About this file
B50 Cooling Tower Deck Replacement - Technical Specification
This is a Technical Specification document for a cooling tower deck replacement project in Florida. The project involves the purchase and installation of a new fiberglass reinforced plastic (FRP) fan deck for a Marley F499A-4.0-10B cooling tower located at Brandy Branch Generating Station. The scope of work includes removal and disposal of the existing FRP fan deck, with the awarded contractor required to furnish all labor, supervision, materials, cranes, and subcontracts necessary to complete the installation. A mandatory pre-response meeting is scheduled for September 1, 2026, at 11:00 AM, with responses due by September 22, 2026.
The technical specifications detail the requirements for the replacement fan deck, including performance standards, material specifications, dimensional requirements, and installation procedures specific to the Marley F499A-4.0-10B cooling tower model. The specifications establish the technical parameters that the submitted equipment and installation methodology must meet to ensure compatibility with the existing cooling tower system and operational requirements at the generating station.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1412213278 JEA Bid Bond.pdf | ||
| 1412213278 Appendix B - Bid Forms.pdf | ||
| 1412213278 Appendix B- Subcontractor Form.xlsx | XLSX spreadsheet | |
| 1412213278 Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1.0 Location of Property
JEA Brandy Branch Generating Station is located at 15701 West Beaver Street, Jacksonville, Florida 32234.
2.0 Scope of Work
2.1. This specification covers the purchase and installation of a new fiberglass reinforced plastic (FRP) fan deck for a Marley F499A-4.0-10B cooling tower at Brandy Branch Generating Station. This specification also covers removal and disposal of the existing FRP fan deck. The awarded Company is to furnish all labor, supervision, material, cranes, subcontracts, etc. to perform the before mentioned work.
2.1.1. The Company shall remove and dispose of the existing one-foot FRP deck panels that are being replaced. The Company shall provide all material and labor for installation of the FRP deck.
2.1.2. The Company shall take every precaution to not damage the cooling tower structural while removing current deck panels and while installing the new deck panels.
2.1.3. The Company shall remove all existing lighting and temporary support the cable tray. Lighting and cable trays will need to be restored in a manner that is similar to the existing lighting after the new fan deck is in place.
2.1.4. The Company shall remove and securely store all existing lightning protection and restore the lightning protection after the new fan deck is in place. Any damaged lightning protection shall be pointed out to JEA.
3.0 Codes and Standards
The following codes and standards, as amended to date, are applicable under this contract:
• Codes, Rules and Regulations of the State of Florida
• Occupational Safety and Health (OSHA) o 1917.120
• American Society of Civil Engineers (ASCE) o ASCE Standard ANSI/ASCE 7-2010
4.0 Existing FRP Fan Deck
4.1. The existing FRP fan deck has UV damage and cracks in multiple areas. An inspection performed by the OEM recommends replacing the deck with an upgraded design that uses two-foot FRP panels instead of the one-foot panels that are currently in place.
5.0 Demolition and Removal
5.1 The existing FRP deck panels is connected to the cooling tower structure, which is not being replaced. Extreme care must be taken so that no damage is done to the cooling tower or any other equipment during the removal of the existing fan deck. It is emphasized that equipment located adjacent to and below grade in the working area are very essential elements of the plant. All such adjacent equipment must be kept safe during all demolition and installation work. When possible, equipment will be de-energized by JEA personnel.
JEA will tag-out any equipment that needs to be de-energized.
5.2 The Company shall erect and properly maintain danger signs, barricades, tags, lights and other safeguards as may be required for safe working conditions.
5.3 All materials from the fan deck removal shall become the property of the Company and shall be removed promptly from the site. Removal of debris from the site shall be done frequently to avoid any collection of debris.
6.0 Replacement FRP Fan Deck
6.1 The Company shall be fully responsible for the complete replacement of the existing cooling tower fan deck including verification of field dimensions and verification of possible obstructions. The Company shall purchase new two-foot FRP deck panels to replace the existing one-foot deck panels. The Company shall inspect the condition of the existing cooling tower structural to ensure there will be no issues connecting the deck panels.
6.2 Any hardware required shall be provided by the Company and shall be stainless.
7.0 Shipment
7.1 The Company shall be fully responsible for the safe shipment, storage, and handling of the components of the deck panels. The Company shall be fully responsible for the deck panels on the job site until the system is turned over to the Plant. The Company is responsible for all shipping costs and for all truck loading and unloading of material at the job site.
7.2 Hardware, and other miscellaneous parts shall be packed in suitable boxes for storage at the job site.
8.0 Construction
8.1 Temporary Utilities
A. JEA will provide limited 110V - 20 ampere single-phase and 480V - 60 ampere three-phase electrical power at designated locations in the cooling tower area.
Company shall be responsible for additional power supply (Generator) requirements and transformers to provide any other required voltages. Company shall make electrical connections and supply sufficient quantities and lengths of cables and electrical connectors in safe working order.
B. Service air for construction activities is not available.
C. Isolating and tagging out of equipment prior to work by the Company will be provided by JEA.
D. Company to provide designated trash dumpsters, labeled by debris type. At project completion, all debris, screws and construction materials will be properly disposed.
E. Company to provide adequate sanitary facilities for all their personnel serviced at a minimum 3 times a week.
F. Company to provide any required break areas for personnel.
G. Contractor parking area is located on West side of plant ~1600’ from work area.
Only company placarded vehicles will be allowed @ work area.
8.2 Laydown & Assembly Area
The Company shall notify the JEA Project manager of the size of their required laydown and assembly area. The laydown and assembly location will be determined jointly by the JEA Project Manager and Company.
8.3 Project Schedule
A. The tentative outage schedule for Brandy Branch combined cycle is tentatively March 8, 2027 through April 21, 2027. The Company will have about 40 days available to perform scope of work thus allowing operational shutdown, startup, and testing activities. Tentative working days are 3/11/27-4/18/27.
B. Company shall provide the JEA Project Manager a detailed resource loaded project schedule within 2 weeks of award. Schedule shall outline all project details including but not limited to: Mobilization, Assembly, demobilization. It shall be in MPP format with copy in PDF format.
C. The project schedule for this contract shall be prepared and maintained by Company to provide coordination between subcontractors and suppliers, to establish the basis for measuring and monitoring Company progress and overall Project progress, to detect problems for the purpose of taking corrective action.
14.4 Project Meetings
A. Once Company has mobilized to Jobsite, JEA and Company representatives shall meet daily to update the following:
Current status of the job progress
Look-Ahead Schedule (requirements listed in Item B. below)
Current and projected manpower
Changes in the Work
Safety and Quality Control issues
Problem areas or concerns
B. The Look-Ahead Schedule shall:
Report all planned work that is to be accomplished during the current week and the next two weeks in support of, and in accordance with, Company's detailed Construction Schedule
Be personnel and resource loaded
Report the planned and actual progress of the previous week
Report critical activities that are identified to be completed by others, the delay of which would prevent Company from starting and completing its planned work activities in accordance with the detailed Construction Schedule.
| 1.0 Location of Property |
| 2.0 Scope of Work |
| 3.0 Codes and Standards |
| 4.0 Existing FRP Fan Deck |
| 5.0 Demolition and Removal |
| 6.0 Replacement FRP Fan Deck |
| 7.0 Shipment |
| 8.0 Construction |
| 8.3 Project Schedule |
| 14.4 Project Meetings |