About this file

This document is a bid schedule and engineer's cost estimate for the Garden Acres Bridge Replacement project for the City of Longmont, Colorado. The project involves replacing a pedestrian bridge in Garden Acres Park that spans the Oligarchy Ditch, utilizing a salvaged bridge from the Resilient St. Vrain Project. The scope includes bridge demolition, installation of a new bridge with improved decking and rails, utility work, landscape restoration, and maintaining access to an adjacent ditch diversion and pump station. The project requires work on trails, landscaping, and irrigation in the bridge's immediate vicinity, with careful consideration to preserve the ditch channel and detention area capacity.

The engineer's estimates provide three cost scenarios: a base bid of $681,440 for standard bridge replacement, an open trench utility installation option at $718,880, and a bored utility installation option at $801,056. The bid schedule includes base bid items such as mobilization, field engineering, traffic control, bridge removal and installation, utility work, and various restoration activities. Additional bid options focus on sustainability, including 75% project waste recycling and reducing embodied carbon in concrete and steel, with specific references to Colorado Office of the State Architect recommendations for environmental product declarations. The project emphasizes technical precision, environmental considerations, and comprehensive infrastructure replacement.

View the file

Other files for this state and local contract opportunity

Other files attached to Garden Acres Bridge Replacement, newest first.
File Type Posted
218058-008 Garden Acres Bridge Replacement - Bid Schedule.xlsx.pdf PDF
Project Plans - 218058-008 Garden Acres Bridge Replacement_Bid Documents 03.21.25.pdf PDF
IFB-425047 Bid Submittal.pdf PDF
IFB-425047 Project Manual.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PEC-estimates 351 Linden Street, Fort Collins, CO 80524 Phone (970) 232-9558 Garden Acres Bridge Replacement Longmont, CO.

PEC PROJECT NO. 218058-008

Prepared by: NAR Estimate Date: 2/21/2025

GARDEN ACRES BRIDGE REPLACEMENT BID DOCUMENT COST ESTIMATE

ENGINEER'S OPINION OF PROBABLE COST FOR MUNICIPAL PARK BRIDGE REPLACEMENT ALTERNATE UTILITY INSTALL _ OPEN TRENCH UTILITY INSTALLATION Bridge Replacement, Auxilarry Landscape, Flat, & Utility Work

ITEMDESCRIPTIONQUANTITYUNITUNIT PRICECOST
Miscellaneous Construction Items
Mobilization/Demob1LS$ 40,000.00$ 40,000.00
Survey1LS$ 6,000.00$ 6,000.00
Traffic Control (cones, signage)1LS$ 12,000.00$ 12,000.00
Erosion Control & Contractor Staging Area1LS$ 18,500.00$ 22,500.00
Material Testing1LS$ 6,500.00$ 6,500.00
Potholes5EA$ 1,000.00$ 5,000.00
Subtotal$92,000.00
Miscellaneous Demolition Items
Demolish concrete & landscaping1LS$ 9,500.00$ 9,500.00
Remove & stockpile riprap1LS$ 6,500.00$ 6,500.00
Haul/Dispose Demo'ed Materials1LS$ 12,000.00$ 12,000.00
Subtotal$ 28,000.00
Bridge Replacement
Demo & Remove Existing Bridge, Abutments, & Utilities1LS$ 44,500.00$ 44,500.00
Haul Replacement Bridge1LS$ 14,500.00$ 14,500.00
Replacement Bridge Improvements (Decking, Rails, Etc.)1LS$ 46,800.00$ 46,800.00
Abutment Installation1LS$ 94,500.00$ 94,500.00
Install Improved Replacement Bridge1LS$ 115,000.00$ 115,000.00
Subtotal$ 315,300.00
Auxillary Landscape, Flat, & Utility Work
6" C200 PVC180LF$ 95.00$ 17,100.00
6" Ductile iron pipe0LF$ 105.00$ -
6" Ductile iron Megalug fittings10LS$ 450.00$ 4,500.00
Trenching, Imported Backfill, & Dewatering180LF$ 150.00$ 27,000.00
Electrical conduit110LF$ 65.00$ 7,150.00
Restoration, concrete1,700SF$ 23.00$ 39,100.00
Restoration, riprap protection900SF$ 13.50$ 12,150.00
Restoration, turf grass1,350SF$ 4.50$ 6,075.00
Restoration, native grass3,100SF$ 3.50$ 10,850.00
Tree Planting & Tree Protection1LS$ 2,400.00$ 2,400.00
Subtotal$ 126,325.00
Sub-Total Construction Costs 18% Contractor OH & Profit 10% Contingency
TOTAL PROJECT COSTS$ 561,625.00

