This document is a detailed pricing schedule for a state and local contract indefinite delivery vehicle (IDV) with Aerospace Holding Corporation, specifically covering maintenance and inspection services for King Air B300 and B200GT aircraft. The contract appears to be aligned with specification 195A-25 and includes comprehensive pricing for various inspection phases and maintenance tasks for aircraft with specific serial numbers (FL977 and BY183).
The contract provides a comprehensive pricing structure for aircraft inspections, with hourly labor rates ranging from $140 to $210 per hour depending on the service type (standard inspection, maintenance, overtime). The pricing covers multiple inspection phases for both aircraft models, including detailed breakdowns for tasks such as engine maintenance, structural inspections, and component-specific checks. Each inspection phase is meticulously documented with associated parts and labor costs, with most inspections ranging from $140 to $13,420 in total cost. The contract includes provisions for periodic inspections of Pratt & Whitney Canada PT6A-60A and PT6A-52 engines, with specific pricing for various interval checks including minor, routine, and hour-based inspections. All parts pricing is noted to be inclusive of necessary oil for performing services.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pricing
| 195A-25 Pricing | ||||
| Vendor Name: | Aerospace Holding Corporation | |||
| Please quote and insert below, your lowest net delivered prices for the commodities (or services) herein described, guaranteed firm for the contract duration for : King Air B300 and/or B200GT, OEM parts, components, accessories, and the inspection and/or maintenance/repair. Please note the "Parts" sections noted with an asterisk as these inspections are to be inclusive of the cost of oil. | ||||
| Bid Item | Item Description | Quote Hourly Labor/Travel Rates | ||
| 1 | Inspection | $140.00 | per hour | |
| 2 | Maintenance | $140.00 | per hour | |
| 3 | Overtime | $210.00 | per hour | |
| 4 | Travel Time | $140.00 | per hour |
| Total cost of Inspections on a B300 Series Serial Number FL977 per Beechcraft Maintenance Manual 130-590031-11. Revision & Date entered below; | ||
| Revision: C5, Revision Date: Mar 1, 2024 | ||
| 1.1 | Inspection Phase 5 gives a list of tasks to be completed at the first dual inspection interval. The first dual inspection interval contains all Phase 1 and Phase 2 inspections, without duplicates. | Total Cost |
| a. Parts* | $820.00 | |
| b. Labor | $12,600.00 | |
| Total Cost Item 1.1a & 1.1b | $13,420.00 | |
| 1.2 | Inspection Phase 6 gives a list of tasks to be completed at the second dual inspection interval. The second dual inspection interval contains all Phase 3 and Phase 4 inspections, without duplicates. | Total Cost |
| a. Parts* | $820.00 | |
| b. Labor | $12,600.00 | |
| Total Cost Item 1.2a & 1.2b | $13,420.00 | |
| 1.3 | Inspection Phase 8 gives a list of tasks to be completed every 12 months. | Total Cost |
| a. Parts* | ||
| b. Labor | $2,100.00 | |
| Total Cost Item 1.3a & 1.3b | $2,100.00 | |
| 1.4 | Inspection Phase 9 gives a list of tasks to be completed every 1200 hours. | Total Cost |
| a. Parts* | ||
| b. Labor | $2,100.00 | |
| Total Cost Item 1.4a & 1.4b | $2,100.00 | |
| 1.5 | Inspection Phase 10 gives a list of tasks to be completed every 1000 cycles. | Total Cost |
| a. Parts* | ||
| b. Labor | $840.00 | |
| Total Cost Item 1.5a & 1.5b | $840.00 | |
| 1.6 | Inspection Phase 11 gives a list of tasks to be completed every 2400 hours or 30 months, whichever occurs first. | Total Cost |
| a. Parts* | $102.50 | |
| b. Labor | $1,680.00 | |
| Total Cost Item 1.6a & 1.6b | $1,782.50 | |
| 1.7 | Inspection Phase 12 gives a list of tasks to be completed every 24 months. | Total Cost |
| a. Parts* | ||
| b. Labor | $1,540.00 | |
| Total Cost Item 1.7a & 1.7b | $1,540.00 | |
| 1.8 | Inspection Phase 15 gives a list of tasks to be completed in accordance with the King Air Structural Inspection and Repair Manual (P/N 98-39006) that occur at the same inspection interval. Refer to the Table 201 Inspection Interval for Index Items (9), (12), and (13) in Chapter 57-18-02, 201. | Total Cost |
| a. Parts* AND SERVICES | $3,280.00 | |
| b. Labor | $4,480.00 | |
| Total Cost Item 1.8a & 1.8b | $7,760.00 | |
| 1.9 | Inspection Phase 25 gives a list of tasks to be completed at the first 200 flight hours on a new airplane / first 200 flight hours after new cable installation or rigging break initial, then every 48 months thereafter. | Total Cost |
| a. Parts* | ||
| b. Labor | $6,300.00 | |
| Total Cost Item 1.9a & 1.9b | $6,300.00 | |
| 1.10 | Inspection Phase 29 gives a list of tasks to be completed at the first 200 flight hours, then every 1200 flight hours thereafter or any time the landing gear hydraulic system is contaminated. | Total Cost |
| a. Parts* | ||
| b. Labor | $70.00 | |
| Total Cost Item 1.10a & 1.10b | $70.00 | |
| 1.11 | Inspection Phase 31 gives a list of tasks to be completed at the first 600 flight hours, then every 18 months thereafter. | Total Cost |
| a. Parts* | ||
| b. Labor | $560.00 | |
| Total Cost Item 1.11a & 1.11b | $560.00 | |
| 1.12 | Inspection Phase 32 gives a list of tasks to be completed every 2500 cycles until 10,000 cycles, then every 1000 cycles thereafter. | Total Cost |
| a. Parts* | ||
| b. Labor | $6,300.00 | |
| Total Cost Item 1.12a & 1.12b | $6,300.00 | |
| 1.13 | Inspection Phase 33 gives a list of tasks to be completed 60 months after being placed in service but no longer than 63 months after date of manufacture. | Total Cost |
| a. Parts* | ||
| b. Labor | $140.00 | |
| Total Cost Item 1.13a & 1.13b | $140.00 | |
| 1.14 | Inspection Phase 34 gives a list of tasks to be completed at the first 72 months then every 12 months thereafter. | Total Cost |
| a. Parts* | ||
| b. Labor | $840.00 | |
| Total Cost Item 1.14a & 1.14b | $840.00 | |
| 1.15 | Inspection Phase 35 gives a list of tasks to be completed 120 months from the date of manufacture. | Total Cost |
| a. Parts* | ||
| b. Labor | $140.00 | |
| Total Cost Item 1.15a & 1.15b | $140.00 | |
| 1.16 | Inspection Phase 36 gives a list of tasks to be completed in accordance with the applicable vendor manual. | Total Cost |
| a. Parts* | ||
| b. Labor | $840.00 | |
| Total Cost Item 1.16a & 1.16b | ||
| 1.17 | Inspection Phase 37 gives a list of tasks to be completed in accordance with the crew oxygen mask manufacturer's component maintenance manual. | Total Cost |
| a. Parts* | ||
| b. Labor | $280.00 | |
| Total Cost Item 1.17a & 1.17b | $280.00 | |
| 1.18 | Inspection Phase 38 gives a list of tasks to be completed in accordance with the landing gear wheel manufacturer's component maintenance manual. | Total Cost |
| a. Parts* | ||
| b. Labor | $1,050.00 | |
| Total Cost Item 1.18a & 1.18b | $1,050.00 | |
| 1.19 | Inspection Phase 41 gives a list of tasks to be completed in accordance with 174095-SIL-1 or subsequent. | Total Cost |
| a. Parts* | ||
| b. Labor | $280.00 | |
| Total Cost Item 1.19a & 1.19b | $280.00 | |
| 1.20 | Inspection Phase 42 gives a list of tasks to be completed at the next scheduled inspection after wing installation, then every 12 months thereafter. | Total Cost |
| a. Parts* | ||
| b. Labor | $140.00 | |
| Total Cost Item 1.20a & 1.20b | $140.00 | |
| 1.21 | Inspection Phase 43 gives a list of tasks to be completed every 800 flight hours or 24 months, whichever occurs first. | Total Cost |
| a. Parts* | ||
| b. Labor | $560.00 | |
| Total Cost Item 1.21a & 1.21b | $560.00 | |
| 1.22 | Inspection Phase 44 gives a list of tasks to be completed at the first 200 hours after installation. | Total Cost |
| a. Parts* | ||
| b. Labor | $560.00 | |
| Total Cost Item 1.22a & 1.22b | $560.00 | |
| 1.23 | Inspection Phase 45 gives a list of tasks to be completed every 6500 flight hours or 48 months, whichever occurs first, or after removal and installation. | Total Cost |
| a. Parts* | ||
| b. Labor | $420.00 | |
| Total Cost Item 1.23a & 1.23b | $420.00 | |
| 1.24 | Inspection Phase 46 gives a list of tasks to be completed every 2000 flight hours or 48 months, whichever occurs first. | Total Cost |
| a. Parts* | ||
| b. Labor | $560.00 | |
| Total Cost Item 1.24a & 1.24b | $560.00 | |
| 1.25 | Inspection Phase 51 gives a list of tasks to be completed in accordance with the King Air Structural Inspection and Repair Manual (P/N 98-39006) that occur at the same inspection interval. Refer to the Table 201 Inspection Interval for Index Item (11) in Chapter 57-18-02, 201. | Total Cost |
| a. Parts* | ||
| b. Labor | $280.00 | |
| Total Cost Item 1.25a & 61.25 | $280.00 | |
| 1.26 | Inspection Phase 52 gives a list of tasks to be completed in accordance with the King Air Structural Inspection and Repair Manual (P/N 98-39006) that occur at the same inspection interval. Refer to the Table 201 Inspection Interval for Index Item (8) in Chapter 57-18-02, 201. | Total Cost |
| a. Parts* | ||
| b. Labor | $140.00 | |
| Total Cost Item 1.26a & 1.26b | $140.00 | |
| 1.27 | Inspection Phase 53 gives a list of inspection tasks to be completed at the first 2500 cycles, then every 500 cycles thereafter. | Total Cost |
| a. Parts* | ||
| b. Labor | $3,360.00 | |
| Total Cost Item 1.27a & 1.28b | $3,360.00 |
| Pratt & Whitney Canada PT6A-60A Engine, Maintenance Manual - PT6A-60A/PT6A-60AG/PT6A-61 Issue No. 3034342 Revision & Date entered below, EMM 72.00.00 Table 601 Periodic Inspection items. | ||
| Revision: 63 Date: __Oct 07/2024___ | ||
| 1.29 | Cost of Table 601 Periodic Inspection; Interval MINOR item(s) | |
| a. Parts* | ||
| b. Labor | $560.00 | |
| Total Cost Item 1.29a & 1.29b | $560.00 | |
| 1.30 | Cost of Table 601 Periodic Inspection; Interval ROUTINE item(s) | |
| a. Parts* | $100.00 | |
| b. Labor | ||
| Total Cost Item 1.30a &1.30b | $100.00 | |
| 1.31 | Cost of Table 601 Periodic Inspection; Interval 200 Hour item(s) | |
| a. Parts* | ||
| b. Labor | $140.00 | |
| Total Cost Item 1.31a & 1.31b | $140.00 | |
| 1.32 | Cost of Table 601 Periodic Inspection; Interval 200 Hour or 6 months item(s) | |
| a. Parts* | $40.00 | |
| b. Labor | $140.00 | |
| Total Cost Item 1.32a & 1.32b | $180.00 | |
| 1.33 | Cost of Table 601 Periodic Inspection; Interval 300 Hours Item(s) | |
| a. Parts* | ||
| b. Labor | $1,400.00 | |
| Total Cost Item 1.33a & 1.33b | ||
| 1.34 | Cost of Table 601 Periodic Inspection; Interval 600 Hours Item(s) | |
| a. Parts* | ||
| b. Labor | $140.00 | |
| Total Cost Item 1.34a &1.34b | $140.00 | |
| 1.35 | Cost of Table 601 Periodic Inspection; Interval 600 Hours or 12 months Item(s) | |
| a. Parts* | ||
| b. Labor | $560.00 | |
| Total Cost Item 1.35a & 1.35b | $560.00 | |
| 1.36 | Cost of Table 601 Periodic Inspection; Interval 1000 Hours Item(s) | |
| a. Parts* | $1,691.25 | |
| b. Labor | $420.00 | |
| Total Cost Item 1.36a & 1.36b | $2,111.25 | |
| 1.37 | Cost of Table 601 Periodic Inspection; Interval 1800 Hours Item(s) | |
| a. Parts* | $25.00 | |
| b. Labor | $2,240.00 | |
| Total Cost Item 1.37a & 1.37b | $2,265.00 |
| Total cost of Inspections on a B200GT Series Serial Number BY183 per Beechcraft King Air 200 Series Maintenance Manual 101-590010-19. Revision & Date entered below; | ||
| Revision: E4, Revision Date: Nov 1, 2024 | ||
| 2.1 | Total cost of a Phase 1 & 2 inspection on a KingAir B200GT Serial Number BY183 | Total Cost |
| a. Parts* | $871.25 | |
| b. Labor | $12,600.00 | |
| Total Cost Item 2.1a & 2.1b | $13,471.25 | |
| 2.3 | Total cost of a Phase 3 & 4 inspection on a KingAir B200GT Serial Number BY183 | Total Cost |
| a. Parts* | $871.25 | |
| b. Labor | $12,600.00 | |
| Total Cost Item 2.3a & 2.3b | $13,471.25 |
| Pratt & Whitney Canada PT6A-52 Engine, Maintenance Manual Issue No. 3072862 Revision & Date entered below, EMM 72.00.00 Table 601 Periodic Inspection items. | ||
| Revision: _32_ Date: Oct 07/2024 | ||
| 2.4 | Cost of Table 601 Periodic Inspection; Interval MINOR item(s) | |
| a. Parts* | ||
| b. Labor | $560.00 | |
| Total Cost Item 2.4a & 2.4b | $560.00 | |
| 2.5 | Cost of Table 601 Periodic Inspection; Interval ROUTINE item(s) | |
| a. Parts* | $102.50 | |
| b. Labor | ||
| Total Cost Item 2.5a & 2.5b | $102.50 | |
| 2.6 | Cost of Table 601 Periodic Inspection; Interval 200 Hour item(s) | |
| a. Parts* | ||
| b. Labor | $140.00 | |
| Total Cost Item 2.6a & 2.6b | $140.00 | |
| 2.7 | Cost of Table 601 Periodic Inspection; Interval 200 Hour or 6 months item(s) | |
| a. Parts* | $41.00 | |
| b. Labor | $140.00 | |
| Total Cost Item 2.7a & 2.7b | $181.00 | |
| 2.8 | Cost of Table 601 Periodic Inspection; Interval 600 Hours Item(s) | |
| a. Parts* | ||
| b. Labor | $140.00 | |
| Total Cost Item 2.8a & 2.8b | $140.00 | |
| 2.9 | Cost of Table 601 Periodic Inspection; Interval 600 Hours or 12 months Item(s) | |
| a. Parts* | ||
| b. Labor | $560.00 | |
| Total Cost Item 2.9a & 2.9b | $560.00 | |
| 2.10 | Cost of Table 601 Periodic Inspection; Interval 1000 Hours Item(s) | |
| a. Parts* | $1,691.25 | |
| b. Labor | $420.00 | |
| Total Cost Item 2.10a & 2.10b | $2,111.25 | |
| ** All Parts pricing submitted shall be inclusive of all oill needed to preform the service, where applicable. |