A20_PMIS_318433-_Restriping_RI_Mainline_Roadway_SOW_Pkg_0001.pdf
PDF 3 MB Posted
- Attached to
- RESTRIPE RIDGELAND MOTOR ROAD
- Solicitation number
- 140P5222Q0019
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P5222Q0019_Amd_0001.pdf | ||
| Sol_140P5222Q0019.pdf | ||
| B03_Madison_county.txt | TXT text file | |
| A20_PMIS_318433-_Restriping_RI_Mainline_Roadway_SOW_Pkg.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT SPECIFICATIONS
PMIS 318433
RESTRIPE MAINLINE ROADWAY
IN RIDGELAND DISTRICT
PROJECT AREA
MP 86- MP 102
RIDGELAND, MS
INDEX OF SPECIFICATIONS
DIVISION 1 - GENERAL REQUIREMENTS
01110 Summary of Work
01599 Traffic and Safety
DRAWINGS
Sheet 1 – E634-03
Sheet 1 – E634-04
PRICE PROPOSAL FORM
1 Sheet – Price Proposal Form
APPENDIX
NATR 3P22 Striping Schedule for Reference
FHWA FP-14 Section 633
FHWA FP-14 Section 635
05/2021 01110-1
SUMMARY OF WORK
SECTION 01110
(Rev. 05/2021)
SUMMARY OF WORK
PART 1 GENERAL
1 .1 DESCRIPTION
A. The Natchez Trace Parkway is soliciting quotes for re-striping the Ridgeland Mainline Motor-road between MP 86 and MP 102.46. The work shall include restriping all lines within the mainline roadway including gore/neutral (hatch striped) areas, legend striping and the radiuses and stop bars at all intersections and/or ramps. The work shall not include re-striping ramps, pull-offs or other intersecting roadways/accesses beyond the existing radius striping.
B. Summary of Work: shall include furnishing all materials, labor, and equipment necessary to install the following under the conditions as stated herein:
• Quantity- approx. 66,268 Linear Feet Pavement Markings, Type I, Broken
(Yellow/White)
• Quantity- approx. 180,672 Linear Feet Pavement Markings, Type I, Solid
(Yellow/White)
• Quantity- approx. 43,330 Linear Feet Pavement Markings, Type I, Solid (40 mil thickness only) to recover existing Profiled Pavement Markings at Bridges.
• Quantity- approx. 5 Each Pavement Markings, Type I, Turn Arrow
C. This shall be a firm-fixed price contract. The quantities provided are approximate and are based off of previous striping projects in the project area. The contractor shall be responsible for verifying quantities prior to providing a quote for the work. Increase and/or decrease in quantities in the field during construction shall not incur a change in contract price except where outlined in FAR Clause 52.211-18.
D. Restriping traffic control shall conform to MUTCD Standards for mobile striping operations, Section 01599 of the Statement of Work, and Section 635 of the U.S. Department of
Transportation, FWHA, Standard Specifications for Construction of Roads and Bridges on
Federal Highway Projects (FP-14). These standards and specifications are included in the contract documents by reference. Section 634, has been included in the appendix.
1 .2 LOCATION
A. Project is located within the Ridgeland District of the Natchez Trace Parkway, from MP 86 to MP
102.46 at the terminus.
Local POC – Christopher Ellington – (601) 416-0532
Ridgeland District Office- MP 102
100 East Jackson Street
Ridgeland, MS 39157
1 .3 CONTRACTOR’S USE OF PREMISES
05/2021 01110-2
A. Work hours shall be Monday through Friday, 7:30 AM until 4:00 PM. The contractor shall not work outside of these hours nor work on Saturdays, Sundays, or Federal Holidays without prior consent from the CO. Work on Sundays shall not be permitted except in case of emergencies.
B. Contractor shall, at all times, conduct his operations to ensure the least inconvenience to the government. A minimum of twenty-four hours prior notice shall be provided before any utility to any building is turned off to commence work.
C. Confine storage of materials to locations designated by the CO or COR. Staging areas shall be determined during the pre-construction conference. The Contractor may store materials and equipment at the work site at his own risk.
D. Existing Facilities:
1. The contractor shall be responsible for the preservation from injury or damage, resulting directly or indirectly from the execution of the work, of all public and private property along and adjacent to the parkway. The contractor shall use every precaution necessary to prevent damage to pipes, conduits, and other underground structures; also, all overhead structures such as wires, cables, etc.; and poles, trees, shrubbery and crops, within or outside of the right of way. All utility lines damaged by the contractor shall be repaired immediately at the contractor’s expense. All trails and roads adjacent to or intersecting the project shall be protected from damage. Contractor shall protect curbs and sidewalks from damage. At the completion of the project, bridges and curbs shall be swept clean to remove any loose material or fresh hot mix that was deposited during construction.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, the contractor shall repair the utility at no additional expense to the
Government.
3. All damage to existing facilities resulting from the contractors’ actions shall be repaired to original condition by the contractor.
4. Coordination:
a. The Parkway’s facilities shall not be closed to the public during construction. The contractor shall coordinate with maintenance staff on the Park’s operations during construction.
E. Hauling Restrictions: Hauling on the Parkway shall only occur along the shortest possible routes from the Parkway’s access ramps to where the contractor is working.
