This is a Design-Build Request for Proposal (RFP) Volume 2 Design Narratives document prepared by the Orange County Sheriff's Department (OCSD), Orange County Public Works (OCPW), and OC Facilities Design & Construction Management for the Emergency Operations Center (EOC) relocation project at 1382 Bell Avenue, Tustin, California. The project encompasses construction of a new five-story parking structure providing 520 parking stalls designed with photovoltaic readiness, reconfiguration of the existing site including utility relocation and landscape enhancements, expansion of the existing building through approximately 17,250 square feet of new second-floor EOC space, renovation of approximately 840 square feet of ground-floor storage, and selective infrastructure upgrades. The design must comply with California Building Standards Code (Title 24), Essential Services Buildings Seismic Safety Act (ESBSSA) requirements for the EOC tenant improvement spaces, and incorporate redundant utility systems for operational resiliency. The project is to remain fully operational throughout demolition and construction, requiring careful phasing and coordination with existing occupants.

The Design-Build Entity (DBE) must provide detailed sustainability analysis including LEED v4 Interior Design and Construction Silver equivalence or certification for office/interior spaces and Parksmart certification for the parking garage, submit comprehensive design submittals at 50%, 90%, and 100% completion stages for County review and approval, coordinate with the Orange County Fire Authority and Division of the State Architect for regulatory approvals, and deliver the project consistent with established schedule and budget goals. Critical design factors include exterior insulation evaluation for thermal comfort, Southern California Edison utility incentive applications, thermal comfort reports, energy modeling, resilient design strategies, and mechanical equipment sizing calculations. The facility must balance security requirements with aesthetic integration to the existing 1382 Bell Avenue campus, incorporate low-VOC materials and circular design strategies, and achieve 90% occupant satisfaction through post-occupancy evaluation. Design standards must align with OCPW Architectural and Engineering Standards, and all project deliverables including as-built documentation, warranties, and operation manuals are required upon project completion.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ORANGE COUNTY SHERIFF DEPARTMENT

OC Public Works OC Facilities Design & Construction Management | A&E Project Management

DESIGN-BUILD

REQUEST FOR PROPOSAL

VOLUME 2 of 4

Design Narratives

15D-036-15D-DP15-4200

February 13, 2026

100% progress issuance

Docusign Envelope ID: 1E6286FB-9BA9-841D-835B-8AED7EFFA8BE

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 2 of 172

February 13, 2026 DESIGN NARRATIVES 15D-036-15D-DP15-4200

TABLE OF CONTENTS

PART 1 - SIGNATURE PAGE

PART 2 - PERFOMANCE CRITERIA TEAM

PART 3 - PROJECT OVERVIEW

Glossary of terms

Executive summary

Performance Criteria Guide

Design Submittals

Building Codes, Standards and References, Authorities Having Jurisdiction

Project Description

Aspirations

Critical Success Factors

Key Performance Indicators

Exhibits

PART 4 - SUSTAINABILITY

Goals and requirements

General requirements

Standards & references

County of Orange – Climate Action Plan

Title 24 building energy efficiency standards

Energy

Utility energy incentives

Embodied Carbon Strategies

Material Ingredient Reporting

Low VOC materials

Circular design strategies

Resilient design strategies

Construction Phase Strategies

Parking Garage

Exhibits

PART 5 - BUILDING DESIGN CRITERIA

Essential Services

Sustainability

Architectural Visual Measure

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 3 of 172

Main Office Building 2nd Floor Addition

Parking Structure

Roof Systems

Exterior Windows and Openings

Interior Design

Interior Doors

Door Hardware

Wayfinding and Signage

Exhibits

PART 6 - BUILDING CODE ANALYSIS

Applicable Codes

Authorities Having Jurisdiction

Project Code Description

Special Requirements

Occupancy Classification

Building Height and Area

Fire Resistance Rated Construction

Fire Protection Systems

Means of Egress

Parking Facility

Exhibits

PART 7 - PROGRAM CRITERIA

Program Strategy

Space Program

Room Data Sheets

Schematic Room Diagrams

Program Summary

Furnishings Performance Criteria

Millwork

Equipment Access

Exhibits

PART 8 - HAZARDOUS MATERIALS ASSESSMENT NARRATIVE

PART 9 - SITE DESIGN CRITERIA

Existing Site Conditions

Site Demolition

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 4 of 172

Site Grading

Access / ADA

Site Improvements

Site Utilities

Landscape Design Criteria

Exhibits

PART 10 - STRUCTURAL SYSTEMS

Overview

Design Criteria

Lateral Design Criteria

Soil Design Criteria

Structural System – Parking Garage

Structural System – 2nd Floor Addition

Parking Design Criteria

Photovoltaic Arrays

Experience and Qualifications of Buehler Engineering, Inc

Limitations

Exhibits

PART 11 - MECHANICAL

Mechanical Scope and Goals

Existing Mechanical System

Mechanical Design Criteria

Mechanical System Requirements

Controls

PART 12 - PLUMBING

Scope and Goals

Existing Plumbing

Plumbing Fixtures

Plumbing Systems Criteria

Storm Drainage

Design Criteria

Piping

PART 13 - EMERGENCY OPERATIONS CENTER - FIRE PROTECTION SYSTEM

Existing fire protection system

General

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 5 of 172

Water supply

Sprinkler system

Fire sprinklers

Standpipe System

Existing fire alarm system

Fire alarm system

PART 14 - PARKING GARAGE - FIRE PROTECTION SYSTEM

General

Water supply

Sprinkler system(s)

