SOW_Bulk_Nitrogen_System_MTF_-__Jan_2018.docx
DOCX document 32 KB Posted
- Attached to
- Dugway MTF Bulk Nitrogen System
- Solicitation number
- 18-233-SOL-00312
View the file
Other files
| File | Type | Posted |
|---|---|---|
| MTF_Bulk_Nitro_System_Location.pptx | PPTX presentation | |
| CTD_MTF_Pads_A_LS.PDF | ||
| CTD_MTF_Area_A_LS.PDF |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work: Building 8027 “MTF” Bulk Nitrogen System
WDTC PROJECT DRD Project 3522 “Bulk Nitrogen System MTF”
SCOPE OF WORK
For Building 8027 Material Test Facility Nitrogen Bulk Tank Pad and Nitrogen Line Installation
1. Introduction:
This Scope of Work is to install a concrete pad for a 3000 gallon liquid nitrogen tank and install stainless pipe Nitrogen Gas distribution system for Building 8027 into the three test chambers.
2. Background / History:
Building 8027 MPC, ATC and CSC chambers along with the Safety Air Monitoring room used are used to support the Next Generation Chemical Detector (NGCD) test programs and all future testing. Currently the nitrogen used to support the current test programs and safety air monitoring are being provided using 110 and 230 gallon bottles and tanks. With the upcoming installation of the new NGCD test fixtures, the amount of Nitrogen Gas exceeds our portable bottle capability. It is projected that five to six NGCD test fixtures will be operating four days a week, eight hours per day and each test fixture requires five separate Nitrogen Gas lines at various flow rates (average 100 – 150 L of Nitrogen Gas) per minute. This installation of a bulk 3000 gallon Nitrogen system with evaporator and 1” stainless steel pipes will provide the necessary Nitrogen gas without gas fluctuation or reduced flow rates and provide a safe and more cost effective way to provide nitrogen to the chamber, test fixtures and Safety Air Monitoring room.
3. Definitions:
CO – Contracting Officer – The only government employee authorized to make changes in the contract or to make payments.
COR – Contracting Officer Representative – The government employee tasked with the day-to-day operation of the contract, but is not authorized to make changes or issue funds.
NGCD – Next Generation Chemical Detector – Future test programs requiring bulk Nitrogen gas
Project Manager – The government employee task to inform the COR of day to day activities of the contract, but is not authorized to make changes or issue funds.
WDTC – West Desert Test Center.
DPG - Dugway Proving Grounds
4. Government Responsibilities:
WDTC will be responsible for notification to employees of any work that may impact day to day activities for employees.
WDTC will provide access to project area.
WDTC will provide a lay down area for the contractor’s materials and equipment.
WDTC will provide a solid concrete pad foundation to support the Bulk Nitrogen tank, evaporator and various materials.
WDTC will provide crane support to off-load and position the bulk tanks systems. Coordination will be through Herbert Davila, (435) 831-5004.
WDTC will provide a 1” Stainless Steel Valve so the Bulk Nitrogen tank gas can be attached to supply nitrogen to facility.
The WDTC Project Manager will inspect all work completed by contractor, this inspection shall be random throughout the project to ensure project has been completed in accordance with the scope of work (SOW). Ensure developing progress and issues are resolved in a timely manner. Coordinate with the DPG government responsible personnel to keep them informed and up to date on all aspects of the effort. Stop work orders and contract modifications will be done IAW developing data and issue resolution and coordinated through the CO from the COE.
The WDTC Project Manager will coordinate with the contractor(s) to provide access to the MTF and building 8027 where the pad and bulk nitrogen system will be installed. The WDTC Project Manager will coordinate with contractor(s) to provide access to the various chambers and rooms within building 8027 for installation of the 1” stainless steel lines. The WDTC Project Manager will have the area of termination clean and accessible; any sensitive equipment will be moved or protected against dust and debris.
5. Requirements:
a. The contractor shall provide all necessary materials, labor, tools, and equipment necessary to complete all requirements of this SOW.
b. The contractor shall perform cleanup and housekeeping of the contractor’s staging area, working areas, and any other areas affected throughout the construction process.
c. The contractor shall make a site visit to determine the layout of the facility. During this initial visit, the contractor shall review the work area and coordinate with WDTC’s Project Manager a lay down area for equipment and materials.
d. The contractor shall stop all work if any indication of asbestos or lead paint is found; the contractor is required to inform project manager immediately of any findings before work is continued.
e. The contractor shall provide all safety training and equipment for his employees.
f. Any damage caused by the contractor or their employees to existing structures, facilities, utilities or equipment will be repaired, to at least equal or better than existing status by the contractor, at no additional cost to the government.
g. All welding and flame producing operations will be coordinated through the WDTC project manager to DPG’s fire department and safety office. The contractor will have a fire department approved fire extinguisher and an additional person to watch for hot slag contacting combustible materials during all cutting or welding operations. A hot work permit must be secured from the fire department prior to starting work.
h. All work in this contract will be completed in accordance with the latest version of the following: National Fire Protection Association (NFPA), International Building Code (IBC) National Electrical Code (NEC) Federal, State, and DPG standards.
i. Supports, anchors, and restraints will be selected to withstand all static and dynamic conditions of loading to which they may be subjected.
j. If required the contractor shall obtain and comply with the requirements of a signed excavation permit from the WDTC Project Manager prior to commencing any excavation work.
k. If applicable, the contractor shall deliver to project manager a MSDS on any questionable item brought onto DPG property.
l. All scheduled power outages or other interruptions of utility services required for this project will be coordinated through the project manager. A 48-hour notification is required, with the work being scheduled and performed at the convenience of the government.
m. Requirements for entry:
1. This project is located within a restricted area; therefore the contractor will be required to be fitted for an escape mask/bottle.
2. Contractor will participate in all CAIRA exercises in the form of accountability of all personnel during any CAIRA exercises or in the event of a real alarm. DPG will provide contact information for these events.
3. The contractor shall conform to the Security Requirements.
n. Contractor will furnish a bi-monthly report on schedule and resources. Contractor will furnish a near term schedule as well as a project schedule. The daily work schedule will be coordinated three weeks out as much as possible for inclusion into the DPG schedule for resources and impacts on other test efforts ongoing in 8027.
o. Contract will not be considered to be complete nor final payment made until all contractors' badges and masks are returned or accounted for.
Statement of Work:
a. The Contractor will coordinate delivery of the Bulk Nitrogen system to Dugway Proving Ground, Utah 84022. Delivery will be coordinate through Herbert Davila, (435) 831-5004. Delivery will only be Monday through Thursday, 0700 – 1700 hours. Delivery will be to the installation site, building 8027, MTF, Ditto Area.
b. The Contractor will install the bulk Nitrogen Tank, Evaporator and various stainless steel lines for both Vapor and liquid nitrogen. Installation will include installing the necessary hardware, bolts and materials necessary to secure bulk tank and evaporator. The contractor will tie various vapor lines to existing building Stainless Steel lines ensuring all fitting are compatible to existing system 1” lines.
c. The Contractor will ensure the system is operating and functioning per operating manual.
6. Performance Period:
Contractor effort will begin within 14 days after receipt of Notice to Proceed order pertaining to this SOW. All work shall be completed within 60 days after receipt of Notice to Proceed order.
7. Final Acceptance:
WDTC Project manager to review work with contractor, if any issues are identified a punch list of items will be developed and completed.