This document contains an amendment to a solicitation and related questions and answers regarding a federal construction contract opportunity. The Federal Bureau of Prisons is seeking a contractor to relocate the grease trap at the Federal Correctional Institution in Marianna, Florida. The scope of work involves demolishing existing drain lines and a grease interceptor, installing new drain lines and floor drains, and placing a new grease interceptor. The amendment changes the bid due date to August 10, 2022, extends the period of performance to 200 calendar days, and incorporates bidder questions and answers as well as additional drawings. The opportunity is designated as a 100% small business set-aside for a contractor with a NAICS code of 237110 and less than $39.5 million in annual revenue.

View the file

Other files for this federal contract opportunity

Other files attached to FCI Marianna - Relocate Grease Trap FPC, newest first.
File Type Posted
Abstract.pdf PDF
Amendment 0001.pdf PDF
1 - Instruction to Bidders.pdf PDF
6 - SF-24 Bid Bond Form .pdf PDF
7 - Criminal History Check Form.pdf PDF
2 - Solicitation 15BFA022B00000008A.pdf PDF
5 - Construction Wage Rates - FL20220017 2-25-2022.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

15BFA022B00000008A/0002 Page 1 of 6

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE PAGE OF PAGES

1 6

2. AMENDMENT/MODIFICATION NUMBER

3. EFFECTIVE DATE

07/15/2022

4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

BFAOCODE

Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, TX 75051

Julie Bergami jbergami@bop.gov

6. ISSUED BY 15B308CODE

Federal Bureau of Prisons FCI Marianna

3625 FCI ROAD

Marianna, FL 32446

7. ADMINISTERED BY (If other than Item 6)

9A. AMENDMENT OF SOLICITATION NUMBER

15BFA022B00000008A

CODE FACILITY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, country, state and ZIP Code) (X)

X 9B. DATED (SEE ITEM 11)

06/15/2022

10A. MODIFICATION OF CONTRACT/ORDER

NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X XThe above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning __1__copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

ORDER NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return _______ copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Amendment 0002 is hereby issued to incorporate the following into the Invitation for Bids 15BFA022B00000008A:

1) Change bid due date to August 10, 2022, no later than 2:00 pm CST;

2) Change performance completion from 120 calendar days to 200 calendar days after receiving notice to proceed;

3) Incorporate Bidder questions with BOP responses (see attached); and

4) Incorporate seven additional drawings.

[End of Amendment 0002]

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Julie Bergami Contract Specialist

(Signature of person authorized to sign)

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED

By (Signature of Contracting Officer)

16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

Julie Bergami Typewritten Text

22Z3AB4

Julie Bergami Highlight

Invitation for Bids 15BFA022B00000008A Relocate Grease Trap FPC – FCI Marianna Questions and Answers

Question 1:

What will be the extent of the background checks? Will badging be a requirement?

BOP Response: Clarification NCIC and Attachment 10 paperwork will be required, same as site visit requirement.

Question 2:

There was discussion of a trough/trench installed in front of the Tilt Skillet leading down to the floor drain. There is a Watts Dead Level Trench Drain in the SOW. Is this the product for that installation for there is not detail in the drawings? Could we receive clarification?

Watts dead level trench drain or equal.

Question 3:

Does the contractor need to install an epoxy cove base around the perimeter of the floor? If so, what would be the dimensions?

No cove base is required. Wall may need to be dressed/smoothed after demo to provide aesthetics for painting by owner.

Question 4:

Clarification that the owner will recycle material (Steel/Piping) that is demoed?

Owner will dispose of all recyclable steel/piping. Container will be provided on site by owner to receive demoed steel/piping.

Question 5:

The drawings detail clean outs in the receiving corridor. Upon the site visit, it was determined there were no clean outs. How would the contractor need to proceed? Would new clean-outs need to be installed in this location?

Contractor will install new clean outs as per drawings provided.

Question 6:

What allowable downtime will be available to the contractor when the installing/tying in the new septic lines?

From review of the site visit, the existing septic lines are routed in the location of the New Grease Trap which would result in a sufficient amount of downtime for the installation of grease trap and piping.

Allowable downtime will be as minimal as practical and not to exceed 2 weeks of sanitary sewer disruption for the Administration Building areas. The owner expects the Administration Building sanitary sewer re-direct to be priority for to return to service once disrupted.

Question 7:

Would additional time be available for this project? Due to the lead time of the Grease Trap being 14-16 weeks and the extent of demolition and piping, we perceive that the project duration may not be sufficient.

BOP Response: Change See Amendment 2 changing completion of performance to 200 days from notice to proceed.

Question 8:

Will any shoring be required once the existing grease trap is removed from inside the building until dirt and compaction has been completed?

Shoring will be utilized if required by standard industry practices.

Question 9:

What is the approximate thickness and anticipated reinforcement of the slab on grade? Are there any anticipated structural footers that will be encountered? If so, what are the dimensions and what shall be the requirements for demolition, reinforcement, and replacement of said footers?

BOP Response: Change See Amendment 2, additional drawings.

Question 10:

Drawings Plan C100 details 3 septic and/or grease drains coming through the doorway from the receiving corridor. Is there an additional drain line in addition to the 2 coming through the door frame noted on Drawing P-101.

Drawing 8.P01R provided for reference.

Question 11:

Who will be the approving party on the low-pressure testing?

The owner will be the approving party.

Question 12:

If any existing electrical, gas, telephone, or fiber utilities are discovered during investigation, will the contractor bear the cost to replace and/or reroute these utilities to complete the installation of Septic/Grease line and/or Grease Trap?

If additional existing utilities are discovered, the contractor will submit a RFI to the owner to determine a plan to resolve the issue.

The contractor remains responsible to verify and locate utilities prior to commencing earth work to avoid damage to existing utilities.

Question 13:

Will the contractor be responsible for painting of any walls that minor removal and replacement are performed for epoxy floor installation and/or vent repair?

The owner will be responsible for painting of walls as needed.

Question 14:

Will the owner be responsible for the disconnecting, moving and reconnection of kitchen equipment?

The owner will be responsible for disconnecting, moving and re-connecting of kitchen equipment.

Question 15:

What are the max allowable contractors allowed for the one allowable escort provided by the owner?

Up to 10 contractors per one escort.

Question 16:

Will subcontractors be able to visit the site during the bidding process to provide accurate bids being it would difficult to bid without reviewing the site?

A site visit was scheduled and conducted on June 28, 2022. Per the solicitation, that is the only site visit to be held before bid opening.

Question 17:

Will any compaction testing be required? Will existing soil be acceptable for fill? What testing will need to be required and at what lifts?

No compaction testing required. Existing soil is acceptable for fill. No testing required.

Question 18:

It appears that the Governments estimate could potentially be too low to perform this project. Will additional funds be available if the bidder exceeds the government’s top dollar estimate?

At this time, the government’s estimated magnitude for this project will not change. Should there be an increase, the government will reassess based on the circumstances.