Bid Package Summary

This is a bid package and contract document for the 777 Pump Station Improvement Project issued by the Brookfield Water Pollution Control Authority (WPCA) in Connecticut. The project involves the installation of a turnkey packaged pump station with valve pit and associated appurtenances, including removal of the existing pump station wet well and valve pit, dewatering, and temporary sewer bypass operations. The work also includes removal of an existing propane tank and generator to be replaced with a diesel generator, and retrofitting of an existing oversized manhole structure inlet with a grinder. Rock removal is not anticipated. Contract documents are available for examination at the WPCA office (53A Commerce Road, Brookfield, CT 06804) beginning July 29, 2026, between 9:00 AM and 4:00 PM at a cost of $100 per set, plus $15 for mail delivery. A pre-bid meeting is scheduled for August 12, 2026 at 10:00 AM at the WPCA office. Sealed bids must be received by 11:00 AM on September 11, 2026. The contract completion time is 120 consecutive calendar days from the notice to proceed, with a required work commencement within 10 calendar days of notification. Liquidated damages are assessed at $500 per calendar day for late completion beyond the contract period.

Bidders must submit bids with 5% bid security (cashier's check, certified check, or bid bond), a Consent of Surety agreeing to furnish Performance and Payment Bonds each at 100% of the contract price, and evidence of three comparable projects completed within the past three years. The successful bidder must furnish Performance and Payment Bonds from a surety company licensed in Connecticut with an A.M. Best & Co. rating of at least A-minus. Connecticut prevailing wage rates apply to this project, which exceeds $100,000 in contract value. Bidders must provide comprehensive insurance coverage including Workers Compensation, Commercial General Liability ($3,000,000 per occurrence), Owner's Protective Liability, Motor Vehicle Insurance, Builder's Risk Property Insurance, and Completed Operations coverage. The contract is governed by Connecticut law and includes provisions for local labor preference, non-discrimination in employment, and compliance with OSHA and state safety requirements. No bids will be accepted by mail, and no bid may be withdrawn within 120 days after bid opening.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TOWN OF BROOKFIELD, CONNECTICUT

WATER POLLUTION CONTROL AUTHORITY

AUTHORITY MEMBERS

NELSON MALWITZ

Chairman

LOUISE TROJANOWSKI-MARCONI

Vice Chairperson

JAMES MURRAY RYAN BERGERON

Treasurer Alternate Member

MATTHEW WOLK DAVID MCCLAIN

Member Alternate Member

LORETTA DONOVAN

Member

KRISTI MCPADDEN ALLISON KENNEDY

Executive Administrator Operations Manager

ROGER PRINZ MARY RAJCULA ONGARO

Chief of Maintenance Senior Financial Specialist

TIM STRID STEPHEN G. HARDING, ESQ.

Senior Inspector & Maintenance Specialist Commission Attorney

CONTRACT 2026-01

777 Pump Station

Langan Job No. 190085123

W. Charles Utschig, P.E.

License No. P.E.N. 19262

Langan CT, Inc.

White Plains, NY

Date: July 23, 2026

TABLE OF CONTENTS

ADVERTISEMENT FOR BIDS A-1 to A-2

INFORMATION FOR BIDDERS IB-1 to IB-8

PROPOSAL, BIDDER'S AFFIDAVIT, BID BOND, SURETY GUARANTEE AND OTHER

FORMS

P-1 to P-17

CONTRACT C-1 to C-3

GENERAL CONDITIONS GC-1 to GC-43

GENERAL SPECIFICATIONS

Section S1 – Earthwork and Backfill S1-1 to 7

Section S2 – Concrete S2-1 to 3

Section S3 – Steel Reinforcement S3-1

Section S4 – Pipes, Support, and Appurtenances S4-1 to 7

Section S5 – Restoration of Surfaces S5-1 to 2

Section S6 – Erosion and Sediment Control S6-1 to 5

Section S7 – Site Preparation S7-1 to 8

Section S8 – Administrative Requirements S8-1 to 4

Section S9 – Photographic Documentation S9-1 to 3

Section S10 – Dewatering S10-1 to 3

Section S11 – As-Built Requirements S11-1 to 2

Section 11200 – Wastewater Pumping Station S12-1 to 14

PUMP STATION ELECTRICAL AND INSTRUMENTATION SPECIFICATIONS

Section 260010 Basic Electrical Materials and Methods 260010-1 to 3

Section 260505 Selective Demolition for Electrical 260505-1 to 2

Section 260519 Low Voltage Electrical Power Conductors and Cables 260519-1 to 10

Section 260523 Control Voltage Electrical Power Cables 260523-1 to 7

Section 260526 Grounding and Bonding for Electrical Systems 260526-1 to 6

Section 260529 Hangers and Supports for Electrical Systems 260529-1 to 5

Section 260533.13 Conduit for Electrical Systems 260533.13-1 to 9

Section 260533.16 Boxes for Electrical Systems 260553.16-1 to 5

Section 260553 Identification for Electrical Systems 260553-1 to 7

Section 262416 Panelboards 262416-1 to 6

Section 262726 Wiring Devices 262726-1 to 6

Section 262815 Electrical Enclosure 262815-1 to 4

Section 262816.13 Enclosed Circuit Breakers 262816.13-1 to 4

Section 262816.16 Enclosed Switches 262816.16-1 to 4

Section 262923 Variable Frequency Motor Controllers 262923-1 to 7

Section 263213 Engine Generators 263213-1 to 10

Section 263600 Transfer Switches 263600-1 to 5

CONTRACT ITEMS

CI 1 Mobilization and Demobilization CI 1-1 only

CI 2 Removals CI 2-1 to 2-2

CI 3 Pump Station Installation CI 3-1 to 3-2

CI 4 Temporary Sewer Bypass CI 4-1 to 4-2

CI 5 Dewatering CI 5-1 to 5-3

CI 6 Cast-In-Place Concrete CI 6-1 only

CI 7 Forcemain CI 7-1 to 7-2

CI 8 PVC Sewer Pipe CI 8-1 to 8-2

CI 9 Modifications to Existing Manhole CI 9-1 only

CI 10 Erosion & Sediment Control Devices CI 10-1 to 10-2

CI 11 Miscellaneous Additional Work CI 11-1 only

CI 12 As-Built CI 12-1 only

APPENDICIES

Appendix A – Boring Logs

Appendix B – Photo Log

Appendix C – Connecticut Department of Labor Prevailing Wage Rates

Appendix D – Eversource Three-Phase Distribution Installation Guidelines

See detailed Table of Contents at beginning of General Conditions

WPCA Contract No. 2026-01

A-1

ADVERTISEMENT FOR BIDDERS

ADVERTISEMENT FOR BIDS

TOWN OF BROOKFIELD, CT

WATER POLLUTION CONTROL AUTHORITY

CONTRACT 2026-01

777 Pump Station, Brookfield, CT

Pump Station Replacement

Notice is hereby given that sealed bids will be received, publicly opened and announced by the Brookfield Water Pollution Control Authority (Authority), on Friday September 11, 2026 at

11:00 AM local time.

The work covered under this contract includes the installation of a turnkey packaged pump station with valve pit and associated appurtenances. The existing pump station wet well and valve pit will be removed. The project will include dewatering and a temporary sewer bypass. Rock removal is not anticipated. The project also includes removal of the existing propane tank and generator, to be replaced with a diesel generator. Additionally, the existing oversized manhole structure inlet will be retrofitted with a grinder.

Contract documents may be examined and obtained at the office of the Brookfield

Water Pollution Control Authority, 53A Commerce Road, Brookfield, CT. 06804 starting

Wednesday July 29, 2026 between the hours of 9:00 AM and 4:00 PM, except weekends and holidays.

Copies may be obtained at the Authority office upon payment of $100.00 for each set, with checks made payable to the Brookfield Water Pollution Control Authority. Contract documents may be obtained by mail upon payment of an additional $15.00 for postage and handling. Refunds will not be granted.

A pre-bid meeting will be held on Wednesday August 12, 2026 at 10:00 AM at the

Authority office. The meeting is not mandatory, but prospective bidders are urged to attend.

Bids must be submitted on standard proposal forms in the manner designated therein and be enclosed in a sealed envelope bearing the name and address of the bidder on the outside, addressed to the Brookfield Water Pollution Control Authority. The words “777 Pump

Station Contract 2026-01" must be printed on the face of the envelope.

Sealed bids will be received by the Authority at the Brookfield Water Pollution Control

Authority, 53A Commerce Road, Brookfield, CT. prior to the date and time established for opening of bids. No bids will be received by mail.

Each individual Bid Proposal must be accompanied by a bid security in the amount of five percent (5%) of the bid, a certificate guaranteeing the furnishing of Performance and

Payment Bonds (Consent of Surety), and all other documents identified in the Form of

A-2

ADVERTISEMENT FOR BIDDERS

Proposal. Bid security may be in the form of a bid bond, cashier's check, or certified check.

The successful bidder must furnish a Performance Bond and a Payment Bond, each in the full amount of the contract price, issued by a surety company licensed to issue such bonds in the

State of Connecticut, and having an A.M. Best & Co. rating of at least A-minus.

No bidder may withdraw his bid within 120 days after the date of the opening thereof.

The Authority reserves the right to waive any informality in the bids, to reject any or all bids, and to make its awards in the best interests of the Town of Brookfield, CT.

Attention is called to the State requirements regarding employment, nondiscrimination, safety and wage scales.

Attention is called to provisions in the Contract Documents providing for preference to local laborers and subcontractors.

Brookfield Water Pollution Control Authority

By: Nelson Malwitz, Chairman

IB-1

INFORMATION FOR BIDDERS

1. RECEIPT AND OPENING OF BIDS - The Brookfield Water Pollution Control Authority

(hereafter called the "Authority" or the “Owner”) will receive sealed bids for “777 Pump Station, Contract 2026-01" at the office of the Brookfield Water Pollution Control Authority, 53A

Commerce Road, Brookfield, CT. until 11:00 AM local time on Friday September 11, 2026 at which time they will be opened and announced.

Proposals shall be enclosed in opaque sealed envelopes plainly marked “777 Pump Station

Contract 2026-01”, with the name and address of the bidder.

No bids will be received by mail.

2. CONTRACT DOCUMENTS - Contract Documents may be examined at the office of the

Brookfield Water Pollution Control Authority, 53A Commerce Road, Brookfield, CT. 06804 or at the office of Langan Engineering and Environmental Services, Inc. (hereinafter called the

"Engineer"), 1 North Broadway – Suite 910, White Plains, New York 10601 (Tel. 914-323-7400).

Copies may be obtained at said offices upon payment of $100.00 for each set, with checks made payable to Brookfield Water Pollution Control Authority. Contract Documents may be obtained by mail upon payment of an additional $15.00 for postage and handling. Refunds will not be granted.

3. DESCRIPTION OF WORK – The work covered under this contract includes the installation of a turnkey packaged pump station with valve pit and associated appurtenances. The existing pump station wet well and valve pit will be removed. Electrical improvements / upgrades associated with the packaged pump station shall be coordinated with the manufacturer. Site electrical and mechanical improvements, included rerouted conduits, and a proposed generator are included within the proposed work. The project will include dewatering and a temporary sewer bypass. The project also includes removal of the existing propane tank and generator, to be replaced with a diesel generator. Additionally, the existing oversized manhole structure inlet will be retrofitted with a grinder.

4. ADDENDA AND INTERPRETATIONS - No interpretations of the meaning of the Contract

Documents will be made to any prospective bidder orally. Every request for such interpretation should be in writing addressed to Langan Engineering and Environmental Services, Inc., One

North Broadway – Suite 910, White Plains, New York 10601, and to be given consideration must be received on or before the end of the business day on Friday August 21, 2026 via email or regular mail. Any and all such interpretations and any supplemental instructions will be in the form of written addenda to the Contract Documents which will be emailed with return receipt to all prospective bidders (at the respective email address furnished for such purposes) not later than the end of the business day on Friday September 4, 2026. Failure of any bidder to receive any such addenda or interpretations shall not relieve said bidder from any obligations under his bid as submitted. All addenda so issued shall become part of the Contract Documents.

5. OBLIGATION OF BIDDER - Each bidder must inform himself fully of the conditions relating to the construction and the labor provisions under which the work will be performed; failure to

IB-2

do so will not relieve a successful bidder of his obligation to furnish all material and labor necessary to carry out the provisions of the Contract Documents and to complete the contemplated work for the consideration set forth in his bid.

At the time of the opening of bids each bidder will be presumed to have inspected the site and to have read and to be thoroughly familiar with the Contract Documents (including all addenda). The failure or omission of any bidder to receive or examine any form, instrument, or document shall in no way relieve any bidder from any obligation in respect to his bid.

Bidders are notified that it is obligatory upon them to obtain by their own means information which they may require as to the existing physical condition, and in particular as to subsurface and ground water conditions. The Owner will make available to the bidder all information obtained by investigations prior to the bid openings, but makes no guarantee with respect to the accuracy of such information, and each bidder in bidding represents that he relies exclusively upon his own investigations, and he makes his bid with a full knowledge of all conditions, and the kinds, quality, and quantity of work required.

6. SUBSURFACE UTILITIES - The approximate locations of certain existing subsurface pipes and structures are indicated on the drawings. The Owner does not guarantee that the locations and/or depths of such utilities are even approximately correct. Contractor must contact “Call

Before You Dig” 1-800-922-4455, or 203-281-5435.In addition, the contractor is obligated to retain the services of a qualified utility locator company to have all existing utilities located on the project site. Refer to item 16 of “Information for Bidders.”

7. INFORMATION NOT GUARANTEED - All information given on the drawings, or in the

Contract Documents, relative to the existing utilities, existing pipes and other structures is from the best sources at present available to the Owner. All such information and the drawings of existing construction are furnished only for the convenience of bidders.

It is understood and agreed that the Owner does not warrant or guarantee that the materials, conditions, and pipes or other structures encountered during construction will be the same as those indicated by the boring samples or by the information given on the drawings.

The bidder must satisfy himself regarding the character, quantities, and conditions of the various materials and the work to be done.

It is understood and agreed that the bidder or the Contractor will not use any of the information made available to him, or obtained in any examination made by him, in any manner as a basis or ground for claim or demand of any nature against the Owner or the Engineer, arising from or by reason of any variance which may exist between the information offered and the actual materials or structures encountered during the construction work.

8. PREPARATION OF PROPOSAL - Proposals must be submitted on the prescribed form. All blank spaces for unit prices, extended totals, and summations must be filled in, in ink or typewritten, in both words and figures. The bidder must sign the bid, and give his title and business address. All forms attached to the Proposal shall be completed by the bidder and submitted with the bid as well as any other documentation requested by these bid documents and required by law.

IB-3

9. ERRORS IN BID - In the event there is a discrepancy between the unit prices (if any) and the extended totals, the unit price shall govern. In the event there is a discrepancy between prices written in words and written in figures, the prices written in words shall govern. In case of error in the bidder’s extended summation, the computed total of the Engineer shall govern.

If an error in any bid item is obvious, and is corroborated by extensions or additions, the Owner may make the appropriate correction and accept the bid.

10. APPROXIMATE QUANTITIES - The quantities given in the Proposal are approximate only, being given as a basis for the uniform comparison of bids, and the Owner does not expressly or by implication agree that the actual amount of work will correspond therewith.

11. BIDDERS TO CHECK APPROXIMATE QUANTITIES - Bidders must satisfy themselves by personal examination of the location of the proposed work, and by such other means as they may choose, as to the actual conditions and requirements of the work, and the accuracy of the estimate of the Engineer, and shall not, at any time after the submission of a bid, dispute or complain of such statement or estimate of the Engineer, nor assert that there has been any misunderstanding in regard to the nature or amount of the work to be done.

12. PRICES NOT CHANGED BY CHANGE OF QUANTITIES - An increase or decrease in the quantities listed in the Proposal for any item shall not be regarded as sufficient grounds for an increase or decrease in the unit price of that item, nor in the time allowed for the completion of the work, except as provided in the Contract. The Owner reserves the right to delete portions of the work, or to add to the work, as it deems necessary, and such changes shall be based upon the unit prices bid or upon reasonable prices established by the Engineer.

13. INFORMAL BIDS - The Owner may reject as informal, bids which are incomplete, conditional, or obscure, or which contain additions not called for, erasures not properly initialed, alterations or irregularities of any kind, or the Owner may waive such informalities.

14. INTENT OF CONTRACT DOCUMENTS - The intent of the Contract Documents is to obtain a complete job, satisfactory to the Owner and the Engineer. It shall be understood that the bidder is cognizant of the full requirements of the Contract, and has based his Proposal upon such understanding. Compensation for all work and materials required to complete the

Contract shall be considered included in the price bid in the Proposal.

15. RIGHT TO ACCEPT OR REJECT BIDS - The Owner reserves the right to select the lowest responsive and responsible bid, to waive any informalities in the bids, to reject any or all bids, and to make its awards in the best interests of the Town of Brookfield. Conditional bids may be rejected.

16. LOCATING UTILITIES - The Contractor shall obtain advance information on the vertical and horizontal location of all utilities, structures, or other facilities located within the project area.

Such information shall be obtained from utility mark-outs, test pits, or pipe locating devices, and the obtaining of such information is exclusively the Contractor’s responsibility. Any conflicts must be reported to the Engineer sufficiently in advance of the work schedule to avoid delays or extra work. The cost of obtaining such advance information shall be included in the prices bid for the various items of work.

IB-4

17. BID SECURITY - Each bid must be accompanied by a cashier's check, a certified check of the bidder or a bid bond issued by a surety company licensed to issue such bonds in the State of Connecticut in the amount of five percent (5%) of the amount of the bid, drawn to the benefit of the Brookfield Water Pollution Control Authority. Such checks will be returned to all except the three lowest responsive bidders within three days after the opening of bids. The remaining checks will be returned to the three lowest bidders within 48 hours after the Owner and the accepted bidder have executed the Contract, or if no Contract has been so executed, within 120 days after the date of the opening of bids, upon demand of the bidder at any time thereafter, so long as he has not been notified of the acceptance of his bid. Bid bonds will not be returned, except on written request.

18. CONSENT OF SURETY/SURETY GUARANTEE - In addition to the checks or bid bonds for bid security, each bid must be accompanied by a guaranty from a surety company, qualified and authorized to do business in this State, and having an A.M. Best & Co. rating of at least A-minus, agreeing to furnish Performance and Payment Bonds, each in the full amount of the contract price in the event of award of Contract.

19. QUALIFICATION OF BIDDER - The Owner may make such investigations as are deemed necessary to determine the ability of the bidder to perform the work, and the bidder shall furnish to the Owner all such information and data for this purpose as the Owner may request.

The Owner reserves the right to reject any bid if the evidence submitted by, or investigation of such bidder, fails to satisfy the Owner that such bidder is properly qualified and/or financially capable to carry out the obligations of the contract and to complete the work contemplated therein within the time limit stipulated. The bidder shall submit evidence of successful performance of at least three projects of a similar scope and dollar volume within the last three years.

20. WITHDRAWAL OF BIDS - Upon proper request and identification, a bidder may withdraw his bid prior to the scheduled time for the opening thereof. However, no bid may be withdrawn after the first bid has been opened and thereafter not for a period of 120 days after the date of the opening thereof.

21. LIQUIDATED DAMAGES FOR FAILURE TO ENTER INTO CONTRACT - The successful bidder, upon his failure or refusal to execute and deliver the Contract and the required

Performance and Payment Bonds within ten (10) days after he has received notice of the acceptance of his bid, shall forfeit to the Owner as liquidated damages for such failure or refusal, the security deposited with his bid.

22. CONTRACT BONDS AND INSURANCE - Simultaneously with his delivery of the executed

Contract, the successful bidder must deliver to the Owner Performance and Payment (labor and materials) bonds, each in the amount of one hundred percent (100%) of the accepted bid, as security for the faithful performance of his Contract, and for the payment of all persons performing labor or furnishing materials in connection therewith; prepared in a form acceptable to the Owner (see forms attached) and having as security thereon such surety company or companies as are acceptable to the Owner and as are authorized to transact business in this

IB-5

State, and having an A.M. Best & Co. rating of at least A-minus. The bonds shall comply with

Section 49-41 et seq. of the Connecticut General Statutes.

Simultaneously with the delivery of the executed contract, the successful bidder must deliver approvable insurance certifications, as specified in Article 8 of the General Conditions.

The Contractor shall obtain and pay for, and shall provide proof of insurance for the types and limits of insurance as more particularly specified in Article 8 for the General Conditions.

23. EXECUTION OF CONTRACT - The bidder to whom the contract is awarded will be required to furnish the Contract Bonds duly executed by a satisfactory surety (as defined above), and to execute the contract within the time limit stated in the Proposal after notification that the contract is ready for signature.

24. POWER OF ATTORNEY - Attorneys-in-fact who sign Contract Bonds must file with each bond a certified and effectively dated copy of their power of attorney.

25. TIME FOR COMPLETION AND LIQUIDATED DAMAGES - The bidder to whom the contract is awarded must agree to commence work within 10 calendar days from the date of receipt of written notice to proceed from the Owner, and shall substantially complete the work in all respects except for maintenance and placement of permanent pavement within 120 consecutive calendar days following the service of said notice. Liquidated damages for late completion shall be as stipulated in the Contract.

26. LAWS AND REGULATIONS - This contract will be governed by the laws of the State of

Connecticut. The attention of the bidder is specifically directed to the provisions of the General

Conditions relative to laws and ordinances, State Labor Standards, Non-discrimination

Provisions and Safety Provisions.

27. NON-DISCRIMINATION IN EMPLOYMENT - Contracts for work under this proposal will obligate the contractors and subcontractors not to discriminate in employment practices. The

Contractor must comply with all applicable State, Federal and Local statutes dealing with non-discriminatory practices.

The Contractor shall take affirmative action to insure that applicants for employment are employed, and that employees are treated during employment, except in the case of a bona fide occupational qualification or need, without regard to their race, color, religious creed, age, sex, sexual orientation, marital status, national origin, mental retardation, learning disability, or physical disability. Such action shall include, but not be limited to, the following: employment, upgrading, demotion, or transfer; recruitment or advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship.

The Contractor shall post in conspicuous places and make available to employees and applicants for employment, notices to be provided by the State setting forth the provisions of this nondiscrimination clause. The Contractor shall state that all qualified applicants will receive consideration for employment without regard to their race, color, religious creed, age, sex, sexual orientation, marital status, national origin, mental retardation, or physical disability.

IB-6

The Contractor shall incorporate the requirements of this paragraph in all subcontracts for

Work performed under this Agreement.

28. WAGE RATES - Where the project is for new public works construction greater than

$1,000,000 or where repair / rehabilitation work is greater than $100,000, the Contractor must abide by State Wage Rates as published by Department of Labor in accordance with

Connecticut General Statute Sec. 31-53(g).

The wages paid on an hourly basis to any mechanic, laborer or workman employed upon the Work herein contracted to be done and the amount of payment or contribution paid or payable on behalf of each such employee to any employee welfare fund, as defined in Section

31-53 (h) of the Connecticut General Statutes, shall be at a rate equal to the rate customary or prevailing for the same work in the same trade or occupation in the town where the work is being performed. Any contractor who is not obligated by agreement to make payment or contribution on behalf of such employees to any such employee welfare fund shall pay to each employee as part of his wages, the amount of payment or contribution for his classification on each pay day.

Prevailing Wage Rates. Please note: The regulations require that the Authority contact the

Labor Commissioner at least 10 days, but not more than 20 days, before the contract is to be advertised to ascertain the proper prevailing wage. Normally, the applicable prevailing wage rate is either included with the bid documents or is added to the bid documents as an

Addendum prior to the opening of bids. In this way all bidders are operating off of the same wage rates and the wage rates become a part of the contract documents.

29. OVERTIME AND HOLIDAY WORK - Bidders are advised that all bids are to be premised on the assumption that work will be performed during regular working hours, from 7 AM to 6 PM, Monday to Friday. Where overtime (after 6 PM), work on holidays, or work on weekends, is required, written permission must be obtained from the Owner or its delegated officials. The

Contractor shall not be entitled to additional compensation for work outside regular working hours. Also note that required working hours, when construction is along state roads, shall meet the State Department of Transportation requirements.

30. TRAFFIC CONTROL - A Traffic Control Plan with advance notification, signage, temporary barricades, warning lights, cones, barriers, etc. must be submitted to the Town of Brookfield

Police Department for approval, as required. The cost of traffic controllers must be included in the prices bid. Also as per DOT requirements the work performed on state roads will be between the hours of 9:00 AM and 4:30 PM.

31. NON-COLLUSION; NO KICKBACKS - The Contractor warrants that no person has been employed or retained to solicit or secure the Agreement upon an agreement or understanding for a commission, percentage, brokerage or contingent fee; and that no Commissioner or any employee of the Owner has any interest, financially or otherwise, in the Contractor's organization.

IB-7

For breach or violation of this warranty, and without limiting any other remedies provided by law, the Owner shall have the right to terminate the Agreement without liability or at its discretion to deduct from the Contract Price or consideration, the full amount of such commission, percentage, brokerage or contingent fee.

32. PAYMENTS TO SUBCONTRACTORS - The Contractor must comply with Section 49-41a

(as more fully provided in Article 39 of the General Conditions) of the Connecticut General

Statutes, as to payment to subcontractors.

33. USE OF LOCAL LABOR - In the employment of mechanics, laborers, and workers, in the performance of the Contract, the Contractor shall give preference to citizens who are, and continuously for six months prior to the contract date, have been residents of the Town of

Brookfield; and if no such persons are available; then to residents of the State of Connecticut, if no such persons are available, then to residents of other States, in accordance with Section 31-

52, and 31-53 of the Connecticut General Statutes.

34. SAFETY - Bidders are notified that the Contractor shall be solely responsible for initiating, maintaining and supervising all safety precautions and programs necessary to the safe and proper performance of the work and that the Contractor shall be solely responsible for taking all necessary precautions to insure the safety of all employees, subcontractors and other persons, including the public, exposed to the contract work. The Contractor shall comply with all current safety requirements mandated by the Occupational Health and Safety Act (OSHA), the

Connecticut Department of Transportation (DOT), and any other applicable State statutes.

In addition to any other indemnification provisions contained in the Contract Documents, the Contractor shall at all times indemnify and save harmless the Owner, the Town of

Brookfield, The Water Pollution Control Authority, the Engineer, and their officers, agents and employees on account of and from any and all claims, damages, losses, judgments, worker's compensation payments, litigation expenses, and counsel fees arising out of injuries to any person (including death) or damage to property alleged to have been sustained by any person as a result of the acts, omissions, or neglect of the Contractor, its employees or subcontractors. The existence of insurance shall in no way limit the scope of this indemnification. The Contractor shall further be liable to the Owner, the Town of Brookfield, the Engineer, and their officers, agents and employees for all attorneys' fees, costs and other expenses incurred by it or them in enforcing this indemnity provision, provided however, that the Contractor is found to be liable for injury as a result of any act, omission or neglect by it or its employees or subcontractors.

Neither action nor inaction on the part of the Engineer or Owner, or their representatives, shall make them responsible for safe conditions, or make them liable for bodily injury or property damage on this project.

35. STATE REQUIREMENTS - If needed, the Contractor must obtain a General Permit for the

Discharge of Stormwater and Dewatering Waste waters from construction activities, as issued by the State Department of Energy and Environmental Protection.

IB-8

36. INLAND WETLANDS COMMISSION REQUIREMENTS – BWPCA and/or the project engineer will submit to the inland wetlands commission to obtain a wetland permit for construction. The contractor shall provided supplemental information to the application as applicable including but not limited to construction sequencing and dewatering submittal.

37 BORING LOGS – Boring logs previously conducted on the site are included in Appendix A.

38. PAYMENT OF TAXES, CHARGES AND ASSESSMENTS - Each person who submits a bid shall be deemed to have agreed that the Owner may apply payments otherwise properly due to such person to the reduction of all real estate or personal property taxes and/or sewer charges and assessments (including interest, fees and penalties thereon) owed to the town or Owner by such person, which taxes are delinquent and have been so delinquent for a period of not less than one (1) year. Prior to making any payment to any person awarded the contract, the

Owner shall ascertain from the Tax or Sewer Collector whether such person owes past due taxes on real or personal property or sewer charges or assessments and shall deduct from such payment the amount of taxes or charges (plus penalties, interest and fees thereon) which are delinquent and have been delinquent for a period of at least one (1) year as of the time of withholding.

39. EXEMPTION FROM TAXES - State and Local sales taxes on construction materials required for construction shall not be included in the bid. The Brookfield Water Pollution

Control Authority is exempt from payment of State and Compensating Use Taxes of the State of Connecticut on all materials sold to it, or for the project pursuant to the provisions of the

Contract Documents. The purchase by subcontractors of materials to be furnished pursuant to the provisions of the contract shall be a purchase for resale to the Contractor (either direct or through other subcontractors) and hence exempt from sales tax, regardless of the terms of the contract between the prime contractor and the subcontractor.

40. WIDTH OF OPERATIONS - The bidder’s attention is directed to the width limitations for operations in various portions of the project.

During construction, the Contractor will be required to perform operations as follows:

a) Where so indicated, no activities will be permitted outside the limits of disturbance.

Work must be confined to in-line operation, unless otherwise authorized in writing.

b) Limits of disturbance are to be clearly marked by silt fencing, or equivalent as shown on the drawings.

c) Staging areas are to be established, in field consultation between the Contractor, the

Engineer, and the WPCA representative. Such areas shall not exceed 2,000 sq. feet and are to be delineated by snow fencing.

P-1

PROPOSAL

TOWN OF BROOKFIELD, CONNECTICUT

777 Pump Station

Langan Job No. 190085123

WPCA CONTRACT NO. 2026-01

Brookfield Water Pollution Control Authority

53A Commerce Road

Brookfield, Connecticut 06804

Made by

P.O./ Address

Pursuant to and in compliance with your request for bids, the undersigned states that he has examined the Contract Documents and the site of the work, made all investigations which he has deemed necessary or desirable, and that he understands the purport and magnitude of the work intended, and the undersigned hereby offers to furnish all plant, labor, material, supplies, equipment, and other facilities and things necessary or proper for or incidental to the proper construction of the work advertised, and to construct the said work in strict accordance with the Contract Documents of which this Proposal is a part and such detailed directions, plans, and drawings as may be furnished from time to time during the progress of construction by the Engineer at the following prices, which prices include all incidental work including traffic control:

SCHEDULE OF PRICES

UNIT

UNIT PRICES

AMOUNT BID

ITEM EST. ITEM WITH (IN NUMBERS)

NO. QUANTITY UNIT PRICES

Dollars Cents Dollars Cents

(IN WORDS)

1 1 L. S.

Mobilization and Demobilization (see max. bid price allowed)

L.S.

P-2

AMOUNT BID

ITEM EST. ITEM WITH (IN NUMBERS)

NO. QUANTITY UNIT PRICES

Dollars Cents Dollars Cents

(IN WORDS)

2 1 L.S.

Removals

3 1 L.S.

Pump Station Installation

4 1 L.S.

Temporary Sewer Bypass

5 1 L.S.

Dewatering

6 20 C.Y.

Cast-In-Place Concrete

C.Y.

7 25 L.F.

6” Dia. DIP Force Main

L.F.

8 1 L.S.

10” Dia. PVC Sewer Pipe

9 1 L.S.

Modifications to Existing Manhole

P-3

AMOUNT BID

ITEM EST. ITEM WITH (IN NUMBERS)

NO. QUANTITY UNIT PRICES

Dollars Cents Dollars Cents

(IN WORDS)

10A 175 L.F.

Silt Fence

L.F.

10B 3 EA

Inlet Protection

EA

10C 8 C.Y.

Stabilized Construction Entrance

C.Y.

11 1 F.L.S.

Misc. Additional Work

Fifty Thousand Dollars

$50,000

F.L.S

12 1 L.S.

As-Built

P-4

AMOUNT BID

ITEM EST. ITEM WITH (IN NUMBERS)

NO. QUANTITY UNIT PRICES

Dollars Cents Dollars Cents

(IN WORDS)

13A 1 L.S.

Generator Installation

L.S.

13B 1 L.S.

Electrical Enclosure

13C 1 L.S.

VFD Installation

L.S.

13D 1 L.S.

Electrical Demolition

L.S.

13E 1 L.S.

Miscellaneous / Other Electrical

SUMMATION OF BASE BID ITEMS

DOLLARS

CENTS

P-5

The summation of the bid for this contract is based on the prices for the various items. This summation is made with the understanding that it is not a part of the bid and is solely a matter of information for convenience in comparing the bids at the time of opening.

The undersigned proposes to commence work within ten (10) calendar days of receipt of written notice to proceed from the Owner to do so, and shall complete the work in all respects except for maintenance and final pavement within one hundred and twenty (120) calendar days following service of said notice. The undersigned is also aware of the provision of payment to the Owner for liquidated damages should he fail to complete the work within the time stipulated above.

Accompanying this proposal, under separate cover, is a cashier's check, certified check or bid bond for ________________ dollars ($_________________) payable to the Owner.

In case this Proposal is accepted by the Owner and the undersigned shall fail to execute the

Contract with, and deliver Contract Bonds to the Owner in accordance with the information for Bidders, then the said cashier's check, certified check, or the amount of the Bid Bond shall become the property of the

Owner and shall be the maximum obligation of the Contractor or his Surety for the aforesaid failure of the

Contractor, otherwise it shall be returned to the undersigned upon request.

If written notice of the acceptance of this bid is mailed, telegraphed, or delivered to the undersigned within ninety (120) days after the date of opening of the bids, or any time thereafter before this bid is withdrawn, the undersigned shall, within ten (10) days after the date of such mailing, telegraphing, or delivering of such notice, execute and deliver a contract in the Form of Contract attached hereto, and

Contract Bonds as hereinafter specified. The undersigned hereby designates the above address as his office to which such notice of acceptance may be mailed, telegraphed or delivered.

The bidder hereby acknowledges the receipt of the following issues of addenda, if any, distributed by the Engineer:

Addendum No. _____ Dated __________ Addendum No. __________ Date __________

The Brookfield Water Pollution Control Authority reserves the right to reject any and all bids for any reason, to waive any informality in the bidding and to award the Contract to the lowest responsible and qualified bidder or the responsible and qualified bidder with the lowest combination of Base Bid and

Alternates, where applicable, selected by the Authority.

P-6

INFORMATION SHOWING QUALIFICATIONS FOR WORK:

THE BIDDER SHALL SUBMIT WITH HIS BID HIS MOST RECENT CERTIFIED FINANCIAL STATEMENT

The bidder shall here furnish the following summary information relative to his ability and financial resources available for the fulfillment of the Contract, if such be awarded to him:

How many consecutive years has he or they been engaged in the construction business under the present firm name?

When organized?

Where incorporated?

Credit available for this Contract $

Contracts in hand- Number

Gross Amount

List Permanent Field Personnel

List Construction Equipment Owned

Has the firm ever refused to sign a Contract at the original bid?

Has the firm ever defaulted on a Contract?

Has the firm ever been adjudged a bankrupt or been subject to a receivership or an order of reorganization? If so, give details and particulars

Is the business at this time subject to any court order relating to bankruptcy, receivership, liquidation or reorganization?

Does the bidder hold a current “DAS Contractor Prequalification Certificate” from the Connecticut

Department of Administrative Services?

If so, what is the single project limit for which the bidder is so qualified?___________________________

If so, what is the contractor category or categories in which the bidder is so prequalified?_____________

P-7

Is the bidder, or any affiliated entity, or principal stockholder or officer, indebted to the Town of Brookfield or to the Brookfield Water Pollution Control Authority on account of unpaid real or personal property taxes or on account of Sewer charges or assessments?

Financial Resources- Information relative to the firm’s financial resources can and may be obtained from the following: (Give name, business and address).

Listing of current contracts of comparable size:

Name or Location Value Contact & Tel. No.

Upon request, the bidder will be expected to amplify the foregoing statements as necessary to satisfy the Owner concerning the ability to successfully perform the work in a satisfactory manner.

The undersigned hereby certifies that no person interested in this proposal is directly or indirectly interested in or connected with any other bid or proposal for said work, and no member of the Owner or other officer or employee of the Owner is directly or indirectly interested therein, or in any portion thereof.

The undersigned hereby certifies that this bid is genuine and not collusive or sham; that said bidder has not colluded, conspired, connived, or agreed, directly or indirectly, with any bidder or person, to put in a sham bid, or that such other person shall refrain from bidding, and has not in any manner, directly or indirectly sought by agreement or collusion, or communication or conference, with any person, to fix the bid price of any other bidder, or to fix any overhead profit or cost element of said bid price, or of that of any other bidder, or to secure any advantage against the Owner or any person interested in the proposed

Contract; and that all statements contained in said proposal or bid are true; and further, that such bidder has not, directly or indirectly submitted this bid, or the contents thereof, or divulged information or data relative thereto to any association or to any member or agent thereof.

P-8

The undersigned hereby certifies that neither he nor his agent nor any other party for him has paid or agreed to pay, directly or indirectly, a person, firm or corporation any money or valuable consideration for assistance in procuring or attempting to procure the contract herein referred to, and further agrees that no such money or reward shall be hereafter paid.

Date Firm Name:**

By:

Title

Address

Seal

**Insert Bidder's name

If corporation, give the State of Incorporation, using the phrase "A corporation organized under the laws of

If a partnership, give names of the partners, using also, the phrase "Co-partners trading and doing business under the firm name and style of

If an individual using a trade name, give individual name, using also the phrase "An individual doing business under the firm name and style of

P-9

BIDDER'S AFFIDAVIT

(This Affidavit is part of the Proposal)

State of

SS:

County of

By:

being duly sworn, deposes and says that he resides at that he is the ________________________ of the

(Title) (Name of Bidder) who signed the above Proposal, that he was duly authorized to sign and that the bid is the true offer of the

Bidder; that the seal attached is the seal of the Bidder and that all the declarations and statements contained in the Proposal are true to the best of his knowledge and belief.

(/s/)

Subscribed and Sworn to before me this ____________ day of _______, 20___

(SEAL)

Notary Public

My Commission Expires

P-10

FORM OF

CONSENT OF SURETY/SURETY GUARANTY

(To accompany Proposal)

KNOW ALL MEN BY THESE PRESENTS, that for and in consideration of the sum of $1.00, lawful money of the United -States, the receipt whereof is hereby acknowledged, paid the undersigned corporation, and for other valuable consideration, the ________________________________________

(Name of Surety Company) a corporation organized and existing under the laws of the State of _____________________________ and licensed to do business in the State of Connecticut certifies and agrees, that if

________________________________________________________________________(Contract) is awarded to ____________________________________________________________

(Name of Bidder) the undersigned corporation will execute the Performance and Payment bond or bonds as required by the

Contract Documents and will become surety in the full amount of the Contract price for the faithful performance of the Contract and for payment of all persons supplying labor or furnishing materials in connection therewith.

(To be accompanied by the usual proof of authority of officers of surety company to execute the same).

P-11

BID BOND

KNOW ALL MEN BY THESE PRESENTS, That we, the undersigned as principal; and ______________________________as Surety, are hereby held and firmly bound unto the

__________________in the penal sum of $_______________ for the payment of which, well and truly to be made, we hereby jointly and severally bind ourselves, our heirs, executors, administrators, successors and assigns.

Signed this ________ day of _________20___

The condition of the above obligation is such that whereas the Principal has submitted to the owner as defined, a certain Bid, attached hereto, and hereby made a part hereof, to enter into a contract in writing, for

NOW, THEREFORE,

(A) If said Bid shall be rejected, or, in the alternate

(B) If said Bid shall be accepted and the Principal shall execute and deliver a contract in the form of

Contract attached hereto (properly completed in accordance with said Bid) and shall furnish a bond for his faithful performance of said Contract, and for the payment of subcontractors, laborers and material men, shall in all other respects perform the Agreement created by the acceptance of said Bid.

Then, this obligation shall be void, otherwise the same shall remain in force, and effect; it being expressly understood and agreed that the liability of the Surety for any and all claims hereunder shall, in no event, exceed the penal amount of this obligation as herein stated.

The Surety, for value received, hereby stipulates and agrees that the obligations of said Surety and its bond shall be in no way impaired or affected by any extension of the time within which the Principal may accept such Bid; and said Surety does hereby waive notice of any such extension.

IN WITNESS WHEREOF, the Principal and the Surety have set their hands and seals, and such of them as are corporations having caused their corporate seals to be hereto affixed and these presents to be signed by their proper officers, the day and year first set forth above.

Principal: ______________________ (L.S.)

Surety _________________________________ By: ___________________________

P-12

PERFORMANCE BOND

KNOW ALL MEN BY THESE PRESENTS:

THAT ________________________________________________, as Principal, hereinafter called Contractor, and

____________________________________________________ as Surety, are held and firmly bound unto the

Brookfield Water Pollution Control Authority as Obligee, hereinafter called the Owner, in the amount of

____________________________________________ Dollars ($________________), for the payment whereof

Contractor and Surety bind themselves, their heirs, executors, administrators, successors, and assigns, jointly and severally, firmly by these presents.

WHEREAS, Contractor has by written agreement dated ________________________ entered into a contract with the Owner for the pump station improvement project entitled Contract 2026-01 777 Pump Station, which contract with all its terms, covenants, conditions and stipulations is incorporated herein to form a part hereof as fully as if said contract was recited at length herein.

NOW, THEREFORE, the condition of this obligation is such that, if the Contractor shall promptly and faithfully perform said Contract, then this obligation shall be null and void; otherwise it shall remain in full force and effect.

PROVIDED, that any alterations which may be made in the terms of the contract, or in the work to be done under it, or the giving by the Owner of any extension of time for the performance of the contract, of any other forbearance on the part of either the Owner or the Contractor to the other shall not in any way release the Contractor and the Surety, or their successors or assigns from their liability hereunder. Notice to the

Surety of any such alterations, extension or forbearance is hereby expressly waived.

WHENEVER Contractor shall be, and declared by the Owner to be, in default under the Contract, the Owner having performed the Owners obligations thereunder, the Surety, upon written notice of such default, may promptly remedy the default or shall promptly:

1. Complete the Contract in accordance with its terms and conditions, by another contractor acceptable to the Owner, said other contractor to act as an agent of the Surety, or

2. Obtain a bid or bids for submission to the Owner for completing the Contract in accordance with its terms and conditions, and upon determination by the Owner and Surety of the lowest acceptable and responsible bidder, arrange for a contract between such bidder and the Owner, and make available as work progress sufficient funds to pay the cost of completion less the balance of the contract price (even though there should be a default or a succession of defaults under the contract or contracts of completion arranged under this paragraph), but not exceeding, including other costs and demands for which the surety may be liable hereunder, the amount set forth in the first paragraph hereof. The term, “balance of the contract price” as used in this paragraph shall mean the total amount payable by the

Owner to the Contractor under the Contract and any amendments thereto, less the amount properly paid by the Owner to Contractor.

IN WITNESS WHEREOF, the above-bounded parties have executed this instrument under their several seals this ______________ day of _____________________, 20___, the name and corporate seal of each corporate party being hereto affixed and these presents signed by its undersigned representative, pursuant to authority of its governing body.

IN THE PRESENCE OF:

P-13

__________________________________ _______________________________ L.S.

(Principal) (Affix Seal)

__________________________________ By____________________________

(Title)

__________________________________ _______________________________ L.S.

(Surety) (Affix Seal)

__________________________________ By____________________________

(Attorney-in-fact)

ACKNOWLEDGMENT OF PRINCIPAL

STATE OF _______________________ )

) ss.: _______________ ______________, 20___ COUNTY OF

Personally appeared ______________________ who acknowledged himself to be the

_______________________ of_______________________________ (Principal), that he knows the seal of said

Corporation; that the seal affixed to said instrument is such Corporate Seal, that it was so affixed to the resolution of the Board of Directors of said Corporation, and that he, as such __________________________ being authorized to do so, executed the foregoing instrument for the purposes therein contained, by signing the name of the corporation by himself as ________________.

In witness whereof I hereunto set my hand and seal.

ACKNOWLEDGMENT OF SURETY COMPANY

STATE OF __________________ )

) ss.: ________________ ______________, 20___

COUNTY OF ________________ )

________________________ of ________________________________ (Surety), that he knows the seal of said

Corporation; that the seal affixed to said instrument is such Corporate Seal, that it was so affixed to the resolution of…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .