Solicitation No. 140R6018R0013

View the file

Other files for this federal contract opportunity

Other files attached to EC - ECAO BARRIER PROJECT, newest first.
File Type Posted
Amendment_No._0003.pdf PDF
Amendment_No._0002.pdf PDF
Amendment_No._0001.pdf PDF
FedConnect File —

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. 140R6018R0013

Eastern Colorado Area Office Active Vehicle Barrier Installations Colorado

U.S. Department of the Interior Bureau of Reclamation JUNE 2018 Great Plains Region

This page intentionally left blank

ACTIVE VEHICLE BARRIER INSTALLATIONS

Colorado

FOREWORD

Work under this solicitation is to be performed at four (4) Bureau of Reclamation, Eastern Colorado Area Office facilities located in Colorado:

1. Two barriers are located along Heeney Road near Green Mountain Dam, 30 miles northwest of Silverthorne, Colorado in Summit County.

2. Two barriers are located along Mt. Elbert Forebay Dam Road near Mount Elbert Forebay Dam, 14 miles southwest of Leadville, Colorado in Lake County.

3. Two barriers are located along Turquoise Lake Road (Lake County Road 4) near Sugar Loaf Dam, 5 miles west of Leadville, Colorado in Lake County.

4. Three barriers are located along S. Larimer County Road 31 near Carter Lake Dam, 11 miles southwest of Loveland, Colorado in Larimer County.

Principal components of work under these specifications:

1. Furnishing and installing active vehicle barriers along various roadways that access dam crests. Work includes installation of retaining walls, shoulder widening and drainage improvements.

2. Furnishing and installing new guide rail in the vicinity of active vehicle barriers.

The Government anticipates award of a firm fixed priced construction contract with an anticipated period of performance of 400 days.

POINT OF CONTACT

The point of contact is Contracting Officer Gerri Voto-Braun. All questions and correspondence concerning this solicitation shall be directed to her via email at gvotobraun@usbr.gov. To ensure all communication will be properly documented for record purposes, phone calls will not be accepted.

PROPOSAL CLOSING DATE

See Section “A”: “SOLICITATION, OFFER, AND AWARD, STANDARD FORM 1442” immediately following the “TABLE OF CONTENTS”

METHOD OF SUBMISSION OF PROPOSALS

See Section L of this Solicitation

Foreward - 1

TYPE OF CONTRACT

This requirement is solicited as a “Request for Proposal (RFP), Lowest Price Technically Acceptable, using the Federal Acquisition Regulation Sub Part 15, Contract by Negotiation Procedures. Results from this solicitation will be an anticipated award of a Firm Fixed Price Contract.

COMPETITION REQUIREMENTS

This acquisition is restricted to a Total Small Business set-aside.

RECLAMATION SAFETY AND HEALTH STANDARDS (2014) EDITION)

For information regarding the Bureau of Reclamation’s publication “RECLAMATION SAFETY AND HEALTH STANDARDS” (2014 Edition):

http://www.usbr.gov/ssle/safety/RSHS/rshs.html, which is applicable to work under the anticipated contract. See Clause WBR 1452.223-81 SAFETY AND HEALTH.

PRE PROPOSAL SITE VISITS

Pre-proposal organized site visits will be held as follows:

For the two (2) locations near Mt. Elbert Dam and Reservoir and the two (2) locations near Sugar Loaf Dam: The organized site visit is Tuesday, June 26th, 2018, at 8:00 AM MOUNTAIN (COLORADO) TIME ZONE. Participants shall meet at the Bureau of Reclamation’s Mt. Elbert Powerplant located at 5583 Highway 82, Twin Lakes CO 81251.

For the two (2) locations near the Green Mountain Dam: The organized site visit is Tuesday, June 26th, 2018, at 1:00 PM MOUNTAIN (COLORADO) TIME ZONE. Participants shall meet at the Bureau of Reclamation’s Green Mountain Powerplant located at 170 County Road 1813, Heeney CO 80498.

For the three (3) locations near Carter Lake Dam: The organized site visit is Wednesday, June 27th, 2018, at 8:00 AM MOUNTAIN (COLORADO) TIME ZONE. Participants shall meet at the Bureau of Reclamation’s Eastern Colorado Area Office, 11056 West County Road 18E, Loveland CO 80537

Prospective Offerors should make arrangement by contacting John Foreman at telephone number 970-962-4527. Attendees are to provide and wear safety boots, hard hats, and safety vests.

SAM: Effective July 29, 2012, any contractor interested in doing business with the Government must register in the System for Award Management (SAM) database, prior to award of a contract or agreement. SAM is a Federal Government owned and operated FREE website that consolidates the Central Contractor Registration (CCR), the Online Representations and Certifications Application (ORCA), and the excluded parties list system (EPLS). The contractor’s DUNS and Bradstreet number and banking information are required for registration.

Contractors may obtain information on registration and annual confirmation requirements via the SAM website at https://www.sam.gov/portal/public/sam or by the Federal Service Desk at telephone number 1-866-606-8220. The Contractor's DUNS and Bradstreet number and banking information are required for registration. Contractors may obtain information on registration and

FOREWARD - 2

FOREWARD - 3

annual confirmation requirements via the SAM website, which can be accessed at https://www.sam.gov/portal/public/sam, or by telephone at the Federal Service Desk at 1-866- 606-8220.

PAYMENTS: Payment requests for the anticipated contract must be submitted electronically through the U.S. Department of the Treasury’s Internet Payment Platform (IPP) System. The IPP website is https://www.ipp.gov. The contractor must use the IPP website to register, access, and use IPP for submitting requests for payment. Contractor assistance with enrollment can be obtained by contacting the IPP production helpdesk via email at ippgroup@bos.frb.org or at telephone number 1-866-973-3131. If the contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the contractor must submit a waiver request in writing to the contracting officer with their proposal.

Active Vehicle Barrier Installations Solicitation No. 140R6018R0013

This page intentionally left blank.

