR 52.236-5, Material and Workmanship)

7.01 All materials and equipment shall be new unless otherwise specified. All work shall be completed in accordance with the plans and specifications, applicable industry standards, UFC, UFGS, NFPA, ASHRAE, NEC, SMACNA, NEBB, AABC, MUTCD, SDDCTEA, and AASHTO standards; federal, state and local codes, regulations of EPA, OSHA, NEPA, and MSHA, if required; Network Enterprise Center (NEC) and SSVEC requirements; Fort Huachuca Energy Policy and Army Energy and Water Management Program. All government permits, certifications, lead paint and asbestos analyses, if required, etc. shall be obtained by the Contractor prior to commencement of work or prior to beginning construction and are the specific responsibility of the Contractor (Federal, State and local governments). Air quality control permitting efforts must be coordinated with DPW ENRD Air Quality Program prior to the start of any construction and prior to making any irrevocable decisions (i.e. purchasing equipment) related to equipment, activities or processes that have the potential to emit air pollutants such as combustion exhaust, dust, asbestos, evaporative emissions, refrigerant, etc. All certifications are the responsibility of the contractor (potable water health certifications, gas weld certifications, refrigerant technician certifications, asbestos removal certifications, etc.) and must be provided to the COR prior to final payment.

7.02 The contractor shall obtain specific approval for all materials and equipment that vary from the standards established herein. All work shall be performed in a skillful and workmanlike manner to current applicable industry standards and in accordance with manufacturer instructions

7.03 Environmental work statement clause for all exterior work (SWPPP)

7.03.01 Through the Arizona Pollutant Discharge Elimination System (AZPDES) permitting program, the Arizona Department of Environmental Quality (ADEQ) regulates the discharge of storm water from construction sites throughout the state including those on military installations.

8.0 Clean Up (FAR 52.236-12, Cleaning Up)

8.01 The contractor shall at all times keep the work area, including storage areas, free from accumulation of waste materials. All trash will be removed from the site on a daily basis. Upon completion of the project, all equipment, materials and other items associated with the project shall be removed from the project site and the site shall be left clean. Any and all waste products created during performance of the work shall be removed from the project site, packaged in an environmentally approved manner and disposed of OFF-POST at an environmentally approved disposal site.

9.0 Utilities

9.01 Where available, onsite utilities will be provided to the contractor at their expense and will require a Utility Sales Agreement with Fort Huachuca. These utilities shall be used only in the performance and support of the project.

9.02 Any temporary connection to the utility system will be coordinated with the contracting officer’s representative prior to hook-up. The contractor shall complete the temporary connection and all temporary electrical work in accordance with applicable codes and standards. Temporary electrical wiring and devices shall comply with the current National Electrical Code. Temporary wiring and devices shall be removed at project completion. All temporary electrical work shall be at the contractor’s expense.

10.0 Storage Areas/Lay Down Yards

10.01 The contractor and the Contracting Officer’s Representative will agree on temporary storage areas and lay down yards in the general location of the project. Request for proposed storage area shall be submitted with the proposal documents. The contractor shall be responsible for the safety, security and maintenance associated with storage areas. Storage areas shall be kept clean and in a neat and organized appearance at all times. If the storage area is not maintained, the Contracting Officer may direct the contractor to store materials off the installation. Storage areas and lay down yards shall be returned to the existing stable state, which may require some rehabilitation of the land, like re-seeding with native grass mixtures.

11.0 DD Form 1354 Worksheet Preparation

11.01 The contractor shall prepare a DD Form 1354 Information Worksheet near completion of the project and submit it to the Government prior to final inspection and acceptance. The contractor may obtain a DD Form 1354 Information worksheet from the DOC CS or the DPW COR.

12.0 Contractor Quality Control (CQC)

12.01 The contractor is responsible for quality control and shall establish and maintain an effective quality control system and shall include the following:

12.01.01 The Quality control system shall consist of plans, procedures, and organization necessary to produce an end product that complies with the specified requirements of this project. The system shall cover all construction activities, both on site and off site, and shall be coordinated with the proposed construction schedule.

12.01.02 The contractor shall submit to the COR for review and approval a Contractor Quality Control Plan proposed to implement the specified requirements. The plan shall identify personnel, procedures, controls, instructions, tests, records, and forms to be used. Construction will be permitted to begin only after acceptance of the CQC plan.

13.0 Inspection

13.01 All work is subject to inspection and testing by the Government at all places and at all reasonable times before acceptance, in accordance with FAR 52.246-12, Inspection of Construction. Government inspections and tests do not relieve the contractor of the responsibility for providing adequate quality control measures, nor does it constitute or imply Government acceptance of the work. The presence or absence of a Government inspector does not relieve the contractor of complying with the specified requirements, nor is the Government inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.

14.0 Accident Prevention

14.01 The contractor shall comply with 29 CFR part 1926, 29 CFR part 1910, all state and local occupational safety and health requirements, and the requirements of EM 385-1-1, U.S. Army Corps of Engineers Safety and Health Requirements Manual.

14.02 The contractor is responsible for accident prevention and safety and shall establish and maintain an effective system.

15.0 Submittals

15.01 The contractor shall provide information and/or submit samples of materials that the contractor contemplates incorporating in the work. All submittals shall be at the contractor’s expense.

15.02 The following submittal items are required for this project:

15.02.01 Submittals required prior to start of construction (normally at the PRECON) shall include:

15.02.01.01 Construction schedule

15.02.01.02 Project designs, specifications, design analysis

15.02.01.03 Shop drawings

15.02.01.04 Submittal Register (ENG FORM 4025 and 4288) 15.02.01.05 Catalog cuts (equipment and materials) 15.02.01.06 Finish material samples and/or product data

15.02.01.07 Sub-contractor personnel list (POC with phone number)

15.02.01.08 Quality Control, Accident Prevention, Disposal/Borrow Pit Plans

15.02.01.09 Permits and certifications (Dig Permit, SWPPP/NOIs, 4.01 permits, Hot Work, etc.)

15.02.01.10 Air Quality Control and other Environmental submittals as appropriate

15.02.02 Submittals required during the construction period shall include:

15.02.02.01 Monthly reports to COR

15.02.02.02 Air Quality Control Reports and other Environmental submittals

15.02.02.03 Draft DD Form 1354 Worksheet

15.02.03 Submittals required near the end of the project but before final inspection:

15.02.03.01 Final DD Form 1354 Worksheet

15.02.03.02 As-Built drawings (per contract requirements)

15.02.03.03 Certified Commissioning Reports

15.02.03.04 O&M manuals – 3 hard copies and one computer disk (CD)

15.02.03.05 Repair parts list and vendors

15.03 If any of the equipment/material submittals are disapproved, the contractor shall resubmit the disapproved submittals for review and comment within five (5) working days of notification of their disapproval. This process shall continue until all equipment/materials are approved by the government.

15.04 If contractor uses or installs materials or equipment without approval, he does so at the risk of subsequent rejection, and replacement at his cost.

15.05 Final Inspection and Acceptance

15.06 Final inspection and acceptance shall be conducted after the pre-final inspection is completed by the CQC representative and the pre-final inspection punch list items are completed by the contractor. The CQC representative compiles the pre-final punch list immediately after the work is completed. The Government’s PM/COR/QA representative will sign for completion documents after the final inspection and its punch list items are corrected; and upon receipt of acceptable As-Built Drawings and any delayed work (seeding prior to rainy season, Air Conditioning Test, Adjustment and Balancing in summer months, etc.).

16.0 Warranty Requirements

16.01 All work shall be covered under the one-year warranty of construction (FAR 52.246-21, Warranty of Construction).

16.02 In addition to the one-year warranty of construction, the contractor shall obtain all warranties that would normally be given in commercial practice and, upon final acceptance of the work (or before), provide a list to the Government of each warranted equipment item, feature of construction, or system. The list shall indicate the following:

16.02.01 Name of item.

16.02.02 Model and Serial Number.

16.02.03 Installed location.

16.02.04 Name and phone numbers of manufacturers or suppliers.

16.02.05 Names, addresses, and phone numbers of sources of spare parts.

16.02.06 Warranties and terms of warranty. Items with warranties extending beyond the one- year warranty shall be indicated with separate warranty expiration dates.

16.02.07 Start date and duration of warranty period.

16.02.08 Summary of maintenance procedures required to continue the warranty in force with cross-reference to specific pertinent operation and maintenance manuals as applicable.

16.03 At approximately four and nine months after acceptance the Government may conduct warranty inspections. The inspections will be scheduled by the Government COR/Project Manager and conducted with the user, and, if possible, contractor personnel attending. A list of deficiencies existing at the time will be compiled and furnished to the Contractor for correction.

17.0 AT Level I Training:

17.01 This requirement is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil Access and general protection/security policy and procedures. This requirement is for contractor employees with an area of performance within Army controlled installation, facility, or area. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

17.02 DoD Facility and Installation Access:

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

17.03 iWATCH Training:

This requirement is for contractor employees with an area of performance within an Army controlled installation, facility or area. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 05 calendar days of new mployees commencing performance with the results reported to the COR NLT 30 calendar days after contract award. Training Information can be found at: https://www.lrn.usace.army.mil/Portals/49/docs/Security/iWatch_USACE%20Contractors%2024AUG20.pdf

17.04 OPSEC Training:

Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter. OPSEC Awareness for Military Members, DoD Employees and Contractors is available at the following website: http://cdsetrain.dtic.mil/opsec/index.htm.

FIG 1: Pedestal.

FIG 2: Communication Shelter.

FIG 3: Trench

FIG 4: Service Entrance.

FIG 5: 4” PVC Conduit on Hand

FIG 6: NODE A

FIG 7: Existing MH #8

FIG 8: East Range Communication.

FIG 9: Fiber Optic Cable on Hand

FIG 10: Fiber Optic Cable image1.jpeg image2.png image3.png image4.jpeg image5.png image6.png image7.png image8.png image9.png image10.png