Attachment A – Price Schedule

BASE YEAR

BURN CELL COMPLEX QUATITY UNIT UNIT PRICE AMOUNT

Burn Cells 96 Each $ $ Flashover Cells 24 Each $ $ Multi-Room Burn Building 4 Each $ $

OPTION YEAR 1

BURN CELL COMPLEX QUATITY UNIT UNIT PRICE AMOUNT

Burn Cells 96 Each $ $ Flashover Cells 24 Each $ $ Multi-Room Burn Building 4 Each $ $

OPTION YEAR 2

BURN CELL COMPLEX QUATITY UNIT UNIT PRICE AMOUNT

Burn Cells 96 Each $ $ Flashover Cells 24 Each $ $ Multi-Room Burn Building 4 Each $ $

OPTION YEAR 3

BURN CELL COMPLEX QUATITY UNIT UNIT PRICE AMOUNT

Burn Cells 96 Each $ $ Flashover Cells 24 Each $ $ Multi-Room Burn Building 4 Each $ $

OPTION YEAR 4

BURN CELL COMPLEX QUATITY UNIT UNIT PRICE AMOUNT

Burn Cells 96 Each $ $ Flashover Cells 24 Each $ $ Multi-Room Burn Building 4 Each $ $

Estimated Total $

NOTE: The quantities per year reflect a realistic expectation for order under the resulting IDIQ Contract, however the quantities per year are provided for purposes of price evaluation only. The Government may order less than the stated quantities, and the contractor shall not be entitled to revise pricing based upon variations in the quantities, nor shall they be entitled to an equitable adjustment based upon change quantities.