Standpipe system

Fire sprinklers

Fire alarm system

PART 15 - ELECTRICAL

Existing electrical systems

Scope and goals

Electrical utility service

Building distribution

Alternate power systems

Electrical room requirements

Feeder and branch circuit design

Miscellaneous systems

PART 16 - LIGHTING

Lighting design criteria

Lighting controls

Egress lighting and egress lighting controls

Emergency lighting

Lighting requirements for site and exterior

Light level recommendations

PART 17 - INFORMATION & COMMUNICATION TECHNOLOGY (ICT) SYSTEMS

Utility Service, Distribution and Backbone Infrastructure

Network Switches and Routers

Telephony System

Motorola Computer Aided Dispatch (CAD) System

Wireless Network

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 6 of 172

In-Building Radio Frequency Distribution Antenna System

Synchronized Digital Clock System

Electronic Security System

Audiovisual Systems

Exhibits

PART 18 - ACOUSTICAL DESIGN

Acoustic Design Overview

HVAC and Building System Noise and Vibration Control

Plumbing

Electrical

Emergency Generator (if used)

Noise Impact on Surrounding Properties

Reverberation Time and Room Acoustics

Interior Sound Isolation

Building Exterior Shell Sound Isolation

Building Vibration

Environmental Impact Report Noise Requirements

Evaluation and Testing

END OF TABLE OF CONTENTS

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 7 of 172

PART 1 - SIGNATURE PAGE

Emergency Management Division, Orange County Sheriff’s Department: Michelle Anderson

Orange County Sheriffs Technology Division: Dave Fontneau

Orange County CEO’s Office: Michelle Aguirre

Orange County Public Works: Casey Garrison

HGA Architects and Engineers: Fielding Featherston

Kimberly Engelby

Scott Dessort

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 8 of 172

PART 2 - PERFOMANCE CRITERIA TEAM

Orange County Public Works (OCPW)

Contact: Casey Garrison, Sr. Project Manager

Phone: 714.714.6360

Email: casey.garrison@ocpw.ocgov.com

OC Sheriff | Emergency Management Division (OC EOC)

Contact: Michelle Anderson, County Emergency Manager

Phone: 714.628.7158

Email: manderson@ocsheriff.gov

HGA | Architecture, Interior Design, Cost Estimate

Contact: Delphine Msika, AIA, CID, NCIDQ, Sr. Project Manager

Phone: 619.202.9109

Email: dmsika@hga.com

Contact: Camilla Do, AIA, NOMA, LEED AP BD+C, Sr. Project Architect

Phone: 703.317.6046

Email: cdo@hga.com

Contact: Erik Bakken, AIA, Project Architect

Phone: 617.366.1808

Email: ebakken@hga.com

Contact: Therese Ethier, Sr. Interior Designer

Phone: 619.202.9113

Email: tethier@hga.com

Contact: Joe Tarlizzo, Sr. Cost Estimator

Phone: 612.758.4417

Email: JTarlizzo@hga.com

Psomas | Civil Engineering

Contact: Jeremy Johnson, P.E., Sr. Project Manager/Vice President

Phone: 661.705.4410

Email: jeremy.johnson@psomas.com

Agency Artifact | Landscape Architecture

Contact: Emilio Uranga, Senior Designer

Phone: 626.733.6596

Email: emilio@agencyartifact.com

Buehler Engineering | Structural Engineering & Parking Design

Contact: John Harvey, SE, DBIA, LEED AP BD+C, Principal

Phone: 415.495.1635 x 501

Email: jharvey@buehlerengineering.com

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 9 of 172

Glumac | Mechanical, Electrical, Plumbing Engineering, Energy + Sustainability, Low

Voltage, Lighting, Fire Protection and Fire Alarm Systems

Contact: Jenna Baker, Project Manager

Phone: 209.256.3228

Email: jbaker@glumac.com

Woden | Codes Consultant

Contact: Andrew Thul, P.E., Principal Engineer

Phone: 714.330.2181

Email: athul@wodenfire.com

Acoustical Engineering Consultant | Acoustical Engineer

Contact: Amir Yazdanniyaz, P.E.

Phone: 310.295.7313

Email: amir.yazdanniyaz@AESacoustics.com

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 10 of 172

PART 3 - PROJECT OVERVIEW

Glossary of terms

Refer to Exhibit A

Executive summary

This Performance Criteria document has been developed by the

Architect/Engineer team in collaboration with Orange County Public Works (OCPW), the Orange County Sheriff’s Department (OCSD), and the Orange County Emergency

Operations Center (OC EOC). Its purpose is to define the program, intent, functional requirements, and performance expectations for the Design-Build Entity (DBE).

The information contained herein establishes minimum project requirements and does not relieve the DBE of its responsibility to perform independent due diligence, code analysis, and professional services in accordance with applicable standards of care.

Performance Criteria Guide

The Performance Criteria Guide is presented in four (4) main volumes and a set of

Exhibits and Appendices:

A. Volume 1

The Contract Requirements focus on requirements for the contract, and other general requirements associated with this project (Created separately by OCPW).

B. Volume 2

The Design Guidelines establish the minimum requirements necessary to meet

Project goals. The Criteria Document is organized by discipline. The document summarizes the guiding principles to which the design build team should adhere.

C. Volume 3

The Exhibits, which were available and considered as part of Volume 2 Narrative

D. Volume 4

The Appendices section includes progress documentation that was made available late during the narrative development and therefore could not be included in the design recommendations. This information may be referred to for information only and/or be of use to the DBE in the development of their stipulated sum and/or execution of the project. They may NOT be relied upon as forming a basis of the contract. Information in the reference documents required to design and deliver the project, such as a Geotechnical Report or site survey, must be developed or repeated by the DBE for their use.

All drawings and/or Exhibits provided in these criteria shall be considered

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 11 of 172 conceptual, incomplete, and not for construction. The DBE is responsible for producing their own due diligence, investigations, reports, and design and engineering solutions to comply with the performance criteria.