$ 101,092.50 $ 56,162.50 $ 718,880.00

351 Linden Street, Fort Collins, CO 80524 Phone (970) 232-9558 Garden Acres Bridge Replacement Longmont, CO.

PEC PROJECT NO. 218058-008

Prepared by: NAR Estimate Date: 2/21/2025

GARDEN ACRES BRIDGE REPLACEMENT BID DOCUMENT COST ESTIMATE

ENGINEER'S OPINION OF PROBABLE COST FOR MUNICIPAL PARK BRIDGE REPLACEMENT ALTERNATE UTILITY INSTALL _ BORED UTILITY INSTALLATION Bridge Replacement, Auxilarry Landscape, Flat, & Utility Work

ITEMDESCRIPTIONQUANTITYUNITUNIT PRICECOST
Miscellaneous Construction Items
Mobilization/Demob1LS$ 40,000.00$ 40,000.00
Survey1LS$ 6,000.00$ 6,000.00
Traffic Control (cones, signage)1LS$ 12,000.00$ 12,000.00
Erosion Control & Contractor Staging Area1LS$ 18,500.00$ 22,500.00
Material Testing1LS$ 6,500.00$ 6,500.00
Potholes5EA$ 1,000.00$ 5,000.00
Subtotal$ 92,000.00
Miscellaneous Demolition Items
Demolish concrete & landscaping1LS$ 9,500.00$ 9,500.00
Remove & stockpile riprap1LS$ 6,500.00$ 6,500.00
Haul/Dispose Demo'ed Materials1LS$ 12,000.00$ 12,000.00
Subtotal$ 28,000.00
Bridge Replacement
Demo & Remove Existing Bridge, Abutments, & Utilities1LS$ 44,500.00$ 44,500.00
Haul Replacement Bridge1LS$ 14,500.00$ 14,500.00
Replacement Bridge Improvements (Decking, Rails, Etc.)1LS$ 46,800.00$ 46,800.00
Abutment Installation1LS$ 94,500.00$ 94,500.00
Install Improved Replacement Bridge1LS$115,000.00$ 115,000.00
Subtotal$ 315,300.00
Auxillary Landscape, Flat, & Utility Work
6" C200 PVC60LF$ 95.00$ 5,700.00
6" Ductile iron pipe120LF$ 105.00$ 12,600.00
6" Ductile iron Megalug fittings10LS$ 450.00$ 4,500.00
Utility Boring Installation120LF$ 750.00$ 90,000.00
Electrical conduit110LF$ 65.00$ 7,150.00
Restoration, concrete1,700SF$ 23.00$ 39,100.00
Restoration, riprap protection900SF$ 13.50$ 12,150.00
Restoration, turf grass1,350SF$ 4.50$ 6,075.00
Restoration, native grass3,100SF$ 3.50$ 10,850.00
Tree Planting & Tree Protection1LS$ 2,400.00$ 2,400.00
Subtotal$ 190,525.00
Sub-Total Construction Costs 18% Contractor OH & Profit 10% Contingency
TOTAL PROJECT COSTS$ 625,825.00

$ 112,648.50 $ 62,582.50 $ 801,056.00

351 Linden Street, Fort Collins, CO 80524 Phone (970) 232-9558 Garden Acres Bridge Replacement Longmont, CO.

PEC PROJECT NO. 218058-008

Prepared by: NAR Estimate Date: 1/31/2025

GARDEN ACRES BRIDGE REPLACEMENT BID DOCUMENT COST ESTIMATE

ENGINEER'S OPINION OF PROBABLE COST FOR MUNICIPAL PARK BRIDGE REPLACEMENT

Bridge Replacement, Auxilarry Landscape, Flat, & Utility Work

ITEMDESCRIPTIONQUANTITYUNITUNIT PRICECOST
Miscellaneous Construction Items
Mobilization/Demob1LS$ 40,000.00$ 40,000.00
Survey1LS$ 6,000.00$ 6,000.00
Traffic Control (cones, signage)1LS$ 12,000.00$ 12,000.00
Erosion Control & Contractor Staging Area1LS$ 18,500.00$ 22,500.00
Material Testing1LS$ 6,500.00$ 6,500.00
Potholes5EA$ 1,000.00$ 5,000.00
Subtotal$ 92,000.00
Miscellaneous Demolition Items
Demolish concrete & landscaping1LS$ 9,500.00$ 9,500.00
Remove & stockpile riprap1LS$ 6,500.00$ 6,500.00
Haul/Dispose Demo'ed Materials1LS$ 12,000.00$ 12,000.00
Subtotal$ 28,000.00
Bridge Replacement
Demo & Remove Existing Bridge, Abutments, & Utilities1LS$ 44,500.00$ 44,500.00
Haul Replacement Bridge1LS$ 14,500.00$ 14,500.00
Replacement Bridge Improvements (Decking, Rails, Etc.)1LS$ 46,800.00$ 46,800.00
Abutment Installation1LS$ 94,500.00$ 94,500.00
Install Improved Replacement Bridge1LS$ 115,000.00$ 115,000.00
Subtotal$ 315,300.00
Auxillary Landscape, Flat, & Utility Work
6" C200 PVC45LF$ 95.00$ 4,275.00
6" Ductile iron pipe90LF$ 105.00$ 9,450.00
6" Ductile iron Megalug fittings10LS$ 450.00$ 4,500.00
6" Galvanized steel pipe hangers9LS$ 125.00$ 1,125.00
Electrical conduit110LF$ 65.00$ 7,150.00
Restoration, concrete1,700SF$ 23.00$ 39,100.00
Restoration, riprap protection900SF$ 13.50$ 12,150.00
Restoration, turf grass1,350SF$ 4.50$ 6,075.00
Restoration, native grass3,100SF$ 3.50$ 10,850.00
Tree Planting & Tree Protection1LS$ 2,400.00$ 2,400.00
Subtotal$ 97,075.00
Sub-Total Construction Costs 18% Contractor OH & Profit 10% Contingency
TOTAL PROJECT COSTS$ 532,375.00

$ 95,827.50 $ 53,237.50 $ 681,440.00

Table 1 City of Longmont Garden Acres Bridge Replacement Engineers’ Assessment of Probable Quantities The Bid Form below is to include Base Bid and Addition/Deduction items, as applicable. Contractor will complete the Base Bid Work detailed in the Scope of Work in accordance with the Contract Documents for a Lump Sum Price as depicted below and will add to and/or deduct from the Base Bid in accordance with the quantities and unit prices listed below:

Bid Schedule – Garden Acres Bridge Replacement
ItemDescriptionIncluded
QuantityUnitUnit Price ($)Total ($)
0General Conditions1LS
1Mobilization/Demobilization1LS
2Field Engineering, Survey, & Construction Staking1LS
3Traffic Control1LS
4Temporary Erosion & Sediment Control1LS
5Miscellaneous Demolition1LS
6Remove Existing Bridge, Abutments, & Utilities1LS
7Remediation of Replacement Bridge1LS
8Abutment Installation1LS
9Installation of Replacement Bridge1LS
10Electrical Conduit Replacement & Reconnections1LS
116” C200 PVC45LF
126” Ductile Iron Pipe90LF
13Irrigation Appurtenances1LS
14Restoration – Concrete1700SF
15Restoration – Riprap Protection900SF
16Restoration – Turf Grasses1350SF
17Restoration – Native Grasses3100SF
18Tree Planting & Tree Protection1LS
Total Base Bid:
Bid Schedule B – Addition/Deduction Items
75% recycling of project waste1LS
Reduce Embodied Carbon of concrete and steel1LS
Meet Colorado Office of the State Architect recommendations for limits for concrete and other structural elements on the kilograms of carbon dioxide equivalent per ton. Here is the link to the recommendations: https://www.nrmca.org/association-resources/sustainability/environmental-product-declarations/
Not all manufacturers report EPDs, but here is a list of manufacturers that have published environmental product declarations (EPDs) for concrete: https://www.nrmca.org/association-resources/sustainability/environmental-product-declarations/

Addition/Deduction Total:

Base Bid + Addition/Deductions:

image1.jpeg

File details come from the government source that posted it. Updated .