Price_Schedule.pdf
PDF 22 KB Posted
- Attached to
- Robbin Rhoades On-Site Septic System Replacement Federal contract opportunity
- Solicitation number
- 17-102-SOL-00049
About this file
Price Schedule
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_0001.pdf | ||
| WD.pdf | ||
| wh347.pdf | ||
| RFQ.pdf | ||
| Attachment_C_-_SPECIFICATIONS.pdf | ||
| Attachment_D_-_Technical_Provisions.pdf | ||
| WD.pdf | ||
| Attachment_B_-_Design.pdf | ||
| Attachment_A_-_Location_Map.pdf | ||
| Attachment_B_-_Design.pdf | ||
| PO-15-B94I_Rhoades_OSS_Repair.rtf | RTF text file | |
| Attachment_A_-_Location_Map.pdf | ||
| Attachment_D_-_Technical_Provsions.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCHEDULE Continued Issue Date
Item No. Supplies/Services Quantity Unit Unit Price Amount
The Contractor shall provide all management, supervision, labor, and materials, to fulfill requirements of the attached specifications, drawings, or notes attached hereto.
The resulting award will be awarded on a firm fixed-price basis.
0001 The contractor shall furnish all labor, equipment, materials, supplies, supervision, and transportation necessary and incidental to provide mobilization and de-mobilization To the place of performance, in accordance with the attached SOW, specifications, technical provisions, drawings, or notes attached hereto, including all the provisions and clauses provided in the RFQ.
EST
DY
0002 The contractor shall furnish all labor, equipment, materials, supplies, supervision, and transportation necessary and incidental to provide underground cleanout, in accordance with the attached SOW, specifications, technical provisions, drawings, or notes attached hereto, including all the provisions and clauses provided in the RFQ.
EA
0003A The contractor shall furnish all labor, equipment, materials, supplies, supervision, and transportation necessary and incidental to provide 4” PVC solid sewer pipe, in accordance with the attached SOW, specifications, technical provisions, drawings, or notes attached hereto, including all the provisions and clauses provided in the RFQ.
LF
0003B The contractor shall furnish all labor, equipment, materials, supplies, supervision, and transportation necessary and incidental to provide 8” PVC solid sewer pipe, in accordance with the attached SOW, specifications, technical
0004 The contractor shall furnish all labor, equipment, materials, supplies, supervision, and transportation necessary and incidental to provide curtain drain, in accordance with the attached SOW, specifications, technical provisions, 0005 The contractor shall furnish all labor, equipment, materials, supplies, supervision, and transportation necessary and incidental to provide 1,200 gallon concrete septic tank, in accordance with the attached SOW, specifications, technical
0006 The contractor shall furnish all labor, equipment, materials, supplies, supervision, and transportation necessary and incidental to provide 1,200 gallon concrete pump tank, in accordance with the attached SOW, specifications, technical provisions, drawings, or notes attached hereto, including all the provisions and clauses provided in the RFQ.
0007 The contractor shall furnish all labor, equipment, materials, supplies, supervision, and transportation necessary and incidental to provide 2” PVC sewer transport pipe, in accordance with the attached SOW, specifications, technical
SCHEDULE Continued Issue Date
Item No. Supplies/Services Quantity Unit Unit Price Amount
0008 The contractor shall furnish all labor, equipment, materials, supplies, supervision, and transportation necessary and incidental to provide low-pressure drainfield mound, in accordance with the attached SOW, specifications, technical
0009 The contractor shall furnish all labor, equipment, materials, supplies, supervision, and transportation necessary and incidental to provide tank abandonment, in accordance with the attached SOW, specifications, technical provisions, 0010 The contractor shall furnish all labor, equipment, materials, supplies, supervision, and transportation necessary and incidental to provide mound removal, in accordance with the attached SOW, specifications, technical provisions, CY
0011 The contractor shall furnish all labor, equipment, materials, supplies, supervision, and transportation necessary and incidental to provide washed pea gravel, in accordance with the attached SOW, specifications, technical provisions, drawings, or notes attached hereto, including all the provision and clauses provided in the RFQ.
CY
Total (0001-0011)
Price Schedule Notes:
1. Line Items 0001-0009 shall include all salaries, overhead, G&A, fringe benefits, insurance, bonding, profit, travel, materials to include all subcontracting costs, and any other costs detailed in the attached specifications, notes, details, and, plans necessary to perform the work herein. Offeror(s) must submit pricing for the line items in the above schedule. In the event that estimated quantities are lower or higher than estimated (+ or – 25%), any negotiated change will be based on the firm-fixed unit prices in the schedule.
2. Line Item 0010: Payment for mound removal as specified in the design drawings shall be made at the contract unit price for the number of cubic feet removed. Payment shall include removal of existing mound system including chambers, piping, and biomat (contaminated soil). Payment shall include over-excavation of contaminated soil and removal of chambers, contaminated soil, and piping from site and disposal in accordance with Washington Department of Ecology regulations. Un-contaminated material may be used as cover for new mound.
3. Line Item 0011: Payment for washed pea gravel shall be made at the contract unit price for the number of cubic feet installed. Payment shall include pea gravel fill to natural grade. Pea gravel is not needed if biomat does not extend below elevation of natural grade.
4. Line items under negotiated changes shall only be reimbursed for actual costs performed at the firm-fixed unit price not-to-exceed the total amount for each item in the change. Associated work should be validated and approved by the Contracting Officer’s Representative (COR). Travel expenses will not be reimbursed. Failure to quote in this manner may result in proposal rejection.
KEY:
DY=Day EST=Estimated EA=Each LF=Linear Feet CY=Cubic Yard