Amendment_No__0002_to_140R2022B0003_0002.pdf

PDF 2 MB Posted

Attached to
Floating Dock Replacement at New Melones Lake
Solicitation number
140R2022B0003
Issued by

About this file

This is an amendment to a solicitation for floating dock replacement services at New Melones Lake. The Department of the Interior Bureau of Reclamation is seeking to replace floating docks through a competitive procurement under solicitation number 140R2022B0003. The amendment provides additional instructions to offerors and adjusts submission dates but does not otherwise modify the required products or services, which include removing existing docks and installing new modular floating docks to specifications provided. Offerors must submit proposals by the amended due date of [date redacted] for evaluation and contract award, with work to be completed by [date redacted].

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

������������������������������������� !��"��"�#�������������������������������������������������#��$����������#������������#����!����#��#��!���#���������$��������� ��������!$������#���#��������������!�������������������������$���#�%��&'()*+,�-&�.-*+�'/01-2),34,5,16�6-��,�+,/,(7,3�'6�68,�9)'/,�3,:(41'6,3�&-+�68,�+,/,(96�-&�-&&,+:�9+(-+�6-�68,�8-*+�'13�3'6,�:9,/(&(,3�5'.�+,:*)6�(1�+,;,/6(-1�-&�.-*+�-&&,+%��(�����<�#�$����������������������$�����#���������"���������#��!#������$�������=��$�������"�����������������!����#��#��!���#���������$��������=��#�<����������!����#��#��!���#���������$���������������#���#��������������!����������������������������=��������#����<����#��#��������������"���$#�������������������%

>?@A?BCDEF�GH�IJK

JL�KIK

K���GFEE?MC�N?OP�FFB�QL�K�J
�RSTSUSFD�FV�H@WXSUSESFD�>CATS@CUCMSFD?Y�ZVVS@C[S\L]?@SVS@�CMSFD�XAC?X�FV�C@Y?B?ESFD �Ĵ�_̂

àb�cdef�ecgh�ijkl�mnnkegf�ci�hioepeqmceij�ip�qijcrmqcfsirogrfb��ec�hioepegf�cdg�qijcrmqcsirogr�jib�mf�ogfqretgo�ej�ecgh�̀ubvw%�'//-*16(14�'13�'99+-9+('6(-1�3'6'�xyz�{|}~�{|�� ���������������%�����������=�(�����������v�=�����#��$#���"-���#���$�������� !��"��#��������������������������#��#����������$#�����������������������������!�����������#�����������=�����������������!!� ��"���������������������!����"6������<���$���#�����!������������������������������#������(����v�%��6�����$#����������������������#�#����������-���#�`̀b�cdef�ecgh�ijkl�mnnkegf�ci�mhgjohgjcf�ip�fikeqecmceijf&'/()(6.�/-3,�/-3,� v��%�3'6,3�x����y�������v�'%�5-3(&(/'6(-1�-&�/-16+'/6�-+3,+�1-%��%�3'6,3�x����y��������'%�'5,135,16�-&�:-)(/(6'6(-1�1-%

/-3,� �%�1'5,�'13�'33+,::�-&�/-16+'/6-+�x�������{||�����~���������|������y�����|�

�%�'35(1(:6,+,3��.�xyz����|{������y�|����/-3,� %�(::*,3��. 9'4,���-&��9'4,:�%�+,¡*(:(6(-1�9*+/8':,�+,¡%�1-%¢%�,&&,/6(7,�3'6,w%�'5,135,16�5-3(&(/'6(-1��1-%� �%�9+-;,/6�1-%�xyz��££¤���¥¤|�v%��/-16+'/6�(3�/-3,mhgjohgjc�ip�fikeqecmceijshioepeqmceij�ip�qijcrmqc