1. When hauling on National Park Service roads, the contractor shall not exceed the following load restrictions:
Single Units Gross Vehicle Weight –Lbs.
2 axles 40,000
3 axles 48,000
4 or more axles 52,000
Combination Units
3 axles 57,000
4 axles 62,000
5 or more axles 66,000
05/2021 01110-3
Where the ground is saturated with water or during periods of freezing and thawing, the
Contracting Officer may impose further load restrictions or suspend hauling.
2. Haul vehicles shall turn around only at intersections and parking areas, not on the Park
Road.
3. Operate loaded vehicles hauling material at speeds not exceeding 40 MPH and spaced at
500-foot minimum intervals. On bridges, speeds shall not exceed 25 MPH and not more than one loaded hauling vehicle shall be allowed on any bridge at one time. Hauling of materials, supplies, and equipment over the park road, other than within the limits of the project, shall not be permitted without prior approval of the Contracting Officer. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Contracting Officer.
F. Housekeeping: Keep project neat, orderly, and in a safe condition at all times. Store and use equipment, tools, and materials in a manner that does not present a hazard. Immediately remove all hazardous rubbish. Do not allow rubbish to accumulate. Provide onsite containers for collection of rubbish and dispose of it at frequent intervals during progress of work. Equipment that is leaking any type fluids shall be repaired immediately or removed from the parkway boundary. Cleaning equipment at the end of work day shall only be performed at locations approved by the COR.
1 .4 FIELD VERIFICATION
A. Examination of the site: All potential contractors are urged to visit the job site and examine existing conditions before submitting a quote. All potential contractors will be held to have the same knowledge concerning the site and the on ground conditions as if they had inspected the job site. See FAR 52.236-27 - Site Visit (Construction).
B. The contractor shall field verify all new and existing dimensions affecting the work of this contract before ordering products.
1 .5 PERFORMANCE PERIOD:
A. The contractor shall have 15 Working Days to complete all work awarded under this contract. A
Working Day shall be considered every day that does not fall on a federal holiday, Saturday, or
Sunday. In the case of rain, wet soil, other weather-related delays, or delays required by the government, time may be extended. The Contractor shall provide documentation as to which days, within their Period of Performance, time should not be charged due to weather, to the COR for
Review and Approval.
1 .6 INSPECTION – CONTROL OF WORK
A. The CO or COR shall decide all questions which may arise as to the quality or acceptability of materials furnished or work performed and shall decide all questions which may arise as to the interpretation of the plans and specifications and all questions as to the acceptable fulfillment of the terms and provisions of the contract.
B. No work shall be done nor material used without inspection by the COR, and the contractor shall furnish every reasonable facility for ascertaining whether or not the work performed and materials used are in accordance with the requirements and intent of the specifications and contract. Any work done or materials used without inspection by the CO or COR may be ordered removed and
05/2021 01110-4 replaced at the contractor's expense. Materials will be inspected and approved as promptly as practicable on delivery at the job site. The work will be inspected as it progresses. Failure to reject any defective work or material shall not in any way prevent later rejection.
1 .7 CONSTRUCTION MATERIALS
A. All materials shall be Contractor-furnished.
B. Unless otherwise provided, tests of materials shall be made by the contractor in accordance with the methods given in the current edition of the AASHTO publication Standard Specifications for
Highway Materials and Methods of Sampling and Testing in effect on the date of invitation for bids.
C. Materials shall be so stored as to ensure the preservation of their quality and fitness for the work.
Stored materials, even though approved before storage, may be inspected prior to their use in the work, and they shall meet the requirements of the specifications at the time it is proposed to use them.
1 .8 ACCIDENT PREVENTION
A. Description: The work of this section consists of establishing and implementing an effective accident prevention program and providing a safe environment for all personnel and visitors.
Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations).
B. Submittals:
1. Safety Plan: A Safety Plan shall be prepared and submitted to the COR before work can begin. The Safety Plan shall be a written document that describes the process for identifying the physical and health hazards that could harm workers, procedures to prevent accidents, and steps to take when accidents occur. The safety plan shall also include
COVID-19 prevention positive action procedures. The written safety plan is your blueprint for keeping workers safe. The plan needs to compile the list of activities and what hazards exist and what safety equipment will be used to prevent accidents from occurring. The plan shall include:
a. Name of responsible supervisor to carry out the program
b. 24 hour emergency contact information
c. First aid procedures
d. Training, both initial and continuing
e. Planning for possible emergency situations
f. Contractor to identify nearest location of medical facility for emergencies
g. Recognition that work may be performed in remote areas with limited communication or cell phone coverage
2. Safety Meetings: As a minimum, conduct one weekly 15 minute "toolbox" safety meetings.
These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week.
Document and submit meeting minutes to the COR within one day after the meeting.
05/2021 01110-5
C. Qualification of Employees:
1. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.
2. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
D. Accident Reporting: The Contractor shall report all accidents to the COR within 24 hours and assist the CO and other officials as required in the investigation of the accident.
E. First Aid Facilities: Provide adequate facilities for the number of employees and the type of construction at the site.
F. Protective Equipment: The contractor shall require all those working on or visiting the site to wear the necessary protective equipment. For that reason, the contractor shall maintain, at minimum, four (4) sets of Personal Protective Equipment (PPE) necessary for the work being performed, onsite at all times.
G. Hazardous Materials: Store and handle hazardous materials in accordance with manufacturer’s and OSHA 29CFR1926 Subpart D requirements. Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical. All operators and contractors, functioning within the park, shall properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state and local regulations, and as outlined within the operator's
Safety or Hazardous Materials Business Plan.
1. If a spill, leak or other release occurs, the operator shall, without impeding cleanup, notify the National Park Service Emergency Dispatch within 24 hours.
1 .9 PRECONSTRUCTION CONFERENCE: See FAR 52.236-26
A. Pre-construction Conference: Before the start of work, the CO will arrange for a prework conference with the Contractor to determine any requirements that must be resolved to accommodate the work. Upon completion of the meeting and/or resolution of any items required, site work may proceed in concurrence with the Notice to Proceed.
1 .10 SUBMITTALS
A. General Submittal Procedures:
1. General: Prepare and submit submittals required by individual Specification Sections.
Types of submittals are indicated in individual specific sections.
a. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using National Park Service form CM-16 form. The form will be provided by the
CO. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form.
2. Preconstruction Conference Submittal: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. If all of these documents
05/2021 01110-6 have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the CO will consider other contractual remedies. Work shall not commence until written Notice to
Proceed has been issued. CO will notify Contractor of tentative date for the Pre-
Construction Conference:
B. Shop Drawings, Product Data, and Samples:
1. Product data, shop drawings, and any necessary samples shall be submitted for approval by the CO and COR. Product data shall be given for each component of the system identifying the manufacturer and the product specifications. Shop drawings shall include detailed notes and drawings indicating the system design and layout including the layout and location of the outdoor/indoor units, wiring diagrams, routing of coolant lines, etc.
2. For submittals specified above, forward submittals to CO at least 5 working days before need for approval (depends on length of project).
3. After approving submittals, CO will return one copy to the Contractor. If submittals are not approved, CO will return all copies to Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.
C. Approved Equals: Refer to FAR 52.211-6 - If an item in this solicitation is identified as “brand name or equal” or lists more than 3 manufacturers, the purchase description reflects the characteristics and level of quality that will satisfy the Government’s needs. The salient physical, functional, or performance characteristics that “equal” products must meet are specified in the solicitation or relevant specification.
1. For each item proposed as an “approved equal,” submit supporting data, including:
a. Drawings and samples as appropriate.
b. Comparison of the characteristics of the proposed item with that specified.
c. Changes required in other elements of the work because of the substitution.
d. Name, address, and telephone number of vendor.
e. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.
2. A request for approval constitutes a representation that Contractor:
a. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
b. Will provide the same warranties for the proposed item as for the item specified.
c. Has determined that the proposed item is compatible with interfacing items.
d. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
e. Waives all claims for additional expenses that may be incurred as a result of the substitution.
3. Approved Equals will be evaluated and approved/disapproved during the submittal process.
05/2021 01110-7
1 .11 PROJECT CLOSEOUT
A. Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures, and safety precautions.
B. Cleaning: Remove all tools, equipment, surplus materials, and rubbish. At time of final inspection, project shall be thoroughly clean and ready for use.
C. Substantial Completion and Final Inspection: Submit written certification that project is substantially complete, and a final inspection must be requested to the CO in writing. The CO or
COR will make an inspection within 10 days of receipt of request or at a mutually agreeable time.
1. If the work is determined to be substantially complete, following the final inspection, the.
CO will prepare a Punch List and the work will be considered substantially complete.
2. If the work is not determined to be substantially complete following the final inspection, the CO will notify Contractor in writing. Contractor shall request a new final inspection after completing the work. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
3. Contractor shall complete the Punch List within 10 calendar days, documented weather permitting.
4. If CO determines that the work is not substantially complete; he will immediately notify
Contractor in writing, stating reasons. After completing work, Contractor shall resubmit certification and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
5. If the Contractor fails to complete the work within the time frame, the CO may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.
6. Disposition of any permits and warranties required by the specifications in this section.
D. Acceptance of the Work: After all deficiencies have been corrected, the project can be accepted. A
Letter of Acceptance may be issued. A Release of Claims document must be executed and submitted to the CO before final payment can occur.
E. Warranties
1. Manufacturer’s warranties and product registration shall be completed with the manufacturer as required by the contractor within 10 days after completion of the applicable item of work. Copies shall be submitted to the CO.
2. Provide All Warranty information of products installed organized by Division. All contact information, extents and conditions shall be clearly noted as well as date of overall project
Substantial Completion.
3. Information shall include operation and maintenance manuals for each warranted material.
05/2021 01110-8
PART 2 PRODUCTS
2 .1 PERMANENT PAVEMENT MARKINGS
A. Pavement Markings shall be in conformance with the U.S. Department of Transportation, FWHA, Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-
14), Section 634, “Permanent Pavement Markings”, Thermoplastic Markings (Type I). These specifications are included in the contract documents by reference. Section 634, has been included in the appendix.
PART 3 EXECUTION
3 .1 PERMANENT PAVEMENT MARKINGS
A. Pavement Markings shall be in conformance with the U.S. Department of Transportation, FWHA, Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-
14), Section 634, “Permanent Pavement Markings”, Thermoplastic Markings (Type I). These specifications are included in the contract documents by reference. Section 634, has been included in the appendix.
