SOW.pdf
PDF 291 KB Posted
- Attached to
- YOSE Propane Tank Farm Repairs
- Solicitation number
- 140P8518Q0003
About this file
Scope of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P8518Q0003.pdf | ||
| SCA_Wage_Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
E XP E R IE N C E YO U R AM E R I C A
The National Park Service cares for special places saved by the American people so that all may experience our heritage.
Statement of Work
Objective
Drain and clean two (2) 6,500+ gallon propane tanks and inspect, repair/replace above ground components of liquid propane gas (LPG) tank farm at Rancheria Road El Portal, Ca. 95318
Background
The buildings and grounds branch of Yosemite National Park has an immediate need for the complete replacement of LPG tank farm components in El Portal, Ca. The tank farm regulators have failed, making it necessary to use an electric vaporizer to supply LPG to residences. The tank farm is not designed to run in this manner. In recent weeks the vaporizer has been failing regularly. When the vaporizer fails, 30+ homes lose LPG supply and the ability to use LPG burning appliances. Additionally maintenance personnel are called out to relight pilot lights at each location. The vaporizer is close to failing completely, when this happens the entire supply will be lost until component replacement can take place, leaving residences without LPG and use of appliances.
The location of the work to be done is at about 2,000 feet above sea level. Weather conditions
October- April may range from high temperatures, to rain or snow.
Scope
This tank farm supplies propane to roughly 30 Government-owned homes. Prior to work beginning, a temporary tank large enough to meet the usage demands of typical “whole house” residential use for 30 homes shall be delivered, tied into the existing supply line at the tank farm, filled and monitored to ensure customers are not without propane while work is underway.
Based on “whole house” propane use, the average daily usage for all 30 homes is 80 gallons.
The contractor shall be responsible for removing the existing propane prior to cleaning the tanks, storing the propane, and replacing the propane after the first pressure test. It is acceptable for the contractor to fill the temporary tank with the propane removed from the existing tanks.
The park’s propane supply contractor will make deliveries to the temporary tank if the existing supply of propane runs out while the temporary tank is in use; these deliveries will be coordinated by the COR.
The contractor shall provide with their offer a schedule showing the major milestones of the services required by this statement of work.
Work shall begin within two weeks of contract award.
Yosemite National Park
Tank Farm SOW
Stephanie Kincaid
Buildings and Grounds
Phone: 209-379-1054
04/06/2016
National Park Service
U.S. Department of the Interior
The National Park Service cares for special places saved by the American people so that all may experience our heritage.
Tanks shall be drained, pooled oil or “ends” shall be removed and the tanks shall be cleaned
All regulators shall be replaced with new regulators. Repaired or rehabbed regulators will not be accepted
A new gas powered vaporizer shall replace the existing 240V electric vaporizer
All existing plumbing from tank to regulators and vaporizer shall be replaced with plumbing of the appropriate local and state plumbing codes
Isolation valves shall be installed one at each tank and one on each line to the regulators and vaporizer so that isolation may take place when needed
Dump tanks shall be installed to capture excess oil or “ends”
One (1) pressure test shall be done before tanks are refilled, and one (1) after tanks are refilled to ensure functionality of newly installed systems
The existing emergency remote shut off switch shall be replaced
All old materials shall be removed and disposed/recycled by the contractor at an approved offsite facility
The contractor shall not dispose of any material in dumpsters within the El Portal community, or Yosemite National Park
All work done will meet NFPA/California codes and regulations for LPG storage and distribution. Applicable regulations include NFPA 58: Liquefied Petroleum Gas Code.
The contractor shall supply all parts, materials, equipment, tools and labor necessary to complete this project.
Yosemite National Park will not provide parts, materials, equipment, tools or labor.
The following documents will be required prior to the issuance of the Notice to Proceed. No work may begin before the following documents are received and approved by the Government:
Site-specific safety plan. This plan must be reviewed and approved by the Yosemite safety office.
If the contractor proposes any on-site soldering or welding work, the contractor may be required to obtain a hot work permit from the Yosemite safety office.
Certificate of Insurance in accordance with the requirements of Section I.2 of the solicitation.
Submittals for the proposed equipment and materials to be installed. These submittals will be reviewed in order to verify compliance with NFPA codes.
The National Park Service cares for special places saved by the American people so that all may experience our heritage.
Although it is not mandatory, it is highly recommended that interested offerors participate in a one day only site visit on a date to be determined. Offerors are responsible for familiarizing themselves with the contract requirements, site access limitations, and existing site conditions before submitting an offer. The Government is not responsible for any offeror’s failure to do so.
Interested offerors shall contact Stephanie Kincaid at 209-379-1054 for date and time of site visit.
Tank Farm, Rancheria Road
El Portal, CA 95318