Active Vehicle Barrier Installations Specifications No. 60-C0674

Table of Contents 00 01 10 - 1

SECTION C - DESCRIPTION / SPECIFICATIONS

TABLE OF CONTENTS

SECTION A – SOLICITATION, OFFER and AWARD, Standard Form 1442

SECTION B – SCHEDULE

SECTION C -- SPECIFICATIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 14 10 Use of Site 01 14 15 Forest Service Requirements 01 33 00 Submittals 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 30 Contractor's On-Site Safety Personnel 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 46 20 Testing Agency Services 01 51 00 Temporary Utilities 01 55 00 Vehicular Access and Parking 01 55 20 Traffic Control 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 56 32 Temporary Safety Fence 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 57 50 Tree and Plant Protection 01 57 60 Protected Species 01 60 00 Product Requirements 01 71 20 Surveying 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents

DIVISION 02 - EXISTING CONDITIONS

Not Used

DIVISION 03 - CONCRETE

03 30 00 Cast-In-Place Concrete

Table of Contents 00 01 10 - 2

DIVISION 04 - DIVISION 30

Not Used

DIVISION 31 - EARTHWORK

31 02 10 Water for Dust Abatement 31 11 00 Clearing and Grubbing 31 14 10 Stripping 31 23 10 Earthwork for Roadway Backfill and Compaction 31 23 11 Earthwork for Structures 31 37 10 Barrier Rock

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 12 10 Removal of Existing Pavement, Concrete Curb, Sidewalk, Driveway and/or Structures

32 12 22 Asphalt Concrete Pavement 32 92 20 Seeding and Soil Supplements

DIVISION 33 - UTILITIES

33 42 30 Corrugated Metal Pipe Culverts

DIVISION 34 - TRANSPORTATION

34 71 10 W-Beam Guardrails 34 71 15 Precast Concrete Vehicle Barriers 34 75 13 Active Vehicle Barrier

DIVISION 35 - DIVISION 51

Not Used

DIVISION 52 - DRAWINGS

52 00 00 Drawings

DIVISION 53

Not Used

SECTION D – PACKAGING AND MARKETING

Not Used

Table of Contents 00 01 10 - 3

SECTION E – INSPECTION AND ACCEPTANCE

E.1 Material and Workmanship…………………………………………………E-1 E.2 Inspection and Construction ………………………………………………. E-1 E.3 Warranty of Construction …………………………………………..……... E-2

SECTION F – DELIVERIES or PERFORMANCE F.1 Commencement, Prosecution, and Completion of Work ………………… F-1 F.2 Variation in Estimated Quantity……………………………………………F-1 F.3 Suspension of Work…........................…………………………………....... F-1

SECTION G – CONTRACT ADMINISTRATION DATA

G.1 Authorities and Delegations ……………………………………………….. G-1 G.2 Electronic Invoicing and Payment Requirements – Invoice Processing

Platform (IPP) ……………………………………………………………... G-2 G.3 Notice to Contractors – Contractor Performance Assessment Reporting

System ……………………………………………………………………... G-2

SECTION H – SPECIAL CONTRACT REQUIREMENTS

H.1 Site Security ……………………………………………………………….. H-1

PART II – CONTRACT CLAUSES

SECTION I – CONTRACT CLAUSES

I.1 Clauses Incorporated by Reference………………………………………... I-1 I.2 Commercial and Government Entity Code Maintenance………………….. I-3 I.3 Basic Safeguarding of Covered Contractor Information Systems………..... I-4 I.4 Order of Precedence – Uniform Contract Format ………………………….I-5 I.5 Minimum Wages Under Executive Order 13658 …………………………..I-6 I.6 Estimate of Percentage of Recovered Material Content for EPA

Designated Items……………………………………………………………I-9 I.7 Buy American – Construction Materials ......................................... ……..... I-10 I.8 Bid Guarantee …………………………………………………………....... I-12 I.9 Additional Bond Security ………………………………………………..... I-13 I.10 Performance and Payment Bonds – Construction ………………………… I-13 I.11 Federal, State, and Local Taxes …………………………………………… I-15 I.12 Payments under Fixed-Price Construction Contracts……………………… I-15 I.13 Prompt Payment for Construction Contracts…….………………………… I-16 I.14 Performance of Work by the Contractor …………………………………...I-25 I.15 Differing Site Conditions …………………………………………………. I-25 I.16 Physical Data …………………………………………………………….... I-25 I.17 Accident Prevention ……………………………………………………….. I-26 I.18 Specifications and Drawings for Construction Alternate II ……………….. I-26 I.19 Changes …………………………………………………………………..... I-27 I.20 Authorized Deviations in Clauses ………………………………………..... I-28

Table of Contents 00 01 10 - 4

I.21 Restriction on Endorsements – Department of the Interior …………….…. I-29 I.22 Release of Claims – Department of the Interior …………………………... I-29 I.23 Examination of Records by the Department of the Interior ……………….. I-29 I.24 Liability Insurance – Department of the Interior ……………………...…... I-29 I.25 Incorporation of Technical Proposal ……………………………………..... I-30 I.26 Asbestos-Free Warranty………………………………………………….....I-30 I.27 Safety and Health – Bureau of Reclamation ……………………………I-30

I.28 Protecting Federal Employees and the Public from Exposure to Tobacco Smoke in the Federal Workplace – Bureau of Reclamation …….. I-31

I.29 Hazardous Substances …………………………………………………....... I-31 I.30 Nonconforming Hazardous Materials ……………………………………... I-31 I.31 Preservation, Packaging, Packing, Marking, and Labeling of

Hazardous Materials (HAZMAT) for Shipments …………………………. I-32 I.32 Certification of Representatives for Corporate Sureties—Bureau of Reclamation …………………………………………………………….. I-33 I.33 Equipment Ownership and Operating Expense – Bureau of

Reclamation ……………………………………………………………….. I-33 I.34 Payment for Mobilization and Preparatory Work – Alternative III ………. I-35

I.35 Payment for Technical Data ………………………………………………..I-37 I.36 Claims Accounting – Bureau of Reclamation …………………………….. I-37 I.37 Other Contracts (Deviation) ………………………………………...….…. I-38 I.38 Preservation of Cultural Resources-Bureau of Reclamation …………........ I-38 I.39 Security Requirements—Bureau of Reclamation ……………….………… I-40 I.40 Modification Proposals – Alternative IV ………………………………….. I-47

PART III – DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

SECTION J – DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

General Decision Number CO180023, dated March 2, 2018 General Decision Number CO180024, dated January 5, 2018 Standard Form 24 – Bid Bond Past Performance Questionnaire Subcontracting Percentage Worksheet

PART IV – REPRESENTATIONS AND INSTRUCTIONS

SECTION K – REPRESENTATIONS, CERTIFICATIONS and OTHER STATEMENTS

OF OFFERORS

K.1 Annual Representations and Certifications ................................................... K-1 K.2 Information Regarding Responsibility Matters ………………………….... K-4 K.3 Certification Regarding Tax Matters …………………………………….... K-6

Active Vehicle Barrier Installations Solicitation No. 140R6018R0013

Table of Contents 00 01 10 - 5

SECTION L – INSTRUCTIONS, CONDITIONS, AND NOTICES TO BIDDERS

L.1 System for Award Management ................................................................... L-1 L.2 Commercial and Government Entity Code Reporting................................... L-2 L.3 Alternative Line Item Proposal …………………………………………..... L-3 L.4 Availability of Specifications Listed in the GSA Index of Federal

Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29 ……………………………………………………….... L-3

L.5 Availability of Specifications, Standards, and Data Item Descriptions Listed in the Acquisition Streamlining and Standardization Information System (ASSIST) ..........................................................................................L-4

L.6 Submission of Offers in the English Language ............................................ L-4 L.7 Submission of Offers in U.S. Currency ........................................................ L-4 L.8 Instructions to Offerors – Competitive Acquisition ..................................... L-4 L.9 Requirements for Certified Cost or Pricing Data and Data Other Than

Certified Cost or Pricing Data …………………………………………… L-9 L.10 Type of Contract …………………………………………………………... L-10 L.11 Construction Wage Rate Requirements—Secondary Site of the Work…… L-10 L.12 Notice of Requirement for Affirmative Action to Ensure Equal

Employment Opportunity for Construction ……………………………….. L-10 L.13 Site Visit (Construction) Alternate I.............................................................. L-12 L.14 Preparation of Proposals – Construction........................................................L-12 L.15 Authorized Deviations in Provisions ………………………………….…... L-13 L.16 Notice of Buy American Requirement--Construction Materials...................L-13 L.17 Service of Protest -- Department of the Interior (Deviation) ..................... L-14

L.19 Source Evaluation and Selection Procedures – Bureau of Reclamation …...L-15 L.20 General Proposal Instructions – Bureau of Reclamation ………………...... L-18 L.21 Technical Proposal Instructions – Bureau of Reclamation ………………... L-19 L.22 Pricing Proposal Instructions – Bureau of Reclamation …………………... L-20 L.23 Notice of Proposed Partnering -- Bureau of Reclamation ..............................L-21 L.24 Instruction for Mobilization and Preparatory Work Schedule Line Item …. L-22

SECTION M – EVALUATION FACTORS FOR AWARD

M.1 Evaluation Factors for Award – Lowest Price Technically Acceptable Source Selection Process - Bureau of Reclamation ………………………….......M-1

M.2 Notice of World Trade Organization Government Procurement Agreement Evaluations—Bureau of Reclamation …………………….…….M-5

L.18 Use and Disclosure of Proposal Information - Department of the Interior.. L-14

Active Vehicle Barrier Installations Specification No. 60 C0674

This page is intentionally left blank.

PART I -- THE SCHEDULE

Ger i Voto-Braun

140R6018R0013

F.1

X x

(Price Schedule I CLINS 1-16, Price Schedule 2 CLINS 17-40, Price Schedule 3 CLINS 41-53, Price Schedule 4 CLINS 54-71)

See Continuation of SECTION B - Supplies or Services and P

Price Schedule B - 1

CONTINUATION OF

SECTION B – SUPPLIES OR SERVICES AND PRICES

EASTERN COLORADO AREA OFFICE

ACTIVE VEHICLE BARRIER INSTALLATIONS

COLORADO

B.1 PRICE SCHEDULE

(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.

(b) Offers are subject to the terms and conditions of this solicitation.

(c) Quantities in the Price Schedule are estimated quantities for comparison of offers only.

Except as provided in the contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns. The contract clause at FAR 52.211-18, Variation in Estimated Quantity does not apply to lump sum items.

(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.

(e) Definitions:

(1) CLIN – Contract Line Item Number

PRICE SCHEDULE 1

2 Locations near Green Mountain Dam

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

1 WBR

1452.232-81

Mobilization and Preparatory Work

For the lump sum of $

2 01 55 20 Traffic Control For the lump sum of $

3 03 30 00 Cast-In-Place Concrete 18 yd3 $ $

4 03 30 00 Drain Rock 3 yd3 $ $

5 31 23 10 Embankment In-Place 4 yd3 $ $

6 31 23 11 Excavation for Structures 88 yd3 $ $

Price Schedule B - 2

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

7 31 23 11 Backfill about Structures 50 yd3 $ $

8 31 23 11 Compact Backfill about Structures

50 yd3 $ $

9 31 23 11 Compact In-Situ Base 8 yd3 $ $

10 32 12 22 Aggregate Base 28 tons $ $

11 32 92 20 Seeding and Soil Supplements

For the lump sum of

12 34 71 10 Type 3 W-Beam 69 lf $ $

13 34 71 10 Nested Type 3 W-Beam 138 lf $ $

14 34 71 10 50’ End Anchorage, (Nonflared)

2 each $ $

15 34 71 10 Terminal Section 4 each $ $

16 34 75 13 Mobile Crash Beam Barrier 2 each $ $

TOTAL FOR PRICE SCHEDULE 1 $_________________

PRICE SCHEDULE 2

3 Locations near Carter Lake Dam

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

17 WBR

1452.232-81

Mobilization and Preparatory Work

For the lump sum of $

18 01 55 20 Traffic Control For the lump sum of $

19 03 30 00 Cast-In-Place Concrete 12 yd3 $ $

20 31 23 10 Excavation for Roadways 22 yd3 $ $

21 31 23 10 Embankment In-Place 18 yd3 $ $

22 31 23 11 Excavation for Structures 48 yd3 $ $

23 31 23 11 Backfill About Structures 18 yd3 $ $

24 31 23 11 Compact Backfill about Structures

18 yd3 $ $

Price Schedule B - 3

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

25 31 23 11 Compact In-Situ Base 4 yd3 $ $

26 32 12 10 Saw Cutting 508 lf $ $

27 32 12 10 Asphalt Removal 114 yd2 $ $

28 32 12 22 Aggregate Base 69 tons $ $

29 32 12 22 Asphalt Concrete Patch 51 tons $ $

30 32 92 20 Seeding and Soil Supplements

For the lump sum of $

31 33 42 30 15-Inch Diameter Corrugated Metal Pipe Culverts

5 lf $ $

32 33 42 30 15-Inch Diameter Metal Flared End Sections

1 each $ $

33 34 71 10 Type 3 W-Beam 230 lf $ $

34 34 71 10 Nested Type 3 W-Beam 208 lf $ $

35 34 71 10 End Anchorage, (FLEAT 350)

5 each $ $

36 34 71 10 End Anchorage, (Type 3K)

1 each $ $

37 34 71 10 Transition Type 3J 1 each $ $

38 34 71 10 Terminal Section 1 each $ $

39 34 75 13 Mobile Crash Beam Barrier

3 each $ $

40 34 71 15 Precast Concrete Barriers 3 each $ $

TOTAL FOR PRICE SCHEDULE 2 $_________________

Price Schedule B - 4

PRICE SCHEDULE 3

2 Locations near Mt. Elbert Forebay Dam and Reservoir

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

41 WBR

1452.232-81

Mobilization and Preparatory Work

For the lump sum of $

42 01 55 20 Traffic Control For the lump sum of $

43 03 30 00 Cast-In-Place Concrete 8 yd3 $ $

44 31 23 11 Excavation for Structures 24 yd3

45 31 23 11 Backfill about Structures 16 yd3

46 31 23 11 Compact Backfill about Structures

16 yd3 $ $

47 31 23 11 Compact In-Situ Base 2 yd3 $ $

48 31 37 10 Barrier Rock 140 tons $ $

49 32 12 10 Saw Cutting 27 lf $ $

50 32 12 10 Asphalt Removal 105 yd2 $ $

51 32 12 22 Aggregate Base 12 yd3

52 32 92 20 Seeding and Soil Supplements

For the lump sum of $

53 34 75 13 Permanent Crash Beam Barrier

1 each $ $

TOTAL FOR PRICE SCHEDULE 3 $_________________

PRICE SCHEDULE 4

2 Locations near Sugar Loaf Dam

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

54 WBR

1452.232-81

Mobilization and Preparatory Work

For the lump sum of $

55 01 55 20 Traffic Control For the lump sum of $

56 03 30 00 Cast-In-Place Concrete 32 yd3 $ $

57 31 23 10 Excavation for Roadways 180 yd3 $ $

Price Schedule B - 5

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

58 31 23 10 Embankment In-Place 258 yd3 $ $

59 31 23 11 Excavation for Structures 100 yd3 $ $

60 31 23 11 Backfill about Structures 50 yd3 $ $

61 31 23 11 Compact Backfill about Structures

50 yd3 $ $

62 31 23 11 Compact In-Situ Base 9 yd3 $ $

63 32 12 22 Aggregate Base 95 tons $ $

64 32 92 20 Seeding and Soil Supplements

For the lump sum of $

65 34 71 10 Type 3 W-Beam 580 lf $ $

66 34 71 10 Nested Type 3 W-Beam 208 lf $ $

67 34 71 10 50’ End Anchorage, (Nonflared)

3 each $ $

68 34 71 10 End Anchorage, (FLEAT 350)

4 each $ $

69 34 71 10 Widening End Anchorage, (Flared)

1 each $ $

70 34 71 10 Terminal Section 2 each $ $

71 34 75 13 Mobile Crash Beam Barrier

2 each $ $

TOTAL FOR PRICE SCHEDULE 4 $_________________

Price Schedule B - 6

SUMMARY PRICE SCHEDULE TOTALS

9 Total Locations

Price Schedules Total Price per Schedule

Price Schedule 1 $

Price Schedule 2 $

Price Schedule 3 $

Price Schedule 4 $

TOTAL $_________________

END OF SUPPLIES OR SERVICES AND PRICES

Summary of Work 01 11 00 - 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 LOCATION

A. Work under this solicitation is to be performed at four (4) Bureau of Reclamation, Eastern Colorado Area Office facilities located in Colorado:

1. Two barriers are located along Heeney Road near Green Mountain Dam, 30 miles northwest of Silverthorne, Colorado in Summit County.

2. Two barriers are located along Mt. Elbert Forebay Dam Road near Mount Elbert Forebay Dam, 14 miles southwest of Leadville, Colorado in Lake County.

3. Two barriers are located along Turquoise Lake Road (Lake County Road 4) near Sugar Loaf Dam, 5 miles west of Leadville, Colorado in Lake County.

4. Three barriers are located along S. Larimer County Road 31 near Carter Lake Dam, 11 miles southwest of Loveland, Colorado in Larimer County.

1.02 PRINCIPAL COMPONENTS OF WORK

A. Furnishing and installing active vehicle barriers along various roadways that access dam crests. Work includes installation of retaining walls, shoulder widening and drainage improvements.

B. Furnishing and installing new guide rail in the vicinity of active vehicle barriers.

1.03 SPECIFICATIONS REQUIREMENTS

A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 52.

B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.

C. Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.

1.04 DEFINITIONS

A. When specifications use a word or term defined in Federal Acquisition Regulations (FAR), definition of the word or term shall be in accordance with FAR sections in effect at the time solicitation was issued.

1.05 ACRONYMS

A. The following acronyms apply to specifications Divisions 1 through 52:

Summary of Work 01 11 00 - 2

1. CO: Contracting Officer.

2. COR: Contracting Officer’s Representative.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

END OF SECTION

Use of Site 01 14 10 - 1

SECTION 01 14 10

USE OF SITE

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. Cleaning Manual-2012 Inspection and Cleaning Manual for Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2012 Edition Available online at: http://www.usbr.gov/mussels/prevention

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:

1. For each Contractor use site on Government land.

a. Show use location and extent of impact. Uses include but are not limited to the following:

1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.

2) Parking areas, temporary roads, and haul routes.

3) Utilities including air, power, and water lines; fire hydrants; and compressor station.

4) First-aid and medical facilities.

5) Areas for processing, storing, and disposing of waste materials from construction operations.

6) Temporary fences.

b. Describe methods to preserve, protect, and repair, vegetation (such as trees, shrubs, and grass) and other landscape features on or adjacent to jobsite, which are not to be removed and which do not interfere with work required under this contract. Include methods to mark work area limits, protect disturbed areas, and prevent erosion.

Use of Site 01 14 10 - 2

c. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near jobsite.

d. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.

2. Submit revised drawings of changes in use of Government land made during design and erection stages or after use of Government land is in operation.

1.04 PROJECT CONDITIONS

A. Government land may be used for required construction facilities.

B. When private land is used for construction facilities, or other construction purposes, make necessary arrangements associated with use of private land.

C. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of COR.

D. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.

E. Housing for construction personnel will not be permitted on Government land, except housing for guards or watchmen as may be approved by COR.

F. All work is located along public roadways and will require traffic control plan approval from several county highway agencies prior to commencement of construction activities.

Refer to Section 01 55 20 – Traffic Control of these Specifications.

G. A 69kV buried, high voltage transmission line is located in the drainage ditch along the north side of Heeney Road at the Green Mountain Dam North Gate site Refer to Section 52 00 00 – Drawings for the approximate location. Field verify the line’s actual location and utilize additional safety precautions and utility protection while performing work at this location.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 CLEANING

A. Construction equipment:

1. Before bringing on site, clean construction equipment to remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds, and invasive plant and animal species.

Use of Site 01 14 10 - 3

2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in Cleaning Manual.

3. COR will inspect construction equipment following procedures described in Cleaning Manual before allowing equipment onsite.

3.02 RESTORATION

A. Restore Contractor use areas to pre-construction condition.

B. Restore temporary construction roads to original contours and make impassable to vehicular traffic when no longer required.

C. After completion of work, regrade and scarify Government land used for construction purposes and not required for completed installation so that surfaces blend with natural terrain and are in a condition that will facilitate revegetation, provide proper drainage, and prevent erosion.

Use of Site 01 14 10 - 4

Active Vehicle Barriers Specifications No. 60-C0674

Forest Service Requirements 01 14 15 - 1

SECTION 01 14 15

FOREST SERVICE REQUIREMENTS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work, except as specified.

2. Contractor is responsible for restoration costs and repair of damage from unauthorized work in restricted areas,

1.02 PROJECT CONDITIONS

A. For operations performed on national forest land, comply with applicable rules and regulations of Secretary of Agriculture governing use and occupancy of national forests regarding disposal of timber; prevention and control of forest fires; sanitation; land occupancy for camps, storage yards, temporary roads, borrow areas for roads, and other construction-related operations and activities; and other rules and regulations which generally govern construction work performed on these lands.

B. Forest supervisor of the White River National Forest will be available for discussion with Contractor and prospective offerors regarding these rules and regulations.

1. Name and address of forest supervisor will be furnished by CO.

2. Make arrangements with forest supervisor in advance for these meetings.

3. Green Mountain Dam is in the White River National Forest.

C. Forest supervisor of the San Isabel National Forest will be available for discussion with Contractor and prospective offerors regarding these rules and regulations.

1. Name and address of forest supervisor will be furnished by CO.

2. Make arrangements with forest supervisor in advance for these meetings.

3. Sugar Loaf and Mt. Elbert Forebay are both in the San Isabel National Forest

D. Obtain from Forest Service, through CO, necessary permits and instructions which relate to use and occupancy of national forest lands and use of national forest products, except those timber sale and burning permits which are specifically mentioned below.

E. Contractor shall be responsible for restoration costs and damages resulting from unauthorized operations within restricted areas.

Active Vehicle Barriers Specifications No. 60-C0674

Forest Service Requirements 01 14 15 - 2

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 PREVENTION AND CONTROL OF FOREST FIRES

A. For purpose of fighting forest fires on or in vicinity of project which are not caused by Contractor or Contractor's employees and when requested by CO, place Contractor's employees and equipment temporarily at disposal of Forest Service.

1. Payment for such services will be made by Government at not less than current rate for firefighting services established by Forest Service in area concerned.

2. Employees and equipment furnished will be relieved from firefighting as soon as Forest Service finds that it is practicable to employ other labor and equipment adequate for protection of area.

3. An equitable adjustment in contract time will be made for this period.

3.02 TEMPORARY ACCESS ROADS

A. Except for those access roads and borrow areas specifically covered in these specifications, approval of CO shall be obtained in advance before locating additional access roads or borrow areas on national forest land. Mark proposed locations of access roads and borrow areas on the ground for approval by CO in advance of construction.

B. Temporary Access Roads:

1. To prevent excessive erosion, do not use grades in excess of 8 percent, except those which are approved in writing by CO.

2. Generally, back slopes of cut banks shall be stable and compatible with existing topography, except where rock is encountered and flatten and round such slopes into natural ground surface so far as practicable.

3. Install suitable devices and drainage structures in sufficient number to prevent accumulation of excessive water and erosion of the road surface, drainage ditches, and scarred areas.

Submittals 01 33 00 - 1

SECTION 01 33 00

SUBMITTALS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. American Society of Mechanical Engineers (ASME)

1. ASME Y14.1-12 Decimal Inch Drawing Sheet Size and Format

B. National Institute of Building Sciences (NIBS)

1. NIBS NCS-14 United States National CAD Standards, Version 6

1.03 DEFINITIONS

A. Days: Calendar days.

B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.

C. Submittals: Considered “shop drawings” within the terms of the clause at FAR 52.236- 21, Specifications and Drawings for Construction.

1.04 SUBMITTAL REQUIREMENTS

A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.

B. General:

1. Prepare in English.

2. Label with contract number and title, and RSN.

3. Measurement Units: US Customary Units.

C. Drawings:

1. Minimum Identification in Title Block:

a. Contract number and title.

b. Contractor’s or supplier’s title and drawing number.

Submittals 01 33 00 - 2

c. Date.

2. Provide space next to title block for review stamps.

3. Print Size: D size (22 inches by 34 inches).

4. Draw to scale using computer drafting or drafting equipment, unless otherwise specified.

a. Lettering shall be neat when drawing preparation with drafting equipment is allowed.

5. Government Format drawings:

a. Prepare drawings designated as “Government Format” in the specifications as follows:

1) Title block and sheet format:

a) As shown on Drawing 40-D-7102.

b) Government will provide specific title block information to be used.

2) Drawing format:

a) AUTOCAD, Version 2007 or later.

b) In accordance with NIBS NCS.

3) Government will provide an electronic AutoCAD template.

6. Final drawings:

a. Drawing format: AUTOCAD, Version 2007 or later.

b. Show as-built changes, including revision dates, made during installation.

Indicate changes by clouding.

c. Electronic files: On CD or DVD discs.

d. Government will provide an electronic AutoCAD template.

D. Product Data:

1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.

a. Identify manufacturer's name, type, model, size, and characteristics.

b. Illustrate that product or equipment meets requirements of specifications.

c. Mark items to be furnished in a manner that will photocopy (no highlighter).

d. Strike through items that do not apply.

E. Certifications:

Submittals 01 33 00 - 3

1. Certifications by a registered professional: Signed and sealed by registered professional.

2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.

1.05 SUBMITTALS PROCEDURES

A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.

B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.

C. Submit sets specified in “Sets to be sent:” columns in Table 01 33 00A - List of Submittals.

1. Electronic submittals:

a. In Portable Document Format (PDF).

b. Include RSN transmittal letter.

c. Do not include Personally Identifiable Information (PII) in electronic submittals.

2. Submit electronic submittals via email or CD/DVD based on size:

a. The Government can receive e-mails up to 25 MB. However, e-mails over 10 MB should be considered extra large. E-mailing of electronic submittals exceeding 10 MB should only occur after transmittal of larger size e-mail has been verified.

b. Address e-mail of electronic submittals less than extra large size to:

1) sha-GPR-CONSTSVCS@usbr.gov

c. Include electronic submittals that are too large to e-mail with paper copy of submittal. These electronic submittals shall be on thumb drive.

D. Include the following information in transmittal letters:

1. Contract number and title.

2. RSN for each attached submittal.

3. Responsible code.

4. Number of sets for each RSN.

5. Identify submittal as initial or resubmittal.

E. Resubmittal of submittals not approved:

1. Mark changes such that they are readily identifiable and show revision date.

Submittals 01 33 00 - 4

2. Describe reasons for significant changes in transmittal letter.

3. Resubmit returned submittals within 28 days after receiving comments, unless otherwise directed.

4. Requirements for initial submittals apply to resubmittals.

F. Each submittal shall be submitted under a separate transmittal letter. Multiple RSNs submitted under a single letter will be returned to the Contractor for resubmittal.

1.06 REVIEW OF SUBMITTALS

A. Time Required:

1. Submittal review will require 21 days for review of each submittal or resubmittal, unless otherwise specified.

2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.

B. Time in Excess of Specified:

1. CO may extend contract completion date to allow additional time for completing work affected by excess review time:

a. Time extension will be to extent that excess review time caused delay to contract completion date.

b. Time extension will not exceed time used in excess of specified number of days for review of submittals or resubmittals.

c. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending contract completion date.

2. No time extension will be allowed if Contractor fails to make complete action submittals in sequence and within time periods specified.

3. Adjustment for delay will be made only to extent that:

a. Approval was required under contract, and.

b. Requests for approval were properly and timely submitted and were approved.

4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work; however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.

C. Submittal Response:

1. A response letter from the COR for each submittal will be sent to the Contractor indicating if the submittal is either approved, not approved, acceptable, not acceptable, or acknowledged receipt.

Submittals 01 33 00 - 5

a. Revise and resubmit submittals not approved or not acceptable.

b. Do not change designs without approval of the COR after drawings, documentation, and technical data have been approved.

1.07 TRANSMITTAL

A. Addresses for codes listed in Table 01 33 00A - List of Submittals:

1. Where the recipient is the Contracting Officer, address the transmittal letter to Bureau of Reclamation, Attention: GP-5000, P.O. Box 36900, Billings, MT 59107-6900. Physical address is 2021 4th Avenue North, Billings, MT 59101.

2. Where the recipient is the Contracting Officer’s Representative, address the transmittal letter to Bureau of Reclamation, Attention: GP-2600, P.O. Box 36900, Billings, MT 59107-6900. Physical address is 2021 4th Avenue North, Billings, MT 59101.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Submittals 01 33 00 - 6

Table 01 33 00A. - List of Submittals ** CO indicates Contracting Officer, and COR indicated Contracting Officer’s Representative.

RSN

Clause or

Section Title

Submittals required Due date or delivery time

Respon-sible code

No. of sets to be sent to: **

CO COR

1 Bonds 52.228-15

Performance and Payment Bonds

Within 10 calendar days after award

CO 1 paper 0

2 Insurance-work on a Government Installation 1452.228-70

1) Written certification that the required insurance has been obtained

2) Current certification of insurance for each subcontractor

Before commencing on-site work CO 1 paper

1 paper

3 Liability Insurance 1452.228-70

Acceptable Certificate of Liability Insurance

Prior to commencement of work under the contract

CO 1 paper 0

4 Equal Opportunity 52.222-26

Information required by Executive Order

112246 (SF-100)

Within 30 days following award CO 1 paper 0

5 Reporting Executive Compensation and First Tier Subcontract Awards 52.204-10

Certification that executive compensation and subcontract awards were reported

Within 10 days of each report being submitted

CO 1 paper 0

6 Site Security

GP-7

List of all contractor and subcontractor employees

At least 10 days prior to arriving at worksite

COR 0 2 paper

7 Site Security

GP-7

List of all vehicles and equipment to be brought onsite

At least 10 days prior to arriving at worksite

COR 0 2 paper

8 Release of Claims 1452.204-70

Release of Claims (DI-137) against the Government

After completion of the work and prior to final payment

CO 1 paper 0

9 Labor Standards Data 52.222-11

1) List of subcontractors

2) Statement and Acknowledgement Form (SF-1413) for each subcontract

Within 14 days after preconstruction meeting

COR 1 paper 1 paper + 1 electronic

10 Payrolls 52.222-08

Copies of all payrolls

Weekly for each week of contract performance

CO 1 paper 2 paper

11 Schedules for Construction Contracts 52.236-15

Practicable schedule Within 5 days after preconstruction meeting or another period of time as determined by Contracting Officer

COR 1 paper 1 paper + 1 electronic

Submittals 01 33 00 - 7

Table 01 33 00A. - List of Submittals ** CO indicates Contracting Officer, and COR indicated Contracting Officer’s Representative.

RSN

Clause or

Section Title

Submittals required Due date or delivery time

Respon-sible code

No. of sets to be sent to: **

CO COR

12 Schedules for Construction Contracts 52.236-15

Updated schedule showing actual progress

Monthly or as directed by the Contracting Officer

COR 1 paper 1 paper + 1 electronic

DIVISION 1 – General 01 14 10-1 Use of Site Land Use And

Landscape Rehabilitation Plan

At least 21 days before use of Government land

COR 0 1 paper + 1 electronic

01 35 10-1 Safety Data Sheets

Complete LHM And

SDS

At least 21 days before jobsite delivery of hazardous material

COR 0 1 paper + 1 electronic

01 35 10-2 Safety Data Sheets

Updated LHM And

SDS

At least 21 days before jobsite delivery of hazardous material not previously listed

COR 1 1 paper + 1 electronic

01 35 20-1 Safety and Health

Safety Program Submitted and accepted before commencing onsite work. See section 3 of RSHS

COR 1 1 paper + 1 electronic

01 35 20-2 Safety and Health

Monthly Accident Summary Report

First day of each month. See paragraph 3.8 of RSHS

COR 0 1 paper + 1 electronic

01 35 20-3 Safety and Health

Respirator User Documentation

At least 21 days before beginning on-site work

COR 0 2 paper

01 35 20-4 Safety and Health

Crane Operation Certificates

At least 21 days before beginning on-site work

COR 0 2 paper

01 35 20-5 Safety and Health

Exposure Assessment Form (if applicable)

Within 7 days of exposure COR 0 2 paper

01 35 20-6 Safety and Health

Other Training Certificates

At least 21 days before beginning on-site work

COR 0 2 paper

01 35 30-1 Contractor‘s Onsite Safety Personnel

Qualifications At least 21 days before beginning on-site work

COR 0 2 paper

01 35 30-2 Contractor’s Onsite Safety Personnel

Safety Inspection Reports

Submit to COR monthly COR 0 1 paper + 1 electronic

01 46 20-1 Testing Agency Services

Testing Agency Services Plan

At least 21 days before beginning on-site work

COR 0 1 paper + 1 electronic

01 55 00-1 Vehicular Access and Parking

Preconstruction Video

At least 21 days before beginning on-site work

COR 0 1 paper + 1 electronic

01 55 00-2 Vehicular Access and Parking

Post Construction Video

At least 21 days before leaving site.

COR 0 1 paper + 1 electronic

01 55 00-3 Vehicular Access and Parking

Private Land Usage (If Necessary)

At least 21 days before beginning on-site work.

COR 0 1 paper + 1

Submittals 01 33 00 - 8

Table 01 33 00A. - List of Submittals ** CO indicates Contracting Officer, and COR indicated Contracting Officer’s Representative.

RSN

Clause or

Section Title

Submittals required Due date or delivery time

Respon-sible code

No. of sets to be sent to: **

CO COR

01 55 20-1 Traffic Control Right-Of-Way Permits

At least 21 days before affecting public traffic.

COR 0 1 paper + 1 electronic

01 57 20-1 Environmental Controls

Copy of Applicable Air Quality Permit(s)

At least 21 days before beginning on-site work.

COR 0 1 paper + 1 electronic

01 57 30-1 Water Pollution Control

Water Management Plan

At least 21 days before commencing construction activities

COR 0 1 paper + 1 electronic

01 57 30-2 Water Pollution Control

Spill Prevention, Control, and Countermeasure (SPCC) Plan

At least 21 days before delivery or storage of oil

COR 0 1 paper + 1 electronic

01 57 50-1 Tree and Plant Protection

Protection Plan At least 21 days before commencing on site construction work

COR 0 1 paper + 1 electronic

01 71 20-1 Surveying Surveying Plan At least 21 days before beginning survey work

COR 0 1 paper + 1 electronic

01 71 20-2 Surveying Resumes At least 21 days before beginning survey work; At least 28 days before personnel change

COR 0 2 paper

01 71 20-3 Surveying Accuracy Check Results

At least 21 days before beginning survey work

COR 0 1 paper + 1 electronic

01 71 20-4 Surveying Completed and Reduced Survey Notes

Within 2 days of completing and reducing notes

COR 0 1 paper + 1 electronic

01 71 20-5 Surveying Quantity Survey Notes and Computations

Accompanying progress payment requests

COR 0 1 paper + 1 electronic

01 71 20-6 Surveying Workday's Survey Notes

At conclusion of workday when requested by Government

COR 0 1 paper + 1 electronic

01 74 00-1 Cleaning and Waste Management

Waste Production and Disposal Plan

At least 28 days before starting onsite work

COR 0 1 paper + 1 electronic

01 74 00-2 Cleaning and Waste Management

Waste Production and Disposal Records

Within 7 days of waste disposal COR 0 1 paper + 1 electronic

01 74 00-3 Cleaning and Waste Management

Environmental Consultant Resume (if required)

At least 35 days before beginning environmental assessment

COR 0 2 paper

01 74 00-4 Cleaning and Waste Management

Environmental Site Assessment (if required)

Within 14 days of completion of work

COR 0 1 paper + 1 electronic

01 78 30-1 Project Record Documents

Final As-built Drawings

Within 21 days of completion of work

COR 0 1 paper + 1

DIVISION 3 – Concrete

Submittals 01 33 00 - 9

Table 01 33 00A. - List of Submittals ** CO indicates Contracting Officer, and COR indicated Contracting Officer’s Representative.

RSN

Clause or

Section Title

Submittals required Due date or delivery time

Respon-sible code

No. of sets to be sent to: **

CO COR

03 30 00-1 Cast-In Place Concrete

Mix Design At least 21 days before starting onsite work

COR 0 1 paper + 1 electronic

DIVISION 31-Earthwork 31 23 10-1 Earthwork for

Roadway Backfill and Compaction

Test Results At least 21 days before starting onsite work for Laboratory Compaction

Within 7 days of completion for In-Place density tests

COR 0 1 paper + 1 electronic

1 paper + 1 electronic

31 23 10-2 Earthwork for Roadway Backfill and Compaction

Borrow Source At least 21 days before material delivery

COR 0 1 paper + 1 electronic

31 23 11-1 Earthwork for Structures

Test Results At least 21 days before starting onsite work

COR 0 1 paper + 1 electronic

31 23 11-1 Earthwork for Structures

Borrow Source At least 21 days before material delivery

COR 0 1 paper + 1 electronic

31 37 10-1 Barrier Rock Weight Tickets Upon material delivery COR 0 1 paper + 1 electronic

31 37 10-2 Barrier Rock Product Certification At least 21 days before starting onsite work

COR 0 1 paper + 1 electronic

DIVISION 32 – Exterior Improvements 32 12 22-1 Asphalt

Concrete Pavement

Mix Design Data At least 21 days before starting onsite work

COR 0 1 paper + 1 electronic

32 12 22-2 Asphalt Concrete Pavement

Certifications At least 21 days before starting onsite work

COR 0 1 paper + 1 electronic

32 92 20-1 Seeding and Soil Supplements

Seeding Plan At least 21 days before starting onsite work

COR 0 1 paper + 1 electronic

32 92 20-2 Seeding and Soil Supplements

Certifications At least 21 days before material delivery

COR 0 1 paper + 1 electronic

DIVISION 34 – Transportation 34 71 10-1 W-Beam

Guardrail Certifications At least 21 days before starting onsite work COR 0 1 paper + 1 electronic 34 75 13-1 Active Vehicle

Barrier Certifications At least 21 days before starting onsite work COR 0 1 paper + 1 electronic 34 75 13-2 Active Vehicle

Barrier Approval Drawings and Data

At least 21 days before starting onsite work

COR 0 1 paper + 1

Safety Data Sheets 01 35 10 - 1

SECTION 01 35 10

SAFETY DATA SHEETS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 DEFINITIONS

A. LHM: List of Hazardous Materials.

B. SDS: Safety Data Sheet.

1. Referred to as Material Safety Data Sheets in the clause at 52.223-3, Hazardous Material Identifications and Material Safety Data - Alternate 1.

1.03 APPLICATION

A. For the purposes of this contract, “delivered under this contract” in paragraph (b) of the clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1, includes:

1. Materials delivered to Government.

2. Materials incorporated into work.

3. Materials used by the Contractor during contract performance at the jobsite.

1.04 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 35 10-1, Complete LHM and SDS.

C. RSN 01 35 10-2, Updated LHM and SDS:

1. Comply with paragraph (e) of clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1.

1.05 DELIVERY

A. Do not deliver hazardous materials to jobsite which are not included on original or previously updated LHM and SDS before receipt of updated LHM and SDS by the COR.

Safety Data Sheets 01 35 10 - 2

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Safety and Health 01 35 20 - 1

SECTION 01 35 20

SAFETY AND HEALTH

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include the cost of complying with this section in the prices offered in the Price Schedules for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. RSHS Reclamation Safety and Health Standards including revisions posted at http://www.usbr.gov/ssle/safety/RSHS/rshs.html

2. FIST 1-1 (2012) Hazardous Energy Control Program available at: www.usbr.gov/power/data/fist_pub.html

B. Occupational Safety and Health Administration (OSHA)

1. 29 CFR Part 1910 Occupational Safety and Health Standards.

2. 29 CFR Part 1926 Safety and Health Regulations for Construction.

3. Available on the Internet at www.osha.gov.

C. American Conference of Governmental Industrial Hygienists (ACGIH), Threshold Limit Values (TLVs):

1. Available at www.acgih.org.

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 35 20-1, Safety Program:

1. Cover aspects of onsite and applicable off-site operations and activities associated with this contract.

a. Submit a comprehensive, job-specific safety and health program in accordance with Section 01 33 00 – Submittals and in accordance with the requirements of Section 3.3 of the Reclamation Safety and Health Standards (RSHS) and these specifications.

b. Follow the outline in Appendix B of the RSHS.

Safety and Health 01 35 20 - 2

c. The Safety Program will not be accepted for review by the COR unless it addresses, in order, lettered and numbered per Appendix B of the RSHS, a…