This document is a Quality Assurance Surveillance Plan (QASP) for a federal contract opportunity titled "Interest Program Requirement". The QASP outlines the procedures and guidelines the Office of Servicewide Interest (OSI) will use to ensure the required performance standards or service levels are achieved by the Contractor.

The key objectives of the contract are for the Contractor to provide support and assistance with sensitive taxpayer information to provide Net Rate Netting (NRN) computations, apply Internal Revenue Code (IRC) 6621(d), compute and verify NRN computations using the current interest computation software. The Contractor will be required to review NRN submissions received on behalf of taxpayers, consider all factors including statute of limitation periods, and determine if the NRN requests should be allowed in full, adjusted or denied. The QASP defines the roles and responsibilities, performance standards, surveillance methods, quality assurance documentation requirements, and analysis of quality assurance monitoring for this contract. It also includes attachments with a Performance Requirements Summary and Quality Assurance Surveillance Form.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PWS Attachment 1

QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)

24-71-A-PMO-OITA Interest Program Requirement

TABLE OF CONTENTS

1INTRODUCTION3
1.1Purpose3
1.2Performance Management Approach3
1.3Performance Management Strategy3
2ROLES AND RESPONSIBILITIES4
2.1The Contracting Officer4
2.2The Contracting Officer’s Representative4
3IDENTIFICATION OF REQUIRED PERFORMANCE STANDARDS/QUALITY LEVELS4
4METHODOLOGIES TO MONITOR PERFORMANCE4
4.1Surveillance Techniques4
4.2Customer Feedback5
4.3Acceptable Quality Levels5
5QUALITY ASSURANCE DOCUMENTATION5
5.1The Performance Management Feedback Loop5
5.2Monitoring Forms6
6ANALYSIS OF QUALITY ASSURANCE ASSESSMENT6
6.1Determining Performance6
6.2Reporting6
6.3Reviews and Resolution6

7 ATTACHMENTS: A PERFORMANCE REQUREMENTS SUMMARY

B QUALITY ASSURANCE SURVEILLANCE FORM

24-71-A-PMO-OITA INTEREST PROGRAM REQUIREMENT

Quality Assurance Surveillance Plan (QASP)

1. INTRODUCTION

This quality assurance surveillance plan (QASP) is pursuant to the requirements listed in the Performance Work Statement (PWS) entitled 24-71-A-PMO-OITA Interest Program Requirement. This plan sets forth the procedures and guidelines the Office of Servicewide Interest (OSI) will use in ensuring the required performance standards or services levels are achieved by the Contractor.

This Attachment describes the desired outcomes, performance requirements, standards, surveillance methods, and incentives for this award order. The Table below is divided into 4 discrete tasks. It is intended to align Contractor’s goals and objectives with the IRS program goals and objectives as follows:

The Table below reflects the guidance and methods for determining metrics, Acceptable Quality Levels, and incentives/disincentives for this PWS.

All Deliverables, Documents, and Services shall satisfy program and project requirements, and comply with IRS CMMI standards, existing IRS standards and guidelines, and integrate with IRS, security requirements and Section 508.

1.1 Purpose

The purpose of the QASP is to describe the systematic methods used to monitor performance and to identify the required documentation and the resources to be employed. The QASP provides a means for evaluating whether the Contractor is meeting the performance standards/quality levels identified in the PWS and the Contractor’s quality control plan (QCP), and to ensure that the government pays only for the level of services received.

This QASP defines the roles and responsibilities of all members of the team, identifies the performance objectives, defines the methodologies used to monitor and evaluate the Contractor’s performance, describes quality assurance documentation requirements, and describes the analysis of quality assurance monitoring results.

1.2 Performance Management Approach

The PWS structures the acquisition around “what” service or quality level is required, as opposed to “how” the Contractor should perform the work (i.e., results, not compliance). This QASP will define the performance management approach taken by the Office of Servicewide Interest (OSI) to monitor and manage the Contractor’s performance to ensure the expected outcomes or performance objectives communicated in the PWS are achieved. Performance management rests on developing a capability to review and analyze information generated through performance assessment. The ability to make decisions based on the analysis of performance data is the cornerstone of performance management; this analysis yields information that indicates whether expected outcomes for the project are being achieved by the Contractor.

Performance management represents a significant shift from the more traditional quality assurance (QA) concepts in several ways. Performance management focuses on assessing whether outcomes are being achieved and to what extent. This approach migrates away from scrutiny of compliance with the processes and practices used to achieve the outcome. A performance-based approach enables the Contractor to play a large role in how the work is performed, as long as the proposed processes are within the stated constraints. The only exceptions to process reviews are those required by law (federal, state, and local) and compelling business situations, such as safety and health. A “results” focus provides the Contractor flexibility to continuously improve and innovate over the course of the contract as long as the critical outcomes expected are being achieved and/or the desired performance levels are being met.

1.3 Performance Management Strategy

The Contractor is responsible for the quality of all work performed. The Contractor measures that quality through the Contractor’s own quality control (QC) program. QC is work output, not workers, and therefore includes all work performed under this contract regardless of whether the work is performed by Contractor employees or by subcontractors. The Contractor’s QCP will set forth the staffing and procedures for self-inspecting the quality, timeliness, responsiveness, customer satisfaction, and other performance requirements in the PWS. The Contractor will develop and implement a performance management system with processes to assess and report its performance to the designated government representative. The Contractor’s QCP will set forth the staffing and procedures for self-inspecting the quality, timeliness, responsiveness, customer satisfaction, and other performance requirements in the PWS. This QASP enables the government to take advantage of the Contractor’s QC program. The QCP shall be submitted thirty (30) days after award order.

1.3.2 The government representative(s) will monitor performance and review performance reports furnished by the Contractor to determine how the Contractor is performing against communicated performance objectives. The Contractor will be responsible for making required changes in processes and practices to ensure performance is managed effectively.

2. ROLES AND RESPONSIBILITIES

2.1 The Contracting Officer

The Contracting Officer (CO) is responsible for monitoring contract compliance, contract administration, and cost control and for resolving any differences between the observations documented by the Contracting Officer's Representative (COR) and the Contractor. The CO will designate one full-time COR as the government authority for performance management. The number of additional representatives serving as technical inspectors depends on the complexity of the services measured.

2.2 The Contracting Officer’s Representative

The COR is designated in writing by the CO to act as his or her authorized representative to assist in administering a contract. COR limitations are contained in the written appointment letter. The COR is responsible for technical administration of the project and ensures proper government surveillance of the Contractor’s performance. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the government’s behalf. Any changes that the Contractor deems may affect contract price, terms, or conditions shall be referred to the CO for action. The COR will have the responsibility for completing QA monitoring forms used to document the inspection and evaluation of the Contractor’s work performance. Government surveillance may occur under the inspection of services clause for any service relating to the contract.

3. IDENTIFICATION OF REQUIRED PERFORMANCE STANDARDS/QUALITY LEVELS

The required performance standards and/or quality levels are included in the PWS and in Attachment A, “Performance Requirements Summary.”

4. METHODOLOGIES TO MONITOR PERFORMANCE

4.1 Surveillance Techniques

In an effort to minimize the performance management burden, simplified surveillance methods shall be used by the government to evaluate Contractor performance when appropriate. The primary methods of surveillance are:

· Periodic Reviews – COR typically performs the periodic reviews on a monthly basis.

4.2 Customer Feedback

The Contractor is expected to establish and maintain professional communication between its employees and customers. The primary objective of this communication is customer satisfaction. Customer satisfaction is the most significant external indicator of the success and effectiveness of all services provided and can be measured through customer complaints.

Performance management drives the Contractor to be customer focused through initially and internally addressing customer complaints and investigating the issues and/or problems, but the customer always has the option to communicate complaints to the COR, as opposed to the Contractor.

Customer complaints, to be considered valid, must set forth clearly and in writing the detailed nature of the complaint, must be signed, and must be forwarded to the COR. The COR will accept those customer complaints and investigate.

Customer feedback may also be obtained either from the results of formal customer satisfaction surveys or from random customer complaints.

4.3 Acceptable Quality Levels

The acceptable quality levels (AQLs) included in Attachment A, Performance Requirements Summary Table, for Contractor performance are structured to allow the Contractor to manage how the work is performed. For certain critical activities such as those involving contractual deliverables, invoice submission, and management reports, the desired performance level is at 100 percent. Other levels of performance are keyed to the relative importance of the task to the overall mission performance of the Office of Servicewide Interest (OSI).

5. QUALITY ASSURANCE DOCUMENTATION

5.1 The Performance Management Feedback Loop

The performance management feedback loop begins with the communication of expected outcomes. Performance standards are expressed in the PWS and are assessed using the performance monitoring techniques shown in Attachment A.

Approval of all deliverables will be the responsibility of the contract Program Manager. The COR will provide acceptance of deliverables.

5.2 Monitoring Forms

The government’s QA surveillance, accomplished by the COR, will be reported using the monitoring form in Attachments B. The form, when completed, will document the government’s assessment of the Contractor’s performance under the contract to ensure that the required results of contractual deliverables, invoice submission, and management reports are being achieved.

5.2.1 The COR will retain a copy of all completed QA surveillance forms.

6. ANALYSIS OF QUALITY ASSURANCE ASSESSMENT

6.1 Determining Performance

Government shall use the monitoring methods cited to determine whether the performance standards/service levels/AQLs have been met. If the Contractor has not met the minimum requirements, it may be asked to develop a corrective action plan to show how and by what date it intends to bring performance up to the required levels. Failure to meet the AQL may result in a negative performance assessment. Likewise, a positive performance assessment is the incentive for the Contractor to perform well.

6.2 Reporting

The COR will prepare a written report quarterly summarizing the overall results of the quality assurance surveillance of the Contractor’s performance. This written report will become part of the QA documentation. It will enable the government to demonstrate whether the Contractor is meeting the stated objectives and/or performance standards, including cost/technical/scheduling objectives.

6.3 Reviews and Resolution

The COR may require the Contractor’s project manager, or a designated alternate, to meet with the COR and other government IPT personnel as deemed necessary to discuss performance evaluation. The COR will define a frequency of in-depth reviews with the Contractor, including appropriate self-assessments by the Contractor; however, if the need arises, the Contractor will meet with the COR as often as required or per the Contractor’s request. The agenda of the reviews may include:

· Monthly performance assessment data and trend analysis

· Issues and concerns of both parties

· Projected outlook for upcoming months and progress against expected trends, including a corrective action plan analysis

· Recommendations for improved efficiency and/or effectiveness

· Issues arising from the performance monitoring processes

The COR must coordinate and communicate with the Contractor to resolve issues and concerns regarding marginal or unacceptable performance.

The COR and Contractor should jointly formulate tactical and long-term courses of action. Decisions regarding changes to metrics, thresholds, or service levels should be clearly documented. Changes to service levels, procedures, and metrics will be incorporated as a contract modification at the convenience of the CO.

Attachment A: PERFORMANCE REQUIREMENTS SUMMARY Required Services (Tasks) Performance Standards Acceptable Quality Levels Methods of Surveillance Incentive /Disincentive (Positive and/or Negative)

Task 1: Orientation Briefing (Optional)
Deliver Orientation Briefing

Prepare/Complete Sign-In Sheet for meeting participants.

Take Meeting Notes.

Provide copy of Briefing Slide/notes presented to include names, telephone numbers and addresses (physical and e-mail) for key task participants as well as roles for both the Contractor and Program Office.

Due 5 days after Orientation Brief

This briefing is a one- time only occurrence.
Positive / Negative Performance Evaluation may result.

Required Services (Tasks) Performance Standards Acceptable Quality Levels Methods of

Incentive /Disincentive (Positive and/or Negative)

Task 2: Interest Computations for Net Rate Netting (NRN)
(1) Contractor shall be provide knowledge and experience in the process and criteria for submitting valid Form 843 NRN cases for computing/verifying NRN computations.

(2) Contractor shall provide the knowledge and experience with IRS account transactions and how activities impact the interest computation.

(3) Contractor shall provide NRN computations and case resolutions for NRN inventory.

Review will be performed within approximately 15 calendar days from receipt of each deliverable.

If deficiencies are found, the Contractor will be notified by the COR in writing of the deficiencies within a 30 working day review period and the final product, together will be marked "Rejected", and will be returned with appropriate annotations indicating the deficiencies. Comment by Spruill Adrienne M: Recommend you include language if the calculations are incorrect. See sample language. Comment by Dressler Stacey L: Provided timeframes.

The Contractor shall have 15 working days from the notification of deficiencies to respond with final corrected project products.

100% review by COR and/or IRS PM.
Positive / Negative Performance Evaluation may result.

Required Services (Tasks) Performance Standards Acceptable Quality Levels Methods of

Incentive /Disincentive (Positive and/or Negative)

Task 3: Award Status Reports

(1) Contractor shall provide a summary of work performed, including a list of deliverables, and a list of government furnished property currently possessed by the Contractor at the end of the Base Period and each Optional Period of Performance. Comment by Bovay Richard W (Contractor): Should this be “formerly” (currently and formerly)? In this context, the word “formally” seems out of place

(2) Government reserves the right to request this report at any point during the performance of the award at the discretion of the CO or COR. This ad hoc report, if desired, will be requested no more than twice per year during the life of the award and is in addition to the regularly scheduled Period of Performance Summary Report.

(1) Information shall be provided at the end of the Base Period and each Optional Period of Performance.

(2) Ad hoc reports, if desired, shall be requested no more than twice per year.

100% review by COR and/or IRS PM.
Positive / Negative Performance Evaluation may result.
Task 4: Transition Out (Optional)
Contractor shall develop, document, and provide a Transition-Out Plan no later than one hundred eighty (180) calendar days after the date of award.
Contractor shall develop, document, and provide a Transition-Out Plan no later than 180 calendar days after the date of award, or earlier if directed by the Contracting Officer, and shall be updated annually.
100% review by COR and/or IRS PM.

Positive / Negative Performance Evaluation may result.

PERFORMANCE REQUIREMENTS

Performance Standard requirements for this PWS are identified as indicated in table above. The Performance Standards are a critical component of the performance objectives that relate directly to the overall objectives of the PWS herein. A Performance Standard is associated with each performance requirement.

Attachment B: Quality Assurance Surveillance Form

QUALITY ASSURANCE SURVEILLANCE FORM

(Additional pages may be added)

SERVICE or STANDARD:

MONITORING PERIOD:

SURVEILLANCE METHOD (Check):

· COR Monitoring Inspection Testing Random Sampling Report

· User/Customer Observations/Complaints

LEVEL OF SURVEILLANCE (Check):

· Weekly Monthly Quarterly As needed

CRITERIA/DOCUMENTATION USED FOR SAMPLE:

ANALYSIS OF RESULTS:

Contractor’s Performance (Check): Meets Standards Does Not Meet Standards

Narrative of Performance During Survey Period:

PREPARED BY: DATE: