21-002 Specifications 2021 BCPS District Roofing-1.pdf

PDF 600 KB Posted

Attached to
BATTLE CREEK PUBLIC SCHOOLS ROOFING PROJECT State and local contract opportunity
Solicitation number
RFP BATT 210000001147 1
Issued by
Calhoun County, Michigan

About this file

Battle Creek Public Schools District Roofing Project - 2021 Specifications

This specifications document outlines roofing renovation work for Battle Creek Public Schools, a Michigan K-12 educational institution. The project encompasses multiple roofing system options including 2-ply fluid applied liquid membrane systems, shingle replacement on specific buildings, and comprehensive roof restoration across district facilities. The work includes removal of existing roofing systems down to deck level, installation of polyisocyanurate insulation, recovery board installation, base sheet application, and fluid-applied membrane systems with fabric reinforcement. Specific work areas include the Miller Stone building and Administration building, with shingle replacement specified for certain sections. The project requires a pre-bid conference attendance as a mandatory requirement for bid qualification, with all technical questions directed to the Awarded Manufacturer Company representative and Ryan Long of Elite Companies (Ryan.long@elite-companies.com). Work must commence within thirty days of contract award and be completed within sixty days of the start date, with a penalty of $300 per day assessed for delays beyond the agreed completion date, unless delayed by inclement weather, material unavailability, or strike actions.

Pricing is submitted on a lump-sum basis with the contractor assuming responsibility for all cost estimating and measurement accuracy. A performance and payment bond is required from an acceptable bonding company, with costs paid directly by the contractor. Payment terms include progress payments limited to ninety percent of estimated labor and material values, with a ten percent retainer held until warranty delivery. Final payment is withheld until all specifications are met and the Owner receives written verification of completion. The contractor must maintain comprehensive general liability insurance of not less than $1,000,000 per person and per occurrence, along with workmen's compensation coverage. All materials must be delivered with manufacturer labels intact, and the Awarded Manufacturer representative must conduct inspections a minimum of three times per week throughout the project duration. The contractor provides a two-year workmanship warranty from the date of final acceptance, while the manufacturer provides a warranty period extending from thirty years for fluid-applied systems to twenty years for single-ply restorations, both contingent upon strict adherence to specifications and approved contractor installation.

View the file

Other files for this state and local contract opportunity

Other files attached to BATTLE CREEK PUBLIC SCHOOLS ROOFING PROJECT, newest first.
File Type Posted
Roofing 21-002 Admin-Willard Roof Report-2.pdf PDF
Roofing 21-002 Miller Stone Compiled.pdf PDF
Project Manual - 21-002 BCPS District Roofing 2021-2.pdf PDF
Roofing 21-002 Clarification 01-4.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Battle Creek Public Schools Section 00 10 00 .001 Page 1 Summary of Work

SECTION 00 10 00 .001

SUMMARY OF WORK

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Attached SUMMARY OF WORK, INTENT OF THE SPECIFICATIONS, PROTECTION, HOUSEKEEPING, forms a component part of this section.

1.2 SUMMARY OF WORK: 2-Ply Fluid Applied Liquid Membrane

A. Wet vacuum the roof clear of loose gravel and debris.

B. Make any necessary repairs, including removal of any wet insulation and roofing materials and replace with like materials.

C. Allow repairs to cure completely.

D. Fully adhere ½” dens deck primed over existing roofing system per manufacturer’s guidelines. Once dens deck is installed, apply SA Primer to dens deck.

E. Base Sheet Installation:

a. Miller Stone:

i. Once dens deck is installed, apply a layer of SA primer over dens deck. Allow to cure before installing base sheet.

ii. Once SA primer is applied, install HPR SA FR base sheet in shingle pattern starting at the lowest part of the roof.

b. Administration:

i. Once dens deck is installed, apply a layer of SA primer over dens deck. Allow to cure before installing base sheet.

ii. Once SA primer is applied, install HPR SA FR base sheet in shingle pattern starting at the lowest part of the roof.

c. Base sheet should be installed on the flashings and field prior to Fluid Applied application.

F. Where necessary, install new edge metal.

G. Carefully clean all roof surfaces prior to Fluid Applied cap sheet installation. Power wash (if necessary) all roof surfaces with greater than 2,000 psi pressure to remove debris, rust, scale, dirt, dust, chalking, peeling or flaking coatings, etc. Do not force water into the roof system or damage roof surfaces.

H. If the roof surface becomes contaminated with dirt, dust or other particles at any time during the application of the LiquiTec system, cleaning measures must be taken to restore the surface to a suitable condition.

I. LiquiTec Base Coat is to be installed at three (3) gallons per square (48 wet mils) over entire roof. 36-inch-wide Grip Polyester Soft reinforcement will be embedded immediately into coating with a minimum of 3-inch laps using shingle method. Any vertical flashings are to be coating twice with thinner coats to ensure sagging does not occur.

J. All area of the roof to receive a LiquiTec Topcoat of two (2) gallons per square (32 wet mils). Samples shall be taken periodically to ensure the proper thickness is being installed. Do not apply more coating than what is indicated.

K. All drains are to be painted red.

L. Throughout duration of project, a representative from Awarded Manufacturer will provide job site inspections (3) times per week to ensure strict accordance with the design and bidding documents.

Battle Creek Public Schools Section 00 10 00 .001 Page 2 Summary of Work

1.2A SUMMARY OF WORK: 2-Ply Fluid Applied Liquid Membrane Replacement

A. Remove existing roofing system down to decking, including but not limited to: all previous roof layers, perimeter and penetration flashings, edge metal, fasteners, counter-flashings, termination bars, etc.

Properly dispose of all materials.