B. The following special construction requirements (SCRs) are to be included as errata and modifications to the referenced standards and will supersede the subsections to which they refer:
634.03. Add the following to the first paragraph:
Place traffic markings before a winter suspension of paving operations.
Reestablish the existing passing and no-passing zones as determined in the field or as otherwise directed by the COR.
Break parkway centerline striping at intersections.
634.07(b). Delete the text and substitute the following:
Use two bead dispensers. Apply Type 3 glass beads on the thermoplastic at a minimum rate of 12 pounds per 100 square feet immediately followed by a second application of Type 1 glass beads at the same rate.
C. Per Section 634, Thermoplastic Stripe shall be 60mils on the edge lines only; All other areas, including the centerline, the stripe shall be 90 mils.
D. Raised Profile Striping (Profiled Pavement Markings) on bridges and at the bridge approaches shall be restriped with Type I (non-profiled) Thermoplastic Pavement Markings at 40 mil thickness.
E. Areas where the existing striping is less worn, reduce stripe thickness as directed by the COR to prevent water from ponding at stripe.
F. Project does not include restriping 9 small wedge and level sections that were recently paved and striped between MP 89- MP 100 totaling approximately 8300 LF. Contractor shall verify quantity of work precluded in the field prior to providing quotes for the work.
05/2021 01110-9
PART 4 MEASUREMENT AND PAYMENT
Measurement and payment shall be as per the items, units, and prices quoted on the price sheet according to the work completed and accepted.
All work shall be performed under a single contract. Quantities of work are estimated and subject to change. Final Contract price shall be as per the lump sum firm-fixed price quoted.
END OF SECTION
07/2020 01599-1
TRAFFIC AND SAFETY
SECTION 01599
(Rev. 07/2020)
PART 1 GENERAL
1 .1 DESCRIPTION
A. Work under this section consists of the furnishing of all labor, materials, equipment, and signs required by these specifications.
PART 2 PRODUCTS NOT USED
PART 3 EXECUTION
3 .1 PROTECTION OF PUBLIC
A. Flaggers: Where required, the contractor shall furnish two (2) capable, physically and mentally qualified flaggers for maintaining traffic flow during construction operations. The flaggers shall be English speaking. Flaggers shall wear fluorescent orange or green vests and shall be equipped with a standard hand-held warning (Stop/Slow) sign. Flags shall not be allowed for traffic control.
They shall also be equipped with two-way radios that are capable of dependable transmission for one mile.
B. Safety Equipment: All slow moving equipment shall be equipped with slow moving vehicle emblems and high intensity flashing lights. Emblem and flashing lights shall meet OSHA standards.
C. Laws to be Observed: The contractor shall keep fully informed of all federal and state laws, all local laws, ordinances, safety codes, regulations, and all orders and decrees of bodies or tribunals having any jurisdiction or authority, which in any manner affect those engaged or employed on the work, or which in any way affect the conduct of the work. He shall at all times observe and comply with all such laws, ordinances, safety codes, regulations, orders, and decrees; and shall protect and indemnify the Government and its representatives against any claim or liability arising from or based on the violation of any such law, ordinance, safety code, regulation, order, or decree, whether by himself or his employees.
D. Public Convenience and Safety: The contractor shall at all times so conduct his work as to assure the safety and convenience of the general public and the residents along the parkway and to assure the protection of persons and property. Care shall be taken at all times to regulate the operations so as to protect visitors and campers in the park
E. Barricades, Warning Signs, and Other Devices: The contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Suitable warning signs shall be provided to properly control and direct traffic.
Portable construction traffic control devices shall be relocated after each 3000 foot progression of work. During a lane closure, traffic cones/barrels shall be used to delineate the work area. Utilization of all barricades, traffic delineators, warning signs, lights, temporary signals, flagmen and pilot car
07/2020 01599-2 operators and equipment, and other protective devices shall be in accordance with the current edition, Part VI of the Manual on Uniform Traffic Control Devices (MUTCD) for Streets and Highways, published by the U.S. Government Printing Office. Part VI of the manual may be examined by prospective contractors at Natchez Trace Parkway Headquarters, Tupelo, Mississippi.
Signing/flagging details, traffic control plans and/or other detailed drawings are included with these specifications. The contractor shall furnish, erect, maintain, and remove, or otherwise as directed by the COR, all signs shown within the contract documents.
F. “DO NOT PASS”, “NO PASSING ZONE” and “PASS WITH CARE” signs shall be installed at the appropriate locations before any pavement markings are covered by paving operations (when applicable).
END OF SECTION
Item ESTIMATED Number DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT
1 Mobilization 1.0 LPSM
2 Pavement Markings, Type I, Broken 66268.0 LF
Pavement Markings, Type I, Solid 180672.0 LF
3 Recover existing Profiled Pavement Markings, Type I, Solid (40 mil thickness only) 43330.0 LF
5 Pavement Markings, Type I, Turn Arrow 5.0 EA
TOTAL CONTRACT AMOUNT :
GENERAL NOTES:
3. In case of descrepancies, the final contract firm-fixed price shall be based on the "Unit Price." Therefore the totals shall be the sum of "Amount" column based on the the "Unit Price" per unit quantity for both the Base Item and Price Option 1.
1. Quantities are estimated and subject to increase/decrease in the field. The contractor shall verify quantities of work during site visit and/or prior to providing a quote.
2. Provide a "Unit Price" for each item listed. Proposals with blank unit prices will be considered irregular and non-responsive.
PRICE SCHEDULE
PMIS #318433- RESTRIPE RIDGELAND MAINLINE MP 86 - MP 102.46
BASE ITEM
APPENDIX
FOR REFERENCE ONLY
FOR REFERENCE ONLY
Section 634
Section 634. — PERMANENT PAVEMENT MARKINGS
Description
634.01 This work consists of applying paint, markings, and markers on finished pavement.
Pavement markings are designated as follows:
Type A – Solventborne traffic paint with Type 1 glass beads;
Type B – Waterborne traffic paint with Type 1 glass beads;
Type C – High-build waterborne traffic paint with Type 1 and Type 3 glass beads;
Type D – Epoxy markings with Type 1 glass beads;
Type E – Epoxy markings with Type 1 and Type 3 glass beads;
Type H – Thermoplastic markings with Type 1 glass beads;
Type I – Thermoplastic markings with Type 1 and Type 3 glass beads;
Type J – Preformed pavement marking tape; or
Type K – Nonreflectorized markings.
Material
634.02 Conform to the MUTCD and the following Subsections:
Epoxy markings 718.11
Epoxy resin adhesives 718.17
Glass beads 718.14
Pavement markers 718.15
Preformed pavement marking tape 718.13
Solventborne traffic paint 718.09
Thermoplastic markings 718.12
Waterborne traffic paint 718.10
Construction Requirements
634.03 General. Where existing and final pavement marking locations are identical, stake the limits of existing pavement markings before beginning pavement work.
Submit manufacturer’s MSDS and product data sheets at least 7 days before applying pavement markings.
A field demonstration may be required to verify the adequacy of the material.
Ship marking material in suitable containers plainly marked with the following information as appropriate for the material being furnished:
(a) Manufacturer’s name and address;
(b) Name of product;
(c) Lot and batch numbers;
(d) Color;
(e) Net mass and volume of contents;
(f) Date of manufacture;
(g) Date of expiration;
(h) Statement of contents (if mixing of components is required);
(i) Mixing proportions and instructions; and
(j) Safety information.
Establish marking patterns or locations according to the MUTCD, plans, or state requirements. In curve widening areas, establish the edge line markings at the limits of the traveled way and the centerline markings equal distance between the edge lines.
Remove loose particles, dirt, tar, grease, and other deleterious material from the surface to be marked.
Where markings are placed on rigid pavement less than 1-year old, clean the pavement of laitance and curing compounds.
Remove temporary pavement markings the same day permanent pavement markings are applied. Remove temporary and conflicting pavement makings according to Subsection 635.13 before applying permanent pavement markings.
Obtain approval before applying markings. Apply markings to a clean, dry surface, and according to the manufacturer’s recommendations. Produce markings that are clean-cut and uniform in appearance by day and night.
Current state approved pavement marking material may be used, when approved by the CO. Submit proof of compliance with state specifications.
Apply glass beads immediately following paint or markings application to ensure adhesion.
Protect markings from traffic until dried to a no-tracking condition. Remove tracking marks, spilled marking material, markings in unauthorized areas, and defective markings.
634.04 Solventborne Traffic Paint (Type A). Apply paint when pavement and air temperatures are at
35 °F (2 °C) and rising. Do not heat the paint above 120 °F (49 °C). Spray paint at a 15 mil
(0.38 millimeters) minimum wet film thickness or at a rate of 107 square feet per gallon (2.6 square meters per liter).
Apply Type 1 glass beads on the paint at a rate of 6 to 8 pounds per gallon (0.72 to 0.96 kilograms per liter) of paint.
On new asphalt pavements or new asphalt surface treatments, apply two applications of paint and glass beads. Apply second application after first application is track free.
634.05 Waterborne Traffic Paint (Type B and Type C). Apply paint when pavement and air temperatures are 50 °F (10 °C) and rising.
(a) Type B. Do not heat the paint above 120 °F (49 °C). Spray paint at a 15 mil (0.38 millimeters) minimum wet film thickness or at a rate of 107 square feet per gallon (2.6 square meters per liter).
Apply Type 1 glass beads on the paint at a rate of 6 to 8 pounds per gallon (0.72 to 0.96 kilograms per liter) of paint.
On new asphalt pavements or new asphalt surface treatments, apply two coats.
(b) Type C. Spray paint at 25 mil (0.63 millimeters) minimum wet film thickness or at a rate of
71 square feet per gallon (1.7 square meters per liter).
Use two bead dispensers. Apply Type 3 glass beads on the paint at a rate of 6 to 8 pounds per gallon
(0.72 to 0.960 kilograms per liter) followed by Type 1 glass beads on the paint at a rate of 6 to
8 pounds per gallon (0.72 to 0.96 kilograms per liter) of paint.
634.06 Epoxy Markings (Types D and Type E). Apply epoxy when pavement and air temperatures are
35 °F (2 °C) and rising. Heat components as specified by the manufacturer. Apply at a 25 mil
(0.63 millimeters) minimum dry film thickness or at a rate of 71 square feet per gallon (1.7 square meters per liter).
