223 Route 82 Water Main Lining.pdf
PDF 3 MB Posted
- Attached to
- Route 82 Water Main Lining
- Solicitation number
- 27-23
- Issued by
- New London County, Connecticut
About this file
This is a project description document for the City of Norwich, Connecticut, acting on behalf of Norwich Public Utilities, for the Route 82 Water Main Lining project. The work encompasses furnishing, installing, and maintaining all barricades, signing, and traffic control measures necessary for project execution. The primary scope includes furnishing and installing new insertion valves, water main lining, and associated appurtenances along Route 82. The contractor must excavate and support all excavations in compliance with OSHA regulations and perform comprehensive surface restoration, including temporary and permanent roadway pavement, mill and overlay work, curbs, sidewalks, pavement markings, and lawn re-establishment.
The document does not specify response dates, bid due dates, site visit schedules, or bidder's conferences within the provided content. Similarly, no award date, contract term, renewal options, pricing terms, set-aside provisions, incumbent contractor information, or funding sources and amounts are detailed in this project description file. The scope of work focuses on the technical and logistical requirements for completing the water main lining project while maintaining traffic safety and restoring affected infrastructure to its original condition.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
16 South Golden Street, Norwich, Connecticut 06320
Project Manual & Specifications For:
Route 82 Water Main Lining
West Main St. (Route 82) Eastbound Over the
East Branch of the Yantic River
Under Bridge No. 06009
Norwich, Connecticut
Revised: September 2, 2026 (Issued for Bid)
Revised: August 26, 2026
August 17, 2026
Prepared By:
CLA Engineers, Inc.
Consulting Engineers
317 Main Street
Norwich, CT 06360
Ph: 860-886-1966 F: 860-886-9165 www.claengineers.com http://www.claengineers.com/
Norwich Public Utilities Route 82 Water Main Lining
CLA Engineers, Inc.
Civil · Structural · Survey
TABLE OF CONTENTS
I. ADVERTISEMENT FOR BIDS
II. INSTRUCTIONS TO BIDDERS
III. PROPOSAL FORMS
1. List of Required Documents
2. Proposal
3. Bid Form
4. Form of Bid Bond
5. Statement of Bidders Qualifications
6. Proposed Subcontractors
7. Proposed Suppliers
8. Non-Discrimination in Employment
9. Non-Collusion Affidavit of Prime Bidder
10. Certificate as to Corporate Principal
IV. AGREEMENT AND BOND FORMS
1. Agreement Between Owner and Contractor
2. Certification
3. Form of Performance Bond
4. Form of Payment Bond
V. STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT
VI. SUPPLEMENTARY CONDITIONS
VII. NORWICH PUBLIC UTILITIES SAFETY GUIDELINES, PROCEDURES FOR BLASTING
NEAR ACTIVE GAS MAINS AND SERVICES & CITY OF NORWICH SEXUAL
HARASSMENT POLICY
VIII. TECHNICAL SPECIFICATIONS
IX. PREVAILING WAGE REQUIREMENTS & RATES
I. ADVERTISEMENT FOR BIDS
Invitation for Bid/Proposal Bid No. 27-23
The Purchasing Agent, City of Norwich, on behalf of Norwich Public Utilities, will receive bids/proposals for Water Main Lining services until 2:00 P.M. prevailing time on September 30, 2026, at which time they will be opened on the Procurement website and be available to view. All bids are to be submitted via the City of Norwich Procurement Portal at the following website :
City of Norwich Procurement Portal
The bid documents may be downloaded from the following website:
City of Norwich Procurement Portal
Addenda, if any, will be posted on the website listed above. All bidders, prior to submitting their bids, should check the websites to ensure they have received all issued addenda.
Norwich Public Utilities reserves the right to reject and all bids, in whole or in part, to waive minor irregularities in the bidding and to award the bid to other than the low bidder if deemed in the best interest of the City of Norwich.
No Bidder may withdraw its bid within sixty (60) days of the bid opening date. Should there be reason why the contract cannot be awarded within the specified time, the time may be extended by mutual agreement between Norwich Public Utilities and the designated, qualified low bidder.
All final awards of the bid shall be in compliance with the City of Norwich Code of Ordinances §7-46 – Delinquent Tax Setoff Against Money Due Bidder or Contractor.
By submitting a bid to this RFP, the vendor certifies they are not on a state or federal debarment or suspended list and are not prohibited from performing any state or federal work.
All bidders must submit bids/proposals through the City Procurement Portal.
Responding bidders must ensure that employees and applicant for employment are not discriminated against because of their race, color, religious creed, age, marital status, national origin, ancestry, sex, gender identity or expression, intellectual disability, mental disability or physical disability, including, but not limited to blindness, unless it is shown by such bidder that such disability prevents performance of the work involved.
Karl J. Klein Jr.
Purchasing Agent
City of Norwich Department of Finance – Purchasing Agent Phone: (860)823-3706 100 Broadway, Room No. 105 Fax: (860)823-3812 Norwich, CT 06360 E-mail: kklein@cityofnorwich.org https://norwichct.bonfirehub.com/portal/?tab=openOpportunities
BIDDER'S INSTRUCTIONS
IFB 27-23
NORWICH PUBLIC UTILITIES ROUTE 82 WATER MAIN LINING
The following instructions and specifications shall be observed by all proposers:
Time and Place of Bid Opening Proposals will be received on SEPTEMBER 30, 2026 at 2:00 P.M. online at:
https://norwichct.bonfirehub.com/portal/?tab=openOpportunities Proposals will not be allowed after the time and date of the opening.
Availability of Documents Vendors are advised that all documents relative to this project are only available online at the following web address:
https://norwichct.bonfirehub.com/portal/?tab=openOpportunities
Addenda If additional information becomes available or changes are made to the documents, an addendum will be issued not later than 3 days prior to the opening date. All addenda shall become part of the Contract Documents.
It is incumbent on the Vendor to ensure that it has received all issued addenda by checking the websites listed above. Failure of any Vendor to receive any such addendum shall not relieve it of the obligations under its proposal.
Notice of any addendum will be posted on the following website:
https://norwichct.bonfirehub.com/portal/?tab=openOpportunities
Instructions Proposals must be submitted to the City of Norwich Procurement portal at:
https://norwichct.bonfirehub.com/portal/?tab=openOpportunities Proposals will not be accepted by mail, in person or by email.
All forms and associated documents must be uploaded through the procurement portal. Sales and Use Tax Vendors are reminded that the Connecticut State Sales and Use Tax and associated Federal taxes are not applicable under this contract, and therefore these taxes are not to be included in the price.
Under the terms of Connecticut Agencies Regulations §12-426-18, Contractors and Subcontractors, the contractor may purchase materials and supplies as are to be installed or placed in projects being performed under these contracts and will remain in such projects after completion, including tangible personal property that remains tangible personal property after its installation or placement, without payment of the tax and shall not charge any such exempt organization or agency any sales or use tax thereon.
Definitions For the purposes of these documents:
The word “City” means the City of Norwich, CT.
The word “Proposer” or “Vendor” refers to the party or parties submitting a proposal to perform the work to be done or materials to be furnished under the Contract; the legal representatives of such party or parties.
Certificate in Good Standing Any corporation whose proposal is being considered for acceptance by the City may be required, if requested, to provide a “Certificate of Good Standing” from the Office of the Secretary of State for Connecticut.
https://norwichct.bonfirehub.com/portal/?tab=openOpportunities
Acceptance/Rejection of Proposals The City may reject proposals which are incomplete, conditional, obscure, contain additions not called for, erasures or corrections not initialed, or which contain alterations or irregularities of any kind. The City may rightfully waive informalities. Determination of the best interest of the City shall include consideration of active or pending civil litigation between the City and any firm (or its subcontractors or suppliers) submitting a proposal to the City.
Withdrawal of Proposal Submitted Any bid may be withdrawn prior to the designated date and time for receipt of proposals. Proposals may be withdrawn ninety (90) days after the opening if no award has been made by the City. If the City does not award a contract within ninety (90) days after the opening, all proposals will be null and void, except this time may be extended by mutual agreement of the City and the selected vendor.
Award Execution The firm whose proposal is accepted will be issued a “Notice of Award.” The Vendor will be required to execute the “Notice of Award,” and provide a certificate of insurance within ten working days from the date the Notice of Award is issued.
Freedom of Information All proposals shall be made available for public inspection, in accordance with the provisions of Connecticut General Statutes § 1-210, Freedom of Information. Copies of any information resulting from any proposal opening are generally not available until a contract has been awarded or a purchase order issued.
Non-Collusion The individual signing the proposal hereby declares that no person or persons other than members of its organization are interested in this proposal or in the contract proposed to betaken; that it is made without any connection to any other person or persons submitting a proposal for the same work and is in all respects fair and without collusion or fraud; that no person acting on behalf of or employed by the City of Norwich is directly or indirectly interested in the supplies or work to which they relate or will receive any part of the profit or any commission therefrom in any manner which is unethical or contrary to the best interests of the City of Norwich.
II. INSTRUCTIONS TO BIDDERS
(EJCDC C-200)
EJCDC C-200 Instructions to Bidders for Construction Contracts Copyright © 2007 National Society of Professional Engineers for EJCDC. All rights reserved.
Page ii
Copyright © 2007 National Society of Professional Engineers 1420 King Street, Alexandria, VA 22314-2794
(703) 684-2882 www.nspe.org
American Council of Engineering Companies 1015 15th Street N.W., Washington, DC 20005
(202) 347-7474 www.acec.org
American Society of Civil Engineers 1801 Alexander Bell Drive, Reston, VA 20191-4400
(800) 548-2723 www.asce.org
Associated General Contractors of America 2300 Wilson Boulevard, Suite 400, Arlington, VA 22201-3308
(703) 548-3118 www.agc.org
The copyright for this EJCDC document is owned jointly by the four EJCDC sponsoring organizations and held in trust for their benefit by NSPE.
http://www.nspe.org/ http://www.acec.org/ http://www.asce.org/ http://www.agc.org/
Page ii
TABLE OF CONTENTS
Page Article 1 – Defined Terms
Article 2 – Copies of Bidding Documents
Article 3 – Qualifications of Bidders
Article 4 – Examination of Bidding Documents, Other Related Data, and Site
Article 5 – Pre-Bid Conference
Article 6 – Site and Other Areas
Article 7 – Interpretations and Addenda
Article 8 – Bid Security
Article 9 – Contract Times
Article 10 – Liquidated Damages
Article 11 – Substitute and “Or-Equal” Items
Article 12 – Subcontractors, Suppliers and Others
Article 13 – Preparation of Bid
Article 14 – Basis of Bid; Comparison of Bids
Article 15 – Submittal of Bid
Article 16 – Modification and Withdrawal of Bid
Article 17 – Opening of Bids
Article 18 – Bids to Remain Subject to Acceptance
Article 19 – Evaluation of Bids and Award of Contract
Article 20 – Contract Security and Insurance
Article 21 – Signing of Agreement
Article 22 – Sales and Use Taxes
Article 23 – Retainage
Article 24 – Employment of Labor
Article 25 – Provisional Items Article 26 – Safety Standards
ARTICLE 1 – DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office – The office from which the Bidding Documents are to be issued and where the bidding procedures are to be administered. In this case the City of Norwich Purchasing Office located at 100 Broadway, Room 105, Norwich, Connecticut.
ARTICLE 2 – COPIES OF BIDDING DOCUMENTS
2.01 Complete sets of the Bidding Documents in the number and for the deposit sum, if any, stated in the advertisement or invitation to bid may be obtained from the locations stated in the advertisement. Neither the Owner nor Engineer will be responsible for full or partial sets of Bid Documents obtained from any other source.
2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license for any other use.
ARTICLE 3 – QUALIFICATIONS OF BIDDERS
3.01 To demonstrate Bidder’s qualifications to perform the Work, within 5 days of Owner’s request, Bidder shall submit written evidence such as financial data, previous experience, present commitments, and such other data as may be called for below or as otherwise requested by the Owner.
A. Not Applicable
B. List of major equipment available for this contract.
3.02 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.
3.03 Not Applicable
ARTICLE 4 – EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA, AND
SITE
4.01 Not Applicable
4.02 Underground Facilities
A. Information and data shown or indicated in the Bidding Documents with respect to existing Underground Facilities at or contiguous to the Site is based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities, including Owner, or others.
4.03 Not Applicable
4.04 Not Applicable
4.05 On request, Owner will provide Bidder access to the Site to conduct such examinations, investigations, explorations, tests, and studies as Bidder deems necessary for submission of a Bid.
Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies. Bidder shall comply with all applicable Laws and Regulations relative to excavation and utility locates. The Bidder must perform these investigations within the bid advertisement period and at a time at the discretion of the Owner.
4.06 Not Applicable
4.07 It is the responsibility of each Bidder before submitting a Bid to:
A. examine and carefully study the Bidding Documents, and the other related data identified in the Bidding Documents;
B. visit the Site and become familiar with and satisfy Bidder as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;
C. become familiar with and satisfy Bidder as to all federal, state, and local Laws and Regulations that may affect cost, progress, and performance of the Work;
D. Not Applicable
E. Not Applicable
F. agree at the time of submitting its Bid that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price(s) bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents;
G. become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;
H. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder; and
I. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work.
4.08 The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Bidding Documents and applying any specific means, methods, techniques, sequences, and procedures of construction that may be shown or indicated or expressly required by the Bidding Documents, that Bidder has given Engineer written notice of all conflicts, errors, ambiguities, and discrepancies that Bidder has discovered in the Bidding Documents and the written resolutions thereof by Engineer are acceptable to Bidder, and that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work.