The Performance Criteria does not relieve the Design Build Entity and all its subconsultants from their responsibility to provide their own due diligence, code analysis and standards of care. The DBE shall be responsible for the implementation of these Criteria in a code compliant manner to achieve the desired function, operation, aesthetic, schedule, and budget goals.

Design Submittals

Upon Notice to Proceed the Design Build Entity (DBE) shall begin design and preconstruction services as outlined in the RFP. The DBE shall develop Exhibits with sufficient detail to establish the project schedule and budget consistent with the requirements of these documents and the proposals submitted by the DBE.

A building systems workshop shall be coordinated by the DBE. All project team members including DBE, OCPW, OC EOC and the 1382 Bell Building Facility representatives and Design teams shall attend.

The DBE shall present their understanding of the Performance Criteria, program, functional requirements, adjacencies, and any unique requirements. The DBE shall propose building systems and designs that meet or exceed the requirements and any subsequent changes approved for review and approval by the approved stakeholders.

1. The Basis of Design narrative shall describe the commissioning process.

2. Design Submittals shall be inclusive of the following items related to the

Critical design factors:

a) Exterior insulation evaluation for condensation and interior thermal comfort / inboard vs. outboard

b) Southern California Edison (SCE) Utility Incentive Application – California

Energy Design Assistance, CEDA or CEDA-light SCE - CEDA

c) Thermal Comfort Report

d) Energy Model Reports

e) Resilient Design Strategies Report

f) Mechanical Equipment Sizing Calculations (Heat Gain / Psychrometric)

g) Mechanical Zoning Diagrams

3. The Basis of Design narrative, plans and specifications, are to be reviewed by

OCPW team members. Any comments or questions shall be fully resolved by the DBE entity prior to submission to the Authority Having Jurisdiction.

4. Decisions regarding the acceptance of systems, or modifications to the performance criteria, or items that warrant further study shall be memorialized in writing.

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 12 of 172

5. For each increment package (Demolition, Site, New Building, Building Addition, etc. as determined by the DBE and agreed to by OCPW) the DBE will provide design submittals and the Basis of Design narratives for review and approval by OCPW at pre-determined milestones prior to submission to the AHJ. The

DBE shall be responsible for validating the AHJ review procedures, policies, and timelines when considering increment packages and accounting for such in developing OCPW’s review and approval schedule. Reviews are expected to occur at a minimum as follows, unless otherwise agreed to in writing.

a) 50% Construction Documents

b) 90% Construction Documents

c) 100% Construction Documents

6. Deviations from the Performance Criteria documents, program requirements, or functions shall be made known to OCPW, OCSD and EOC’s representatives.

Written approval of the deviation shall be obtained prior to any implementation in subsequent design deliverables.

7. All sections of the Performance Criteria are intended to be complementary to each other. In the event of conflicting information, contact OCPW for clarification prior to proceeding. In general, the most stringent information shall be the basis of design.

8. Where these Performance Criteria remain silent, direct the DBE to coordinate, and/or require verification with OCPW, the DBE shall, as part of their due diligence, engage with OCPW, OCSD and EOC to obtain direction in writing prior to implementation of any additional directives into the project.

9. Changes to the contract terms shall follow the requirements set forth in the contract and the RFP documents.

10. The abbreviation “OCPW” shall mean any county agency who is required to, or may wish to, provide input. In most cases this will either be OCPW, OCSD or

EOC representatives. Communications with shall follow the guidelines and procedures outlined in the general conditions.

11. Design and Contract Documents approved for construction shall be maintained in both the BIM model and other project formats to reflect RFIs

(Request for Information), Change Orders, Supplemental Instructions, Construction Change Directives, and As-Built information. Unless otherwise requested, drawings and deliverables shall be provided in accordance with

OCPW Architectural and Engineering Standards (Exhibit B _ A-E Guide Final

10_2025). As-builts documents shall be provided to the Client and End-Users

(OCPW/EOC/OCSD) upon completion.

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 13 of 172

Building Codes, Standards and References, Authorities Having Jurisdiction

A. Building Codes – Standards and references

The project shall comply with the currently adopted California Building Standards

Code (Title 24), including CBC Chapter 11B accessibility requirements, CalOSHA, and applicable federal ADA standards. See Code Analysis Section for additional information.

The program criteria documentation was also developed while considering portions of the following standards (see Exhibits series G):

1. ASTM E2668

2. DOD Antiterrorism Minimum Standards

3. FEMA

4. NFPA 1225

When more than one standard, code or reference requirement is applicable, the most stringent requirement shall be applied.

B. Authorities Having Jurisdiction

The Orange County Fire Authority (OCFA) shall have primary authority over the project and shall have review authority regarding fire life safety, accessibility compliance and building systems. The DBE shall identify and follow all OCFA policies, procedures, and regulations.

1. DBE shall identify submittal requirements and review duration when establishing the project schedule.

2. The DBE shall identify proposed phasing, if used, and obtain approvals from

OCPW for execution of phased work.

3. The DBE shall identify potential challenges to approvals and/or areas that need clarification early to minimize delays to the project resulting from plan review processes.

4. The DBE shall demonstrate knowledge and experience with OCPW, OCFA and

EOC processes.

The Division of the State Architect (DSA) shall have jurisdiction over the project’s structural safety relative to the Essential Services Buildings Seismic Safety Act. The

San Diego office will oversee the project. The DBE shall identify and follow all DSA policies, procedures, and regulations.

1. DBE shall identify submittal requirements and review duration when establishing the project schedule.

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 14 of 172

2. The DBE shall identify proposed phasing, if used, and obtain approvals from

OCPW for execution of phased work.

3. The DBE shall identify potential challenges to approvals and/or areas that need clarification early to minimize delays to the project resulting from plan review processes.

4. The DBE shall demonstrate knowledge and experience with DSA processes.

Although the project site is located within County of Orange owned property, there may be work that is located within the public right-of-way, or under the jurisdiction of the local building, public works, utilities, or planning departments associated with the City of Tustin. In such cases, the DBE shall identify each location and case and conform to the necessary requirements of the local AHJ for areas not under the control of the County of Orange. The DBE shall coordinate with all relevant agencies where authorities overlap.

1. The DBE shall coordinate with OCPW for work outside of the project boundaries.

2. The DBE shall coordinate with OCPW and OCSD for the stoppage of any utilities or monitoring that impacts OCSD operations within the 1382 Bell Ave.

campus.

The DBE shall follow all local, federal, and state laws including but not limited to

CalOSHA, Executive Orders, and County policies. The DBE is responsible for identifying and applying all applicable codes and regulations.

The DBE shall adhere to the requirements of the US Green Building Council for all

LEED requirements, policies, and procedures if OCPW, OCSD, and EOC elect to pursuit

LEED after cost management review.

The DBE is responsible for the identification of all Authority Having Jurisdiction approval processes and duration. The DBE shall incorporate agency requirements, and review timelines into the project schedule for the purposes of identifying project milestones and Exhibit delivery date. The DBE shall sequence submittals to the AHJs in the order advantageous to the project.

1. Revisions to project contract documents resulting from the various AHJ reviews, or/and client changes, shall be appropriately coordinated between all AHJs for a complete review and approval of the final project plans

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 15 of 172

Project Description

The current Orange County Emergency Operations Center (OC EOC) functions are housed in an aging facility located in Loma Ridge, Orange County, California. This project will relocate EOC personnel, equipment, and operational functions to the modernized Orange County Sheriff’s Department (OCSD) facility at 1382 Bell Avenue, Tustin, California (APN #430-231-05).

To support this relocation, a new parking structure will be constructed to accommodate the increased parking demand generated by the addition of the EOC

Department and to address the projected long-term parking needs of the existing

1382 Bell Avenue campus operations.

The Project consists of comprehensive site and building infrastructure improvements necessary to support the mission-critical functions of the OC EOC, its resiliency and long-term operational capacity. The scope includes:

1. The construction of the new parking structure, reconfiguration of the site,

2. The expansion and renovation of the existing 1382 Bell Avenue building to accommodate essential EOC operations.

A. Existing Site Description

1. The project site is located at 1382 Bell Avenue, Tustin, California 92780. It is an existing occupied and fully functional OCSD facility; both building and surface parking were renovated in 2022.

2. As the project site will remain occupied throughout demolition and construction, the Design-Build Entity (DBE) must work in close collaboration with both the occupants and OCPW to maintain uninterrupted operations.

Effective coordination will be essential, utilizing tools such as scheduled communications, ongoing updates, and strategic construction phasing to ensure a seamless workflow.

3. The current site provides unsecured visitor parking and secured employees parking:

a) Visitor Parking: located at building front area and open (non-gated); 68 stalls + 1 accessible stall and 1 Van accessible that are not fully compliant, total 70 stalls.

b) 4 bicycle parking (In area open to visitors)

c) Secured Parking: 283 stalls + 3 accessible and 3 Van accessible that are not fully compliant; total 289 stalls.

d) For a total of 359 parking stalls, 4 being accessible and 4 being van accessible; “accessible stalls” have been noted to not be 100% accessible and will minor require updates. compliant and would need to be upgraded to the latest code edition as part of the DBE scope of work.

4. The project building is of construction Type III-B; It was seismically retrofitted in 2022 to comply with ESBSSA requirements.

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 16 of 172

5. It is currently composed of a +/- 86,705 SQ FT ground floor and of +/- 37,796 SQ

FT partial second floor.

B. Project Major components

1. Construction of a new five-story parking structure providing 520 stalls, designed to be photovoltaic (PV) ready.

2. Reconfiguration of the existing site, including utility relocation, surface parking modifications, circulation improvements, and landscape enhancements.

3. Expansion of the existing building through construction of approximately

17,250 SF of new second-floor EOC space.

4. Renovation of approximately 840 SF of ground-floor storage and associated impacted areas.

5. Upgrade of the existing first-floor mail room to meet enhanced security requirements.

6. Selective infrastructure upgrades, including utilities

7. optional water/sewer storage systems. – DBE to provide line-item cost for this scope.

The Performance Criteria narrative defines the general extent of first-floor demolition required as a result of the EOC scope of work. However, this narrative does not provide a revised first-floor layout. The Design-Build Entity (DBE) shall include in its scope all required demolition and full reconstruction of first-floor areas impacted by the EOC improvements, including adjacent spaces affected by structural, utility, or programmatic modifications.

The project will remove existing above and below ground infrastructure to accommodate the redevelopment suitable for the EOC and OCSD functions.

Demolition may require remediation of hazardous materials. An hazardous report was not available at the time of this report; the DBE is to cooperate with OCPW in its due diligence effort to obtain this necessary document.

The site and building shall remain operational throughout demolition and construction. The DBE shall provide appropriate phasing, protection, and coordination to ensure uninterrupted operations.

C. Resiliency

Expected to mirror the operations currently managed at the Loma Ridge facility, the EOC spaces will have the capacity of operating 24 hours a day, seven (7) days a week allowing the facility and staff to:

1. Coordinate county resources more effectively in support of local and state government during disasters, OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 17 of 172

2. Provide training facilities and accommodate local, state agencies in disaster preparation coordination, training, and exercises.

The OC EOC facility space (2nd floor office space and ground floor storage) is an essential service project subject to the requirements of the Essential Services

Buildings Seismic Safety Act (ESBSSA). The existing 1382 Bell Avenue building which will house the EOC office and storage spaces was seismically upgraded to ESBSSA standards in 2022.

The new parking structure is not subject to ESBSSA requirements.

D. Sustainability

As part of the performance criteria programmatic research, the design team consulted with the Orange County Climate Action Plan’s representative (CAP). Due to construction budget constraints, the performance criteria herein do not mandate

Sustainable criteria (except as required by California Building Code, including

CalGreen and T24 (CBC). However, the Design-Build Entity (DBE) is asked to provide line-item pricing for the following:

1. Office/interiors space to achieve Leadership in Energy and Environmental

Design (LEED) Commercial Interiors v4.1 certification with a target of Silver certification.

2. Office/interiors space to follow Leadership in Energy and Environmental

Design (LEED) Commercial Interiors v4.1 with a target of Silver equivalence without the certification process.

3. Parking structure to achieve Parksmart certification.

4. Refer to Sustainability Criteria Section for additional information.

Aspirations

The Criteria Performance team of architects and engineers conducted a variety of meetings and workshops with Orange County Public Works (OCPW) personnel and

OC EOC and OCSD staff to develop critical success factors and aspirational goals for the project:

A. Construction Quality, Energy Efficiency, and Style Consistency with OCPW A&E

Standards and Existing Facility Standards

The county is committed to excellence in the design and development of the site, parking structure and tenant improvement. Quality as defined per the A&E Guide

(Exhibit B : A-E Guide Final 10_2025) shall be instilled into all aspects of the project. It will begin with an integrated design approach that will incorporate architectural and engineering aesthetics sensitive to the existing environment. This environmental sensitivity shall include providing user friendly indoor conditions and exemplary building components and materials. The resulting design solution and delivered project shall be a high quality, energy efficient facility design and operational systems will be consistent/compatible with the existing infrastructure. The project aims to be cost effective and easily maintained. This is not a public-facing facility with significant visitor traffic, its presence should remain discreet, harmoniously coexisting with the existing infrastructure and departments located on the same site. Please note the following documents, both provided by and outlining design standards for

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 18 of 172

OCPW facilities:

1. Exhibit C _ OC Workplace Design Guidelines July 2019 Final_091919

2. Exhibit D _ OCCR PARKS RESTROOM FIXTURE GUIDE

3. Exhibit E _ OCSD ERRCS Deployment Guidelines -REV 4.4B

4. Exhibit F _ 5_DHS-ST_EM Technology Recommendations

B. Functional Blend of High-Tech and Low Tech to Serve EOC Roles

The transition of the EOC from the Loma Ridge site to 1382 Bell Ave. Tustin site presents an opportunity to integrate state-of-the-art audiovisual and communications technologies, aligned with the capabilities of the existing OCSD divisions within the same building. At the same time, the design will preserve and support low-tech crisis management methods that have proven efficiency in real-world emergency situations.

C. Working Environment with Dedicated and Shared Support Areas for Emergency

Personnel

Dedicated facilities such as private showers, lockers, bunk areas, wellness rooms, and break rooms will support EOC personnel both during routine operations and at full activation. Quiet indoor respite spaces, along with shared outdoor rest and relaxation areas, will provide additional opportunities for personnel to recharge and maintain well-being to compensate for high pressure work-related situations.

D. Emergency Ready

As a main hub of operations, the project site and buildings should be a beacon of response, projecting a ready to respond environment and effectively carrying out operations as successfully as the Loma Ridge facility has done.

E. Achieve Selective Compliance with Mandatory and Voluntary National Standards for similar facilities

In addition to California building codes and Federal ADA guidelines, the project shall meet a selection of standards as outlined in:

1. Exhibit G_ Exhibit _OC_EOC_Design Considerations_OfflineProgressFile.xls

2. ASTM E2668: Exhibit G-a _ 1_ATSM_E2668_EOC Guide

3. DOD Antiterrorism Minimum Standards: Exhibit G-b _ 3_UFC_Antiterrorism

Facility Specs_Revised 2024 and Exhibit G-c _ 4_ UFC_Resist Forced Entry Specs

4. FEMA: Exhibit G-d _ 2_fema_eoc-quick-reference-guide 2022

5. NFPA 1225

F. Meet the critical OCSD and EOC programming requirements (offices and parking), be code compliant, and be delivered on time and on budget.

CG - Delete, not required.

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 19 of 172

G. Minimize construction-related disruption:

The site and building must be kept functional during the construction process.

Critical Success Factors

The facility design proposed by the Design Build Entity (DBE) shall meet the functional criteria of these documents and shall be consistent with the aspirational goals listed above.

A. This facility must balance

1. The mission to maximize service to the public and coordination with allied agencies.

2. The need to protect the County’s property and staff.

3. The support of efficient departmental operations.

4. Safety, Security, Resilience:

a) The tenant improvement project must meet ESBSSA requirements, allowing continuous operation during an emergency by being structurally stable, accommodating to the preservation of life, having redundant and backup utility systems.

b) The new parking structure is not required to meet the ESBSSA requirements: The A&E team evaluated the feasibility of designing the structure to be ESBSSA compliant; however, this approach was determined to be unnecessary. The analysis concluded that ESBSSA compliance would add significant cost without providing proportional benefit, as surface parking areas are available to accommodate ESBSSA-designated vehicles. Therefore, the parking structure will be designed and constructed to standard code requirements, ensuring cost efficiency while maintaining adequate parking capacity and operational resilience.

Structural and Parking Exhibit M-b provides parking stall allocations by vehicle type and division, accounting for all division/personnel vehicles required by ESSBA to be located on site rather than within the parking structure.

c) The site is already enclosed and access controlled; it also provides (2) two access points for ingress and egress of vehicles. The future parking structure must also provide a minimum of (2) access points for ingress and egress of vehicles.

B. Additional Parking Capacity

1. Additional Parking Count: The project shall maximize the secure parking for

OCSD and EOC staff. The goal for the new parking structure is to provide 520 parking stalls.

2. EOC priority parking: EOC staff members will not park in the parking structure.

EOC staff members/vehicles (Including fleet vehicles and Control Seven

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 20 of 172

Vehicle) must have dedicated surface parking spots adjacent to building entries in proximity of their office space.

3. Parking capacity during EOC activation: During full EOC activation, the combined capacity of the surface parking and the new parking structure may not be sufficient to accommodate both EOC volunteer parking needs and the regular demand from the 1382 Bell Avenue facility. To address this shortfall, EOC, OCSD and OCPW are coordinating on the identification of off-site overflow parking options and on the delineation of which departments will be assigned to on-site versus off-site parking. The DBE shall consider this operational requirement when developing site circulation, access controls, and wayfinding strategies, ensuring that overflow parking operations can be supported safely and efficiently during activation periods. EOC Activated

Personnel will have priority parking when EOC is activated.

4. Fleet Vehicles and Dimensionally Demanding Vehicles Accommodation: The parking facilities, both structure and surface, must be designed to accommodate a variety of fleet vehicles. The surface parking must accommodate some vehicles dimensions that exceed standard parking parameters. Exhibit M-b shows an inventory of vehicles, types and allocation and circulation strategies for those specific vehicles.

5. The DBE shall ensure that the parking design—stall layout, clearances, turning radii, and access routes—can accommodate the range of fleet vehicles while maintaining overall operational efficiency and safety. In addition, the design should incorporate flexibility for future needs, including potential changes in the fleet mix, vehicle electrification requirements, and evolving operational demands. Provisions such as adaptable stall configurations, conduit for future

EV charging, and allowance for oversized or specialized vehicles should be considered as part of the baseline design.

C. Design efficiency

1. The project design shall be effective and efficient while allowing flexibility and nimbleness to respond to a disaster. The design should also anticipate the need for incorporation of future technologies, both in infrastructure and equipment.

2. The project should create a maintainable, durable, and sustainable facility, resulting in lower operating and maintenance costs.

3. Specifically for the tenant improvement scope, the project design—including construction types, finishes, and building systems—must be consistent with those of the existing 1382 Bell facility. This alignment is essential to ensure future operational efficiency, simplify maintenance, and support seamless integration with ongoing facility management practices.

4. The project shall thoroughly commission new systems to ensure efficient and reliable operation.

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 21 of 172

5. The DBE team shall systematically furnish all required warranties, operation and maintenance manuals, record documents, and quickly close out the project with no defects as established by the A-E Guide (See Exhibit B: A-E

Guide Final 10_2025).

6. The project shall meet the functional goals established in these Performance

Criteria, inclusive of the project schedule, and budget set forth by the County of Orange.

7. The DBE shall review and incorporate all possible future mitigation measures as they will be identified in the future EIR (process under CEQA consultant’s purview; CEQA consultant is contracted directly by OCPW). EIR is not yet available at the time of the 100% Performance Criteria Narrative writing.

Key Performance Indicators

Key Performance Indicators (KPIs) are measurable parameters gauging the project’s support of the aspiration and critical success factors. Each KPI should be defined in terms that support this project’s goals which are:

1. Facility uninterrupted functioning during construction.

2. Seismic Safety focus (EOC tenant improvement space- ESBSSA).

3. Resiliency: Utility system redundancy for all the EOC tenant improvement space

4. EOC personnel wellness: acoustic respite spaces, private showers/lockers and sanitary accommodations, dedicated breakroom, shared internal multi-function kitchen and outside patio areas.

5. Additional Parking Capacity. – See Structural section.

6. Within Budget.

7. Project Schedule consistent with Client goals (See RFP).

8. Energy Conservation / Energy conscious/ Solar Readiness.

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 22 of 172

Exhibits

Exhibit A _ Glossary

Exhibit B _ A-E Guide Final 10_2025

Exhibit C _ OC Workplace Design Guidelines July 2019 Final_091919

Exhibit D _ OCCR PARKS RESTROOM FIXTURE GUIDE

Exhibit E _ OCSD ERRCS Deployment Guidelines -REV 4.4B

Exhibit F _ 5_DHS-ST_EM Technology Recommendations

Exhibit G _ 20250820_OC_EOC_Design Considerations_ProgressFile

Exhibit G-a _ 1_ATSM_E2668_EOC Guide

Exhibit G-b _ 3_UFC_Antiterrorism Facility Specs_Revised 2024

Exhibit G-c _ 4_ UFC_Resist Forced Entry Specs

Exhibit G-d _ 2_fema_eoc-quick-reference-guide 2022

Exhibit M-b - STRUCTURAL AND PARKING

CG - Delete, not required.

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 23 of 172

PART 4 - SUSTAINABILITY

Goals and requirements

The Design-Build Entity (DBE) is responsible for compliance with all relevant local, state & federal codes and statutes for the proposed project, including but not limited to the following performance targets:

1. LEED v4 ID+C: Silver equivalent (based on LEED IDC+C v4.1)

2. LEED v4 ID+C: Silver Certification (based on LEED IDC+C v4.1)

3. Parksmart Certification for the parking garage.

The final date for the registration of LEED v4 and v4.1 projects is June 30, 2026. LEED v4 and v4.1 projects must be completed and certified by June 30, 2032.

General requirements

The DBE shall provide detailed calculations prior to construction to confirm the final design, demonstrating all requirements are met. These should verify that the final design meets all specified functional, performance, code, and safety requirements, including structural loads, system capacities, thermal performance, and any specialized criteria for the facility.

To achieve sustainability performance goals, initiate an integrated, holistic design process in the early design phases through construction. Maintain the integrated approach through construction, ensuring that procurement, installation, and construction sequencing support the agreed‑upon sustainability outcomes.

Include sustainability, wellness, and resilience goals in the integrated design and coordination of all building disciplines: architecture, façade, mechanical, electrical, plumbing, lighting, fire protection, structural, civil, and commissioning.

Design the parking garage to align with Parksmart certification principles by integrating energy-efficient lighting, EV charging stations, natural ventilation, and alternative transportation amenities (bike storage, carpool spaces) to enhance sustainability and reduce environmental impact.

Standards & references

1. California Department of Public Health v1.1-2010 or v1.2-2017 Standard Method for the Testing and Evaluation of Volatile Organic Carbon Emissions from

Indoor Sources Using Environmental Chambers

2. The ANSI/BIFMA e3 Furniture Sustainability Standard

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 24 of 172

3. BIFMA M7.1 Testing for VOC Emissions from Office Furniture and Seating

4. Title 24, Part 6, Building Energy Efficiency Standards

5. State Executive Order EO B-18-12

6. State Executive Order EO S-3-05

7. State Executive Order EO B-30-15

8. Assembly Bill 32

9. LEED v4 Interior Design and Construction (ID+C) Commercial Interiors

10. Parksmart Certification

County of Orange – Climate Action Plan

The Climate Action Plan is being designed to target the County’s greenhouse gas sources while also preparing for natural disasters that are becoming more common and assisting the most vulnerable residents with outreach and access to critical information and resources. In context of the EOC, the project should:

1. Incorporate energy‑efficient building systems, renewable‑ready infrastructure, and waste reduction measures to support countywide greenhouse gas reduction goals.

2. Enhance resilience by integrating water conservation, sustainable materials, and efficient mechanical systems — vital during extended emergency response operations.

Title 24 building energy efficiency standards

The new EOC design shall comply with the minimum applicable requirements in the 2025 Title 24, Part 6, Building Energy Efficiency Standards using either the

Prescriptive compliance method or Performance compliance method.

Energy

In alignment with the proposed County decarbonization goals, any new space heating or domestic water heating equipment shall use electricity rather than natural gas. Space heating equipment shall be heat pumps with electric resistance heating used on for low ambient conditions as needed. Refer to the Mechanical and

Plumbing design guidelines for detailed requirements.

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 25 of 172

Utility energy incentives

DBE shall investigate and pursue available utility energy efficiency or electrification incentives for the new building systems. Utility incentives shall be factored into the life cycle assessments when evaluating system design options.

Embodied Carbon Strategies

1. Environmental Product Declarations

2. Require third‑party verified Type III EPDs for a minimum of twenty (20) major building materials, including but not limited to concrete, structural steel, reinforcing steel, glazing assemblies, insulation, interior finishes, and façade components. Product‑specific EPDs shall be incorporated into submittals and used to support LEED Environmental Product Declarations credit achievement.

3. Low‑Carbon Concrete Specification

a) Specify low‑carbon concrete products such as Portland Limestone

Cement (Type 1L) blends and mixes with higher supplementary cementitious material (SCM) content (e.g., fly ash, slag, or calcined clay).

b) Mix designs shall prioritize minimizing global warming potential (GWP) while meeting all structural performance requirements.

Material Ingredient Reporting

1. Require documentation demonstrating the chemical ingredient transparency and human‑health performance of a minimum of ten (10) building materials, consistent with LEED Materials & Resources credits for Material Ingredient

Reporting and Optimization.

2. Specify products that disclose chemical ingredients to at least 1,000 ppm using third‑party verified declarations such as Health Product Declarations

(HPD v2.1+), Declare Labels (LBC Red List Free or Red List Approved), or Cradle to Cradle certifications (Material Health Silver or better). Documentation shall be provided during submittals and included in final closeout to verify compliance with LEED Material Ingredients credit thresholds.

Low VOC materials

Use interior materials that meet recognized volatile organic compound (VOC) content limits or have been tested for low VOC emissions.

A. Apply the criteria to five main categories:

1. Paints and coatings

2. Adhesives and sealants

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 26 of 172

3. Flooring systems

4. Ceilings, walls, thermal/acoustic insulation

5. Furniture and furnishings

B. Wet-Applied Products (Paints, Coatings, Adhesives, Sealants)

1. VOC content must meet South Coast Air Quality Management District

(SCAQMD) standards:

a) Rule 1113 for paints and coatings

b) Rule 1168 for adhesives and sealants

C. Interior Construction Materials (Insulation, Flooring, Ceilings, Wall Panels)

1. Require third-party VOC emissions testing following California Department of

Public Health (CDPH) Standard Method v1.2–2010 or 2017.

D. Acceptable certifications include:

1. GREENGUARD Gold

2. SCS Indoor Advantage Gold

3. CRI Green Label Plus (for carpets and adhesives)

4. 3rd party laboratory tests

E. Furniture and Furnishings

1. Must meet ANSI/BIFMA emissions requirements (M7.1 and e3 sections 7.6.1 and

7.6.2)

Circular design strategies

A. Product Take Back and Manufacturer Responsibility

1. Specify products from manufacturers offering formal take-back programs for end-of-life recovery, refurbishment, or recycling.

2. Require suppliers to provide written confirmation of take-back terms, logistics and material recovery rates.

3. Prioritize vendors with closed-loop systems that reintroduce recovered materials into new products.

4. See Exhibit O for Example of Documentation of Manufacture Program for

Material Recycling

B. Demountable & Modular Partitions

1. Use demountable wall systems with standardized panel sizes and mechanical

(non-adhesive) connections for easy reconfiguration.

2. Require components to be fully reusable without loss of structural or aesthetic quality.

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 27 of 172

3. Maintain an as-built inventory of partition components to facilitate relocation or resale.

C. Material Reuse & Salvage

1. Incorporate reclaimed materials where feasible (e.g., structural steel, timber, ceiling tiles).

2. Require that any removed materials during future renovations be evaluated for reuse before recycling or disposal.

3. Establish on-site sorting areas for salvageable components.

D. Design for Disassembly

1. The Design-Build team should consider material assemblies that are layered so that finishes, substrates, and structure can be separated without contamination.

2. Provide disassembly instructions as part of the project closeout documentation.

Resilient design strategies

A. Wildfire Smoke

1. Integrate high‑efficiency air filtration (MERV‑13 or higher) in HVAC systems to capture fine particulate matter from wildfire smoke.

2. Provide sealed building envelope with controlled ventilation to limit infiltration during smoke events.

B. Heat Waves

1. The Design-Build Team should evaluate options for improving performance of the building over existing conditions during extreme heat, such as

2. Passive cooling through shading devices, reflective roofing, and high‑performance glazing to reduce heat gain.

3. Redundant cooling systems sized for extreme temperature events, with load‑shedding capability to prioritize mission‑critical spaces.

4. Pre-cooling strategies to manage peak loads and maintain comfort during prolonged heat events.

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 28 of 172

Construction Phase Strategies

A. Construction Waste Management

1. The Design‑Build team to implement a Construction Waste Management Plan for interior demolition and fit‑out activities targeting at least 5 material streams for diversion.

2. The general contractor will source-separate waste streams where feasible and track hauling documentation (weight tickets/receipts) to support LEED submittals.

3. The project will target diversion through reuse and recycling using at least three material streams, with a preference for four or more, and a diversion target of 50% minimum with an aspirational goal of 75%, subject to local facility capabilities and project logistics.

B. Indoor Air Quality Assessment:

1. The Design‑Build team will verify acceptable indoor air quality prior to occupancy using either a building flush‑out procedure or baseline IAQ testing, consistent with LEED best practices.

2. A flush‑out can be completed by providing a total of 14,000 cubic feet of outdoor air per square foot of floor area (or partial flush‑out before occupancy with continued ventilation after move‑in), while maintaining temperature between 60-80 deg F and relative humidity no higher than 60%.

The general contractor would have to include flush-out in the construction schedule.

3. Alternatively, the project may conduct third‑party IAQ testing under occupied ventilation conditions to confirm pollutant concentrations meet thresholds identified by LEED for particulate matter and key indoor contaminants.

Parking Garage

A. Recycling Infrastructure

1. Provide recycling bins in all public and employee areas where trash bins are located. Install proper signage on or near bins clearly indicating where each item is to be deposited.

B. Wayfinding

1. Install external directional signage that guides drivers efficiently from the street network to garage entries, reducing circulation and idling.

2. Provide clear internal wayfinding (lane markings, color‑coded levels, stall numbering, directional signs) to shorten search time and improve user experience.

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 29 of 172

C. Bicycle Parking Infrastructure

1. Include bicycle and personal gear storage lockers, mechanic station/workstation and two spaces for cargo/family/oversized bicycles

D. No/Low VOC coatings, paints and sealants

1. Architectural paints and coatings applied to walls and ceilings must not exceed the VOC content limits established in Green Seal Standard GS-11, Paints, 1st Edition, May 20, 1993.

2. Anti-corrosive and anti-rust paints applied to ferrous metal substrates must not exceed the VOC content limit of 250 g/L established in Green Seal

Standard GC-03, Anti- Corrosive Paints, 2nd Edition, January 7, 1997.

3. Clear wood finishes, floor coatings, stains, primers, sealers, and shellacs applied to facility elements must not exceed the VOC content limits established in South Coast Air Quality Management District (SCAQMD) Rule

1113, Architectural Coatings, rules in effect on January 1, 2004.

Exhibits

Exhibit O – Manufacturer Recycling Program

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 30 of 172

PART 5 - BUILDING DESIGN CRITERIA

Essential Services

This project is an essential services facility and requires a robust approach to architecture and engineering. Refer to Section 10 for Structural Systems.

Sustainability

This project shall comply with the applicable version of California Building

Standards Code (Cal. Code Regs., Title 24), Part 11, CALGreen at the time of permitting and construction The architectural approach shall consider each of this project's sustainability goals as an integrated part of the design solution.

1. The DBE shall provide construction cost estimate for review.

2. Refer to Section 4 for Sustainability

3. Refer to Section 11 for Mechanical Systems

4. Refer to Section 12 for Plumbing Systems

5. Refer to Section 15 for Electrical Systems

Architectural Visual Measure

1. The DBE shall endeavor to create visually attractive construction that blends in with the existing 1382 Bell Avenue building, surrounding community, and meeting the required functional and programmatic needs. DBE should attempt to match materials from the rest of the building for maintenance ease. The examples illustrated included within the Program Criteria are intended to be informative, giving the DBE a framework under which to design and implement. Nevertheless, the Program Criteria are not meant to be a finished design solution.

2. The facility design proposed by the DBE shall meet the functional criteria of these documents and shall be consistent with the critical success factors and the Mission and Vision of the OCSD and EOC. This facility must balance: the mission to maximize service to the public and allied agencies; the need to protect the OCSD and EOC property and staff; and the need to support efficient departmental operations. This requires an approach that provides a secure facility which is still inviting to the public and does so in the most efficient, functional, sustainable, maintainable, and cost-effective manner.

3. Physical security measures must be effective without being obvious or institutional in appearance. The project shall be aesthetically pleasing, alisted

OCPW & OCSD EOC - TUSTIN PERFORMANCE CRITERIA Page 31 of 172 and environmental mitigation measures listed, and present a secure and civic appearance.

4. The EOC addition shall have sufficient scale and architectural treatment to be identifiable by the public.