/8,/0�-1, '%�68(:�/8'14,�-+3,+�(:�(::*,3�9*+:*'16�6-��x�£|��z���~���{������68,�/8'14,:�:,6�&-+68�(1�(6,5�v��'+,�5'3,�(1�68,�/-16+'/6�%�68,�'�-7,�1*5�,+,3�/-16+'/6�-+3,+�(:�5-3(&(,3�6-�+,&),/6�68,�'35(1(:6+'6(7,�/8'14,:�x�~����������¦|�����£����¦��zz��|��/%�68(:�:*99),5,16')�'4+,,5,16�(:�,16,+,3�(16-�9*+:*'16�6-�'*68-+(6.�-&�3%�-68,+�x�£|��z����£|��z�����z�������������~���{������££{�£{�������������|������:,6�&-+68�(1�(6,5�v�=�9*+:*'16�6-�68,�'*68-+(6.�-&�&'+��¢%v�¢���% gb�ehnircmjc§ /���#����#� ������� ���#�̈$�#��������"����������$���������#��$#�����������������������������������������$��"�������%�-+3,+�1-%�(1�(6,5�v�'% v�%�3,:/+(96(-1�-&�'5,135,16�5-3(&(/'6(-1�x©{¦���ª|��¥��«�¬��|�������|����¦������¤~���¦���¤�������������{�����~¥®|�������|{�̄�|{|�z|���¥¤|��°CM?@O�RF@�±²��Z ³́C�>FYS@SE?ESFD�@SEC\�SD�µYF@¶�IH�?µFTCP�·YF?ESDM�RF@¶� ÇY?@CBCDE�?E�¹Cº�[CYFDCU�°?¶C�SUĆACµO�?BCD\C\»]XA̧FUC²�³́C�̧XA̧FUC�FV�ÉSU�?BCD\BCDE�SU�EF²��¼�½D@FA̧FA?EC�ÉC�?EE?@́C\�¾XCUESFDU�¿HDUºCAUP� ¼�SD@FA̧FA?EC�ÉC�?EE?@́C\�>C@ESFDU�H�¿�·P�?D\��¼�½D@FA̧FA?EC�ÉC�?EE?@́C\�>SECÀSUSE�?EECD\CCU�YSUE»³́C�\?EC�?D\�ESBC�VFA�AC@CŞE�FV�FVVCAU�SU�́CACµO�Á¹GÂH¹ÃQR�?D\�ACB?SDU�ÄXDC��P�

P�?E�²���̧B�]?@SVS@�³SBC»³́C�FVVCAFA�BXUE�?@¶DFºYC\MC�ÉSU�?BCD\BCDE�µO�UXµBSEESDM�?�USMDC\�@F̧O�FV�ÉSU�>·���?YFDMºSÉ�ÉCSA�̧AF̧FU?Y» v '%�1'5,��'13�6(6),�-&�/-16+'/6(14�-&&(/,+�x��£|��{�£{����v�'%�1'5,�'13�6(6),�-&�:(41,+�x��£|��{�£{���� v�/%�3'6,�:(41,3 v �%�*1(6,3�:6'6,:�-&�'5,+(/'�v��%�/-16+'/6-+�-&&,+-+ v /%�3'6,�:(41,3x��¦���~{|��z�£|{�����~���{�ª|�������¦�� x��¦���~{|��z�����{�����¦�©zz��|{� FU?D?�ÅFXUCVMF?AÆS :6'13'+3�&-+5�¢���+,7%�vv�w�v �9#���#��������4:'�&'+�����/&+���¢%w�¢9#�<��$����������$�$���!� ,����������#�<�������#���=��!!���#����������������������������$�����#���#���������(�����'��#�v�'=������#�����#������"��=�#�������$�����"�����������$!!���#�������������%

Amendment No. 0002 Solicitation No. 140R2022B0003

Floating Dock Replacement at New Melones Lake

Pre-bid Questions and Answers

Question 1: Materials are taking longer to get due to C-19 and other shipping issues. Is there a possibility that 90-day window from award to completion could be extended?

Response 1: Yes, it’s been extended to 180 days from 90 days. Please see the attached revised

Sections A&F.

Question 2: The water levels are low and dropping at the lake. One of the ramps is already out of the water and will not see use again until next year at best. Can we please clarify where the docks should be placed if they cannot immediately be put into service upon delivery due to very low water levels?

Response 2: If the ramp is not in the water at the time of delivery, the dock should be placed on the ramp, attached to the cables and chocked in place. The dock will be placed into service when the water level returns to normal.

SOLICITATION, OFFER, 1. SOLICITATION NO. 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES

ANDAWARD 140R2022B0003 [l<JsEALED BID (IFB)

(Construction, Alteration, or Repair) □ NEGOTIATED (RFP)

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

R20

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO

Bureau of Reclamation

California Great Basin Office

1 I 3

Bureau of Reclamation

Mid-Pacific Region

Regional Office

Division of Acquisition Services

2800 Cottage Way, Room E-1815

Sacramento CA 95825-1898

2800 Cottage Way, Room E-1815, Federal Bldg

Sacramento, CA 95825 - 1898

9. FOR ► a. NAME

INFORMATION

CALL: Rosana Yousefgoarj i

SOLICITATION

b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

916-978-5004

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

A. Title : Floating Dock Replacement at New Melones Lake

B. Work Site Location : The work is located at U.S. Bureau of Reclamation, New

Melones Lake, California.

C. Estimated Price Range : $500,000.00 to $1,000,000.00.

D. Set-aside Information : This requirement is restricted to Total Small Business concerns. FAR Clause 52.219-6 - Notice of Total Small Business Set Aside applies to this requirement. NAIC S Code : 237990 ( Siz e Standard $39.5 Million )

11. The Contractor shall begin performance 7

□ award, [l<J notice to proceed. The perfonnance period is calendar days and complete it within 18 0

[l<Jmandatory □negotiable. (See Section F

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

IBJYES □ NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and copies to perfonn the work required are due at the place specified in Item 8 by calendar days after receiving

12b. CALENDAR DAYS

1300 (hour) local time

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offerer's name and address, the solicitation number, and the date and time offers are due .

b. An offer guarantee IB] is, Dis not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than 90

NSN 7540-01-155-3212

calendar days for Government acceptance after the date offers are due will not be considered and will be rejected .

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED

140R2022B0003

NAME OF OFFEROR OR CONTRACTOR

ITEM NO.

(A)

00010

SUPPLIES/SERVICES

(B)

Legacy Doc #: BOR

Delivery: 180 Days After Notice to Proceed

Floating Dock Replacement at New Melones Lake

(Price Schedule CLIN 1)

See Following Continuation Page

Product/Service Code: Z2PZ

Product/Service Description: REPAIR OR ALTERATION

OF OTHER NON-BUILDING FACILITIES

NSN 7540-01-152-8067

QUANTITY UNIT

(C) (D)

UNIT PRICE

(E)

PAGE

OF

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR /48 CFRl 53. 110

Solicitation No. 140R2022B0003

Amendment No. 0002

F-1

SECTION F - DELIVERIES OR PERFORMANCE

Clause

Title

Date

52.242-14

Suspension of Work

APR 1984

FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND APR 1984

COMPLETION OF WORK

The Contractor shall be required to

(a) commence work under this contract within 7 calendar days after the date the Contractor receives the notice to proceed,

(b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than 180 calendar days after the date the

Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.

New Melones Lake

Boat Dock Site Visit

05/03/2022

1. Doug’s DockWorks, Doug Lucas

2. RX3 Communications, Steve Johnson

3. Stephens Construction, Damien Stephens

4. Mountain Methods, Lindsay Tague & Jim Uhl

5. Distinctive Metals, Darrin Mills

6. Water Ventures, Jason Plaza (Did NOT make it today)

05/11/2022

1. Water Ventures, Maarten Voogd

File details come from the government source that posted it. Updated .