ARTICLE 5 – PRE-BID CONFERENCE
5.01 No pre-bid conference or walk-through will be held. The project site is available for viewing at the bidder’s convenience.
ARTICLE 6 – SITE AND OTHER AREAS
6.01 The Site is identified in the Bidding Documents. Easements for permanent structures or permanent changes in existing facilities are to be obtained and paid for by Owner unless otherwise provided in the Bidding Documents. All additional lands and access thereto required for temporary construction facilities, construction equipment, or storage of materials and equipment to be incorporated in the Work are to be obtained and paid for by Contractor.
ARTICLE 7 – INTERPRETATIONS AND ADDENDA
7.01 No interpretation of the meaning of the Drawings, Specifications, or other prebid documents will be made to any bidder orally. Every request for such interpretation shall be in writing through the City of Norwich Procurement Portal at:
https://norwichct.bonfirehub.com/portal/?tab=openOpportunities Addenda to bid documents may be issued prior to the bid opening as outlined in the Procurement Portal and will be posted on the City of Norwich Procurement Portal. It is the responsibility of bidders to view all addenda. Only questions answered by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.
7.02 Addenda may be issued to clarify, correct, or change the Bidding Documents as deemed advisable by Owner or Engineer.
7.03 Potential Bidders are responsible for checking the City of Norwich Procurement Portal website at https://norwichct.bonfirehub.com/portal/?tab=openOpportunities for any addenda and updates regarding this Bid.
ARTICLE 8 – BID SECURITY
8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 5 percent of Bidder’s maximum Bid price and in the form of a certified check, bank money order, or a Bid bond (on the form attached) issued by a surety meeting the requirements of Paragraphs 5.01 and 5.02 of the General Conditions.
8.02 The Bid security of the Successful Bidder will be retained until such Bidder has executed the Contract Documents, furnished the required contract security and met the other conditions of the Notice of Award, whereupon the Bid security will be returned. If the Successful Bidder fails to execute and deliver the Contract Documents and furnish the required contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited. Such forfeiture shall be Owner’s exclusive remedy if Bidder defaults. The Bid security of other Bidders whom Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of seven days after the Effective Date of the Agreement or 121 days after the Bid opening, whereupon Bid security furnished by such Bidders will be returned.
8.03 Bid security of other Bidders whom Owner believes do not have a reasonable chance of receiving the award will be returned within seven days after the Bid opening.
ARTICLE 9 – CONTRACT TIMES
9.01 The number of days within which the Work is to be substantially completed and ready for final payment is set forth in the Agreement.
9.02 All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.
9.03 Days to Achieve Substantial Completion and Final Payment
A. The Work will be substantially completed within 30 calendar days after the date when the Contract Times commence to run as provided in Paragraph 2.03 of the General Conditions, and completed and ready for final payment in accordance with Paragraph 14.07 of the General Conditions within 60 calendar days after the date when the Contract Times commence to run.
B. The time of completion shall exclude the time period from each December 1 through the following March 31 (the “winter shutdown period”). The Contractor shall install temporary pavement for disturbed trenches, and shall be required to maintain the trench paving, binder, and temporary measures in a stable and safe condition for traffic throughout the duration of the shutdown. There shall be no raised structures left in the roadway. The Contractor shall also be responsible for maintaining erosion & sedimentation control measures and disturbed earth slopes in stable condition throughout the duration of the shutdown. This work shall be completed at no additional expense to the Owner. The Contractor shall be required to return to the site on or before April 1st of the following year to complete the project.
ARTICLE 10 – LIQUIDATED DAMAGES
10.01 Provisions for liquidated damages are set forth in the Agreement and as follows.
10.02 Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial loss if the Work is not completed within the times specified in Paragraph 4.02 above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. The parties also recognize the delays, expense, and difficulties involved in proving in a legal or arbitration proceeding the actual loss suffered by Owner if the Work is not completed on time. Accordingly, instead of requiring any such proof, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty), Contractor shall pay Owner $1,000.00 for each day that expires after the time specified in Paragraph 4.02 above for Substantial Completion until the Work is substantially complete.
ARTICLE 11 – SUBSTITUTE AND “OR-EQUAL” ITEMS
11.01 The Contract, if awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents, or those substitute or “or-equal” materials and equipment approved by Engineer and identified by Addendum. The materials and equipment described in the Bidding Documents establish a standard of required type, function and quality to be met by any proposed substitute or “or-equal” item. No item of material or equipment will be considered by Engineer as a substitute or “or-equal” unless written request for approval has been submitted by Bidder and has been received by Engineer at least 15 days prior to the date for receipt of Bids. Each such request shall conform to the requirements of Paragraph 6.05 of the General Conditions. The burden of proof of the merit of the proposed item is upon Bidder. Engineer’s decision of approval or disapproval of a proposed item will be final. If Engineer approves any proposed item, such approval will be set forth in an Addendum issued to all prospective Bidders. Bidders shall not rely upon approvals made in any other manner.
ARTICLE 12 – SUBCONTRACTORS, SUPPLIERS AND OTHERS
12.01 If the Supplementary Conditions require the identity of certain Subcontractors, Suppliers, individuals, or entities to be submitted to Owner in advance of a specified date prior to the Effective Date of the Agreement, the apparent Successful Bidder, and any other Bidder so requested, shall within five days after Bid opening, submit to Owner a list of all such Subcontractors, Suppliers, individuals, or entities proposed for those portions of the Work for which such identification is required. Such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, individual, or entity if requested by Owner. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit a substitute, without an increase in the Bid.
12.02 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers, individuals, or entities. Declining to make requested substitutions will not constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual, or entity so listed and against which Owner or Engineer makes no written objection prior to the giving of the
Notice of Award will be deemed acceptable to Owner and Engineer subject to revocation of such acceptance after the Effective Date of the Agreement as provided in Paragraph 6.06 of the General Conditions.
12.03 Contractor shall not be required to employ any Subcontractor, Supplier, individual, or entity against whom Contractor has reasonable objection.
12.04 Not Applicable
ARTICLE 13 – PREPARATION OF BID
13.01 The Bid Form is included with the Bidding Documents. Additional copies may be obtained from the Engineer.
13.02 All blanks on the Bid Form shall be completed in ink and the Bid Form signed in ink. Erasures or alterations shall be initialed in ink by the person signing the Bid Form. A Bid price shall be indicated for each part of the Bid Proposal, bid item, and unit price item listed therein. The Bid price(s) shall be written in both words and figures, and in the case of a discrepancy between the two the amount in words shall govern.
13.03 A Bid by a corporation shall be executed in the corporate name by the president or a vice-president or other corporate officer accompanied by evidence of authority to sign. The corporate seal shall be affixed and attested by the secretary or an assistant secretary. The corporate address and state of incorporation shall be shown.
13.04 A Bid by a partnership shall be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership shall be shown.
13.05 A Bid by a limited liability company shall be executed in the name of the firm by a member and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm shall be shown.
13.06 A Bid by an individual shall show the Bidder’s name and official address.
13.07 A Bid by a joint venture shall be executed by each joint venturer in the manner indicated on the Bid Form. The official address of the joint venture shall be shown.
13.08 All names shall be printed in ink below the signatures.
13.09 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.
13.10 Postal and e-mail addresses and telephone number for communications regarding the Bid shall be shown.
13.11 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the state where the Project is located, or Bidder shall covenant in writing to obtain such authority and qualification prior to award of the Contract and attach such covenant to the Bid. Bidder’s state contractor license number, if any, shall also be shown on the Bid Form.
13.12 Bidders shall include a statement that they and all subcontractors will comply with Executive Order No. Three, Executive Order No. Sixteen and Executive Order No. Seventeen, Office of Federal Contract Compliance Programs (OFCC) Executive Order No. 11246, Executive Order 12549 and CGS 31-53a, and federal regulation 2 CFR 200.216 as amended.
13.13 All bidders shall complete and submit the following documents with their bid:
A. Proposal Form:
Acknowledgement of Addendums OSHA Policy & Procedures Included Acknowledgement of NPU Safety Guidelines
B. Bid Form – Unit Pricing
C. Bid Security (Bid Bond or Certified Check)
D. Statement of Bidder’s Qualifications
E. Proposed Subcontractors
F. Proposed Suppliers
G. Non-Collusion Affidavit
H. Non-Discrimination in Employment
I. Certificate as to Corporate Principal
ARTICLE 14 – BASIS OF BID; COMPARISON OF BIDS
14.01 Unit Price
A. Bidders shall submit a Bid on a unit price basis for each item of Work listed in the Bid schedule.
B. The total of all estimated prices will be the sum of the products of the estimated quantity of each item and the corresponding unit price. The final quantities and Contract Price will be determined in accordance with Paragraph 11.03 of the General Conditions.
C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.
14.02 Allowances
A. For cash allowances the Bid price shall include such amounts as the Bidder deems proper for Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 11.02.B of the General Conditions.
ARTICLE 15 – SUBMITTAL OF BID
15.01 Proposals must be submitted to the City of Norwich Procurement portal at:
https://norwichct.bonfirehub.com/portal/?tab=openOpportunities Proposals will not be accepted by mail, in person or by email. All forms and associated documents must be uploaded through the procurement portal.
Sales and Use Tax
Vendors are reminded that the Connecticut State Sales and Use Tax and associated Federal taxes are not applicable under this contract, and therefore these taxes are not to be included in the price.
Under the terms of Connecticut Agencies Regulations §12-426-18, Contractors and Subcontractors, the contractor may purchase materials and supplies as are to be installed or placed in projects being performed under these contracts and will remain in such projects after completion, including tangible personal property that remains tangible personal property after its installation or placement, without payment of the tax and shall not charge any such exempt organization or agency any sales or use tax thereon.
15.02 Not applicable
15.03 The bidder agrees and warrants that in the submission of this sealed bid, they will not discriminate or permit discrimination against any person or group of persons on the grounds of race, color, religion, national origin, sex, or physical disability including, but not limited to blindness, unless it is shown by such bidder that such disability prevents performance of that which must be done to successfully fulfill the terms of this sealed bid or in any manner which is prohibited by the laws of the United States or the State of Connecticut: and further agrees to provide the Human Relations Commission with such information requested by the Commission concerning the employment practices and procedures of the bidder. An Affirmative Action Statement will be required by the successful bidder.
ARTICLE 16 – MODIFICATION AND WITHDRAWAL OF BID
16.01 A Bid may be modified or withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids or authorized postponement thereof.
16.02 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, that Bidder will be disqualified from further bidding on the Work. This provision to withdraw a Bid without forfeiting the Bid Security does not apply to Bidder’s errors in judgment in preparing the Bid.
ARTICLE 17 – OPENING OF BIDS
17.01 Bids will be opened at the time and place indicated in the Advertisement or Invitation to Bid. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids through the City of Norwich Procurement Portal.
ARTICLE 18 – BIDS TO REMAIN SUBJECT TO ACCEPTANCE
18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
ARTICLE 19 – EVALUATION OF BIDS AND AWARD OF CONTRACT
19.01 Owner reserves the right to reject any or all Bids or any part of any Bid, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner further reserves the right to reject the Bid of any Bidder whom it finds, after reasonable inquiry and evaluation, to not be responsible. Owner may also reject the Bid of any Bidder if Owner believes that it would not be in the best interest of the Project to make an award to that Bidder. Owner also reserves the right to waive all informalities not involving price, time, or changes in the Work and to negotiate contract terms with the Successful Bidder.
19.02 More than one Bid for the same Work from an individual or entity under the same or different names will not be considered. Reasonable grounds for believing that any Bidder has an interest in more than one Bid for the Work may be cause for disqualification of that Bidder and the rejection of all Bids in which that Bidder has an interest.
19.03 In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of Award.
19.04 In evaluating Bidders, Owner will consider the qualifications of Bidders and may consider the qualifications and experience of Subcontractors, Suppliers, and other individuals or entities proposed for those portions of the Work for which the identity of Subcontractors, Suppliers, and other individuals or entities must be submitted as provided in the Supplementary Conditions.
19.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers, individuals, or entities proposed for those portions of the Work in accordance with the Contract Documents.
19.06 If Contract is to be awarded, Owner will award the Contract to the responsible Bidder who’s Bid, conforming with all the material terms and conditions of the Instructions to Bidders, is lowest, price and other factors considered. The lowest price will be determined based on the “Total Base Bid Price” plus or minus any “Alternate” amounts as selected by the Owner. If detailed in the bid form, factors such as discounts, transportation costs, and life cycle costs may be used to determine which bidder, if any, is to be offered the award.
19.07 The City reserves the right to waive technical defects, irregularities and omissions if, in its judgment, the best interest of the City will be served.
19.08 Not Applicable
19.09 The Contract will be awarded to the low, responsive and responsible qualified Bidder.
ARTICLE 20 – CONTRACT SECURITY AND INSURANCE
20.01 Article 5 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it shall be accompanied by such bonds.
ARTICLE 21 – SIGNING OF AGREEMENT
21.01 When Owner issues a Notice of Award to the Successful Bidder, it shall be accompanied by the required number of unsigned counterparts of the Agreement along with the other Contract Documents which are identified in the Agreement as attached thereto. Within 15 days thereafter, Successful Bidder shall sign and deliver the required number of counterparts of the Agreement and attached documents to Owner. Within ten days thereafter, Owner shall deliver one fully signed counterpart to Successful Bidder with a complete set of the Drawings with appropriate identification.
ARTICLE 22 – SALES AND USE TAXES
22.01 Owner is exempt from Connecticut state sales and use taxes on materials and equipment to be incorporated in the Work. (Exemption Number will be provided after execution of the agreement).
Said taxes shall not be included in the Bid. Refer to Paragraph 6.10 of the Supplementary Conditions for additional information.
