2-_Specification_-_El_Portal_WWTP_Centrifuge_Controls_Replacement.pdf

PDF 8 MB Posted

Attached to
Yosemite - El Portal Centrifuge Replacement
Solicitation number
140P8523Q0056
Issued by

About this file

This is a solicitation for a centrifuge replacement project at Yosemite National Park's El Portal Wastewater Treatment Plant. The National Park Service is seeking to replace two existing centrifuge control panels and two centrifuge feed pump variable frequency drives. The solicitation involves removing and disposing of old equipment and installing new control panels and VFDs furnished by the government. Responses are due by May 2023 and award will be made to a single prime contractor. Pricing is fixed as a lump sum contract line item for all installation work.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

YOSEMITE NATIONAL PARK,

CALIFORNIA

CENTRIFUGE CONTROLS REPLACEMENT

YOSE 196146

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE (NPS)

DENVER SERVICE CENTER (DSC)

Instructions & Table of Contents (TOC) | NPS DSC Division 1 Specifications | 012822 page 1 of 1

NPS DSC Specifications Table of Contents

National Park Service (NPS) - Denver Service Center (DSC) | 1-28-22

Table of Contents (TOC)

01 11 00 Summary of Work

01 26 01 Contract Modification Procedures

01 27 00 Definition of Contract Line Items

01 31 00 Project Management and Coordination

01 32 16 Construction Schedule

01 32 33 Photo Documentation

01 33 23 Submittal Procedures

01 35 23 Safety Requirements

01 40 00 Quality Requirements

01 64 00 Owner-Furnished Products

Supplement: Manufacturer’s Certificate of Proper Installation

Supplement: Alfa Laval Quote QUHHG2022023R2

Supplement: Alfa Laval 480VAC Control Panel Layout Drawings

01 77 00 Closeout Procedures

26 05 02 Basic Electrical Requirements

26 05 04 Basic Electrical Materials and Methods

26 05 05 Conductors

26 05 26 Grounding and Bonding for Electrical Systems

26 05 33 Raceways and Boxes

26 08 00 Commissioning of Electrical Systems

YOSE 196416 SUMMARY OF WORK

MAY 2023 01 11 00 - 1

PW\DEN003\D3167637\CCR

NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 5-11-21

YOSE 196416

SECTION 01 11 00 – SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes the following:

1. Work Covered by Contract Documents.

2. Government-Furnished Materials.

3. Contractor Use of Site.

4. Occupancy Requirements for Buildings.

5. Conduct of Operations.

6. Work Restrictions.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Yosemite National Park, El Portal Wastewater Treatment Plant.

B. The Work consists of: Install NPS furnished Centrifuge Control Panels and Sludge Feed Pump

Variable Frequency Drives (VFDs). Make other electrical modifications as shown on Drawings to integrate new components.

C. Project will be constructed under a single prime contract.

1.3 GOVERNMENT-FURNISHED MATERIALS

A. In case of Government-furnished materials:

1. Government will arrange and pay for delivery of Government-furnished items.

2. Government will inspect delivered items for damage after delivery.

3. Government will arrange for replacement if Government-furnished items are damaged, defective, or missing.

4. If Government-furnished items are damaged as a result of Contractor’s operations, Contractor shall repair or replace them.

5. Contractor shall install and otherwise incorporate Government-furnished items into Work.

6. See Section 01 64 00, Owner-Furnished Products, for additional information.

MAY 2023 01 11 00 - 2

PW\DEN003\D3167637\CCR

B. Government-Furnished Materials:

1. (2) Each Centrifuge Control Panels.

2. (2) Each Sludge pump VFDs.

1.4 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of site for construction operations. Limit use of premises to areas within the Construction limits indicated on Drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to areas shown on Drawings.

B. Storage of Materials: Confine storage of materials to Work areas.

C. Parking: Confine parking to areas designated by Contracting Officer.

D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to

Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

1.5 OCCUPANCY REQUIREMENTS FOR BUILDINGS

A. Existing Buildings:

1. Full Government Occupancy: Government will occupy buildings under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform Work so as not to interfere with Government’s day-to-day operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Contracting Officer.

b. Maintain existing building in weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and occupants during construction period.

1.6 CONDUCT OF OPERATIONS

A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.

MAY 2023 01 11 00 - 3

PW\DEN003\D3167637\CCR

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 7 calendar days in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.7 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:30 a.m. to 4:00 p.m., Monday through Friday, except when otherwise indicated.

B. Work Sequencing:

1. Replace and commission non-functioning centrifuge control panel and sludge pump VFD prior to replacing and commissioning the second centrifuge control panel and sludge pump

VFD generally in the following steps:

a. Demolish non-functioning centrifuge control panel.

b. Install and test connections of new control panel and one new pump VFD.

c. Coordinate with Contracting Officer and Government-furnished equipment supplier to test and commission new control panel and pump VFD.

d. Demolish second centrifuge control panel.

e. Install and test connections of second new centrifuge control panel and sludge pump

VFD.

f. Coordinate with Contracting Officer and Government-furnished equipment supplier to test and commission second new centrifuge control panel and sludge pump VFD.

2. Coordinate with Contracting Officer and Government-furnished equipment supplier for alternate work sequencing plans if longer equipment outages are allowed to install and test equipment in one step.

C. Existing Utilities:

1. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

2. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the Contract.

D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within

25 feet of entrances, operable windows, or outdoor air intakes.

MAY 2023 01 11 00 - 4

PW\DEN003\D3167637\CCR

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 01 11 00

YOSE 196416 CONTRACT MODIFICATION PROCEDURES

MAY 2023 01 26 01 - 1

PW\DEN003\D3167637\CCR

NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21

YOSE 196416

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section consists of administrative and procedural requirements for Contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Costs incurred in support of all of a Contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent.

2. Utilities.

3. Furnishings.

4. Office equipment.

5. Executive and management staff not exclusively assigned to the Project.

6. Support, accounting, and administrative staff.

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications.

8. Estimating and preconstruction services.

9. Mortgage costs.

10. Real estate and corporate taxes.

11. Automobile maintenance and travel costs for home office personnel.

12. Home office insurances i.e., structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets.

14. Home office supplies (paper, staples, etc.)

15. Legal services.

16. Accounting and data processing.

17. Professional fees/registration.

MAY 2023 01 26 01 - 2

PW\DEN003\D3167637\CCR

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a Contract Time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager (PM), Assistant Project Manager.

2. Superintendent, Assistant Superintendent.

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers.

5. Travel, lodging, and per diem (as established by Federal Travel Regulations).

6. Scheduling.

C. General Requirements: Costs directly associated with the Project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.

The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting.

2. Material handling.

3. Temporary fencing.

4. Port-a-lets.

5. Trash removal, dumpsters.

6. Barricades.

7. Small tools.

8. Safety supplies.

9. Scaffolding.

10. Daily cleaning.

11. Traffic control.

12. Temporary signage.

13. Temporary heating and power.

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on Project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: The hourly rate paid directly to the worker.

b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:

1) Social Security.

2) Medicare.

3) Workers Compensation – Policy and company calculation to be made available.

MAY 2023 01 26 01 - 3

PW\DEN003\D3167637\CCR

4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.

5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.

6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums.

2) Cell Phone.

3) Clothing.

4) 401K and Pensions.

5) Vehicle allowances.

6) Gas allowance.

7) Life insurance premiums.

8) Disability insurance.

9) Other Fringe Benefits required under an enforceable collective bargaining agreement.

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the Project.

Include as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of Contractor to submit within the time frame specified will not be compensable.

2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank

MAY 2023 01 26 01 - 4

PW\DEN003\D3167637\CCR

Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or Contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.

3. Requests for extensions of Contract Time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 16, Construction Schedule, for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.

5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. Labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by NPS.

D. Equipment:

1. Equipment used for the Project must be appropriately sized for work being performed.

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.

http://www.nps.gov/dscw/publicforms.htm

MAY 2023 01 26 01 - 5

PW\DEN003\D3167637\CCR

3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.

6. Standby unit rates used in accordance with Paragraph 1.3, D, 3, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.

8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.

Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the Contract Documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this Project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10% Profit…………………4.35%

2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25 percent. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

MAY 2023 01 26 01 - 6

PW\DEN003\D3167637\CCR

3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to Paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

PART 2 - PRODUCTS (NOT USED)

END OF SECTION 01 26 01

YOSE 196416 DEFINITION OF CONTRACT LINE ITEMS

MAY 2023 01 27 00 - 1

PW\DEN003\D3167637\CCR

NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21

YOSE 196416

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. Section explains in general, what is and is not included in a Contract line item, and limits or cut-off points where one item ends and another begins.

B. If no Contract line item exists for a portion of work, include costs in a related item.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item Number 0001 Installation of Centrifuge Control Panels:

1. This item consists of All work associated with removal and disposal of two (2) existing centrifuge control panels and two (2) centrifuge feed pump variable frequency drives; and installation of two (2) new NPS furnished centrifuge control cabinets, including all wiring and controls; and two (2) new variable frequency drives for the centrifuge feed pumps.

2. Measurement for payment will be portion of work completed.

3. Payment will be made at the Contract lump sum price.

END OF SECTION 01 27 00

YOSE 196416 PROJECT MANAGEMENT

MAY 2023 AND COORDINATION

PW\DEN003\D3167637\CCR 01 31 00 - 1

NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21

YOSE 196416

SECTION 01 31 00 – PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions.

2. Construction Coordination.

3. Submittals.

4. Coordination Drawings.

5. Requests for Information (RFIs).

6. NPS/DSC Project Website.

7. Project Meetings.

B. Related Requirements:

1. Section 01 32 16, Construction Schedule for preparing and submitting Contractor’s construction schedule.

2. Section 01 77 00, Closeout Procedures for coordinating closeout of the Contract.

1.2 DEFINITIONS

A. Agency with Jurisdiction.

1.3 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.

http://www.nps.gov/dscw/definitionsdc_a.htm

PW\DEN003\D3167637\CCR 01 31 00 - 2

3. Coordinate work, including testing requirements listed in Division 26 specifications, with

Government-Furnished equipment supplier.

a. If electrical testing is incomplete or installation is incorrect and results in additional site visits by the Government-Furnished equipment supplier, all costs for the additional work and site visits will be paid for by the Contractor.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:

1. Preparation of Contractor’s Construction Schedule.

2. Delivery and processing of submittals.

3. Progress meetings.

4. Pre-installation conferences.

5. Project closeout activities.

1.4 SUBMITTALS

A. Division 1 Documents: The following items shall be submitted a minimum of one week prior to

Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for Pre-

Construction Conference.

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. Accident Prevention Plan.

4. A List of Subcontractors for this Project.

5. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.

6. Certificates of Insurance or SF1413 for Contactor and all Subcontractors.

7. Quality Control Plan.

B. Provide items listed to Contracting Officer before Pre-Construction Conference. If all documents have not been received one week prior to scheduled Pre-Construction Conference date, conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.

PW\DEN003\D3167637\CCR 01 31 00 - 3

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of

Contract Documents, Contractor shall prepare and submit an RFI utilizing form created on

NPS/DSC management software website.

1. Contracting Officer will not respond to RFIs submitted by other entities controlled by

Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor’s suggested resolution: If Contractor’s suggested resolution impacts Contract

Time or Contract Sum, Contractor shall state impact in RFI.

8. Contractor’s signature.

9. Requested date for response.

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

C. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor’s means and methods.

d. Requests for coordination information already indicated in Contract Documents.

e. Requests for adjustments in Contract Time or Contract Sum.

f. Requests for interpretation of Architect’s/Engineer’s actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Contracting Officer’s action may include a request for additional information; time for response will date from time of receipt of additional information.

3. Contracting Officer’s action on RFIs may result in need for a change to Contract Time or

Contract Sum. All Contract changes will be processed following terms and conditions of

Contract.

PW\DEN003\D3167637\CCR 01 31 00 - 4

1.6 PROJECT DOCUMENT MANAGEMENT SOFTWARE

A. Use NPS/DSC designated Microsoft Teams® folder for communication throughout Contract

Period on:

1. Project directory.

2. Project correspondence.

3. Meeting agendas and minutes.

4. Contract modifications forms and logs.

5. RFI form and processing.

6. Task and issue management.

7. Photo documentation.

8. Baseline schedule, schedule updates, and calendar management.

9. Submittal form and processing.

10. Payment coordination documentation.

11. Drawing and specification document hosting, viewing, and updating.

12. Online document collaboration.

13. Reminder and tracking functions.

14. Archiving functions.

15. Notification of submittal and RFI statuses and current responsible party.

B. Some documents are not suitable to be shared using the NPS/DSC management software.

Documents containing Personal Identifying Information (PII) (i.e., certified payrolls) shall not be shared using NPS/DSC management software and shall be coordinated with Project team as appropriate.

C. Submit to Contracting Officer a list of employees who will need access to the Teams® folder.

Users will receive an invitation to register from Department of Interior (DOI). Once registered on

DOI website, user will be given access to NPS/DSC management software folder.

1.7 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. Meeting agenda will include the following as a minimum:

1. Roles & Responsibilities / Lines of Authority.

2. Park rules and regulations.

3. Jobsite Safety.

4. Resolution of comments on required Division 1 documents.

5. Coordination of Subcontractors.

6. Labor law application.

7. Modifications.

8. Payments to Contractor.

9. Payroll reports.

10. Contract Time.

11. Contractor Performance Evaluation.

12. Notice to proceed.

13. Correspondence procedures.

14. Acceptance/rejection of work.

PW\DEN003\D3167637\CCR 01 31 00 - 5

15. Progress meetings.

16. Submittal procedures.

17. Saturday, Sunday, holiday and night work.

B. Progress Meetings: Contracting Officer will schedule weekly meetings with Contractor.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the

Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:

a. Approval of minutes of previous meetings.

b. Submittal status.

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications.

f. Work in progress and projected.

g. Construction Schedule update.

h. Other business relating to work.

3. Progress Meetings may be omitted at the Contracting Officer’s discretion if detailed Daily

Reports, including photographs, are submitted each day. See Section 01 40 00, Quality

Requirements for additional details.

PART 2 - PRODUCTS (NOT USED)

END OF SECTION 01 31 00

YOSE 196416 CONSTRUCTION SCHEDULE

MAY 2023 01 32 16 - 1

PW\DEN003\D3167637\CCR

NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 5-11-21

YOSE 196416

SECTION 01 32 16 – CONSTRUCTION SCHEDULE

PART 1 - GENERAL

1.1 SUMMARY

A. Section consists of Construction Schedule requirements including:

1. Construction Schedule Requirements.

B. Purpose: The Construction Schedule ensures adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. It shall assist the Contractor and

Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing Contractor’s monthly progress payments. It shall include the dates in the contract, phases, milestones, occupancies, holidays, weather consideration, a critical path, and the requirements of this section.

1.2 DEFINITIONS

A. Activity: A discrete part of a project identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Critical Path Method (CPM): Method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

C. Critical Path: Longest connected chain of interdependent activities through the network schedule that establishes minimum overall Project duration and contains no float.

MAY 2023 01 32 16 - 2

PW\DEN003\D3167637\CCR

D. Float: Measure of leeway in starting and completing an activity.

1. Float: Not for the exclusive use or benefit of the Government or Contractor but is jointly owned.

2. Free Float: Amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

3. Total Float: Measure of leeway in starting or completing an activity without adversely affecting planned Project completion date.

E. Resource Loading: Allocation of manpower and equipment necessary for completion of an activity as scheduled.

F. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.

1.3 SUBMITTALS

A. Electronic Copies: Schedules and reports submitted shall be posted on the NPS/DSC management software website in native electronic file formats. The intent of the Government is to limit the number of printed reports to those determined by the project team as essential.

B. Construction Baseline Schedule: After Contract award and before Pre-Construction conference, submit two paper copies of baseline schedule, large enough to show entire schedule for entire construction period.

1.4 QUALITY ASSURANCE

A. Contractor shall meet with Contracting Officer on day of the preconstruction conference to go over:

1. Review software limitations, content and format for reports.

2. Review time required for review of submittals and re-submittals.

3. Review time required for completion and startup procedures.

4. Review and finalize list of construction activities to be included in schedule.

5. Review baseline schedule comments, resolve issues and progress on incorporating them

1.5 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors, including inspection and startup services performed by the Government-Furnished Equipment supplier.

MAY 2023 01 32 16 - 3

PW\DEN003\D3167637\CCR

PART 2 - PRODUCTS

2.1 CONSTRUCTION SCHEDULE REQUIREMENTS

A. General:

1. Develop and finalize Construction Baseline Schedule so it can be accepted for use no later than 10 days after date established for the Notice of Award.

a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing work within applicable completion dates, regardless of Governments acceptance of schedule.

2. Establish procedures for monitoring and updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.

B. Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work.

1. Activities: Indicate estimated duration, sequence requirements, and relationship of each activity in relation to other activities.

2. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the schedule within the limitations of the Contract Time.

3. Show sequence and interdependence of activities required for completion of work. Ensure work sequences are logical and Construction Baseline Schedule shows a coordinated plan of the work.

4. Time Frame: Proposed duration assigned to each activity shall be Contractor’s best estimate of time required to complete activity considering the scope and resources planned for activity.

a. An early finish date may be shown but the late finish date shall be same date as last day of Contract period. An early completion schedule shall contain:

1) Insert an activity titled “Project Float” as a successor to last activity in early project completion schedule network.

2) Add a milestone titled “Contract End Date” as a successor to the activity

“Project Float”.

3) Add duration to the activity “Project Float” as required so the milestone

“Contract End Date” equals the last day of Contract Period.

b. Contract completion date shall not be changed by submission of a schedule that shows an early completion date.

c. Contractor shall limit use of lead or lag duration’s between schedule activities.

d. Activity Duration: Define so no activity is longer than 14 days, except for non-construction activities including mobilization, shop drawings and submittals, fabrication and delivery of materials and equipment.

MAY 2023 01 32 16 - 4

PW\DEN003\D3167637\CCR

e. Submittal Review Time: Include review and re-submittal times indicated.

Coordinate submittal review times in Construction Baseline Schedule.

f. Startup and Testing Time: Include not less than 5 days for startup and testing.

g. Substantial Completion: Allow time for Government administrative procedures necessary for certification of Substantial Completion. (For more information, refer to Section 01 77 00, Closeout Procedures.)

5. Constraints: Include constraints and work restrictions indicated in Contract Documents and as follows in schedule and show how the sequence of Work is affected.

C. Joint Review, Revision, and Acceptance:

1. Within 7 calendar days of receiving Contractor’s proposed Construction Baseline

Schedule, Contracting Officer shall review initial Construction Baseline Schedule.

2. Within seven calendar days after review, Contractor shall revise and resubmit Construction

Baseline Schedule in accordance with comments presented from review.

3. In the event the Contractor fails to define any element of work, activity, or logic, and the

Contracting Officer review does not detect this omission or error, such omission or error, when discovered by Contractor or Contracting Officer, shall be corrected by Contractor within 7 calendar days and shall not affect Contract period.

4. Upon acceptance of the Construction Baseline Schedule, Contracting Officer saves schedule as a baseline and updates on a monthly basis. Construction schedule update will be used to evaluate Contractor’s monthly applications for payment based upon information developed at monthly Construction Schedule update meeting.

PART 3 - EXECUTION

3.1 CONSTRUCTION SCHEDULE UPDATES

A. Progress Meeting Updates: Provide a 2-week look-ahead schedule, derived from the currently accepted schedule, before each weekly progress meeting. Utilize look-ahead schedule to facilitate and take notes on discussions held during progress meeting.

B. 2-Week Schedule Updates:

1. General: Update Construction Schedule every 2 weeks to reflect construction progress and activities throughout entire Contract period and until Project substantial completion. The status date of each schedule update shall be the 7th and 21st day preceding the progress payment request date.

END OF SECTION 01 32 16

YOSE 196416 PHOTO DOCUMENTATION

MAY 2023 01 32 33 - 1

PW\DEN003\D3167637\CCR

NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21

YOSE 196416

SECTION 01 32 33 – PHOTO DOCUMENTATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for:

1. Existing condition images.

2. Periodic construction images.

B. See Section 01 77 00, Closeout Procedures for a complete listing of closeout documents.

1.2 SUBMITTALS

A. Construction Images: Submit images electronically within 2 days of taking the image. Include:

1. Date, time and number (sequentially number all images) in filename.

2. Description of vantage point, indicating location, direction (by compass point), and elevation or story of construction.

3. Submit digital images exactly as originally recorded in digital camera, without alteration, or modifications using image-editing software.

B. Closeout: Submit complete set of digital image electronic files as a Project Record Document.

PART 2 - PRODUCTS

2.1 FORMAT REQUIREMENTS

A. Images: Provide sRGB (standard Red Green Blue) color images in JPEG (Joint Photographic

Experts Group) format. Minimum sensor size of 8 megapixels, and at image resolution of not less than 1600 by 1200, and 300 dpi (dots per inch).

B. Upload images to Microsoft Teams folder designated by the Contracting Officer.

YOSE 196416 PHOTO DOCUMENTATION

MAY 2023 01 32 33 - 2

PW\DEN003\D3167637\CCR

PART 3 - EXECUTION

3.1 CONSTRUCTION IMAGES

A. General: Take digital images using the maximum range of depth of field, in-focus, to clearly show the Work. No blurry or out-of-focus areas accepted.

1. Maintain index with each set of Construction images and identify the number, date, time, and description for each.

2. Maintain one set of images accessible in field office at Project site available for reference.

B. Existing Condition Images: Before starting construction, take color digital images of Project site and surrounding properties, including existing items to remain during construction, from different vantage points.

1. Take at least fifteen separate images to show existing conditions adjacent to construction area before starting Work.

C. Additional Images: Contracting Officer may issue requests for additional images.

1. Three days advance, where feasible.

2. In emergency situations, take additional images within 24 hours of request.

3. Additional images include, but are not limited to:

a. Immediate follow-up when on-site events result in construction damage or losses.

b. Fabrication locations away from Project site.

c. Substantial Completion of a major phase or component of Work.

d. Extra record images at time of final acceptance.

END OF SECTION 01 32 33

YOSE 196416 SUBMITTAL PROCEDURES

MAY 2023 01 33 23 - 1

PW\DEN003\D3167637\CCR

NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 10-19-21

YOSE 196416

SECTION 01 33 23 – SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.

1.2 DEFINITIONS

A. Action Submittals: Written, graphic information, and physical samples that require Government’s responsive action.

B. Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with requirements.

C. File Transfer Protocol (FTP): Communications protocol that enables transfer of files to and from another computer over a network and that serves as the basis for standard Internet protocols. An

FTP site is a portion of a network located outside of network firewalls within which internal and external users are able to access files.

D. Portable Document Format (PDF): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.

1.3 GENERAL SUBMITTAL PROCEDURES

A. General: Prepare and submit submittals required by individual specification sections and in some cases as requested in Drawings. Types of submittals are indicated in individual specification sections.

1. Contracting Officer (CO) reserves right to require submittals in addition to those called for in individual sections.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review for legibility, accuracy, completeness, and compliance with

Contract Documents.

1. Coordinate submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

MAY 2023 01 33 23 - 2

PW\DEN003\D3167637\CCR

2. Coordinate transmittal of different types of submittals for related parts of Work so processing will not be delayed because of need for concurrent review coordination.

a. Contracting Officer reserves right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

C. Submittal List: Submittal list is attached to the end of this section. The intent is to provide an overall summary of submittal requirements. The requirements of individual specification sections and terms and conditions of the Contract still apply regardless of what is shown on submittal list.

D. Processing Time: Allow time for submittal review, including time for re-submittals, as follows.

Time for review shall commence when e-mail notification is received by Contracting Officer (or designee) indicating submittal has been posted on NPS management software website and is ready for review. When Contracting Officer has completed review, e-mail notification will be sent to

Contractor indicating submittal has been processed. No extension of Contract Time will be authorized because of failure to transmit submittals in advance of Work to permit processing, including re-submittals.

1. Action Submittals:

a. Initial Review: Allow 30 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.

b. Re-submittal Review: Allow 20 days for review of each re-submittal.

2. Informational Submittals:

a. Review: Allow 10 days for review of each submittal.

E. Approved Equals:

1. For each item proposed as an “approved equal,” submit supporting data, including:

a. Drawings and samples as appropriate.

b. Comparison of the characteristics of the proposed item with that specified.

c. Changes required in other elements of the work because of the substitution.

d. Name, address, and telephone number of vendor.

e. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.

2. A request for approval constitutes a representation that Contractor:

a. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.

b. Will provide the same warranties for the proposed item as for the item specified.

c. Has determined that the proposed item is compatible with interfacing items.

d. Will coordinate installation of an approved item and make changes required in other elements of the work because of the substitution.

MAY 2023 01 33 23 - 3

PW\DEN003\D3167637\CCR

e. Waives claims for additional expenses that may be incurred as a result of the substitution.

F. Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:

1. Transmittal Form (CM-16): All submittals shall be transmitted using National Park

Service Transmittal Form (CM-16). The form can be downloaded from the DSC

Workflows website’s Submittal Review page and completed on the NPS/DSC management software website. No action will be taken on a submittal item unless accompanied by this Transmittal Form.

a. Complete the general information at the top of form.

b. Provide all required information based on submittal type.

c. Attach all related documents.

d. Sign the Contractor section at bottom of the Transmittal Form (CM-16).

2. Physical Samples: Complete Transmittal Form (CM-16) on the NPS/DSC management software website as described above. Deliver physical sample to the Contracting Officer

(or designee) on site for processing. All comments and actions will be documented on the

Transmittal Form (CM-16) on the NPS/DSC management software website.

G. Identification: Submittal number or other unique identifier, including revision identifier.

1. Submittal number shall use a sequential number (e.g., .001). Re-submittals shall include alphabetic suffix after another decimal point (e.g., .001.A).

H. Re-submittals: Make re-submittals using same process used with initial submittal.

1. Note date and content of previous submittal.

2. Note date and content of revision in the title block on the Transmittal Form (CM-16) and clearly indicate extent of revision.

3. Re-submit submittals until they are marked “Approved” or “Approved with notations”.

I. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, and others as necessary for performance of construction activities.

J. Use for Construction: Use only final submittals with mark indicating “Approved” or “Approved with notations”. Ensure notations have been incorporated and, at a minimum, keep one copy of final approved submittal on site for use during construction.

1.4 CONTRACTOR’S USE OF CAD/BIM FILES

A. General: At Contractor’s written request, copies of CAD (Computer Aided Design)/BIM

(Building Information Modeling) files will be provided to Contractor for Contractor’s use in connection with Project, subject to:

1. Files provided as is; no format or other changes to files or changes to objects in the drawing will be done by the Government.

https://www.nps.gov/dscw/con_subreview21.htm

MAY 2023 01 33 23 - 4

PW\DEN003\D3167637\CCR

PART 2 - PRODUCTS

2.1 ACTION SUBMITTALS

A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each submittal to show which products and options are applicable.

3. As applicable, include:

a. Manufacturer’s product specifications.

b. Manufacturer’s Installation Instructions: When Contract Documents require compliance with manufacturer’s printed instructions, provide one complete set of instructions to Contracting Officer and keep another complete set of instructions at the Project site until substantial completion.

c. Manufacturer’s Catalog Cuts: Submit only pertinent pages; mark each page of standard printed data to identify specific products proposed for use.

d. Wiring diagrams showing factory-installed wiring.

e. Printed performance curves.

f. Operational range diagrams.

g. Compliance with specified referenced standards.

h. Testing by recognized testing agency.

4. Submit product data in PDF (portable document format) file format before or concurrent with samples.

B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base

Shop Drawings on reproductions of the…

This is the start of the file's text. The full file is on GovTribe.