This document appears to be Amendment 002 to a Request for Information (RFI) for the SARA HVAC CONTROLS solicitation, Solicitation Number 140P4324Q0025, issued by the Department of the Interior National Park Service Northeast Region.
The RFI amendment addresses a question regarding the intent of voltage/phase loss power brown out sensors to shut down all controlled equipment. The amendment clarifies that the intent is to monitor the main service feeders and shut down all controlled equipment upon loss of voltage/phase, rather than individual voltage/phase loss on each piece of equipment.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amd006_0006.pdf | ||
| Sol_140P4324Q0025_Amd_0006.pdf | ||
| IMG_03_0005.jpg | JPG image | |
| IMG_06_0005.jpg | JPG image | |
| IMG_01_0005.jpg | JPG image | |
| IMG_05_0005.jpg | JPG image | |
| Sol_140P4324Q0025_Amd_0005.pdf | ||
| IMG_04_0005.jpg | JPG image | |
| IMG_07_0005.jpg | JPG image | |
| IMG_02_0005.jpg | JPG image | |
| Amd005_0005.pdf | ||
| Amd004_0004.pdf | ||
| Sol_140P4324Q0025_Amd_0004.pdf | ||
| Amd003_0003.pdf | ||
| Sol_140P4324Q0025_Amd_0003.pdf | ||
| Sol_140P4324Q0025_Amd_0002.pdf | ||
| B09-Attachment-3_1990_Plans_0001.pdf | ||
| B09-Attachment-4_2019_Plans_0001.pdf | ||
| B09-Attachment-1_1960_Plans_0001.pdf | ||
| Sol_140P4324Q0025_Amd_0001.pdf | ||
| B09-Attachment-2_1974_Plans_0001.pdf | ||
| B09-140P4324Q0025-Amd001_0001.pdf | ||
| B09-Attachment-1b_1960_Plans_0001.pdf | ||
| WD-2015-4143-Rev26-12_26_23.pdf | ||
| Sol_140P4324Q0025.pdf | ||
| HVAC-CONTROLS-SOW.pdf |
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SARA HVAC Controls, 140P4324Q0025
Amendment 002
RFI# (6)
6. There was a mention of voltage/phase loss power brown out sensors to shut down all motors, condensers, and heaters. Is the intent to monitor the main service feeders and shut down all controlled equipment upon loss?
Yes
Or individual voltage /phase loss on each piece of equipment?
No