Questions and Answer HER.pdf
PDF 67 KB Posted
- Solicitation number
- 15B61920B00000001
About this file
This document contains a solicitation for upgrade of a programmable logic controller system at the Federal Correctional Institution in Herlong, California. The Federal Bureau of Prisons is seeking a firm-fixed-price construction contract to provide all necessary labor, equipment and materials to upgrade the PLC system, including new touch screen monitors. The performance period is 288 calendar days from notice to proceed. This is a 100% small business set-aside for a contractor with a NAICS code of 238210 and size standard of $16.5 million or less. The solicitation will be distributed solely through beta.SAM.gov and all bidders must be registered as a small business on that system.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Abstract.pdf | ||
| AMEND 00001 HER.pdf | ||
| Site Visit Meeting Minutes.pdf | ||
| 5 - Construction Wage Rate (01312020).pdf | ||
| 1 - Instructions to Bidders.pdf | ||
| 6 - SF24 Bid Bond.pdf | ||
| 7 - Criminal History Check Form.pdf | ||
| 2 - Solicitation.pdf | ||
| 5 - Construction Wage Rate.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FCI HERLONG – UPGRADE PLC SYSTEM
PROJECT 6C6K QUESTIONS & ANSWERS
SOLICITATION 15B61920B00000001
SUBMITTED BY JNV GROUP INC:
1) The scope details the provision for new touch screens. However, the scope does not detail the type of software to run on the touch screens. We think the intent is Human Machine Interface (HMI) software is required. Is HMI software required? If yes, manufacturer and version is needed. Also, if there is HMI software required, how are the screens to be graphically laid out on the touch screen computer?
CLARIFICATION: B.3 of SOW contractor has discretion.
2) From the drawing, we understand that ITS stands for Inmate Telephone System, and it is a shutoff/enable by POD. Please confirm.
CLARIFICATION: Yes
3) We understand the fire alarm system interface is for General Fire Alarm activation only. Please confirm. We also understand California State Fire Marshall is NOT the authority having jurisdiction. Please confirm.
CLARIFICATION: Question 1 is yes. Question 2 is yes.
4) We understand there will be a week in June 2020 where there will be no AC power in the facility. Please confirm.
5) We understand the new touch screen monitors will be mounted to the existing
19” wide slope racks in the control room. These monitors will be on a simple tilt VESA mount. Please confirm.
CLARIFICATION: They are to be flat surface mounted touch screen monitors which will mount to the existing 19” consul space and not VESA mounted.
6) From the drawing we note “Audio” going into a PLC. We understand from the site review this is only for selecting audio paging paths to the inputs of the existing TOA amplifiers at each location. Please confirm.
7) We understand at each system location are 1 or more dark fiber connections the
Contractor may use for the in-situ cutover. Please confirm.
CLARIFICATION: No dark fiber will be needed by contractor.
8) We understand the scope to replace existing CAT5 PLC cabling with CAT7. There will be no speed benefit in the system by migrating from CAT5 to CAT7. Please acknowledge and confirm.
CLARIFICATION: We understand there is no speed benefit.
9) We understand the existing system has parts of it NOT working. Please confirm the contractor has no responsibility for existing deficiencies and not responsible for failed ‘equipment’.
CLARIFICATION: The contractor has no responsibility for existing deficiencies and not responsible for failed ‘equipment’.
10) Please confirm how many contractual calendar days the contractor has to complete the scope of work.
CLARIFICATION: See solicitation box 11. (288 calendar days)
11) We understand the FCI Herlong facility in 2019 had no weather-related shutdowns or security shutdowns. Please confirm.
CLARIFICATION: No Shutdowns in 2019. However see pre-bid meeting minutes section 7 #4.
12) We understand that no communications devices are allowed inside the facility.
However, in order for the contractor to complete an in-situ cutover correctional officers will have 2-way radios on a secure independent channel that can be used by the contractor for site communications. Please confirm.
CLARIFICATION: Only Bureau staff are allowed to use the radios or lan lines to communication for this purpose of this project.
13) We understand a recent change requiring ‘stick vests’ by operational staff.
However, the contractors will not be exposed to inmate population and will not be required to wear. Please confirm.
CLARIFICATION: Contractors are not required to wear protective vests.
14) We heard a ‘rumor’ that there will be a change in the proposed network layout and not use the media converters shown on the drawing. It would imply fiber to the PLC controllers. Please kill this rumor; confirm or deny.
CLARIFICATION: No fiber is needed to the PLC controllers.
15) The existing intercom system is not a TOA system as the bid documents describe. Our on-site review shows two (2) Rauland Bord DCC110 talk back amplifiers with only 2 voice paths. Please confirm.
CHANGE: Yes, there is 2 Rauland Borg DCC12 intercom amplifiers and 1 TOA 900 series2 M-9000MK2 in the main PBX room.
| FCI HERLONG – UPGRADE PLC SYSTEM PROJECT 6C6K QUESTIONS & ANSWERS SOLICITATION 15B61920B00000001 |
| CLARIFICATION: B.3 of SOW contractor has discretion. |
| CLARIFICATION: Yes |
| CLARIFICATION: Question 1 is yes. Question 2 is yes. |
| CLARIFICATION: Yes |
| CLARIFICATION: They are to be flat surface mounted touch screen monitors which will mount to the existing 19” consul space and not VESA mounted. |
| CLARIFICATION: Yes |
| CLARIFICATION: No dark fiber will be needed by contractor. |
| CLARIFICATION: We understand there is no speed benefit. |
| CLARIFICATION: The contractor has no responsibility for existing deficiencies and not responsible for failed ‘equipment’. |
| CLARIFICATION: See solicitation box 11. (288 calendar days) |
| CLARIFICATION: No Shutdowns in 2019. However see pre-bid meeting minutes section 7 #4. |
| CLARIFICATION: Only Bureau staff are allowed to use the radios or lan lines to communication for this purpose of this project. |
| CLARIFICATION: Contractors are not required to wear protective vests. |
| CLARIFICATION: No fiber is needed to the PLC controllers. |
| CHANGE: Yes, there is 2 Rauland Borg DCC12 intercom amplifiers and 1 TOA 900 series2 M-9000MK2 in the main PBX room. |