2 Construction Template FAC 2022-08 NWWP92702300048.docx
DOCX document 7 MB Posted
- Solicitation number
- NWWP92702300048SML
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2 AMENDED Construction Template FAC 2022-08 NWWP92702300048.docx | DOCX document | |
| 2 AMENDED Construction Template FAC 2022-08 NWWP92702300048.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION PURCHASE ORDER CLAUSES
(FIXED-PRICE)
UPDATED THROUGH FAC 2022-08 (OCT 2022) (DEVIATION 2022-02) (NOV 2021)
FEDERAL ACQUISITION REGULATION (FAR) CLAUSES
FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address:
https://www.acquisition.gov/far/index.html
(End of Clause)
FAR 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the date of the clause.
(b) The use in this solicitation or contract of any Department of Commerce (48 CFR 1352) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the name of the regulation.
(End of clause)
| CLAUSE NUMBER |
| TITLE |
| DATE |
| FAR 52.203-19 |
| Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements |
| JAN 2017 |
| FAR 52.204-9 |
| Personal Identity Verification of Contractor Personnel |
| JAN 2011 |
| FAR 52.204-10 |
| Reporting Executive Compensation and First-Tier Subcontract Awards |
| JUN 2020 |
| FAR 52.204-13 |
| System for Award Management Maintenance |
| OCT 2018 |
| FAR 52.204-19 |
| Incorporation by Reference of Representations and Certifications |
| DEC 2014 |
| FAR 52.204-23 |
| Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities. |
| NOV 2021 |
| FAR 52.204-25 |
| Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment |
| NOV 2021 |
| FAR 52.209-6 |
| Protecting The Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment |
| NOV 2021 |
| FAR 52.209-10 |
| Prohibition on Contracting with Inverted Domestic Corporations |
| NOV 2015 |
| FAR 52.219-6 |
| Notice of Total Small Business Set-Aside |
| NOV 2020 |
| FAR 52.219-13 |
| Notice of Set-Aside of Orders |
| MAR 2020 |
| FAR 52.219-28 |
| Post-Award Small Business Program Rerepresentation |
| OCT 2022 |
| FAR 52.219-32 |
| Orders Issued Directly Under Small Business Reserves |
| MAR 2020 |
| FAR 52.222-3 |
| Convict Labor |
| JUN 2003 |
| FAR 52.222-6 |
| Construction Wage Rate Requirement |
| AUG 2018 |
| FAR 52.222-7 |
| Withholding of Funds |
| MAY 2014 |
| FAR 52.222-8 |
| Payrolls and Basic Records |
| JUL 2021 |
| FAR 52.222-9 |
| Apprentices and Trainees |
| JUL 2005 |
| FAR 52.222-10 |
| Compliance with Copeland Act Requirements |
| FEB 1988 |
| FAR 52.222-11 |
| Subcontracts (Labor Standards) |
| MAY 2014 |
| FAR 52.222-12 |
| Contract Termination - Debarment |
| MAY 2014 |
| FAR 52.222-13 |
| Compliance with Construction Wage Rate Requirements and Related Regulations |
| MAY 2014 |
| FAR 52.222-14 |
| Disputes Concerning Labor Standards |
| FEB 1988 |
| FAR 52.222-15 |
| Certification of Eligibility |
| MAY 2014 |
| FAR 52.222-19 |
| Child Labor—Cooperation with Authorities and Remedies (Deviation 2020-11) (Aug 2020) |
| JAN 2022 |
| FAR 52.222-21 |
| Prohibition of Segregated Facilities |
| APR 2015 |
| FAR 52.222-26 |
| Equal Opportunity |
| SEPT 2016 |
| FAR 52.222-27 |
| Affirmative Action Compliance Requirements for Construction |
| APR 2015 |
| FAR 52.222-36 |
| Equal Opportunity for Workers with Disabilities |
| JUN 2020 |
| FAR 52.222-50 |
| Combating Trafficking in Persons |
| JAN 2022 |
| FAR 52.222-55 |
| Minimum Wages Under Executive Order 14026 |
| JAN 2022 |
| FAR 52.222-62 |
| Paid Sick Leave Under Executive Order 13706 |
| JAN 2022 |
| FAR 52.223-2 |
| Affirmative Procurement of Biobased Produces Under Service and Construction Contracts |
| SEPT 2013 |
| FAR 52.223-5 |
| Pollution Prevention and Right-to-Know Information (Alternate I) (AUG 2003) |
| MAY 2011 |
| FAR 52.223-15 |
| Energy Efficiency in Energy-Consuming Products |
| MAY 2020 |
| FAR 52.223-17 |
| Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts |
| AUG 2018 |
| FAR 52.223-18 |
| Contractor Policy to Ban Text Messaging |
While Driving
JUN 2020
| FAR 52.225-13 |
| Restrictions on Certain Foreign Purchases |
| FEB 2021 |
| FAR 52.227-4 |
| Patent Indemnity-Construction Contracts |
| DEC 2007 |
| FAR 52.228-11 |
| Pledges of Assets (Deviation 2020-05) (April 2020) |
| FEB 2021 |
| FAR 52.228-14 |
| Irrevocable Letter of Credit |
| NOV 2014 |
| FAR 52.232-5 |
| Payments under Fixed Price Construction Contracts |
| MAY 2014 |
| FAR 52.232-23 |
| Assignment of Claims |
| MAY 2014 |
| FAR 52.232-27 |
| Prompt Payment for Construction Contracts |
| JAN 2017 |
| FAR 52.232-33 |
| Payment by Electronic Funds Transfer--System for Award Management. |
| OCT 2018 |
| FAR 52.232-39 |
| Unenforceability of Unauthorized Obligations |
| JUN 2013 |
| FAR 52.232-40 |
| Providing Accelerated Payments to Small Business Subcontractors (Deviation 2020-05) (April 2020) |
| NOV 2021 |
| FAR 52.233-1 |
| Disputes |
| MAY 2014 |
| FAR 52.233-3 |
| Protest After Award |
| AUG 1996 |
| FAR 52.233-4 |
| Applicable Law for Breach of Contract Claim |
| OCT 2004 |
| FAR 52.236-2 |
| Differing Site Conditions |
| APR 1984 |
| FAR 52.236-3 |
| Site Investigation and Conditions Affecting the Work |
| APR 1984 |
| FAR 52.236-5 |
| Material and Workmanship |
| APR 1984 |
| FAR 52.236-7 |
| Permits and Responsibilities |
| NOV 1991 |
| FAR 52.236-8 |
| Other Contracts |
| APR 1984 |
| FAR 52.236-9 |
| Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements |
| APR 1984 |
| FAR 52.236-10 |
| Operations and Storage Areas |
| APR 1984 |
| FAR 52.236-12 |
| Cleaning Up |
| APR 1984 |
| FAR 52.236-26 |
| Preconstruction Conference |
| FEB 1995 |
| FAR 52.242-14 |
| Suspension of Work |
| APR 1984 |
| FAR 52.243-5 |
| Changes and Changed Conditions |
| APR 1984 |
| FAR 52.244-6 |
| Subcontracts for Commercial Products and Commercial Services |
| JAN 2022 |
| FAR 52.246-12 |
| Inspection of Construction |
| AUG 1996 |
| FAR 52.246-21 |
| Warranty of Construction |
| MAR 1994 |
| FAR 52.248-3 |
| Value Engineering-Construction |
| OCT 2020 |
| FAR 52.249-1 |
| Termination for Convenience of the Government (Fixed-Price) (Short Form) |
| APR 1984 |
| FAR 52.249-10 |
| Default (Fixed-Price Construction) |
| APR 1984 |
| FAR 52.253-1 |
| Computer Generated Forms |
| JAN 1991 |
FAR 52.211-10 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days from the date of award, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 calendar days from notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of Clause)
FAR 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)
(a) Definitions. As used in this clause—
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if–
(A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference. (1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
NONE
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i)The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical components.
(1)The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(2)For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.
(3)The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.
(B) For domestic construction material that is a critical item or contains critical components. (1)The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.
(2)For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.
(3)The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute. (1) (i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
FOREIGN AND DOMESTIC CONSTRUCTION MATERIALS PRICE COMPARISON
| Construction Material Description |
| Unit of Measure |
| Quantity |
| Price (Dollars)* |
Item 1:
| Foreign construction material |
| _______ |
| _______ |
| _______ |
| Domestic construction material |
| _______ |
| _______ |
| _______ |
| Item 2: |
| _______ |
| _______ |
| _______ |
| Foreign construction material |
| _______ |
| _______ |
| _______ |
Domestic construction material
[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.]
FAR 52.228-13 ALTERNATIVE PAYMENT PROTECTIONS (JULY 2000)
(a) The Contractor shall submit one of the following payment protections:
· Irrevocable Letter of Credit
· Payment Bond
(b) The amount of the payment protection shall be 100 percent of the contract price.
(c) The submission of the payment protection is required within ten (10) days of contract award.
(d) The payment protection shall provide protection for the full contract performance period plus a one-year period.
(e) Except for escrow agreements and payment bonds, which provide their own protection procedures, the Contracting Officer is authorized to access funds under the payment protection when it has been alleged in writing by a supplier of labor or material that a nonpayment has occurred, and to withhold such funds pending resolution by administrative or judicial proceedings or mutual agreement of the parties.
(f) When a tripartite escrow agreement is used, the Contractor shall utilize only suppliers of labor and material that signed the escrow agreement.
(End of clause)
DEPARTMENT OF COMMERCE CLAUSES
FOR FULL TEXT OF COMMERCE ACQUISITION CLAUSES OR PROVISIONS YOU MAY TO GO THE FOLLOWING WEBSITE:
http://www.ecfr.gov/cgi-bin/text-idx?sid=2d08a6e69af3b9bb1a7be4eae370d256&c=ecfr&tpl=/ecfrbrowse/Title48/48cfrv5_02.tpl#1300
CAR 1352.201-70 CONTRACTING OFFICER'S AUTHORITY (APRIL 2010)
The Contracting Officer is the only person authorized to make or approve any changes in any of the requirements of this contract and notwithstanding any provisions contained elsewhere in this contract, the said authority remains solely in the Contracting Officer. In the event the Contractor makes any changes at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract terms and conditions, including price.
CAR 1352.201-72 CONTRACTING OFFICER’S REPRESENTATIVE (COR) (APRIL 2010)
(a) The Contracting Officer’s Representative (COR) will be identified under separate cover after award. The COR may be changed at any time by the Government without prior notice to the contractor by issuance of a new appointment letter. The location of the COR will be provided at the issuance of the COR appointment letter.
(b) The responsibilities and limitations of the COR are as follows:
(1) The COR is responsible for the technical aspects of the contract and serves as technical liaison with the contractor. The COR is also responsible for the final inspection and acceptance of all deliverables and such other responsibilities as may be specified in the contract.
(2) The COR is not authorized to make any commitments or otherwise obligate the Government or authorize any changes which affect the contract price, terms or conditions. Any contractor request for changes shall be referred to the Contracting Officer directly or through the COR. No such changes shall be made without the express written prior authorization of the Contracting Officer. The Contracting Officer may designate assistant or alternate COR(s) to act for the COR by naming such assistant/alternate(s) in writing and transmitting a copy of such designation to the contractor.
(End of clause)
CAR 1352.209-73 COMPLIANCE WITH THE LAWS (APRIL 2010)
The contractor shall comply with all applicable laws, rules and regulations which deal with or relate to performance in accord with the terms of the contract.
(End of clause)
CAR 1352.209-74 ORGANIZATIONAL CONFLICT OF INTEREST (APR 2010)
| (a) Purpose. The purpose of this clause is to ensure that the contractor and its subcontractors: | |
| (1) Are not biased because of their financial, contractual, organizational, or other interests which relate to the work under this contract, and | |
| (2) Do not obtain any unfair competitive advantage over other parties by virtue of their performance of this contract. | |
| (b) Scope. The restrictions described herein shall apply to performance or participation by the contractor, its parents, affiliates, divisions and subsidiaries, and successors in interest (hereinafter collectively referred to as “contractor”) in the activities covered by this clause as a prime contractor, subcontractor, co-sponsor, joint venturer, consultant, or in any similar capacity. For the purpose of this clause, affiliation occurs when a business concern is controlled by or has the power to control another or when a third party has the power to control both. | |
| (c) Warrant and Disclosure. The warrant and disclosure requirements of this paragraph apply with full force to both the contractor and all subcontractors. The contractor warrants that, to the best of the contractor’s knowledge and belief, there are no relevant facts or circumstances which would give rise to an organizational conflict of interest, as defined in FAR Subpart 9.5, and that the contractor has disclosed all relevant information regarding any actual or potential conflict. The contractor agrees it shall make an immediate and full disclosure, in writing, to the Contracting Officer of any potential or actual organizational conflict of interest or the existence of any facts that may cause a reasonably prudent person to question the contractor’s impartiality because of the appearance or existence of bias or an unfair competitive advantage. Such disclosure shall include a description of the actions the contractor has taken or proposes to take in order to avoid, neutralize, or mitigate any resulting conflict of interest. | |
| (d) Remedies. The Contracting Officer may terminate this contract for convenience, in whole or in part, if the Contracting Officer deems such termination necessary to avoid, neutralize or mitigate an actual or apparent organizational conflict of interest. If the contractor fails to disclose facts pertaining to the existence of a potential or actual organizational conflict of interest or misrepresents relevant information to the Contracting Officer, the Government may terminate the contract for default, suspend or debar the contractor from Government contracting, or pursue such other remedies as may be permitted by law or this contract. | |
| (e) Subcontracts. The contractor shall include a clause substantially similar to this clause, including paragraphs (f) and (g), in any subcontract or consultant agreement at any tier expected to exceed the simplified acquisition threshold. The terms “contract,” “contractor,” and “Contracting Officer” shall be appropriately modified to preserve the Government’s rights. | |
| (f) Prime Contractor Responsibilities. The contractor shall obtain from its subcontractors or consultants the disclosure required in FAR Part 9.507-1, and shall determine in writing whether the interests disclosed present an actual, or significant potential for, an organizational conflict of interest. The contractor shall identify and avoid, neutralize, or mitigate any subcontractor organizational conflict prior to award of the contract to the satisfaction of the Contracting Officer. If the subcontractor’s organizational conflict cannot be avoided, neutralized, or mitigated, the contractor must obtain the written approval of the Contracting Officer prior to entering into the subcontract. If the contractor becomes aware of a subcontractor’s potential or actual organizational conflict of interest after contract award, the contractor agrees that the Contractor may be required to eliminate the subcontractor from its team, at the contractor’s own risk. |
(g) Waiver. The parties recognize that this clause has potential effects which will survive the performance of this contract and that it is impossible to foresee each circumstance to which it might be applied in the future. Accordingly, the contractor may at any time seek a waiver from the Head of the Contracting Activity by submitting such waiver request to the Contracting Officer, including a full written description of the requested waiver and the reasons in support thereof.
(End of clause)
CAR 1352.237-71 SECURITY PROCESSING REQUIREMENTS—LOW RISK CONTRACTS (APR 2010)
(a) Investigative Requirements for Low Risk Contracts. All contractor (and subcontractor) personnel proposed to be employed under a Low Risk contract shall undergo security processing by the Department's Office of Security before being eligible to work on the premises of any Department of Commerce owned, leased, or controlled facility in the United States or overseas, or to obtain access to a Department of Commerce IT system. All Department of Commerce security processing pertinent to this contract will be conducted at no cost to the contractor.
(b) Investigative requirements for Non-IT Service Contracts are:
(1) Contracts more than 180 days—National Agency Check and Inquiries (NACI).
(2) Contracts less than 180 days—Special Agency Check (SAC).
(c) Investigative requirements for IT Service Contracts are:
(1) Contracts more than 180 days—National Agency Check and Inquiries (NACI).
(2) Contracts less than 180 days—National Agency Check and Inquiries (NACI).
(d) In addition to the investigations noted above, non-U.S. citizens must have a background check that includes an Immigration and Customs Enforcement agency check.
(e) Additional Requirements for Foreign Nationals (Non-U.S. Citizens). Non-U.S. citizens (lawful permanent residents) to be employed under this contract within the United States must have:
(1) Official legal status in the United States;
(2) Continuously resided in the United States for the last two years; and
(3) Obtained advance approval from the servicing Security Officer in consultation with the Office of Security headquarters.
(f) DOC Security Processing Requirements for Low Risk Non-IT Service Contracts. Processing requirements for Low Risk non-IT Service Contracts are as follows:
(1) Processing of a NACI is required for all contract employees employed in Low Risk non-IT service contracts for more than 180 days. The Contracting Officer's Representative (COR) will invite the prospective contractor into e-QIP to complete the SF–85. The contract employee must also complete fingerprinting.
(2) Contract employees employed in Low Risk non-IT service contracts for less than 180 days require processing of Form OFI–86C Special Agreement Check (SAC), to be processed. The Sponsor will forward a completed Form OFI–86C, FD–258, Fingerprint Chart, and Credit Release Authorization to the servicing Security Officer, who will send the investigative packet to the Office of Personnel Management for processing.
(3) Any contract employee with a favorable SAC who remains on the contract over 180 days will be required to have a NACI conducted to continue working on the job site.
(4) For Low Risk non-IT service contracts, the scope of the SAC will include checks of the Security/Suitability Investigations Index (SII), other agency files (INVA), Defense Clearance Investigations Index (DCII), FBI Fingerprint (FBIF), and the FBI Information Management Division (FBIN).
(5) In addition, for those individuals who are not U.S. citizens (lawful permanent residents), the Sponsor may request a Customs Enforcement SAC on Form OFI–86C, by checking Block #7, Item I. In Block 13, the Sponsor should enter the employee's Alien Registration Receipt Card number to aid in verification.
(6) Copies of the appropriate forms can be obtained from the Sponsor or the Office of Security. Upon receipt of the required forms, the Sponsor will forward the forms to the servicing Security Officer. The Security Officer will process the forms and advise the Sponsor and the Contracting Officer whether the contract employee can commence work prior to completion of the suitability determination based on the type of work and risk to the facility ( i.e. , adequate controls and restrictions are in place). The Sponsor will notify the contractor of favorable or unfavorable findings of the suitability determinations. The Contracting Officer will notify the contractor of an approved contract start date.
(g) Security Processing Requirements for Low Risk IT Service Contracts. Processing of a NACI is required for all contract employees employed under Low Risk IT service contracts.
(1) Contract employees employed in all Low Risk IT service contracts will require a National Agency Check and Inquiries (NACI) to be processed. The Contracting Officer's Representative (COR) will invite the prospective contractor into e-QIP to complete the SF–85. Fingerprints and a Credit Release Authorization must be completed within three working days from start of work, and provided to the Servicing Security Officer, who will forward the investigative package to OPM.
(2) For Low Risk IT service contracts, individuals who are not U.S. citizens (lawful permanent residents) must undergo a NACI that includes an agency check conducted by the Immigration and Customs Enforcement Service. The Sponsor must request the ICE check as a part of the NAC.
(h) Notification of Disqualifying Information. If the Office of Security receives disqualifying information on a contract employee, the Sponsor and Contracting Officer will be notified. The Sponsor shall coordinate with the Contracting Officer for the immediate removal of the employee from duty requiring access to Departmental facilities or IT systems. Contract employees may be barred from working on the premises of a facility for any of the following reasons:
(1) Conviction of a felony crime of violence or of a misdemeanor involving moral turpitude.
(2) Falsification of information entered on security screening forms or of other documents submitted to the Department.
(3) Improper conduct once performing on the contract, including criminal, infamous, dishonest, immoral, or notoriously disgraceful conduct or other conduct prejudicial to the Government regardless of whether the conduct was directly related to the contract.
(4) Any behavior judged to pose a potential threat to Departmental information systems, personnel, property, or other assets.
(i) Failure to comply with security processing requirements may result in termination of the contract or removal of contract employees from Department of Commerce facilities or denial of access to IT systems.
(j) Access to National Security Information. Compliance with these requirements shall not be construed as providing a contract employee clearance to have access to national security information.
(k) The contractor shall include the substance of this clause, including this paragraph, in all subcontracts.
(End of clause)
NOAA ACQUISITION MANUAL (NAM) CONTRACT LANGUAGE
FOR FULL TEXT OF THE NOAA ACQUISITION MANUAL YOU MAY GO TO THE FOLLOWING WEBSITE, https://www.ago.noaa.gov/acquisition/AcqManual/09_acquisitionmanualtableofcontents.html
NAM 1330-52.242-304 NOAA ACQUISITION AND GRANTS OFFICE OMBUDSMAN (OCT 2022)
a. The NOAA Acquisition and Grants Office (AGO) Ombudsman is available to organizations to promote responsible and meaningful exchanges of information. Generally, the purpose of these exchanges will be to:
1. Allow contractors to better prepare for and propose on business opportunities.
2. Advise as to technologies and solutions within the marketplace that the Government may not be aware of, or is not fully benefiting from.
3. Identify constraints in transparency and process.
b. The AGO Ombudsman will objectively, reasonably, and responsibly collaborate with parties and recommend fair, impartial, and constructive solutions to the matters presented to him/her. Further, the AGO Ombudsman will maintain the reasonable and responsible confidentiality of the source of a concern, when such a request has been formally made by an authorized officer of an organization seeking to do business with, or already doing business with NOAA.
c. Before consulting with the AGO Ombudsman, interested parties must first address their concerns, issues, disagreements, and/or recommendations with the respective contracting officer for resolution. However, direct access to the AGO Ombudsman may be sought when an interested party questions the objectivity or equity of a contracting officer’s decision, or when there is a bona fide reason to believe that reasonable, responsible, and objective consideration will not be received from an assigned contracting officer.
d. There are several constraints to the scope of the AGO Ombudsman’s authority, for instance:
1. Consulting with the AGO Ombudsman does not alter or postpone the timelines of any formal process (e.g., protests, claims, debriefings, employee employer actions, activities involving A-76 competition performance decisions, judicial or congressional hearings, or proposal, amendment, modification or deliverable due dates, etc.).
2. The AGO Ombudsman cannot participate in the evaluation of proposals, source selection processes, or the adjudication of protests or formal contract disputes.
3. The AGO Ombudsman is not authorized to generate or alter laws, judicial decisions, rules, policies, or formal guidance.
4. The AGO Ombudsman is not authorized to develop or alter opportunity announcements, solicitations, contracts, or their terms or conditions.
5. The AGO Ombudsman cannot overrule the authorized decisions or determinations of the contracting officer.
6. The AGO Ombudsman has no authority to render a decision that binds AGO, NOAA, the Department of Commerce, or the U.S. Government.
7. The AGO Ombudsman is not NOAA’s agent relative to the service of magistrate or judicial process and cannot be used to extend service of process to another party (whether federal, public, or a private entity).
e. After review and analysis of a filed concern or recommendation, the AGO Ombudsman may refer the interested party to another more suitable federal official for consideration. Moreover, concerns, disagreements, and/or recommendations that cannot be resolved by the AGO Ombudsman will need to be pursued through more formal venues.
f. The AGO Ombudsman is not to be contacted to request copies of forms and/or documents under the purview of a contracting officer. Such documents include Requests for Information, solicitations, amendments, contracts, modifications, or conference materials.
g. Questions regarding items (a) through (f) within this language shall be directed to ago.ombudsman@noaa.gov.
NAM 1330-52.237-70 CONTRACTOR COMMUNICATIONS
(a) A contractor employee shall be identified both by the individual’s name and the contractor’s name when:
| 1. Included in NOAA’s locator, and |
| 2. When submitting any type of electronic correspondence to any NOAA employee or stakeholder. |
(b) Any written correspondence from a contractor or any contractor employee shall be printed on company/organization letterhead or otherwise clearly identify the sender as an employee of the company or organization and shall identify the contract number.
(c) Contractors and/or contractor employees shall clearly identify themselves as such in any verbal communications, whether in informal discussion or a formal meeting.
NAM 1330-52.243-70 REQUESTS FOR EQUITABLE ADJUSTMENT (OCT 2017)
(a) The amount of any request for equitable adjustment to contract terms shall accurately reflect the contract adjustment for which the contractor believes the Government is liable. The request shall include only costs for performing the change. All indirect costs included in the request shall be properly allocable to the change in accordance with applicable acquisition regulations.
(b) Any request for equitable adjustment to contract terms that exceeds the simplified acquisition threshold shall bear, at the time of submission, the following certificate executed by an individual authorized to certify the request on behalf of the Contractor:
I certify that the request is made in good faith, and that the supporting data are accurate and complete to the best of my knowledge and belief.
(Official’s Name) (Title)
(c) The certification in paragraph (b) of this clause requires full disclosure of all relevant facts, including:
Certified cost or pricing data, if required, in accordance with subsection 15.403-4 of the Federal Acquisition Regulation (FAR); and Data other than certified cost or pricing data, in accordance with subsection 15.403-3 of the FAR, including actual cost data and data to support any estimated costs, even if certified cost or pricing data are not required.
(d) The certification requirement in paragraph (b) of this clause does not apply to:
Requests for routine contract payments; for example, requests for payment for accepted supplies and services, routine vouchers under a cost-reimbursement type contract, or progress payment invoices; or Final adjustments under an incentive provision of the contract.
1330-52.237-72 CONTRACTOR ACCESS TO NOAA FACILITIES (SEPT 2017)
(a)(1) The performance of this contract requires employees of the prime contractor or its subcontractors, affiliates, consultants, or team members (“contractor employees”) to have access to and to the extent authorized, mobility within, a NOAA facility.
(2) NOAA may close and or otherwise deny contractor employees access to a NOAA facility for a portion of a business day or longer for various reasons including, but not limited, to the following events:
(i) Federal public holidays for federal employees in accordance with 5 U.S.C. 6103;
(ii) Fires, floods, earthquakes, and unusually severe weather, including but not limited to snow storms, tornadoes, and hurricanes;
(iii) Occupational safety or health hazards;
(iv) Lapse in Appropriations; or
(v) Federal Statute, Executive Order, Presidential Proclamation, or any other unforeseen reason.
(3) In such events, the contractor employees may be denied access to a NOAA facility that is ordinarily available for the contractor to perform work or make delivery, as required by the contract.
(b) In all instances where contractors are denied access or required to vacate a NOAA facility, in part or in whole, the contractor shall be responsible to ensure contractor personnel working under the contract comply. If the circumstances permit, the contracting officer will provide direction to the contractor, either directly or through the Contracting Officer’s Representative (COR), which could include continuing on-site performance during the NOAA facility closure period; however, if Government oversight is required and is not available, on-site performance shall not be allowed.
In the absence of such direction, the contractor shall exercise sound judgment to minimize unnecessary contract costs and performance impacts, for example, performing required work off-site if possible or reassigning personnel to other activities if appropriate.
(c) The contractor shall be responsible for monitoring the Office of Personnel Management at www.opm.gov, the local radio, television stations, NOAA web sites, and other communication channels. Once the facility is accessible, the contractor shall resume contract performance as required by the contract.
(d) For the period that NOAA facilities were not accessible to contractors who required access in order to perform the services, the contracting officer may—
(1) Adjust the contract performance or delivery schedule for a period equivalent to the period the NOAA facility was not accessible;
(2) Forego the work; or
(3) Reschedule the work by mutual agreement of the parties.
(e) Notification procedures of a NOAA facility closure, including contractor denial of access, are as follows:
(1) The contractor shall be responsible for notification of its employees of the NOAA facility closure to include denial of access to the NOAA facility. The dismissal of NOAA employees in accordance with statute and regulations providing for such dismissals shall not, in itself, equate to a NOAA facility closure in which contractors are denied access. Moreover, the leave status of NOAA employees shall not be conveyed or imputed to contractor personnel. Accordingly, unless a NOAA facility is closed and the contractor is denied access to the facility, the contractor shall continue performance in accordance with the contract.
(2) Access to Government facilities and resources, including equipment and systems, will be limited and personnel necessary to administer contract performance may not be available. Generally, supply and service contracts that are funded beyond the date of the lapse in appropriation and do not require access to Government facilities, active administration by Government personnel or the use of government resources in a manner that would cause the government to incur additional obligations during the lapse in appropriation may continue. If a delivery date for a contract falls during the period of a lapse in appropriations, Government personnel may not be available to receive delivery. Contractors are directed to consult with a contracting officer before attempting to make a delivery. Contracting officers will be available throughout the lapse in appropriation period to provide guidance.
Once OMB guidance is given, CORs, in consultation with the contracting officer, will notify those contractors that are deemed by the Program Office to be performing excepted work and identify the contractor personnel requiring access to NOAA facilities. CORs will also coordinate with directly with facility management or physical security personnel at respective locations to ensure that the names of contractor personnel requiring access to government facilities during the lapse in appropriations are provided to physical security personnel.
Contractors who are not designated as performing excepted work are not allowed access to Government facilities or to utilize government resources in a manner that would incur any additional obligation of funding on behalf of the government during the lapse in appropriation.
(3) Unless otherwise specified within the contract award, contractors requiring access to NOAA facilities outside normal business hours or outside the normal workweek shall submit a written request in writing through the COR to the contracting officer. The written request shall provide justification supporting the required access and be submitted ________ hours/days (contracting officer insert number of days. If blank, 72 hours applies) before access to the NOAA facility is needed.
NAM 1330-52.237-71 NOAA GOVERNMENT-CONTRACTOR RELATIONS – NON-PERSONAL SERVICES CONTRACT (SEPT 2017)
(a) The Government and the Contractor understand and agree that the services to be delivered under this contract by the Contractor to the Government are non-personal services as defined in FAR Part 37, Service Contracting, and the parties recognize and agree that no employer-employee relationship exists or will exist under the contract between the Government and the Contractor’s personnel. It is, therefore, in the best interest of the Government to afford both parties an understanding of their respective obligations.
(b) Contractor personnel under this contract shall not:
(1) Be placed in a position where they are under relatively continuous supervision and control of a Government employee.
(2) Be placed in a position of command, supervision, administration, or control over Government personnel or over personnel of other Contractors performing under other NOAA contracts.
(c) The services to be performed under this contract do not require the Contractor or the Contractor’s personnel to exercise personal judgement and discretion on behalf of the Government. Rather, the Contractor’s personnel will act and exercise personal judgement and discretion on behalf of the Contractor.
(d) Rules, regulations, directives, and requirements that are issued by the Department of Commerce and NOAA under its responsibility for good order, administration, and security are applicable to all personnel who enter the Government installation and facilities, who are provided access to Government systems, or who travel on Government transportation. This is not to be construed or interpreted to establish any degree of Government control that is inconsistent with a non-personal services contract.
(e) Both parties are responsible for monitoring contract activities for indications of improper employee-employer relationships during performance. In the event a situation or occurrence takes place inconsistent with this contract language, the following applies:
(1) The Contractor shall notify the Contracting Officer in writing within 5 business days from the date of any situation or occurrence where the Contractor considers specific contract activity to be inconsistent with the intent of this contract language. The notice must include the date, nature and circumstance of the situation or occurrence, the name, function and activity of each Government employee or Contractor employee involved or knowledgeable about the situation or occurrence, provide any documents or the substance of any oral communications related to the activity, and an estimated date by which the Government is recommended to respond to the notice in order to minimize cost, delay, or disruption of performance.
(2) The Contracting Officer will review the information provided by the Contractor, obtain additional information (if needed), and respond in writing as soon as practicable after receipt of the notification from the Contractor. The Contracting Officer’s response will provide a decision on whether the Contracting Officer determines the situation or occurrence to be inconsistent with the intent of this contract language and, if deemed necessary, will specify any corrective action(s) to be taken in order to resolve the issue.
1330-52.222-70 NOAA SEXUAL ASSAULT AND SEXUAL HARASSMENT PREVENTION AND RESPONSE POLICY (MAY 2018) In accordance with NOAA Administrative Order (NAO) 202-1106, NOAA Sexual Assault and Sexual Harassment Prevention and Response Policy, it is the policy of NOAA to maintain a work environment free from sexual assault and sexual harassment. NOAA prohibits sexual assault and sexual harassment by or of any employee, supervisor, manager, contractor, vendor, affiliate, or other individual with whom NOAA employees come into contact by the virtue of their work for NOAA.
(a) Definitions.
Contractor Employees - The term “contractor employees,” as used in this solicitation and contract language, refers to employees of the prime contractor or its subcontractors, affiliates, consultants, or team members.
Sexual Assault - The term sexual assault, as used in this solicitation and contract language, means any conduct proscribed by state or federal sexual abuse laws, including, but not limited to, those defined in chapter 109A of title 18 of the U.S. Code (sexual abuse), and assaults committed both by offenders who are strangers to the victim and by offenders who are known or related by blood or marriage to the victim.
Sexual Harassment - As defined by the Equal Employment Opportunity Commission, sexual harassment is a form of sex discrimination that violates Title VII of the Civil Rights Act of 1964. It includes unwelcome sexual advances, requests for sexual favors, and other verbal, non-verbal, or physical conduct of a sexual nature when any of the following are true:
· Submission to such conduct is made either explicitly or implicitly as a term or condition of an individual's employment;
· Submission to or rejection of such conduct by an individual is used as the basis for employment decisions affecting such individual;
· The conduct unreasonably interferes with an individual's work performance or creates an…