Atch_1_Questions_Answers_0001.pdf

PDF 122 KB Posted

Attached to
MIMI Refinish Visitor Center Floors
Solicitation number
140P6324Q0013
Issued by

About this file

This document is a set of Questions and Answers related to a federal contract opportunity to refinish the visitor center floors at Minuteman Missile National Historic Site.

The key details are:

  • The contract number is 140P6324Q0013.
  • The project involves refinishing the visitor center floors at the Minuteman Missile National Historic Site.
  • Weekend and after-hours work will be permitted to minimize disruption to normal facility operations, as the visitor center is closed to the public on Sundays and Mondays.
  • The government will have staff, furniture, equipment, and fixtures removed from the floor areas, except for a few items that are bolted down.
  • A dumpster can be placed on the north side of the building for disposal, but the contractor must ensure it is covered to prevent littering.
  • This is a National Park Service site, so all applicable regulations under 36 CFR apply, including prohibitions on littering.

View the file

Other files

File Type Posted
Atch_2_Site_Visit_Sign_In_Sheet_0001.pdf PDF
Sol_140P6324Q0013_Amd_0001.pdf PDF
Atch_3_Addendum_Updated_Measurements_0001.pdf PDF
Atch_3_DOL_Wage_Determination_SD20240022.pdf PDF
Sol_140P6324Q0013.pdf PDF
Atch_2_Experience_Questionnaire.xls XLS spreadsheet
Atch_1_SOW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Minuteman Missile NHS-Refinish Visitor Center Floors 140P6324Q0013 Ques�ons/Answers

Ques�on 1.

Will weekend work and a�er-hours work be permited for this project? This will help minimize down�me of normal opera�ons for the facility.

Government Response

The park is closed to the public on Sunday and Monday. The normal hours the visitor center is open is 8:00 am to 4:00 pm Tuesday thru Saturday. A�er 4 pm work will be permited to help aid in comple�on of the project, since no park visitors will be on-site during this �me.

Ques�on 2.

Can you confirm that the facility will be moving all furnishings, equipment, and fixtures off of the floor for this project?

Government Response

In the staff lunchroom all chairs and table will be moved, all items on the floor behind the informa�on counter will be moved, all items in the bookstore on the floor will be moved, the two items the will not be moved is the passport cancella�on sta�on and the dona�on box (these are bolted to the floor) these two items will require being tape off and covered while work is being performed.

Ques�on 3.

Will there be an area to place a dumpster for this project?

Government Response

A dumpster can be place on the north side of the building. It is the contractor’s responsibility to ensure that it has a cover (i.e., screen, tarp), to prevent materials from flying out and liter the landscape. This is a Na�onal Park Service site and all rules, regula�ons under 36CFR apply for litering.