ARTICLE 23 – RETAINAGE
23.01 Owner shall make progress payments on account of the Contract Price on the basis of Contractor’s Applications for Payment on or about the Last day of each month during performance of the Work as provided below. All such payments will be measured by the schedule of values established as provided in Paragraph 2.07.A of the General Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no schedule of values, as provided in the General Requirements.
1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Engineer may determine or Owner may withhold, including but not limited to liquidated damages, in accordance with Paragraph 14.02 of the General Conditions.
a. 95 percent of Work completed (with the balance being retainage); and
b. 0 percent of cost of materials and equipment not incorporated in the Work (with the balance being retainage).
23.02 Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to Contractor to 95 percent of the Work completed, less such amounts as Engineer shall determine in accordance with Paragraph 14.02.B.5 of the General Conditions and less 200 percent of Engineer’s estimate of the value of Work to be completed or corrected as shown on the tentative list of items to be completed or corrected attached to the certificate of Substantial Completion.
ARTICLE 24 – EMPLOYMENT OF LABOR
24.01 The wages paid to mechanics, laborers or workmen employed upon the work herein contracted to be done shall be at a rate equal to the rate of wages prevailing for the same work in the same trade or occupation in the Norwich area as determined by the labor Commissioner of the State of Connecticut. See Section 31.53 of the General Statutes of the State of Connecticut, Revision of 195S, as amended.
24.02 Public Act 79-325 passes by the 1979 Legislature covers exemptions from Section 31.53 of the General Statutes. Under the new exemptions, effective October 1985, the regulations that the prevailing wage must be paid for work performed by contractors and subcontractors in connection with work on public facilities will not apply:
To public work alterations, repair, refinishing projects with total cost of less than $100,000.
To public works new construction with a total cost of less than $1,000,000.
All Bidders are informed that the project is considered REPAIR/ALTERATION construction.
24.03 All Bidders are advised to inform themselves and to comply with the requirements of Federal, State and local laws governing the employment of labor.
24.04 The Contractor shall provide certified payroll sheets to the Owner which includes all employees involved with the project for each payroll period during the course of the project.
ARTICLE 25 – PROVISIONAL ITEMS
25.01 Provisional items are delineated in the bid form. Quantities for provisional items may or may not be used in whole or in part at the discretion of the Owner. This shall in no way affect the established contract unit prices. All bid unit prices for provisional items shall be added to establish the total bid amount.
ARTICLE 26 – SAFETY STANDARDS
26.01 Bidder agrees to comply with all of the latest Federal and State Safety Standards and Regulations and certifies that all work required in this bid will conform to and comply with said standards and regulations. Bidder further agrees to indemnify and hold harmless the Town for all damages assessed against the Town as a result of Bidder's failure to comply with said standards and/or regulations.
26.02 Safety and Health Standards: Successful bidders must demonstrate compliance with all applicable OSHA standards including without limitations the following standards:
29 CFR 1926.650 “Excavations-Scope, application, and definitions” 29 CFR 1926.651 “Excavations-Specific Excavation Requirements” 29 CFR 1926.652 “Excavations-Requirements for Protective Systems” 29 CFR 1926.Subpart P Appendix F – “Selection of Protective Systems” 29 CFR 1910.1200 “Hazard Communication” 29 CFR 1910.146 “Permit Required Confined Spaces” DOT “Pipeline Safety Regulations Part 192”
26.03 The successful bidder shall provide written documentation of each employee’s “Operator Qualifications” for the appropriate required tasks.
26.04 The successful bidder shall provide written documentation of the companies Drug & Alcohol policy in accordance with DOT 49 CFR part 199 and DOT 49 CFR part 40
26.05 The successful bidder shall provide written “competent person“ training documentation.
26.06 The contractor is responsible for ensuring OSHA compliance, and his responsibility includes supervising and monitoring work site conditions for OSHA compliance. If the contractor uses subcontractors the contractor is responsible for ensuring that the subcontractors fulfill their obligations with respect to employee safety, particularly including those which affect the entire site.
26.07 The Owner shall consider OSHA violations(s) over the past five years in determining the ability of the Contractor to comply with OSHA requirements and in determining whether contractor is a responsible bidder. If there has been an OSHA violation within the past five (5) years (measured from the date of the bid), the contractor shall provide copies of the citation(s), all documents regarding final determination of such citations including settlement any explanation(s) of such violation(s).
26.08 The Contractor must also comply with the NORWICH PUBLIC UTILITIES SAFETY GUIDELINES included with these specifications. The contractor must submit a signed “Contractors Safety Requirements Acknowledgement Form” to Norwich Public Utilities prior to the start of construction.
III. PROPOSAL FORMS
REQUIRED DOCUMENTS – BIDDER’S CHECKLIST
Bids and all supporting documents shall be submitted through the City of Norwich Procurement Portal
1. Proposal Form:
Acknowledgement of Addendums
OSHA Policy & Procedures Included
Acknowledgement of NPU Safety Guidelines
2. Bid Form – Unit Pricing
3. Bid Security (Bid Bond or Certified Check)
4. Statement of Bidder’s Qualifications
5. Proposed Subcontractors
6. Proposed Suppliers
7. Non-Collusion Affidavit
8. Non-Discrimination in Employment
9. Certificate as to Corporate Principal
PROPOSAL
NORWICH PUBLIC UTILITIES
ROUTE 82 WATER MAIN LINING
NORWICH, CONNECTICUT
Date:
City of Norwich Department of Public Utilities City Hall Norwich, Connecticut 06360
The undersigned doing business in County of State of , has examined the site where the proposed construction is to take place and has carefully read the Information to Bidders, General Conditions, Special Conditions, Technical Specifications, Addenda, and examined the drawings therein referred to and he proposes and agrees that he will contract with the City of Norwich, CT in the form of Contract deposited in the Office of the Purchasing Agent, City Hall, Norwich, Connecticut to provide all necessary machinery, tools, apparatus, equipment, and other means of construction and do all the work and furnish all the materials specified in the contract, called for in the specifications or shown on the drawings in the manner and time prescribed and according to the requirements of the engineer, as herein set forth and that he will take in full payment, therefore, the following sums to wit:
This Bid includes Addenda numbered (to be filled in by Bidder if Addenda are issued).
1. This bid includes Occupational Safety and Health Company Policy and Procedure per Article 26 of "Instructions to Bidders". (check on line).
The above item must accompany bid proposal or bid proposal will be deemed nonresponsive.
2. The Contractors has read and familiarized themselves with the Norwich Public Utilities Safety Guidelines included in these Specifications. (check on line).
A signed copy of the Contractors Safety Requirements Acknowledgement Form will be required prior to construction.
EJCDC C-410 Bid Form for Construction Contracts
Page i
BID FORM
NORWICH PUBLIC UTILITIES
ROUTE 82 WATER MAIN LINING
Page ii
TABLE OF CONTENTS
Page
Article 1 – Bid Recipient
Article 2 – Bidder’s Acknowledgements
Article 3 – Bidder’s Representations
Article 4 – Bidder’s Certification
Article 5 – Basis of Bid
Article 6 – Time of Completion
Article 7 – Attachments to This Bid
Article 8 – Defined Terms
Article 9 – Bid Submittal
ARTICLE 1 – BID RECIPIENT
1.01 This Bid is submitted to:
City of Norwich Procurement Portal
1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.
ARTICLE 2 – BIDDER’S ACKNOWLEDGEMENTS
2.01 Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for 90 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.
ARTICLE 3 – BIDDER’S REPRESENTATIONS
3.01 In submitting this Bid, Bidder represents that:
A. Bidder has examined and carefully studied the Bidding Documents, other related data identified in the Bidding Documents, and the following Addenda, receipt of which is hereby acknowledged:
B. Bidder has visited the Site and become familiar with and is satisfied as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work.
C. Bidder is familiar with and is satisfied as to all Laws and Regulations that may affect cost, progress, and performance of the Work.
D. Bidder has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities) that have been identified in SC-4.02 as containing reliable "technical data," and (2) reports
Addendum No. Addendum Date and drawings of Hazardous Environmental Conditions, if any, at the Site that have been identified in SC-4.06 as containing reliable "technical data."
E. Bidder has considered the information known to Bidder; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying the specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety precautions and programs.
F. Based on the information and observations referred to in Paragraph 3.01.E above, Bidder does not consider that further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents.
G. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.
H. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and the written resolution thereof by Engineer is acceptable to Bidder.
I. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Bid is submitted.
ARTICLE 4 – BIDDER’S CERTIFICATION
4.01 Bidder certifies that:
A. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation;
B. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid;
C. Bidder has not solicited or induced any individual or entity to refrain from bidding; and
D. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 4.01.D:
1. “corrupt practice” means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process;
2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;
3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels; and
4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.
E. Bidder and all subcontractors will comply with Executive Order No. Three, Executive Order No. Sixteen and Executive Order No. Seventeen, Office of Federal Contract Compliance Programs (OFCC) Executive Order No. 11246, Executive Order 12549 and CGS 31-53a, and federal regulation 2 CFR 200.216 as amended, copies of which are attached at the end of this document.
ARTICLE 5 – BASIS OF BID
5.01 Bidder will complete the Work in…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .