A1_Q_As_140R4022R0017_0001.pdf
PDF 62 KB Posted
- Attached to
- AVC Property Boundary Surveys
- Solicitation number
- 140R4022R0017
About this file
This document contains questions and answers regarding Solicitation No. 140R4022R0017 for Arkansas Valley Conduit Property Boundary Surveys. The Bureau of Reclamation is seeking surveying services to establish property boundaries for the Arkansas Valley Conduit project. Bidders should utilize the provided pricing schedule to estimate costs, including applying title commitment costs to the tools and materials line item and adding any required positions not listed. Line item 3 on the pricing schedule can be used for a professional surveyor or field crew time to reset missing monuments. While the pricing schedule specifies classifications and hours, bidders may change quantities as necessary but are strongly advised to use the provided hours to determine their cost per mile.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140R4022R0017_Amd_0001.pdf | ||
| Amendment_0001_Informational_Page_0001.pdf | ||
| Attachment_C_-_Pricing_Schedule_in_Excel_Format.XLSX | XLSX spreadsheet | |
| Sol_140R4022R0017.pdf | ||
| 140R4022R0017_AVC_Property_Boundary_Surveys.pdf | ||
| Attachment_F_-_Survey_Alignment.zip | ZIP file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION NO. 140R4022R0017
ARKANSAS VALLEY CONDUIT
PROPERTY BOUNDARY SURVEYS
QUESTIONS AND ANSWERS
1. Will the BOR be providing Title Commitments for this project, or will the contractor be required to hire a consultant to obtain the required Title Commitments?
a. Please see Section 4.1.1
2. If the consultant is required to obtain the Title Commitments where do these fit on the provided Pricing Schedule?
a. You can apply this cost to the tools and materials line item.
3. On the Pricing Schedule what are line items 4 Senior Project Designer and line item 5 Designer to be utilized for on this project?
a. If you require any design work please fill out this position, if you do not you are not required to budget for this position.
4. The pricing schedule does not contain a line item for field survey crew. Is line item 3 to be utilized?
a. You may add any required positions that are not currently on the price schedule and build it into your price per mile.
5. Is line item 3 on the pricing schedule to be utilized for the Professional Surveyor of Record?
a. You can utilize line item 3 for a professional surveyor.
6. On the Pricing Schedule which line item would be utilized for field crew time to reset missing required monuments.
a. Please see Question 4.
7. The pricing schedule has specific classifications and hours are placed in these classifications. Are those hours to used or do we estimate our own total hours for the project and breakdown by mile?
a. It’s strongly suggested that those hours be used to get your cost per mile.
However, you may change the quantity of hours as you deem necessary.
File details come from the government source that posted it. Updated .