Performance_Work_Statement_24_August_2021_0001.pdf
PDF 785 KB Posted
- Attached to
- ARMATURE 70000060 REPAIR
- Solicitation number
- 140R3021Q0062
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140R3021Q0062_Amd_0001.pdf | ||
| Wage_Determination_2015-5593.pdf | ||
| Performance_Work_Statement.pdf | ||
| Combined_Synopsis_Solicitation.docx | DOCX document | |
| Sol_140R3021Q0062.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS) – ARMATURE 70000060 REPAIR
1.0. SCOPE.
1.1. OBJECTIVE.
1.1.1. This procurement seeks a qualified contractor to inspect, test, troubleshoot, repair, and retest to certify the armature’s repair was successful.
1.1.2. The contractor shall supply a drawing of the actual wiring diagram of the repaired armature.
1.2. BACKGROUND.
1.2.1. Hoover Dam uses rotating armatures to inject 250 volts DC onto generator stator windings. The armature was in service for decades before being sent for rewind under contract R14PC00111. Return shipping by the repair facility was authorized after review of all reports, documents, and photographs.
1.2.2. Armature 70000060 was inspected on delivery and stored for four years before being removed from storage, inspected, tested, and placed in service. A flash (similar to a fire-works sparkler) occurs after voltage is applied. A photo of the burned area is attached. The service life of the armature was eighty-seven seconds.
1.3. REPAIR FACILITY, TOOLS and MATERIALS REQUIREMENT.
1.3.1. The contractor must arrange a transport vehicle and driver trained and licensed to safely operate the vehicle in all types of weather on typical highway and roadway surfaces.
1.3.2. The driver must bring the tools, equipment, and accessories to safely secure the load placed on the transport vehicle at the Hoover Dam Central Warehouse (and at the repair facility).
1.3.2.1. Armature 70000060 weighs approximately 13,000 pounds.
1.3.2.2. Armature 70000060 is crated to minimize damage during shipping.
1.3.2.3. Armature crate dimensions are about 6’ (length) x 6’ (width) x 5’ (height).
1.3.3. The contractor must furnish a clean, secure work site, tools, equipment, cranes, rigging, and other items to unload, repair, rewind, test, balance, crate and reload this armature at the repair facility.
1.3.4. The repair facility must supply all materials to repair armature 70000060.
1.3.5. The repair facility must be operated by an Electrical Apparatus Service Association (EASA) contractor certified to repair rotating armatures in compliance with ANSI/EASA AR100-2020.
1.3.5.1. AR100-2020 lists recommended practices for repair of rotating electrical apparatus.
1.3.5.2. Copies of the Standard are available FREE from EASA website at: www.easa.com.
1.3.5.3. Do not deviate from the Standard without written permission from the Contract Office.
http://www.easa.com/
1.3.5.4. A record of the procedures followed to repair armature 70000060 must be made and certified as being in accordance with the ANSI/EASA AR100-2020 Standard.
1.3.5.5. A copy of the certified repair record must be included in submittals sent to the Agency.
1.4. SUBMITTAL REQUIREMENT.
1.4.1. The Contractor must provide Table 1 submittals to the Hoover point of contact below.
1.4.2. Please attach a cover sheet with the job name and contract number on each submittal.
1.4.3. The Contractor must provide the submittals to the address or Email listed below:
Bureau of Reclamation To be determined at time of award Engineering Office PO Box 60400 Boulder City, NV 89006-0400
1.4.4. The cost to furnish submittals must be included in the price bid for other items of work.
1.4.5. Table 1 – List of Submittals
RSN Item Submittal required Due date 01 Digital photos (PDF format) Photos from three different views
(top, side, bottom) Seven days after arrival at the repair facility
02 Armature measurements in WORD format
Measure and weigh armature on arrival at the repair facility
Seven days after arrival at the repair facility
03 Sketch of the armature with dimensions & weight shown
Sketch of armature providing dimensions & weight before repair
Seven days after arrival at the repair facility
04 Armature Repair Plan for Hoover review and approval
Include a sketch, brief description of proposed repair, tests before repair and tests after repair, an itemized material list, a schedule, and an estimated delivery date for returning the repaired armature.
After the contractor completes the work to create the proposed repair plan
05 Revised Armature Repair Plan (if additional work is required)
Include items not previously listed in RSN 04 above.
Upon discovery of the need for additional work
06 Armature measurements in WORD format.
measure and weigh armature after repairs and tests are complete.
Before shipping back to Hoover Dam
07 Sketch of the armature with dimensions & weight shown
Sketch of armature providing dimensions & weight after repair
Before shipping back to Hoover Dam
08 Certified copy of repairs and test results for the armature
Repairs and test results (including vibration and balancing data)
Before shipping back to Hoover Dam mailto:jroach@usbr.gov
1.4.5. Table 1 – List of Submittals (cont’d)
RSN Item Submittal required Due date 09 Digital copies of armature’s actual wiring diagram in
AUTOCAD
Actual wiring diagram in the latest version of AUTOCAD in .DWG (base) format and in .PDF format
Before shipping back to Hoover Dam
10 Digital photos (PDF format) Photos of three views after repair Before shipping back to Hoover Dam
11 Recommended inspections and tests upon delivery.
List of inspections and tests Before shipping back to Hoover Dam
12 Recommended annual tests during armature storage.
List of recommended annual tests Before shipping back to Hoover Dam
13 On-site inspection photos & acceptance test results
Certified copies of the on-site open-crate inspection photos and on-site acceptance test data
Seven days after delivery to Hoover Dam
1.5. PERIOD OF PERFORMANCE.
1.5.1. The Contractor may take two months to complete the work to repair armature 70000060.
1.5.2. The Contractor must return the armature to Hoover Dam as soon as all work, tests, drawings, and reports are complete and the Contracting Office authorizes return shipping.
1.6. PERFORMANCE STANDARDS.
1.6.1. Electronic reports shall be compatible with Microsoft Office (WORD, etc.) or Adobe PDF.
1.6.2. Electronic drawings and sketches shall be in the latest version of AUTOCAD in .DWG format and in .PDF format.
1.6.3. The Contractor’s repair facility must be properly licensed by a governmental authority.
1.6.4. Armature repairs shall be made in a neat and workmanlike manner following EASA Standards.
1.6.5. All work shall be performed by craftsmen trained in their various crafts or trades.
1.6.6. All parts shall be made accurate to standard gauge to facilitate replacement and repair.
1.6.7. Transport drivers must follow Reclamation Health & Safety Standards while working on-site.
1.6.8. Reclamation Health & Safety Standards are available free on-line at: https://www.usbr.gov
1.6.9. The operation of Hoover Dam and Power-plant requires continuous security measures.
1.6.9.1. The Security Response Force (SRF) enforces controlled access to the Facility.
1.6.9.2. Contractors shall not enter restricted areas without authorization.
https://www.usbr.gov/
2.0 REFERENCES. Documents required to perform this contract include:
2.1. ANSI/EASA AR100-2020 Recommended Practice for the Repair of Rotating Electrical Apparatus, Copyright 2020 (version 0920), Electrical Apparatus Service Association, Inc.
2.1.1. The Standard covers all contract work and is available free by download from www.easa.com
2.2. Photo of the burned area of Armature 70000060 is attached next to the last page of this PWS.
2.3. Sketch of Armature 70000060 with dimensions AS RECEIVED dated 05/26/15, is attached as the last page in the PWS.
3.0 TASKS. The contractor shall perform the following tasks:
3.1. Arrange for a transport vehicle and licensed driver to pick up crated armature 70000060 at the Hoover Dam Central Warehouse and deliver it to the contractor’s repair facility.
3.1.1. Hoover Dam Central Warehouse directions and assistance are listed below.
3.1.1.1. The Central Warehouse is located on Nevada State Route 172 about eight miles East of Boulder City, Nevada. Take Exit 2 (SR-172) and follow the signs.
3.1.1.2. The Central Warehouse is open for pick-ups or deliveries from 0800 to 1700 PDT, Monday thru Friday.
3.1.1.3. The Contract must submit arrival times at least forty-eight hours in advance to the Government point of contact listed in the submittal section above.
3.1.1.4. Advance notice ensures sufficient warehouse staff is available to ship or receive items.
3.1.1.5. Advance notice also ensures Warehousemen and Mechanical Craftsmen are available to operate the forklift and perform rigging that may be needed to load or unload the transport vehicle.
3.1.1.6. The following facilities and equipment will be available for use (upon request and at no charge) in providing the services required under this Performance Work Statement (PWS):
3.1.1.6.1. A place to work at the central warehouse to load the vehicle transporting the armature out for repair and for unloading the armature upon return.
3.1.1.6.2. A forklift and qualified operator to load and unload the transport vehicles.
3.1.1.6.3. An escort for the transport vehicle while loading or unloading the armature.
3.1.1.6.4. Sanitary facilities – Existing restrooms and wash-up facilities.
3.1.1.6.5. No Government phone or internet will be provided for security reasons.
3.1.1.6.6. Cell phone service is available in the central warehouse area.
http://www.easa.com/
3.2. Inspect, photograph, weigh, measure, sketch, test, assess, and report the armature’s condition upon arrival (to the COR via email to: To be determined at time of award for Hoover review.
3.2.1. Photograph all visible damage (three positions minimum) upon removal from its crate.
3.2.2. Record the name plate data and all marks stamped into the metal frame of the armature.
3.2.3. Record the armature’s dimensions (in inches and millimeters) and weight (in pounds).
3.2.4. Record the dimensions and weight on a new sketch of Armature 70000060 as received.
3.2.5. The diameter of the repaired armature must equal the diameter measured upon arrival (within ANSI/EASA AR100-2020 tolerances, or 1/8 inch, whichever is less).
3.3. The repair facility must provide a written Armature 70000060 Repair Plan for Hoover Managers review and approval within a reasonable time after the armature’s arrival.
3.3.1. The repair plan shall include thorough inspection and test of all components located in, around or near the burn areas shown in the photos.
3.3.2. The repair plan shall include such other inspections and tests a prudent EASA Vendor would take to locate the cause of Armature 70000060 failure.
3.3.3. The Repair Plan shall include a thorough inspection and test of all equalizer bar connections and repair any suspect connections.
3.4. Proceed with Armature 70000060 Repair Plan when authorized by the Contracting Office.
3-5. The repair facility must stop work and notify the COR upon discovery of the need for additional repairs outside the scope of the Armature 70000060 Repair Plan.
3.6. The repair facility must provide a Revised Armature 70000060 Repair Plan + a written estimate of the cost, the workdays needed to complete additional repairs and any additional tests required.
3.7. The repair facility must receive authorization from the Contract Office before making additional repairs.
3.8. On completion of all repairs and tests, the repair facility shall use the latest version of AUTOCAD to create an electronic drawing (in .DWG format and in .PDF format) of the actual wiring diagram of Armature 70000060.
3.9. Upon completion of all Armature 70000060 repairs, the repair facility shall promptly send all repair records and test results for review to the COR at the following email address: To be determined at time of award.
3.10. The COR will review and discuss repair records and test results with Contractor’s Repair Team.
3.11. The repair facility must build a new heavy-duty wooden crate to properly secure, support and protect the armature during return shipping to Hoover Dam.
3.12. Dispose of materials removed from Armature 70000060 in an environmentally friendly manner in compliance with local laws, rules, and regulations.
3.13. Request permission to return ship Armature 70000060 via email to the COR.
3.13.1. The COR will recommend the Contract Office authorize return shipping when the terms and conditions of this PWS are completed.
3.14. The Contractor must receive written permission from the Contract Office to return repaired Armature 70000060 to Hoover Dam.
3.14.1. Permission to ship will not relieve the repair facility of its responsibilities to conform to all requirements of this Performance Work Statement (PWS).
3.15. The Contractor must arrange a transport vehicle and qualified driver to pick up and deliver Armature 70000060 to the Hoover Dam Central Warehouse as soon as possible after repairs are completed and permission to ship is received from the Contracting Office.
3.16. The Contractor shall inspect, photograph, test and declare: “… Armature 70000060 arrived at Hoover Dam ready for immediate return to service. …”
3.16.1. The Contractor shall provide the certified on-site photos and test data as required in
RSN-13.
4.0 PERFORMANCE REQUIREMENTS SUMMARY
Task Task Description Performance Indicator
Minimum Acceptable Quality Level
3.1 Transport armature to repair
facility
Email COR photos of armature arrival
Legible photos sent within two days of arrival
3.2 Inspect, photo, weigh, measure, sketch, test, assess, and report the armature’s condition upon arrival
Email COR copies of all documents created on arrival.
Photos, sketch & test results in PDF format.
Report in WORD or PDF format.
3.3 Provide a written Armature
Repair Plan
Email written Repair Plan to COR
Legible copies in Word or PDF format.
3.4 Proceed with the Armature
Repair Plan when authorized by the Contract Office (CO).
Repairs made per written Repair Plan
Repairs meet or exceed the EASA AR100-2020 Standard.
3.5 Stop work & notify COR if
additional repairs are needed
Email notice of additional repairs
Legible documents in WORD or PDF format sent to the COR
Task Task Description Performance Indicator
Minimum Acceptable Quality Level
3.6 Provide estimates and a
Revised Armature Repair Plan for additional repairs
Email estimates & Revised Repair Plan to the COR
Legible documents in WORD or PDF format sent to the COR.
3.7 Proceed with Revised
Armature Repair Plan when authorized by CO.
Armature repairs & tests are completed
Certified repairs and tests meet or exceed EASA AR100-2020 Standard
3.8 Create AUTOCAD drawing
of Armature 70000060
Email .DWG and .PDF files to the
COR
Both files (.DWG and .PDF) open & clearly depict the armature’s actual wiring diagram.
3.9 Send certified repair records
and test results to the COR
Records sent via email
All documents in WORD or Adobe PDF format
3.10 COR reviews & discusses
records with repair team
Discuss via phone conference
All in attendance can hear and repair records are available for review.
3.11 Build a crate to ship the
armature to Hoover Dam
PDF Photo of crate at the repair facility
Crate provides space to secure and protect the 13,000 pound armature
3.12 Proper disposal of removed
materials
Contractor email + disposal receipt
PDF copy of legible disposal receipt
3.13 Request permission to return
the armature
Contractor email to the COR
Any legible email application
3.14 Receive permission to return
the armature
Email from the Contract Office
Any legible email application
3.15 Transport armature back to
Hoover Dam
Armature delivered undamaged
Two days delivery
3.16 Contractor inspects and tests
armature at Hoover’s Central Warehouse
COR observes all inspections & tests required in RSN-11
Certified photos & written test results due in seven days.
Contractor and COR inspections reveal no visible damage.
COR observes Contractor perform all tests required in RSN-11 & verify all test results are satisfactory.
5.0 DATA AND REPORTS - The contractor shall provide the following data and reports:
Item No. Description Content Format Medium Delivery
RSN-01 Arrival photos PWS 1.4.5 Government PDF w/n 7 days of armature arrival
RSN-02 Measurements As received
PWS 1.4.5 Government WORD w/n 7 days of armature arrival
RSN-03 Armature sketch As received
PWS 1.4.5 Government PDF w/n 7 days of armature arrival
RSN-04 Repair Plan PWS 1.4.5 Government WORD or PDF w/n 7 days of armature arrival
RSN-05 Revised Repair Plan (if necessary)
PWS 1.4.5 Government WORD or PDF Upon discovery
RSN-06 Measurements After repair
PWS 1.4.5 Government WORD Before armature return
RSN-07 Armature sketch After repair
PWS 1.4.5 Government PDF Before armature return
RSN-08 AUTOCAD wiring diagram of armature
PWS 1.4.5 Government AUTOCAD
.DWG & .PDF
Before armature return
RSN-09 Certified copy of all repairs & test results
PWS 1.4.5 Government WORD or PDF Before armature return
RSN-10 Digital photos PWS 1.4.5 Government PDF Before armature return
RSN-11 List inspections and tests upon delivery
PWS 1.4.5 Government WORD or PDF When armature return
RSN-12 List recommended tests during storage
PWS 1.4.5 Government WORD or PDF Before armature return
RSN-13 Certified copies of on-site open-crate inspection photos & on-site acceptance test data
PWS 1.4.5 Government WORD or PDF Seven days after on-site inspection & acceptance tests
6.0 DELIVERABLES - The contractor shall submit the following deliverables to complete all work under this PWS:
6.1. Email certified copies of RSN 01 thru RSN 12 to the COR at the times required in Table 1 – List of Submittals on PWS pages 2 and 3 (and before repaired armature 7000060 returns to Hoover).
6-2. Return repaired armature 70000060 to the Hoover Dam Central Warehouse when authorized by the Contract Office.
6.3. Perform inspection and acceptance testing on repaired armature 70000060 upon arrival at the Hoover Dam Central Warehouse.
6-4. Email certified copies of photos, inspections and tests performed on repaired armature 70000060 to demonstrate it is ready for immediate return to service upon delivery to the Warehouse.
6-5. Email certified copies of on-site inspection photos and test data showing armature arrived at Hoover Dam ready for immediate return to service.
6-6. Submit the invoice to receive payment for services in accordance with the contract’s terms.
REVISIONS DATE
9.150”
16.560”16.000”9.550”12.250”
2.950”
0.720”
0.250” 3.000”
0.435”
8.501” 25.000”
.4
.0
4.500”
14.000”34.540”35.970”
.0
CO
M
M U
TA
TO
R
A
RM
AT
U
RE
C
O
RE
W
IN
D
IN
G D
IA
M
ET
ER
W
IN
D
IN
G D
IA
M
ET
ER
| Performance Work Statement |
| 07-01-21 Armature 70000060 PWS + Two Attachments |
| 07-01-21 PWS - N4 Armature Repair.pdf |
| Binder1.pdf |
| N-4 Exciter Burn marks - Doug Ashford |
5-28-15 Shermco's Intake Sketch re Armature 50417 - Carma Asset 76707- Shermco #70000060
09-09-19 Photo - N4 Armature Burn Spot
Exhibit 3 - List of up-rate Generator Data