(a) Type D. Apply Type 1 glass beads on the epoxy at a rate of 6 to 8 pounds per gallon (0.72 to
0.96 kilograms per liter) of epoxy.
(b) Type E. Use two bead dispensers. Apply Type 3 glass beads on the epoxy at a rate of 6 to 8 pounds per gallon (0.72 to 0.96 kilograms per liter) of epoxy followed by Type 1 glass beads on the epoxy at a rate of 6 to 8 pounds per gallon (0.72 to 0.96 kilograms per liter) of epoxy.
634.07 Thermoplastic Markings (Type H and Type I). Apply thermoplastic when pavement and air temperatures are 50 °F (10 °C) and rising. Heat thermoplastic as specified by the manufacturer.
Apply an epoxy resin primer/sealer according to the thermoplastic manufacturer’s recommendations when placing markings on rigid pavements or asphalt pavements more than 2-years old, oxidized, or having exposed aggregates.
Allow the primer/sealer to dry.
For edge lines, apply thermoplastic at 60 mil (1.5 millimeters) dry film thickness. For other lines, apply thermoplastic at 90 mil (2.3 millimeters) dry film thickness.
(a) Type H. Apply Type 1 glass beads on the thermoplastic at a rate recommended by the manufacturer.
(b) Type I. Use two bead dispensers. Apply Type 3 glass beads on the thermoplastic followed by
Type 1 glass beads on the thermoplastic at rates recommended by the manufacturer.
634.08 Preformed Pavement Marking Tape (Type J). Install to form a durable, weather resistant bond to the pavement. Apply preformed markings according to the manufacturer’s recommendations. Use preformed marking tape containing retroreflective beads.
634.09 Nonreflectorized Markings (Type K). Apply solvent borne or waterborne traffic paint without glass beads.
634.10 Pavement Markers. Install raised or recessed pavement markers when the pavement and air temperatures are 50 °F (10 °C) and rising. Apply pavement markers with an epoxy resin adhesive as recommended by the manufacturer when the pavement is dry. Space the markers according to the
MUTCD and plans.
634.11 Acceptance. Material for permanent pavement markings will be evaluated under Subsections
106.02 and 106.03.
Placing of permanent pavement markings will be evaluated under Subsections 106.02 and 106.04.
Measurement
634.12 Measure the Section 634 pay items listed in the bid schedule according to Subsection 109.02 and the following as applicable:
When pavement markings are measured by the linear foot (meter), measure the length of line applied along the centerline of each line applied regardless of color. Measure broken or dotted pavement lines from end to end of the line including gaps. Measure solid pavement lines from end to end of each continuous line. Measure line quantities based on a 4-inch (100-millimeter) wide line. For line widths greater than 4 inches (100 millimeters), adjust the measured length of line in the ratio of the required width to 4 inches (100 millimeters).
When pavement markings are measured by the square foot (square meter), measure the number of square feet (square meter) of line, symbol or letter marking based on the marking area shown in the plans. If not shown, measure the area of each marking in place to the nearest square foot (square meter).
Payment
634.13 The accepted quantities will be paid at the contract price per unit of measurement for the Section
634 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this
Section. See Subsection 109.05.
Section 635
Section 635. — TEMPORARY TRAFFIC CONTROL
Description
635.01 This work consists of furnishing, installing, maintaining, relocating, and removing temporary traffic control devices and services as ordered for the control and protection of public traffic through the project.
Advance warning arrow board, barricade, and warning light types are designated in the MUTCD.
Material
635.02 Conform to the MUTCD and the following Sections and Subsections:
Concrete barrier (temporary) 618
Delineator and object marker retroreflectors 718.08(b)
Guardrail (temporary) 617
Retroreflective sheeting 718.01
Sign panels 633.05
Sign posts 633.04
Temporary plastic fence 710.11
Temporary pavement markings 718.16
Construction Requirements
635.03 Qualifications. Provide flaggers certified by ATSSA, the National Safety Council, a state department of transportation, or other acceptable organization. Use pilot car operators conforming to the qualifications of a flagger.
635.04 General. Furnish, install, and maintain temporary traffic control devices adjacent to and within the project as required by the MUTCD, traffic control plan, and Section 156. Install and maintain traffic control devices as follows:
(a) Furnish and install traffic control devices before the start of construction operations;
(b) Install only those traffic control devices needed for each stage or phase;
(c) Relocate temporary traffic control devices as necessary;
(d) Remove devices that no longer apply to the existing conditions;
(e) Immediately replace devices that are lost, stolen, destroyed, or inoperative;
(f) Keep temporary traffic control devices clean;
(g) Furnish and maintain traffic control devices that meet the "acceptable" standard described in
ATSSA, Quality Standards for Work Zone Traffic Control Devices. Amend the ATSSA standards as follows:
(1) Repair or remove and replace "marginal" devices within 48 hours; and
(2) Repair or remove and replace "unacceptable" devices immediately;
(h) Remove temporary traffic control devices upon contract completion or when approved; and
(i) Furnish crashworthy temporary traffic control devices.
635.05 Barricades. Use barricades of the type and size specified or according to the MUTCD. Use Type
III, IV, IX, or XI retroreflective sheeting.
635.06 Cones and Tubular Markers. Use cones or tubular markers of the height specified or according to the MUTCD. Use Type III or Type VI retroreflective sheeting.
635.07 Construction Signs. Use Type III, IV, VIII, IX, or XI prismatic retroreflective sheeting. Use fluorescent sheeting for orange signs. For roll-up signs, use florescent Type VI retroreflective sheeting.
Install posts according to Section 633. Portable sign supports may be used instead of sign posts when approved by the CO.
Remove or completely cover unnecessary signs. Use metal, plywood, or other acceptable material to cover signs. Do not use adhesives glues, tapes, or mechanical fasteners that mar the face of the panel of the sign to be covered.
635.08 Drums. Use plastic drums that are at least 36 inches (900 millimeters) high and at least 18 inches
(450 millimeters) in diameter. Use Type III or Type VI retroreflective sheeting.
635.09 Flaggers. Use flaggers certified according to Subsection 635.03. Use Type III, IV, VIII, IX, or XI retroreflective sheeting on flagger paddles. Do not use flags.
635.10 Pilot Cars. Use pilot car operators certified according to Subsection 635.03. Mount a "PILOT CAR
FOLLOW ME" sign on the rear and a high-intensity, rotating, flashing, oscillating, or strobe light on the roof of the pilot car.
635.11 Temporary Barriers. Use temporary barriers that are crashworthy and are new or used provided they are not badly damaged. Lifting holes no larger than 4 inches (100 millimeters) or lifting loops are permitted.
Mount white or yellow retroreflectors as applicable, to the top or side of the barrier on 25-foot (8-meter) centers. Mount the retroreflectors at a uniform height at least 24 inches (600 millimeters) above the road surface. Flexible barrier delineators or barrier delineation tape may be used instead of retroreflectors when approved by the CO.
635.12 Temporary Guardrail. Construct temporary guardrail according to Section 617.
Mount white or yellow retroreflectors as applicable, to the top or side of the guardrail on 25-foot (8-meter) centers. Mount the retroreflectors at a uniform height at least 24 inches (600 millimeters) above the road surface.
635.13 Temporary Pavement Markings and Delineation. Before opening a pavement surface to traffic, remove conflicting pavement markings by sandblasting or other methods that do not damage the surface or texture of the pavement. Make the removal pattern uneven to not perpetuate the outline of the removed pavement markings. Lightly coat sandblasted or removal areas on asphalt surfaces with emulsified asphalt.
Place and maintain temporary pavement markings that are neat, crack free, true, straight, and unbroken.
If temporary signs and pavement markers are substituted for temporary pavement markings, install temporary signs and pavement markers according to the MUTCD and plans.
For temporary pavement markings, use preformed retroreflective tape, traffic paint, or pavement markers as follows:
(a) Preformed retroreflective tape. Apply according to the manufacturer’s instructions. Remove loose preformed retroreflective tape before placing additional pavement layers.
(b) Pavement markers. Do not use pavement markers during seasonal suspensions. When chip seals, slurry seals, or tack coats are used after marker placement, protect the markers with an approved protective cover, and remove it after the asphalt material is sprayed.
(c) Traffic paint. Do not apply traffic paint to the final surface. Apply traffic paint as the temporary pavement marking if no work will be performed on the project for at least 30 consecutive days. Apply traffic paint at a 15 mil (0.38-millimeter) minimum wet film thickness or at a rate of 107 square feet per gallon (2.6 square meters per liter). Immediately apply Type 1 glass beads on the paint at a minimum rate of 6 pounds per gallon (0.7 kilograms per liter) of paint.
Remove temporary pavement markers before placing additional pavement layers or permanent pavement markings. Remove temporary markings after 14 days and apply permanent pavement markings unless approved by the CO.
635.14 Vertical Panels. Use vertical panels that are at least 24 inches (600 millimeters) in height and 8 to
12 inches (200 to 300 millimeters) wide. Use Type III, IV, VIII, IX, or XI retroreflective sheeting.
635.15 Warning Lights. Use warning lights of the types shown in the plans or according to the MUTCD.
Install warning lights with a minimum mounting height of 30 inches (750 millimeter) to the bottom of the lens. Secure lights to the top of the traffic control device they are supplementing. Use batteries recommended by the light manufacturer. Mount large batteries below windshield height and preferably on the ground. Replace batteries when they no longer provide satisfactory performance.
Use Type C steady-burn warning lights for delineation on barricades or drums. Use Type A low-intensity flashing warning lights on the first 2 barricades or drums in the merging or shifting taper series. Use Type
B high-intensity flashing warning lights on the first two advance warning signs. Type A and Type C warning lights are intended to warn road users during nighttime hours, while Type B warning lights are intended to warn road users during both daylight and nighttime hours.
635.16 Shadow Vehicle. Use a 19,800 pound (9000-kilogram) ± 990 pound (±450 kilogram) shadow vehicle equipped with a truck-mounted attenuator (crash cushion) attached to the rear of the vehicle, exterior flashing yellow dome light, and an arrow board.
Use the shadow vehicle to provide physical protection to workers from traffic approaching from the rear during moving operations.
Use the following procedures to close a lane of traffic:
(a) Move the shadow vehicle to a point approximately 200 feet (60 meters) from the first advance warning sign for the lane closure and stop on the shoulder;
(b) Activate the flashing lights and flashing arrow board. Begin the arrow board in the caution mode and after approximately 2 minutes display the correct flashing pass arrow;
(c) Move the shadow vehicle (now acting as a protection vehicle) along the shoulder to the first sign location, stopping approximately 100 feet (30 meters) before the sign location in a blocking position;
(d) Place the first sign then proceed to the next advance sign location. Repeat step (c) for the second sign and install that sign. Repeat this procedure until advance warning signs are installed;
(e) After installing the advanced warning signs for the lane closure, move the shadow vehicle into the lane that is to be closed to a position 100 feet (30 meters) before the closing taper location. Install the channelizing devices for the taper in the shielded lane; then
(f) Move the shadow vehicle off the roadway and past the taper on the shoulder and remain in position until the flashing arrow board for the closure (if one is to be provided) is placed and operating. Move the shadow vehicle with the workers as they proceed to set up the remaining devices as additional protection.
Alternate lane closure procedures may be used if approved by the CO.
635.17 Pavement Patch. Use an asphalt mix according to Section 403 or commercial available cold asphalt mix to repair potholes and rough spots in the traveled way before reopening travel lanes to traffic.
If cold asphalt mix is used, remove and replace with hot asphalt mix before placing succeeding hot asphalt lifts.
635.18 Temporary Crash Cushions. Use a crashworthy temporary crash cushion according to manufacturer’s recommendations.
635.19 Temporary Signal System. Use a temporary signal system according to MUTCD Parts 4 and 6.
Provide the names and telephone numbers of at least two emergency contacts who can be reached
24 hours a day, and who are available to arrive on site within 4 hours of notification to repair or replace malfunctioning temporary signal equipment. In addition, provide for emergency flaggers who can be reached 24 hours a day, and who are available to perform traffic control operations within the timeframes specified below until the temporary signal system is operable.
If the traffic signal malfunctions during construction operations, immediately begin traffic control operations using flaggers until the system is returned to normal signal operation. Complete traffic signal repairs within 6 hours of the malfunction.
If the traffic signal malfunctions during a period when no construction activity is taking place, begin traffic control operations using flaggers as soon as possible, but no later than 2 hours after the initial notification. Continue temporary flagging operations until the system is returned to normal signal operation. Complete traffic signal repairs within 12 hours of notification.
No payment will be made for the use of flaggers in place of a malfunctioning or inoperable temporary signal system.
635.20 Temporary Fence. Use temporary fence according to Section 619.
635.21 Temporary Rumble Strip. Use transverse or longitudinal rumble strips according to the MUTCD
Part 6 to alert drivers of an approaching flagger station or work area.
635.22 Steel Plates. Use 1-inch (25-millimeter) or thicker steel plates capable of safely carrying traffic.
Secure the plates to the pavement to prevent movement.
635.23 Acceptance. Material for temporary traffic control devices will be evaluated under Subsections
106.02 and 106.03.
Vehicles for pilot cars and shadow vehicles will be evaluated under Subsections 106.02 and 106.04.
Placement of temporary traffic control devices will be evaluated under Subsections 106.02 and 106.04.
Temporary traffic control services will be evaluated under Subsections 106.02 and 106.04.
Measurement
635.24 Measure the Section 635 pay items listed in the bid schedule according to Subsection 109.02 and the following as applicable when ordered by the CO and installed.
When measuring temporary traffic control pay items, measure only one time even if relocated or replaced, except for pay items paid by the hour.
Measure barricades by the linear foot (meter) of width.
When measuring construction signs by the square foot (square meter), measure front face sign panel. Do not measure posts and temporary supports.
When there is a pay item for moving temporary barriers, do not measure movement of temporary barriers for work access or the convenience of the Contractor.
When measuring temporary pavement markings, measure only one application of pavement markings per lift. When temporary pavement markings are measured by the linear foot or mile (meter or kilometer), measure the number of linear feet or miles (meters or kilometers) of lines applied along the centerline of each 4-inch (100-millimeter) wide line applied regardless of color. Measure solid lines from end to end of each continuous line. Measure broken lines from end to end including gaps. For line widths greater than
4 inches 100 millimeters), adjust the measured length of line in the ratio of the required width to 4 inches
(100 millimeters). When temporary pavement markings are measured by the square foot (square meter), measure the number of square feet (square meters) of symbols or letter markings based on the marking area shown in the plans or, if not shown, the area of each marking measured in place to the nearest square foot (square meter).
When measuring temporary pavement markers, measure only one application of pavement markings per lift, even if replaced. Measure temporary pavement markers used at the option of the Contractor instead of temporary pavement markings as equivalent temporary pavement markings and not as temporary pavement markers.
When measuring pavement marking removal, measure the actual line removed. Do not measure gaps.
When measuring temporary crash cushions, measure each entire crash cushion configuration.
When there is a pay item for moving temporary crash cushion, do not measure movement of temporary crash cushion for work access or the convenience of the Contractor.
Measure replacement barrels or cartridges for crash cushions for the barrels or cartridges damaged by public traffic.
Payment
635.25 The accepted quantities will be paid at the contract price per unit of measurement for the Section
635 pay items listed in the bid schedule. Payment will be full compensation for the work…