B. Remove all abandoned roof penetrations and covered openings with 22-gauge flat stock sheet metal.

C. Make sure deck is clean of dirt and debris.

D. Install 2-layers of 2” polyisocyanurate board insulation with all joints staggered. Install 1/8”:12 sloped tapered polyisocyanurate insulation on top of the base layers. Add saddles / crickets where necessary to ensure water does not pond. Make sure insulation installation meets the wind uplift calculation requirements as specified. Fill all voids, cracks or separations between or surrounding insulation boards to prevent thermal bridging.

a. Concrete Deck Install:

i. All insulation can be adhered in Olybond high rise foam insulation adhesive or generic type III asphalt.

E. If drains new to be replaced, they should be replaced with OMG Hercules Retro Drains with drain leads at each drain location per layout provided.

F. Install cants / saddles at the base of penetration flashings.

G. ¼” dens deck primed recovery board is to be installed over newly installed polyisocyanurate insulation.

a. Recovery Board Install:

i. Olybond high rise foam insulation adhesive H. SBS Modified Base Sheet:

a. HPR TorchBase:

i. Installation is to be torch applied. Heat the back of the roll to induce the melting of the asphalt on the back of the sheet. Keep bleed-out to a ¼”, assuring that the roll is always pushing adequate hot asphalt as unrolled. Use the weighted roller to get air pockets out from under the sheet and to secure all head and side laps.

I. Fully Reinforced LiquiTec:

a. LiquiTec Base CoatStressPly FR Mineral:

i. LiquiTec Base Coat is to be installed at three (3) gallons per square (48 wet mils) over entire roof. 36-inch-wide Grip Polyester Soft reinforcement will be embedded immediately into coating with a minimum of 3-inch laps using shingle method. Any vertical flashings are to be coating twice with thinner coats to ensure sagging does not occur.

b. LiquiTec Top Coat:

i. All area of the roof to receive a LiquiTec Topcoat of two (2) gallons per square (32 wet mils). Samples shall be taken periodically to ensure the proper thickness is being installed. Do not apply more coating than what is indicated.

J. Install all new perimeter and projection flashings using base ply of HPR TorchBase and Fully Reinforced LiquiTec.

K. Any flashing that is terminated prior to passing over the top edge of the perimeter wall or penetration is to receive a termination bar, structural adhesive along the top edge and a counter-flashing detail per provided detail drawings.

L. Install new coping metal or metal edge system on all perimeter sides with either a new metal coping cap or raised metal edge/fascia detail. Install, seal and secure the aluminum cleat per provided application/ installation instructions. Do not install the snap on fascia metal until roof reflective coating application is completed.

M. All drains covers are to be painted red.

Battle Creek Public Schools Section 00 10 00 .001 Page 3 Summary of Work

N. Replace all damaged wood nailers and wood fascia at a unit cost per linear foot. Install additional wood nailers and wood fascia to match the additional height of the new insulation. All wood nailers and wood fascia should be covered by the modified membrane and the specified metal detail. Use compatible contractor provided screws and/or Ring Shank nails when installing the wood. Install two fasteners (pair them up) and install pairs every 16” with staggers. When using treated wood, all fasteners will comply with ASTM A153 by using type 304 or Type 316 stainless-steel fasteners and connectors for corrosion resistance.

O. Raise all roof penetrations to a minimum 8” flashing height. The roofing contractor is responsible for connecting and disconnecting all associated equipment. Any roof curbs or duct work currently being supported by wood blocking shall be replaced with deck mounted steel curbs. All wood nailers that are visible from the inside of the facility must match the décor of the surrounding interior.

P. Power wash all construction debris and dripped asphalt off exterior walls and ground prior to leaving work site.

Q. Clean up all debris and damage done to grounds, building and roof top (if any). Plant new grass seed if necessary. Netting must be installed to hold the new grass seed and straw in place. Plywood should be laid under the dumpster and where any heavy machinery will be driven to prevent deep ruts from forming.

R. All existing ladders, walkways, walls, etc.., must be protected so that these areas are not marked up from material spills or tracking of materials by walking. Contractor is responsible for properly protecting the parking lot, sidewalks, concrete, asphalt, etc.., from damage. Contractor to cover the areas with plywood or whatever material they deem necessary for proper protection. Any damage done to these areas will be repaired by the contractor using “like” material.

S. The contractor is responsible for taking pictures of the interior and exterior of the building before work begins. This will help to determine who is responsible for any interior damage that may take place during the roofing work.

T. All insulation and roll goods must be covered with a tarp at all times. The factory plastic is not acceptable. Wet materials are considered damaged and will not be deemed unacceptable for installation. All rolls goods must be standing up or should be thrown away.

U. All contractors are responsible for roof cores, removing existing coping, metal wall panels, etc.., at time of the pre-bid review for verification of existing roof system and building structure and wall composition before proceeding with their project bid.

The scope of work supersedes any discrepancies in the additional specification sections and/or data sheets.

Any questions with, necessary changes to the scope of work, details, or products being used must be put into writing and e-mailed to Ryan.long@elite-companies.com.

The Contractor is to read through the entire specification package prior to bidding. The scope of work is simply a guide on how the system is to be assembled, additional details on the system are included in the rest of the specification package and must be followed.

1.2B SUMMARY OF WORK: Fluid Applied Liquid Membrane

A. Make any necessary repairs, including removal of any wet insulation and roofing materials and replace with like materials.

B. Allow repairs to cure completely.

C. Carefully power wash all roof surfaces with greater than 2,000 psi pressure to remove debris, rust, scale, dirt, dust, chalking, peeling or flaking coatings, etc. Do not force water into the roof system or damage roof surfaces. Simpson machine is preferred.

D. Wearing personal protective clothing and equipment, treat areas of algae, mildew or fungus with a solution of three quarts of warm water and TSP or Simple Green Solution.

E. Rinse at least twice to be sure all cleaning agents or contaminants are completely removed to prevent adhesion issues.

Battle Creek Public Schools Section 00 10 00 .001 Page 4 Summary of Work

F. If the roof surface becomes contaminated with dirt, dust or other particles at any time during the application of the LiquiTec system, cleaning measures must be taken to restore the surface to a suitable condition.

G. LiquiTec Base Coat is to be installed at three (3) gallons per square (48 wet mils) over entire roof. 36-inch-wide Grip Polyester Soft reinforcement will be embedded immediately into coating with a minimum of 3-inch laps using shingle method. Any vertical flashings are to be coating twice with thinner coats to ensure sagging does not occur.

H. All area of the roof to receive a LiquiTec Topcoat of two (2) gallons per square (32 wet mils). Samples shall be taken periodically to ensure the proper thickness is being installed. Do not apply more coating than what is indicated.

I. All drains are to be painted red.

J. Throughout duration of project, a representative from Awarded Manufacturer will provide job site inspections (3) times per week to ensure strict accordance with the design and bidding documents.

1.2C SUMMARY OF WORK: Shingle Replacement – Miller Stone

A. Remove any loose or damaged shingles from existing structure ensuring substrate is as smooth as possible.

B. Install ½” plywood to ensure new roofing shingles have a smooth and even substrate.

C. Install new self-adhering high temperature synthetic ice and water shield over new plywood substrate.

D. Install new F-Wave High Performance Shingle. Shingle style is to be Estate Series and color will be chosen at a later date by client. F-Wave shingle is to be installed using stainless steel rink shank nails.

E. Install new W-style aluminum valleys and drip edge perimeter metal.

1.2D SUMMARY OF WORK: Shingle Replacement – Administration

A. Remove ALL shingles from existing structure ensuring substrate is as smooth as possible.

B. Install ½” plywood to ensure new roofing shingles have a smooth and even substrate.

C. Install new self-adhering high temperature synthetic ice and water shield over new plywood substrate.

D. Install new F-Wave High Performance Shingle. Shingle style is to be Estate Series and color will be chosen at a later date by client. F-Wave shingle is to be installed using stainless steel rink shank nails.

E. Install new W-style aluminum valleys and drip edge perimeter metal.

F. Install new vented Ridge Vent to match the existing.

1.3 INTENT OF THE SPECIFICATIONS

A. The intent of these specifications is to describe the material and methods of construction required for the performance of the work. In general, it is intended that the drawings shall delineate the detailed extent of the work. When there is a discrepancy between drawings, referenced specifications, and standards and this specification, this specification shall govern.

1.4 PROTECTION

A. The contractor shall use every available precaution to provide for the safety of the property owner, visitors to the site, and all connected with the work under the Contract.

B. All existing facilities both above and below ground shall be protected and maintained free of damage. Existing facilities shall remain operating during the period of construction unless otherwise permitted. All access roadways must remain open to traffic unless otherwise permitted.

C. Barricades shall be erected to fence off all construction areas from operations personnel.

Battle Creek Public Schools Section 00 10 00 .001 Page 5 Summary of Work

D. Safety Requirements:

1. All application, material handling, and associated equipment shall conform to and be operated in conformance with OSHA safety requirements.

2. Comply with federal, state, and local and owner fire and safety requirements.

3. Advise owner whenever work is expected to be hazardous to owner employees and/or operations.

4. Maintain a crewman as a floor guard whenever roof decking is being repaired or replaced and whenever any roofing is being removed.

5. Maintain proper fire extinguisher within easy access whenever power tools, roofing kettles, and torches are being used. A MINIMUM OF A 2 HOUR FIRE WATER

SHALL BE STRICTLY ADHERED TO WHENEVER PROPANE TORCHES ARE IN

USE.

6. ALL SAFETY REQUIREMENTS OF THE BUILDING OWNER MUST BE

FOLLOWED. NO EXCEPTIONS WILL BE PERMITTED. SAFETY ORIENTATION

MEETING REQUIRED PRIOR TO PERFORMING ANY WORK.

1.5 HOUSEKEEPING

A. Keep materials neat and orderly.

B. Remove scrap, waste and debris from the project area.

C. Maintenance of clean conditions while work is in progress and cleanup when work is completed shall be in strict accordance with the “General Conditions” of this contract.

D. Fire protection during construction.

E. Follow all requirements established by the building owner.

END OF SECTION

007200-1

SECTION 00 72 00

GENERAL CONDITIONS

PART 1 GENERAL

1.1 DEFINITIONS

A. The contract document consists of the AGREEMENT, the GENERAL CONDITIONS of the contract, the DRAWINGS and the SPECIFICATIONS, including all revisions hereto.

B. The Owner, the Contractor and the Owner’s Representative shall be indicated as such throughout these documents. The term Contractor as used herein shall designate the successful bidder to whom the roof contract is awarded.

C. The term Owner shall be understood to be Battle Creek Public Schools.

D. The term Owner’s Representative shall be understood to mean the representative of the primary material manufacturer.

1.2 OWNER’S REPRESENTATIVE STATUS

A. The Owner’s Representative shall have general Rights of Inspection of the work and is the agent of the Owner in all matters pertaining to the work as provided in the Contract Documents. The Owner’s Representative has the authority to stop work whenever such stoppage may be necessary to ensure the proper execution of the contract and shall have authority to reject any and all materials, whether worked or unworked, if such materials are not in accordance with the plans and specifications.

1.3 CONDTION OF SITE

A. The bidders shall visit the site before submitting their bids and determine the field conditions affecting their work. In considering the bids, the Owner will assume that the bidders are aware of all items, pertinent to their work and have made allowance for same in their bids.

1.4 VERIFICATION OF DIMENSIONS AND ELEVATIONS

A. Dimensions and elevations indicated on the drawings in reference to existing structures or utilities are the best available data but are not guaranteed by the Owner’s Representative and the Owner’s Representative will not be responsible for their accuracy. Before bidding on any paperwork dependent upon the data involved, the Contractor shall field check and verify all dimensions, grades, lines, levels or other conditions of limitations at the site to avoid construction errors. If any work is performed by the Contractor or any of his/her subcontractors prior to adequate verification or applicable data, any resultant extra cost for adjustment of work as required to conform to existing limitations, shall be assumed by the Contractor without reimbursement or compensation by the Owner.

1.5 PROTECTION OF OWNER’S OPERATIONS

A. The Contractor shall erect such barriers, tarpaulins, doors, etc., as may be necessary to protect the Owner’s operations while work is in progress. Any such

007200-2 openings that are essential to carrying on the work shall be securely closed by the Contractor when not in use to protect the Owner’s operations.

1.6 PROTECTION OF WORK AND PROPERTY

A. The Contractor shall maintain adequate protection of all his/her work from damage and shall protect the Owner’s and adjacent property from injury or loss arising from this contract. He/she shall provide and maintain at all times any danger signs, guards and/or obstructions necessary to protect the public and his/her workmen from any dangers inherent with or created by the work in progress. He/she shall hold the Owner harmless from any loss arising due to injury or accident to the public or his/her workmen, or from theft of materials stored at the job site. All materials will be stored in locations other than on roof surfaces except as necessary and shall then be placed on plywood or other type of material to protect the roof surface at all times.

B. Before starting any work, the Contractor shall protect all grounds, copings, paving and exterior of all buildings where work will be performed.

C. In those areas where materials and/or hot asphalt will be raised to the roof area, a protective covering shall be placed from the base of the wall extending up and over the top edge of the roof. This coverage shall be wide enough to assure that the exterior walls do not become stained or soiled during roofing operations.

D. Any areas of the building or grounds which have become stained or damaged in any way shall be repaired or replaced by the Contractor prior to the final inspections.

The method of repair used must be acceptable to both the Owner and the Owner’s Representative.

1.7 MATERIAL STORAGE AND CLEAN-UP

A. The Contractor shall keep the premises free from rubbish at all times and shall arrange his/her material storage so as not to interfere with the Owner’s operations.

At the completion of the job, all the unused material and rubbish shall be removed from the site. The ground shall be raked clean and the building shall be broom cleaned. If the Contractor refuses at any time to remove his/her debris from the premises, or to keep the working area clean, such cleaning will be completed by the Owner and deducted from the balance due the Contractor.

B. The Contractor shall also remove drippage of bitumen or adhesive from all walls, windows, floors, ladders and finished surfaces. Failure to do so will result in the work being done by others and the cost shall be deducted from the balance due the Contractor.

C. Materials must be delivered with manufacturer’s label intact and legible. Labels must be affixed to the outside of the package stating the type of product, name and address of the manufacturer. All materials shall be stored and protected against weather, vandalism, and theft. Any materials found to be damaged or missing shall be replaced by the Contractor at no cost to the Owner.

1.8 INSPECTION OF WORK

A. Where the drawings or specifications require the inspection and approval of any work in progress by the Owner’s Representative, the Contractor shall give that

007200-3

Representative ample notice to allow for scheduling the inspection, which shall be made promptly to avoid delay of work. If work has progressed without the required inspections or approval by the Representative, it shall be uncovered for inspection at the Contractor’s expense.

B. Uncovering of work not originally inspected, or uncovering questioned work may be ordered by the Owner’s Representative and it shall be done by the Contractor. If examination proves such work to be incorrectly done or not done in accordance with the plans and specifications, the Contractor shall bear all cost of the reexamination.

If the work is proven correctly installed, all such expense shall be born by the Owner.

1.9 INSPECTION OF WORK IN PROGRESS AND UPON COMPLETION

A. If directed by the Owner’s Representative, the Contractor shall cut not more than four (4) cores, of approximately 200 square inches each, from every newly constructed roof area, in order to establish the amount of materials used per square foot, and shall restore all such areas to sound and watertight conditions as prior to the core testing.

B. In the event that such core cuts disclose any deficiency in materials, or soundness of construction, the Contractor shall, at his/her own expense, apply additional materials or otherwise correct the deficiencies to the satisfaction of the Owner’s Representative.

C. Noncompliance with the terms of this specification and ensuing contract can result in either the cancellation of the contract, or complete replacement of the defective areas at the Contractor’s expense. In the event of cancellation, the Owner will not be obligated to compensate the Contractor for any work undertaken in a defective manner

D. Damages caused by water infiltration resulting from the failure of the Contractor to secure each day’s work in a weather tight manner, will be corrected at the Contractor’s expense. Included as damages will be all labor costs incurred by the Owner as a result of such water infiltration.

E. The Owner will require the Owner’s Representative to examine the work in progress, as well as upon completion, in order to ascertain the extent to which the materials and procedures conform to the requirements of these specifications and to the published instructions of the Manufacturer.

F. The authorized Owner’s Representative shall be responsible for:

1. Keeping the Owner informed on a periodic basis as to the progress and quality of the work;

2. Calling to the attention of the Contractor those matters he/she considers to be in violation of the contract requirements;

3. Reporting to the Owner any failure or refusal of the Contractor to correct unacceptable practices;

4. Conducting preliminary and subsequent job-site meetings with the

Contractor’s official job representative;

5. Supervising the taking of test cuts, and the restoration of such areas;

6. Rendering any other inspection services which the Owner may designate; and

7. Certifying, after completion of the work, the extent to which the Contractor has complied with these specifications as well as to the published instructions of the Manufacturing Company.

007200-4

G. The presence and activities of the Owner’s Representative shall in no way relieve the Contractor of his/her contractual responsibilities.

1.10 MISCELLANEOUS UTILITIES

A. Electrical power will be furnished by the Owner for small tools only. All connections to the electrical system will be furnished by the Contractor.

B. Water for concrete, mortar, washing and drinking purposes will be furnished by the Owner. Any connections to the water system shall be completed by the Contractor.

C. At the completion of the work, or when the above connections are no longer required, the Contractor shall remove all connections and leave the facilities in a condition at least as satisfactory as prior to the commencement of his/her work.

D. Toilet facilities will be provided by the Contractor. The Contractor will be responsible for supplying a portable toilet on the job-site. The Contractor’s personnel are not permitted to enter the building without proper authorization from the Owner or Owner’s Representative.

1.11 CHANGES OR EXTRA WORK

A. The Owner may, without invalidating the original contract, order such changes or additions as may from time to time be deemed desirable. In so doing, the contract price shall be adjusted, as stated below, with all work being done under the conditions of the original contract except for such adjustments in extension of time as may be acceptable to the Owner. The value of such extra work shall be determined in one of the following ways:

1. By firm adjustment;

2. By cost plus with a guaranteed maximum;

3. By cost with a fixed fee; or

4. By unit cost.

B. If agreement is reached that the extra cost shall be handled as per methods 2, 3, or 4, the Contractor shall keep and compile a correct amount of the cost together with such vouchers, etc., as may be necessary to substantiate same for presentation to the Owner. The Owner’s Representative shall have authority to make minor job changes or additions as may be necessary to expedite the job providing such changes do not involve additional material cost. No major change or addition shall be made except upon receipt by the Contractor of a signed order from the Owner authorizing such a change. No claims for an extra to the contract price shall be valid unless so authorized.

C. All work covered by unit prices submitted by the Contractor in his/her proposal must be covered by a written work order. The Owner’s Representative will prepare the work order in triplicate covering the quantity of work and the total cost of the work.

The work order which will be written at the end of each day, will be signed by the Owner’s Representative and the Contractor’s foreman and/or superintendent.

1.12 CORRECTION OF WORK PRIOR TO FINAL PAYMENT

A. The Contractor shall promptly remove any work that does not meet the requirements of the plans and specifications or is incorrectly installed or otherwise disapproved by the Owner of the Owner’s Representative as failing to meet the intent of the plans and specifications. The Contractor shall promptly replace any such work without

007200-5 expense to the Owner and shall bear the cost of making good all work of other contractors, or the Owner, destroyed or damaged by such removal or replacement.

1.13 CORRECTION OF WORK AFTER FINAL PAYMENT

A. The Contractor shall guarantee all materials and workmanship for two (2) years from date of final payment of the contract by the Owner. Any defects which may arise during this period shall be promptly repaired by the Contractor including any damage done to the Owner’s property due to such defects.

1.14 DEDUCTION FOR UNCORRECTED WORK

A. If the Owner deems it unacceptable to have the Contractor correct work which has been incorrectly done, a deduction from the contract price shall be agreed upon therefore. Such a deduction from the contract price shall in no way affect the Contractor’s responsibility for defects which may occur nor his/her ability for correcting them, and damage caused by them.

1.15 LIENS

A. The Contractor shall, if required by the Owner, furnish him/her with a release in full of all liens arising out of this contract or in lieu thereof, and receipts in full for all materials and labor on the job. In either case, the Contractor shall furnish an affidavit that the liens or receipts include all the labor and material for which a lien could be filed. In lieu of the above, the Contractor may at his/her option furnish a bond to indemnify the Owner against all hazard of liens. Neither part nor final payment shall in any way release the Contractor from the above obligation and in the event that part or full payment has been made and any lien remains undischarged, the Contractor shall refund to the Owner the necessary funds to discharge such a lien including all cost and attorney’s fees.

1.16 JOB CONDITIONS

A. All surfaces to be covered shall be smooth, dry, and free from dirt, debris, and foreign material before any of this work is installed. Pumping equipment shall be located on the ground at a safe distance from building; the location being subject to the approval of the Owner. The Contractor shall be responsible for guarding against fires, and shall provide suitable fire extinguishers conveniently located at the site.

Competent operators shall be in attendance at all times equipment is in use.

Materials shall be stored neatly in areas designated by the Owner and dispersed so as to present a minimum fire hazard. Loads placed on the roof at any point shall not exceed the safe load for which the roof is designed.

B. There is NO SMOKING allowed inside any buildings and the Contractor shall be responsible for enforcement of this job rule at all times with his/her personnel.

C. The Contractor should be aware of Owner’s property when tearing off the existing roof. This is required for removal of dirt, silt, debris, roof membrane and insulation from the roof surface in order to preserve the ecology, eliminate unsightly conditions and protect building faces. Specific locations will be discussed at the pre bid conference.

D. Ladders: Any ladders used on this project must be in good condition. The ladder must also be secured at the roof line at all times while in use. All ladders must be O.S.H.A. approved.

007200-6

E. No drugs or alcoholic beverages are permitted on the grounds.

F. The Contractor shall place necessary barriers and/or protection around or under all work areas where his/her operations involve risk of injury to plant.

G. The Contractor will also protect the building structure from damage in the process of the job. In the event that damage does occur to any property or equipment, or the Owner’s work in process, notification must be made within two (2) working days of the incidents to the Owner and Owner’s Representative.

H. During the progress of the job, if waste material and rubbish are found or damage resulting from the Contractor’s operations is found, or the Contractor does not comply with the requirement by keeping the premises free of accumulations and correct the damage, it shall be the Owner’s prerogative to hire personnel to do so;

and the cost of this work will be deducted from the balance due the Contractor.

I. Existing roof top equipment walls, windows, etc. shall be completely protected by masking or other effective methods. Any mastics or asphalt must be cleaned off metal surfaces.

J. The Contractor is responsible for protecting all materials from the elements. If any material, such as insulation, becomes wet, it cannot be installed and must be replaced at the Contractor’s expense. NOTE: Insulation and rolled roofing materials must be covered with waterproof tarps at the end of each work day. Plastic wrappers supplied by the insulation manufacturer are not acceptable substitutes for tarps. The Owner’s Representative will reject any covering method material which does not adequately protect roofing materials.

K. Anyone guilty of willful destruction or unlawful removal of company property will be dismissed from the job and is subject to prosecution by law.

L. Any lawns damaged by Contractor vehicles will be restored with a stand of grass at the Contractor’s expense. Any damaged pavements will likewise be restored at the Contractor’s expense.

M. The Contractor must verify that all materials can be installed to accommodate the building design, pertinent codes and regulations, and the manufacturer’s current recommendations.

N. The Contractor will ensure that all substances are clean, dry, sound, smooth, and free of dirt, debris, and other contamination before any materials are supplied.

O. Any isolated areas that must be torn off and replaced will be built-up to the height of the existing roof prior to the installation of the new roofing membrane system.

1.17 WORKMANSHIP

A. All materials will be securely fastened and placed in a watertight, neat and workmanlike manner. All workmen shall be thoroughly experienced in the particular class or work upon which they are employed. All work shall be done in accordance with these specifications and shall meet the approval of the Owner or Owner’s Representative. The Contractor’s representative or job supervisor shall have a complete copy of specifications and drawings on the job-site at all times.

007200-7

B. Contractor shall plan and conduct the operations of the work so that each section started on one day is complete and thoroughly protected before the close of work for that day.

1.18 INSULATION

A. Insulation shall have accurate dimensional stability so as to properly conform to the surfaces of the roof, cants, curbs, pipes, etc. Joints between boards shall be tight and insulation shall be held back ½” from vertical surfaces and sumps. Insulation shall be protected from the weather at all times. No more insulation shall be laid than can be completely covered with roof materials on the same day. A base sheet shall not be considered as a proper weather barrier.

B. Insulation that becomes wet during or after installation shall be removed and replaced with dry insulation. If roofing is in place, the roofing shall be also replaced.

All replacing work shall be done at no added cost to the Owner.

1.19 ROOF DECK

A. Contractor shall notify the Owner or Owner’s Representative of any unforeseen areas of wet insulation. Where the damage is serious and extensive, it will be the Owner’s prerogative to authorize removal and replacement of deteriorated roofing, insulation and repair of the vapor barrier, if present. Where damage to the roof deck is found, the Contractor shall furnish the Owner with a unit price for removal and replacement of the damaged deck.

1.20 SAFETY

A. Contractor shall conform to requirements as designated by the United States Federal Government (O.S.H.A.). Contractor shall abide by all regulations as outlined in the O.S.H.A. handbook and shall have a handbook on location at all times.

B. Contractors hereby acknowledged that they and their workers have undergone Safety Training and shall at all times act in compliance with all NRCA recommended safety compliance rules and regulations.

1.21 INSURANCE

A. The following standard indemnity agreement and minimum insurance requirements are incorporated in the Specifications for all work performed by Contractors for the Owner, its affiliated and associated organizations or subsidiaries, hereinafter referred to as Owner.

1. THE CONTRACTOR AGREES TO INDEMNITY AND SAVE THE OWNER

AND OWNER’S REPRESENTATIVE HARMLESS FROM AND AGAINST

ANY AND ALL COSTS, LOSS AND EXPENSE, LIABILITY DAMAGES, OR

CLAIMS FOR DAMAGES, INCLUDING COST FOR DEFENDING ANY

ACTION, ON ACCOUNT OF ANY INJURY TO PERSONS (INCLUDING

DEATH) OR DAMAGE TO OR DESTRUCTION OF PROPERTY OF THE

OWNER, ARISING OR RESULTING FROM THE WORK PROVIDED FOR

OR PERFORMED, OR FROM ANY ACT, OMISSION, OR NEGLIGENCE OF

THE CONTRACTOR, SUBCONTRACTOR AND THEIR AGENTS OR

EMPLOYEES. THE FOREGOING PROVISIONS SHALL IN NO WAY BE

DEEMED RELEASED, WAIVED OR MODIFIED IN ANY RESPECT BY

007200-8

REASON OF ANY INSURANCE OR SURETY PROVIDED BY THE

CONTRACTOR.

2. All sub-contractors are required to file Certificated of Insurance properly completed and signed by an authorized insurance company representative before their work commences on the job or job site. No monies will be paid until the acceptable certificates are on file with the Contractor. Such certificates shall provide that there will be no cancellation, reduction or modification of coverage without thirty (30) days prior written notice to the Contractor. In the event such certificates are not provided to the Contractor prior commencement of work, Contractor’s failure to demand such certificates shall not be deemed a waiver of Subcontractor’s requirement to obtain the subject insurance.

3. The Contractor shall provide and maintain standard fire, extended coverage perils, vandalism and malicious mischief insurance to protect the interest of both the Contractor and the Owner for materials brought into the job or stored on the premises. Such insurance shall be for 100% of the insurable value of the work to be performed including all items of labor and materials incorporated therein, materials stored at the job-site to be used in completing the work, and such other supplies and equipment incidental to the work as are not owned or rented by the Contractor, the cost of which are included in the direct cost of the work. This insurance shall not cover any tools, derricks, machinery, tar buckets, ladders, engines, workmen’s quarters, boilers, pumps, wagons, scaffolds, forms, compressors, shanties, or other items owned or rented by the Contractor, the cost of which is not included in the direct cost of the work.

4. In accordance with Section (1.21), the Contractor and subcontractor(s) shall maintain the following insurance:

a. Workmen’s Compensation and Employer’s Liability Insurance affording:

1) Protection under the Workmen’s Compensation Law of the States in which the work is performed; and

2) Employer’s Liability protection subject to a minimum limit of $100,000.

b. Comprehensive General Liability Insurance in amounts not less than:

1) Personal Injury: $1,000,000 per person (including bodily injury) $1,000,000 per occurrence

2) Property Damage: $1,000,000 per occurrence

c. Comprehensive Automobile Liability Insurance in the following minimum amounts:

1) Bodily Injury $1,000,000 per person $1,000,000 per occurrence

2) Property Damage $1,000,000 per occurrence

d. This insurance shall:

1) Include coverage for the liability assumed by the Contractor under this section (section 1.21.A.1) (Indemnity);

2) Includes coverage for:

a) Premises, operations and mobile equipment liability

b) Completed operations and products liability

c) Contractual liability insuring the obligation assumed by the subcontractor in this agreement.

d) Liability which subcontractor may incur as a result of the operations, acts or omissions of subcontractors, suppliers or material men and their agents or employees; and

e) Automobile liability including owned, non-owned and hired automobile.

e. All coverage will be on an occurrence basis and on a form acceptable to the Contractor.

007200-9

1) Include completed operation coverage which is to be kept in force by the Contractor for a period of not less than one year after completion of the work provided for or performed under these specifications;

2) Not be subject to any of the special property damage liability exclusions commonly referred to as the exclusions pertaining to blasting or explosion, collapse or structural damage and underground property;

3) Not be subject to any exclusion of property used by the insured or property in the case, custody or control of the insured or property as to which the insured for any purpose is exercising physical control; and

4) The Certificate of Insurance furnished by the Contractor shall show specific reference that each of the foregoing items have been provided for.

5. The Certificates of Insurance furnished by the Contractor as evidence of the Insurance maintained by him shall include a clause obligating the Insurer to give the Owner thirty (30) days prior written notice or cancellation of any material change in the insurance.

1.22 WORK HOURS AND DAYS

A. When the Contract is awarded, the Contractor will contact the Owner’s Representative to arrange the work schedule and the hours of the day that the workmen may be on the building. The job is to be bid under the assumption that all work will be performed on a straight time basis.

1.23 COMPLIANCE WITH LAWS

A. The Contractor shall give notices, pay all fees, permits and comply with all laws, ordinances, rules and regulations bearing on the conduct of work.

1.24 OWNER’S RULES

A. The Contractor and all his/her personnel/agent(s) shall abide by all rules created by the Owner. The Contractor must contact the Owner’s Representative for specific information regarding the rules governing all operations of the project.

B. The Contractor shall properly notify all employees of conditions relating to roof areas with very poor condition and which will be worked on. After such notification, the Contractor must take all necessary precautions to ensure the safety of his/her employees as well as the building personnel.

C. THE CONTRACTOR SHALL “HOLD HARMLESS” THE MATERIAL

MANUFACTURER, AGAINST ANY LITIGATION ARISING FROM ANY

ACCIDENTS DURING THE COURSE OF THE CONTRACT.

1.25 SAFETY AND ECOLOGY

A. The Contractor(s) shall conform to the requirements as designated by the United States Federal Governments (e.g., O.S.H.A).

1.26 ANTI-DISCRIMINATION IN EMPLOYMENT

007200-10

A. Contractors and subcontractors shall not discriminate against any employees or applicant for employment, to be employed in performance of his/her contract, with respect to his/her hire, tenure, terms, conditions or privileges of employment because of his/her race, color, gender, sexual preference, religion, national origin, or ancestry.

PART 2 INSTRUCTIONS TO BIDDERS

2.1 WITHDRAWAL OR MODIFICATION OF BID

A. Any Bidder may withdraw his/her bid at any time before the scheduled closing date of the bid by appearing in person or by sending an authorized representative of the Bidder. An appointment should first be scheduled by calling the Owner’s Representative. The Bidder or his/her representative shall be asked to sign, in writing that the bid was returned to him/her/ after the withdrawal from the contract, the Bidding Contractor may not resubmit them.

2.2 BID OPENINGS

A. Bids will be opened publicly and read aloud at the published date and time. Notice of award will be made by written correspondence.

2.3 QUESTIONS

A. Technical questions regarding this bid can be directed to: Representatives of The Awarded Manufacturer Company and Ryan Long of Elite Companies.

B. If the Contractor feels a conflict exists between what is considered good roofing practice and these specifications, he/she shall state in writing all objections prior to submitting quotations.

C. It is the Contractor’s responsibility, during the course of the work, to bring to the attention of the Owner’s Representative any defective membrane, insulation or deck discovered which has not been previously identified.

2.4 RESPONSIBILITY FOR MEASUREMENTS AND QUANTITIES

A. The Bidding Contractors shall be solely responsible for all accuracy of all measurements and for estimating the material required to satisfy these specifications.

2.5 DISCREPANCIES AND ADDENDA

A. Should a Bidder find any discrepancies in the Drawings and Specifications, or should he be in doubt as to their meaning, he/she shall notify the Owner’s Representative at once, who will send a written Addendum to all Bidders concerned.

Oral instructions or decisions, unless confirmed by Addenda, will not be considered valid, legal or binding.

B. No extras will be authorized because of the Contractor’s failure to include work called for in the Addenda in his/her bid.

C. It shall be the responsibility of all Bidders to call to the Owner’s Representative’s attention at the pre bid meeting, any discrepancies which may exist between or with

007200-11 any of the contract documents, or any questions which may arise as to their true meaning.

D. Modifications to the specifications (if necessary) will be followed by an addendum;

no verbal discussions or agreements shall be recognized.

2.6 COMPETENCY OF THE BIDDERS

A. To enable the Owner to evaluate the competency and financial responsibility of a Contractor, the low Bidder shall, when requested by the Owner, furnish the information indicated in Section 5.0 below, entitled Contractor’s Qualification Statement, which shall be sworn to under oath by him/her or by a properly authorized representative of the Bidder.

2.7 DISQUALIFICATION OF BIDDERS

A. Any one or more of the following causes may be considered sufficient for the disqualification of a Bidder and the rejection of his/her bid(s):

1. Failure to attend the pre bid meeting;

2. Evidence of collusion among Bidders;

3. Lack of responsibility as revealed by either financial, experience or equipment statements, as submitted;

4. Lack of expertise as shown by past work, and judged from the standpoint of workmanship and performance history;

5. Uncompleted work under other contracts which, in the judgment of the Owner, might hinder or prevent the prompt completion of additional work if awarded;

or

6. Being in arrears on existing contracts, in litigation with an Owner, or having defaulted on a previous contract.

2.8 NOTICE OF AWARD

A. The award of this contract for the work is contingent upon receipt of an acceptable bid. Any part of or all bids may be rejected. All bids shall be good for a period of sixty (60) days following the date the bids are due. The contract shall be deemed as having been awarded when the formal notice of acceptance of his/her proposal has been duly served upon the intended awardee by an authorized officer or agent of the Owner.

2.9 WARRANTY

A. A written warranty which will commence from date of acceptance by Manufacturer must be supplied with the roof installation. This warranty will cover all defects in workmanship and materials. Damages caused by storm, vandalism and other trades are not included in the warranty. This warranty shall be from the manufacturer (See further, Statement of Policy).

B. A two (s) year workmanship warranty is required from the Contractor for all remedial maintenance done under the terms of this contract.

2.10 START AND COMPLETION DATE

A. Work shall begin within thirty (30) days from the award of this contract, or as agreed upon by all parties.

007200-12

B. All work as required in these specifications and drawings shall be completed within sixty (60) days of the start date, or as agreed upon by the parties.

C. Unless work is hampered by long period of inclement weather, by due proof of material unavailability, or by strike, the Owner will assess a penalty in the amount of $300.00 a day for each day beyond the agreed completion date.

D. The Contractor is responsible for supplying trained workmen in proper numbers and for scheduling and laying out his/her work, so that it will be started and completed in a professional manner within the time period indicated on his/her Proposal form.

E. If the Contractor sets equipment onto the job-site without commencing work immediately, the action will be considered “Spiking the job” which is unacceptable and will be considered a breach of contract by the Contractor; thereby, the contract will be terminated and the Contractor at no cost to the Owner, must remove his/her equipment and possessions from the job-site upon notification by the Owner.

2.11 PAYMENT

A. Payment for materials shall only be made after the material has been delivered to the job-site. An invoice for the material must be presented to the Owner for payment. Materials are not to be delivered to the job-site until the project is ready to begin. The Contractor must provide a release of lien from the Material Manufacturer. Subsequent requests for payment can made monthly. Final payment for the project will be made following completion, after final inspection has been made and an invoice presented to the Owner. A 10% retainer shall be held until delivery of the warranty.

B. When the job in progress is interrupted for two (2) weeks or longer by causes beyond the Contractor’s control such as a strike, weather, acts of God, etc., the Owner agrees to pay, upon request of the Contractor, a price equivalent to the percentage of work completed at that time. Regular progress payments shall be made for labor and/or materials.

C. Each invoice shall be accompanied by a detailed estimate of the amounts and values of labor expended and materials purchased up to the last day of the preceding month. The amount of the invoice shall not exceed ninety percent (90%) of the labor and material values estimated for the preceding month.

D. Such payments shall be viewed by both parties as progress payments and shall not in any way relieve the Contractor of performance obligations under this contract, nor shall such payments be viewed as approval or acceptance of work performed under this contract.

E. Final payment shall be withheld until all provisions of the specifications are met, including all necessary clean-up, and the Owner receives written verification of completion.

F. Upon completion of the job, the Owner, the Owner’s Representative, and the Contractor will make final inspection of the work done, and the Owner’s Representative if requested by Owner’s Representative.

G. All payments for material used in the execution of this contract can be made by a check issued jointly, payable to the Contractor and Owner’s Representative will sign a completion slip authorizing final payment.

007200-13

H. If requested by the Owner and/or Owner’s Representative, the Contractor shall provide a Letter of Credit from the bank to secure payment to material supplier.

I. If requested by the Owner and/or Owner’s Representative, a certified check shall be paid by the Contractor to material supplied prior to release of order.

J. If requested by the Owner and/or Owner’s Representative, a certified check shall be paid by the Contractor to material supplier via common carrier upon receipt of delivery.

K. Contractor shall have a pre-approved line of credit from the material supplier.

L. Final payment shall be made to the Contractor no later than thirty (30) days after job approval, providing the Contractor submits waivers of lien with his/her final invoice indicating that all suppliers have been paid.

2.12 PERFORMANCE AND PAYMENT BOND

A. The successful Contractor will be responsible for securing a performance and…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .