15-ADOT Loop 101 Cost Proposal Details_Parsons.xlsx
XLSX spreadsheet 21 KB Posted
- Attached to
- Master Agreement AZ|CTR078030
- Contract number
- CTR078030
- Issued by
- Arizona
About this file
This document is a detailed cost proposal from Parsons and Iteris for the Arizona Department of Transportation (ADOT) Loop 101 Integrated Corridor Management (ICM) Decision Support System (DSS) project. The contract involves multiple mobility partners, including ADOT and the Maricopa County Department of Transportation (MCDOT), with Parsons and Iteris collaborating to develop a comprehensive transportation management system.
The contract encompasses four core service areas: Project Management and Administration, DSS Design, DSS Development/Deployment/Integration, and DSS Operations and Maintenance. The total contract value is $1,518,133.41, with an additional $250,000 for iNET ATMS Module License Costs. The project involves developing sophisticated software for traffic management, including capabilities such as system engineering, stakeholder engagement, software development, system testing, training, and ongoing operational support. Key technical components include interfaces for traffic signal systems, dynamic message signs, vehicle detection, ramp metering, CCTV cameras, transit prioritization, and data analytics. The contract includes a two-year warranty and provisions for ongoing maintenance, with assumptions that ADOT will provide necessary cloud services, communication links, and support infrastructure.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CTR078030_Contract_Documents.pdf | ||
| 16-Loop 101 Cost Proposal Annual Operations and Maintenance Support_Parsons.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Cost Breakdown by Task, Individual Classification, hours, rate and ODCs | |||||||||||||||
| Parsons | Iteris | ||||||||||||||
| Task | PM | Principal-in-Charge | Project Engineer | IT Manager | Installation Manager | Senior Engineer | Engineer II | Engineer I | Principal | Lead Engineer | Analyst | Support Staff | ODCs | Total | |
| $326.29 | $372.00 | $235.60 | $235.60 | $198.40 | $198.40 | $148.80 | $99.20 | $375.00 | $275.00 | $150.00 | $135.00 | ||||
| Core Services #1 - Project Management and Administration | $174,640.97 | ||||||||||||||
| Kickoff Meeting | 8 | 2 | 2 | $3,825.55 | |||||||||||
| Develop Project Management Plan | 40 | 4 | 4 | 4 | $16,424.54 | ||||||||||
| Develop System Engineering Management Plan | 4 | 8 | 8 | 64 | 16 | $24,418.77 | |||||||||
| Develop and update Project Schedule | 16 | $5,220.70 | |||||||||||||
| Developo, Maintain, and Update Risk Register | 16 | $5,220.70 | |||||||||||||
| Develop Staffing Plan | 16 | $5,220.70 | |||||||||||||
| Project Management Meetings | 52 | 52 | $36,467.27 | ||||||||||||
| Stakeholder input and Review Meetings | 16 | 16 | 16 | 36 | 72 | 72 | 25 | $500.00 | $60,139.70 | ||||||
| Partnering Meetings/Stakeholder Engagement | 8 | 8 | 8 | 8 | 8 | 8 | $12,482.35 | ||||||||
| Monthly Invoicing & Progress Reporting | 16 | $5,220.70 | |||||||||||||
| Core Services #2 - DSS Design | $273,910.94 | ||||||||||||||
| Design/Stakeholder Engagement Plan | 4 | 4 | 4 | 4 | 4 | 4 | 15 | 40 | 45 | 10 | $300.00 | $31,290.17 | |||
| Conduct Requirements Workshop with Stakeholders | 8 | 16 | 16 | 16 | 16 | 16 | $4,000.00 | $22,879.15 | |||||||
| System Requiremens Specifications | 2 | 4 | 4 | 4 | 16 | 16 | 8 | $9,679.79 | |||||||
| Document DSS Response Plan Recommendations | 2 | 8 | 4 | 4 | 20 | 45 | 40 | $30,148.39 | |||||||
| IT Governce Framework | 2 | 4 | 40 | 40 | 20 | $22,922.99 | |||||||||
| Plan for Software Development | 2 | 16 | 8 | 8 | 40 | 40 | 20 | $23,766.19 | |||||||
| High-Level System Design Document | 2 | 8 | 24 | 8 | 60 | 40 | 20 | $29,618.99 | |||||||
| Interface Control Document | 2 | 8 | 8 | 8 | 80 | 40 | 20 | $29,817.39 | |||||||
| Data Governce Framework | 2 | 8 | 8 | 4 | 24 | 16 | 8 | 3 | 5 | $15,651.79 | |||||
| Requirements Traceability Matrix | 2 | 2 | 2 | 2 | 20 | 16 | 8 | $9,134.19 | |||||||
| Phasing Strategy for System Development | 2 | 8 | 2 | 2 | 20 | 16 | 2 | $9,952.59 | |||||||
| Proposed system and subsystem testing plans | 2 | 8 | 8 | 8 | 40 | 60 | 8 | $23,666.99 | |||||||
| Design meeting agendas, materials and summaries | 8 | 26 | 8 | 8 | 16 | $15,382.35 | |||||||||
| Core Services #3 - DSS Development, Deployment and Integration | $962,716.85 | ||||||||||||||
| Develop DSS software, logic, algorithms, and thresholds for DSS activation | 4 | 144 | 144 | 144 | 800 | 1200 | 1500 | $250,000.00 | $833,807.57 | ||||||
| Implement phased development and testing of DSS capabilities | 4 | 16 | 24 | 24 | 80 | 20 | 80 | $42,274.77 | |||||||
| Provide incremental demonstrations to ADOT and Loop 101 Mobility partners (once per month) | 4 | 8 | 8 | 8 | 16 | 16 | 16 | $13,804.37 | |||||||
| Faciliate tabletop demonstrations to simulate ICM operations in the test environment | 2 | 4 | 4 | 4 | 8 | 8 | 8 | 15 | 40 | 30 | $28,027.19 | ||||
| Complete full system acceptance test with ADOT, MCDOT, Loop 101 Mobility partners and stakeholders | 4 | 8 | 8 | 8 | 16 | 16 | 16 | $13,804.37 | |||||||
| Create summary of full system acceptance tests and sign-off | 2 | 2 | 8 | 40 | $8,662.99 | ||||||||||
| Migrate the DSS from the test enivrtonment to the operational environment | 16 | 16 | $6,944.00 | ||||||||||||
| Prepare plan to roll out the DSS to other Loop 101 Mobility partner agencies | 4 | 8 | 8 | 24 | 24 | 8 | $15,391.57 | ||||||||
| Core Services #4 - DSS Operations and Maintenance- System Testing and Acceptance | $106,864.65 | ||||||||||||||
| Develop training manuals, training resources, and conduct training via workshops | 2 | 16 | 16 | 16 | 16 | 60 | 20 | $25,452.59 | |||||||
| Develop tools and resources to support stakeholder troubleshooting | 2 | 16 | 16 | 16 | 16 | 16 | $16,921.39 | ||||||||
| Prepare an Operations Manual | 2 | 16 | 16 | 16 | 16 | 16 | $16,921.39 | ||||||||
| Provide operational support | 2 | 40 | $4,620.59 | ||||||||||||
| Provide a minimum of a two (2) year warranty support on all software and equipment | 2 | 40 | $4,620.59 | ||||||||||||
| Implement a process for users to submit issues or problems | 2 | 8 | $1,446.19 | ||||||||||||
| Respond to issues, malfunctions, and system interruptions | 2 | 40 | $4,620.59 | ||||||||||||
| Participate in up to three (3) after-action reviews in the first year of operations | 2 | 6 | 6 | 6 | $4,670.19 | ||||||||||
| Participate in in-person annual workshops with all Loop 101 Mobility partners and stakeholders | 2 | 16 | 16 | 16 | $4,000.00 | $15,366.19 | |||||||||
| Provide a monthly report to the Department of issues, issue tickets and summary of response times, diagnoses and issue resolution | 2 | 6 | 6 | 24 | $8,241.39 | ||||||||||
| Develop a recommended strategy and recommendations for proceeding with subsequent phases | 4 | 4 | 4 | 4 | $3,983.57 | Iteris Amount | |||||||||
| Grand Totals | 272 | 16 | 426 | 496 | 454 | 1384 | 1652 | 1870 | 149 | 210 | 195 | 35 | $258,800.00 | $1,518,133.41 | $148,400.00 |
| iNET® ATMS Module License Costs | $250,000 |
| Traffic Signal System | |
| Dynamic Message Sign | |
| Vehicle Detector System | |
| Ramp Metering System | |
| CCTV Cameras | |
| Transit SignAutomatic Vehicle Locational Priority and Preemption Interface | |
| Environmental Sensor Station | |
| Computr Aided Dispatch | |
| Event Management | |
| Decision Support System | |
| Work Zone Traffic Management | |
| Mobile | |
| Center-to-Center | |
| Data Analytics Platform |
| Assumptions |
| 1. ADOT will maintaain all operational communications links to systems, devices and interfaces to support Loop 101 ICM functional integration. |
| 2. ADOT will coordinate any support needed from third parties and agencies to facilitate technical integration for Loop 101 ICM. |
| 3. ADOT will provide all necessary AWS cloud services to support hosting iNET® application in development, testing and production. |
| 4. If on premise hardware is required, the HW and COTS will be provided by ADOT |
| 5. Annual O&M support costs will incur 3% escaltion year-to-year |
| 6. All pertinent Loop 101 ICM agencies/partners will provide accurate and complete documentation |
| 7. To accommodate the 12-month desired schedule, each deliverable will have two submissions, draft and final |
| 8. ADOT and respective ICM/DSS partners shall be responsible for the performance of all existing equipment. |
| 9. For systems not replaced by the Vendor, ADOT shall continue to pay all licensing, maintenance, and support costs associated with existing equipment. |
| 10. ADOT and respective ICM/DSS partners shall be responsible for all third party licensing, support, or required API enablement. As required for all third party systems within the scope of this RFP. |
| 11. ADOT and respective ICM/DSS partners will be responsible for any/all on-premises, ADOT AWS, ITS network, server, storage, and desktop computer environments |
| 12. ADOT and respective ICM/DSS partnersshall provide the required network connectivity, servers, and storage to provision the DSS in ADOT's AWS cloud and on-premises portions of the Project. ADOT shall provide connectivity between ADOT AWS cloud and all external systems as requried to meet the requirements, integrations, and utilzation described in the RFP, requirements, and con-ops. |
| 13. ADOT and respective ICM/DSS partners shall provide VPN access to the Vendor's personnel including subcontractors per the established RACI chart. VPN access shall be limited to the network segments used to provision the Project software. |
| 14. ADOT and respective ICM/DSS partners shall provide and manage VPN access to all ICM/DSS personnel, authorized to utilized the ICM/DSS including subcontractors per an established RACI chart. VPN access shall be limited by ADOT and respective ICM/DSS partners only to approved ICM/DSS resources, in alignemtn with State and ADOT security policies and requirements. |
| 15. ADOT and respective ICM/DSS partners shall provision the private interconnect to the cloud and size it according to the needs of the Project applications. ADOT shall be responsible for the cost and service level key performance indicators (KPIs) on this link. As required for any latency sensitive operations reqruiements for the 101 loop ICM DSS, DOT shall provide direct communications with latency below 100ms between ADOT AWS cloud and any external/on-premises components. |
| 16. ADOT and respective ICM/DSS partners is responsible for computer furniture, desktops, screens, and Operator workstations. ADOT shall be responsible for addressing any issues related to operator browsers/workstations. Workstation issues not directly related to the Vendor-installed software shall not be factored into SLA requirements. |
| 17. ADOT and respective ICM/DSS partners will be responsible for any change to field equipment (e.g. field switches, cameras, etc.),both during the RFP delivery phase and the RFP operations & maintenance phase, and that any work required on the field equipment shall be ADOT’s responsibility. This may include reconfiguration or renewal of equipment. |
| 18. ADOT and respective ICM/DSS partners shall be responsible for all power and communications for field devices. Field device demonstrated failures or proven failures shall not count against the SLA. |
| 19. ADOT and respective ICM/DSS partners shall provide the equipment and hardware needed to back up all on-premises Project data per the established requirements and all other data per ADOT's established retention periods. |
| 20. ADOT and respective ICM/DSS partners shall provide and fund any third party service and/or audit and/or penetration testing required to complete AZRamp assessment and compliance for the life of the ICM/DSS system. Parsons shall not fund any third party service and/or audit and/or penetration testing required to complete AZRamp assessment and compliance for the life of the ICM/DSS system. Parsons is responsible to correct any non-compliance identified through AZ ramp or any security assessment copleted by ADOT and respective ICM/DSS partners, exclusive to the iNET ICM/DSS application components, and software/code, and COTS applications provided by Parsons within the scope of this project. |
| 21. The estimated yealy AWS cost is approximately $100K. This estimated AWS yearly cost is based on RFP requirements,and typical/equivilent costs from similar projects. These estimates will likely change significantly during detailed design phase when all interface, data, retention, and security details are formalized for the ICM/DSS. Actual instance types, utilization, and pricing will depending on ADOT AWS contracts, and system detailed design outcomes. |