This document is a Solicitation for Pavement Markings and Striping at Yellowstone National Park. The National Park Service Intermountain Region is seeking a contractor to provide these services under a single award Indefinite Delivery Indefinite Quantity (IDIQ) contract for up to three years. The contract will have a minimum guarantee of $5,000 and a maximum value of $1,900,000. The work is set aside for small businesses under NAICS code 237310 (Highway, Street, and Bridge Construction). The first task order is estimated to be between $100,000 and $250,000. Offerors must submit pricing for all line items in the Bid Schedule and provide a limitation on subcontracting worksheet. Performance and payment bonds will be required at the task order level if the value exceeds specified thresholds. The contract performance period is 10/1/2024 to 9/30/2027, with the first task order due by 7/31/2025. Offers are due by 8/7/2024.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_5_-_Wage_Determination.pdf | ||
| Attachment_1_-_SoW_Yell_NP_Road_Striping.docx | DOCX document | |
| Attachment_3_-_Bid_Schedule.xlsx | XLSX spreadsheet | |
| Attachment_2_-_Past_Performance_Questionaire.doc | DOC document | |
| Attachment_4_-_Limitation_on_Subcontracting_Worksheet.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION CALL
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040656084
NPS, IMR - Northern Rockies MABO
PO Box 168
Mammoth Supply Center / 22 Stable St Yellowstone NP WY 82190
PIR
Casey Pehrson 1720910967
1x 07/08/2024
140P1424R0018
INVITATION FOR BID
REQUEST FOR PROPOSAL
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
PROJECT DESCRIPTION: Pavement markings and striping at Yellowstone National Park.
TYPE OF CONTRACT: Construction, Single Award, Indefinite Delivery, Indefinite
Quantity (IDIQ) Contract for up to three years with Firm Fixed Priced (FFP) Task
Orders (TOs).
LOCATION: Yellowstone National Park
MAGNITUDE (FAR 36.204): Between $100,000 and $250,000 (First Task Order)
SEED PROJECT/ MINIMUM GUARANTEE: $5,000.00
MAXIMUM CONTRACT VALUE: $1,900,000.00
NAICS: 237310 Highway, Street, and Bridge Construction
SIZE STANDARD: $45 Million
SET-ASIDE: Small Business Set-Aside
Continued ...
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 365 calendar days and complete it within ________________ ________________ calendar days after receiving
08/07/2024
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 12/2022)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
NPS, IMR - Northern Rockies MABO PO Box 168
Mammoth Supply Center / 22 Stable St Yellowstone NP WY 82190
PIR
Casey Pehrson
28. NEGOTIATED AGREEMENT 29. AWARD
and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
10 U.S.C. 3204(a) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 12/2022) BACK
Continued...
and return
(Contractor is not required to sign this document.) Your offer on this
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 47
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140P1424R0018
Delivery: 07/31/2025
Delivery Location Code: 0010977180
Yellowstone National Park
22 Stable Street
Yellowstone National Park WY 82190 US
Period of Performance: 10/01/2024 to 09/30/2027
00010 ROAD STRIPING
Product/Service Code: Z2LB
Product/Service Description: REPAIR OR ALTERATION
OF HIGHWAYS/ROADS/STREETS/BRIDGES/RAILWAYS
Period of Performance: 10/01/2024 to 07/31/2025
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Name: Casey D. Pehrson Email: casey_pehrson@nps.gov
PROJECT DESCRIPTION: Pavement markings and striping at Yellowstone National Park.
TYPE OF CONTRACT: Construction, Single Award, Indefinite Delivery, Indefinite Quantity (IDIQ) Contract for up to three years with Firm Fixed Priced (FFP) Task Orders (TOs).
LOCATION: Yellowstone National Park
MAGNITUDE (FAR 36.204): Between $100,000 and $250,000 (First Task Order)
MINIMUM GUARANTEE: $5,000.00
MAXIMUM CONTRACT VALUE: $1,900,000.00
NAICS: 237310 – Highway, Street, and Bridge Construction
SIZE STANDARD: $45 Million
SET-ASIDE: Small Business Set-Aside
SINGLE AWARD: The Government anticipates award of only one IDIQ contract to meet the needs of this requirement.
ORDERS: Delivery/Task Orders issued against the IDIQ shall be firm fixed price.
ORDERING PERIODS: Contract will include a three-year ordering period, for a total contract performance period not to exceed three years.
AUTHORIZED CONTRACTING OFFICER: Any warranted Contracting Officer in the National Park Service (NPS) may award delivery/task orders against this IDIQ contract.
ORDERING PROCEDURES FOR DELIVERY/TASK ORDERS: Delivery/task orders (DO/TO) will be issued within the terms and conditions of the contract based on the pre-priced contract line items in the awarded bid schedule, and with the order limitations clause in the contract. The order will be signed by the Contracting officer and issued to the contractor utilizing an Optional Form 347, Order for Supplies or Services award form that contains the specifics of the delivery. The DO/TO becomes binding when the Contracting Officer signs the Order.
Bid Bond/ Offer Guarantee: Not required, payment bonds and performance bonds will be required at the TO level as described below. (Bonds in accordance with FAR Clause 52.228-11 and 52.228-15 are required at the TO level, not at the contract level)
National Park Service Contracting Officer
Payment Bonds: Required when any DO/TO is greater than $35,000.00.
Performance Bonds: required when any DO/TO are greater than $150,000.00
SECTION A – FORM SF 1442
SECTION B – SUPPLIES OR SERVICES/PRICES
IDIQ CONTRACT BID SCHEDULE: (Complete Attachment 3 - Bid Schedule)
POINT OF
CONTACT:
COMPANY:
PHONE:
EMAIL:
UEI #:
YOUR FIRM SHALL SUBMIT PRICES FOR ALL ITEMS TO BE CONSIDERED RESPONSIVE. ALL PRICES SHALL BE FULLY BURDENED AND ALL INCLUSIVE (I.E., OVERHEAD, G&A, PROFIT, BONDS, ETC.)
Offerors are required to submit, at a minimum, an offer that conforms to the solicitation documents with pricing for all line items of attachment 3 (Bid Schedule). Failure to do so may render the proposal unacceptable.
SECTION C –DESCRIPTION/SPECIFICATIONS
Specifications are attached and contained in Attachment 1 and are hereby incorporated by reference. See Section J for a list of attachments pertinent this solicitation.
(END OF SECTION C)
SECTION D – PACKAGING AND MARKING
This Section is blank.
(END OF SECTION D)
SECTION E – INSPECTION AND ACCEPTANCE
52.252-2 Clauses Incorporated by Reference (Feb 1998)
This solicitation incorporates one or more Federal Acquisition Regulation (FAR) clauses by reference, with the same force and effect as if they were given in full text. The full text of a FAR clause may be accessed electronically at the following website: www.acquisition.gov/far.
52.246-12 Inspection of Construction (Aug 1996) 52.246-13 Inspection -- Dismantling, Demolition, or Removal of Improvements (Aug 1996) 52.246-21 Warranty of Construction (Mar 1994)
FINAL INSPECTION AND ACCEPTANCE
Final completion of the punch list items, submission of all required submittals, and final cleanup of the project site shall be completed before the contract’s stated completion date. The Contracting Officer or his/her designated representative will perform final inspection. Acceptance of the work will occur only upon written notice of acceptance by the ordering
Contracting Officer, or any Warranted Contracting Officer employed by the NPS and performing authorized duties in conjunction with this contract.
(END OF SECTION E)
52.252-2 Clauses Incorporated by Reference (Feb 1998)
This solicitation incorporates one or more Federal Acquisition Regulation (FAR) clauses by reference, with the same force and effect as if they were given in full text. The full text of a FAR clause may be accessed electronically at the following website: www.acquisition.gov/far.
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)
The Contractor shall be required to (a) commence work under this contract within (will be specified in each individual task order) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use no later than (will be specified in each individual task order) calendar days after receipt of notice to proceed. The time stated for completion shall include final cleanup of the premises.
CONTRACT WORK HOURS
The performance period established for this contract is based upon all work being conducted during regular working hours.
Regular working hours are limited to the time between 7:00 am and 6:00 pm each day Monday through Friday, excluding Government holidays. If the Contractor desires to carry on work outside regular hours, including Saturdays, Sundays, and Government holidays, a request must be submitted to the Contracting Officer in sufficient time to allow satisfactory arrangements to be made by the Government for access to the work site and inspection.
FEDERAL HOLIDAYS
The following Federal Legal Holidays are observed by the NPS:
New Year’s Day Martin Luther King, Jr.
Washington’s Birthday Memorial Day Juneteenth National Independence Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas
(END SECTION F)
SECTION G - CONTRACT ADMINISTRATION DATA
Electronic Invoicing and Payment Requirements – Invoice Processing Platform (IPP) February 2021
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
Invoice to be on company letterhead with stated contract number.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause)
1452.201-70 Authorities and Delegations (SEPT 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause; Waive or agree to modification of the delivery schedule;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum.
The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph
(c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
Notice to Contractors - Contractor Performance Assessment Reporting System (Dec 2015)
1) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
2) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
3) We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 15 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
4) When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.
5) Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/ .
a) Contractor Representatives may then provide comments in response to the evaluation or return the evaluation without comment.
b) Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.
c) All information provided should be reviewed for accuracy prior to submission. d) If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.
d) Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.
https://www.cpars.gov/
e) If you do not sign and submit the CPAR within 60 days , it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."
6) The following guidelines apply concerning your use of the past performance evaluation:
a) Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.
b) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
c) Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
7) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.
8) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
(END OF SECTION G)
SECTION H - SPECIAL CONTRACT REQUIREMENTS
This solicitation incorporates one or more Federal Acquisition Regulation (FAR) clauses by reference, with the same force and effect as if they were given in full text. The full text of a FAR clause may be accessed electronically at the following website: www.acquisition.gov/far.
PROHIBITION OF ALL TERRAIN VEHICLES (ATV)S
The contractor is prohibited from utilizing All-Terrain Vehicles (ATV's) on NPS lands. ATV is defined as: A motorized off-highway vehicle (OHV) traveling on four or more low-pressure tires, having a seat to be straddled by the operator and a handlebar for steering control. Use of Utility Terrain Vehicles (UTV's) are permitted. UTV (Also called a side-by-side) is defined as: A motorized OHV having four or more low pressure tires, designed with side-by-side seats, seatbelts, steering wheel, and optional cab, brush cage, or ROPS.
EXPENSED RELATED TO OFFERS
This solicitation does not commit the Government to pay any costs incurred in the submission of any proposal, in making necessary studies or designs for the preparation thereof, or to acquire or contract for any services. Costs shall not be incurred by recipients of this solicitation in anticipation of receiving direct reimbursement from the Government. It is understood that your bid/proposal/quote will become part of the official file on this matter without obligation to the Government.
CONFIDENTIAL INFORMATION
(a) It is understood that throughout performance of the contract the contractor may have access to confidential information that is the property of the Government. Unauthorized duplication or disclosure of the information provided by the Government or to which the contractor will have access as a result of this contract is prohibited. Except as otherwise expressly provided in this contract, the Contractor shall return all Government documents in its possession upon completion or termination of this contract.
(b) To the extent that the work under this contract requires access to proprietary or confidential business or financial data of other companies, and as long as such data remains proprietary or confidential, the contractor shall protect such data from unauthorized use and disclosure and agrees not to use it to compete with such companies.
(c) No confidential information may be divulged to any person or organization without the advance, written permission of the Contracting Officer or the party in whom title thereto is wholly vested. This clause also applies to any subcontractors and/or consultants used by the contractor.
(d) The foregoing obligations do not apply to:
(1) Information that, at the time of receipt by the Contractor, is in the public domain;
(2) Information that is published after receipt thereof by the Contractor or otherwise becomes part of the public domain through no fault of the Contractor;
(3) Information that the Contractor can demonstrate was in his possession at the time of receipt thereof and was not acquired directly or indirectly from the Government or other companies;
(4) Information that the Contractor can demonstrate was received from a third party who did not require the Contractor to hold it in confidence.
INDEMNIFICATION
The contractor is an 'independent contractor' and shall obtain all necessary insurance to protect himself from liability arising out of this contract. The contractor hereby agrees to indemnify and hold the Government harmless in connection with, any loss or liability from damage to or destruction of property or from injuries to or death of persons (including the agents and employees of both parties) if such damage, destruction, injury or death arises out of, or is caused by performance of work under this contract, unless such damage, destruction, injury or death is caused solely by the negligence of the Government, its agents or employees. The contractor agrees to include this clause, appropriately modified, in all subcontracts to be performed under this contract.
FIRE DANGER SEASON
If allowed to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed.
PRESERVATION OF HISTORICAL AND ARCHEOLOGICAL DATA
(a) The Historic and Archeological Data Preservation Act of 1974, provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
(b) If, in connection with operations under this contract, the Contractor, subcontractors, or the employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the Contractor shall immediately suspend all operations in the vicinity of the cultural value and shall notify the Contracting Officer in writing, giving the location and nature of the findings. No objects of cultural resource value may be removed.
(c) Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the Changes clause.
(d) The Contractor will be responsible for protecting the cultural resources within the affected area from damage. In addition, the contractor will be liable for all damage to the identified cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or his representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.
DAMAGE TO UTILITIES
In the event of a contractor caused utility failure/disruption, the Contractor will first make the area safe, then immediately contact the Contracting Officer Representative and Contracting Officer. If the damaged utilities were previously known or shown to the contractor, or there is negligence on his part, the utilities will be repaired by the contractor in a timely manner at no cost to the government. If the damaged utilities were not previously known or shown to the contractor and there is not negligence on his part, they will be repaired at government expense.
MATERIAL SAFETY DATA SHEET
A Material Safety Data Sheet (MSDS), OSHA Form 20 or accepted equivalent, must be submitted for each hazardous or potentially hazardous material or chemical to be utilized by the contractor. This includes solvents or treated materials, such as preservative treated wood (MSDS for preservative) or fungicide treated rubber goods (MSDS for fungicide). All materials must be approved by the Contracting Officer or their designated representative prior to installation.
KEY PERSONNEL, SUBCONTRACTORS AND OUTSIDE ASSOCIATES OR CONSULTANTS
In connection with the services covered by this contract, any in-house personnel, subcontractors, and outside associates or consultants will be limited to individuals or firms that were specifically identified and agreed to during negotiations. The Contractor shall obtain the Contracting Officer's written consent before making any substitution for these designated in-house personnel, subcontractors, associates, or consultants.
SHUTDOWN
It is recognized that seasonal climatic conditions regularly occur in some of the NPS areas that restrict and sometimes prohibit normal construction activities. The actual timing of a seasonal shutdown will be determined by mutual agreement between the Contractor and the Contracting Officer. The Contractor shall give the Contracting Officer at least two weeks’ notice prior to the anticipated resumption of work. The actual date that work is resumed is subject to the approval of the Contracting Officer. The amount of time during a seasonal shutdown is taken into consideration when the completion time as stated in the Contract is determined. Therefore, the contract time will not be extended due to seasonal shutdowns.
(END OF SECTION H)
SECTION I - CONTRACT CLAUSES
This solicitation incorporates one more Federal Acquisition Regulation (FAR) clauses by reference, with the same force and effect as if they were given in full text. The full text of a FAR clause may be accessed electronically at the following website: www.acqusition.gov/far.
52.202-1 Definitions (Jun 2020) 52.203-3 Gratuities (Apr 1984) 52.203-5 Covenant Against Contingent Fees. (May 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020) 52.203-7 Anti-Kickback Procedures (Jun 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (May 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (Jun 2020) 52.203-13 Contractor Code of Business Ethics and Conduct (Nov 2021) 52.203-17 Contractor Employee Whistleblower Rights (Nov 2023) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (May 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020) 52.204-13 System for Award Management Maintenance (Oct 2018) 52.204-15 Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Oct 2016) 52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014) 52.204-23 Prohibition on Contracting for Hardware, Software and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Dec 2023) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment
(Nov 2021) 52.204-27 Prohibition on a ByteDance Covered Application (Jun 2023) 52.204-30 Federal Acquisition Supply Chain Security Act Orders—Prohibition. (DEC 2023) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or
Proposed for Debarment. (Nov 2021) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (Oct 2018) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015) 52.211-6 Brand Name or Equal (Aug 1999) 52.215-2 Audit and Records - Negotiation (Jun 2020) 52.215-8 Order of Precedence - Uniform Contract Format (Oct 1997) 52.219-6 Notice of Total Small Business Set-Aside (Nov 2020) 52.219-8 Utilization of Small Business Concerns (Sep 2023) 52.219-28 Post Award Small Business Program Representations (Sep 2023) 52.222-3 Convict Labor (Jun 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation. (May 2018) 52.222-6 Construction Wage Rate Requirements (Aug 2018) 52.222-7 Withholding of Funds (May 2014) 52.222-8 Payrolls and Basic Records (Jul 2021) 52.222-9 Apprentices and Trainees (Jul 2005) 52.222-10 Compliance with Copeland Act Requirements (Feb 1988) 52.222-11 Subcontracts (Labor Standards) (May 2014) 52.222-12 Contract Termination-Debarment (May 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014) 52.222-14 Disputes Concerning Labor Standards (Feb 1988) 52.222-15 Certification of Eligibility (May 2014) 52.222-19 Child Labor – Cooperation with Authorities and Remedies (Nov 2023) 52.222-21 Prohibition of Segregated Facilities (Apr 2015) 52.222-26 Equal Opportunity (Sept 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015)
52.222-35 Equal Opportunity for Veterans (Jun 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (Jun 2020) 52.222-37 Employment Reports on Veterans (Jun 2020) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) 52.222-50 Combating Trafficking in Persons (Nov 2021) 52.222-54 Employment Eligibility Verification (May 2022) 52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026. (JAN 2022)" 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) 52.223-5 Pollution Prevention and Right-to-Know Information (May 2024) 52.223-6 Drug-Free Workplace (May 2001) 52.225-13 Restrictions on certain foreign purchases (Feb 2021) 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) 52.227-1 Authorization and Consent (Jun 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (Jun 2020) 52.227-4 Patent Indemnity - Construction Contracts (Dec 2007) 52.228-2 Additional Bond Security (Oct 1997) 52.228-5 Insurance - Work on a Government Installation (Jan 1997) 52.228-12 Prospective Subcontractor Request for Bonds (Dec 2022) 52.228-14 Irrevocable Letter of Credit (Nov 2014) 52.229-12 Tax on Certain Foreign Procurements (Feb 2021) 52.232-5 Payments Under Fixed-Price Construction Contracts. (May 2014) 52.232-16 Alt 1 Progress Payments (Nov 2021) Alternate 1 (Mar 2000) 52.232-17 Interest (May 2014) 52.232-23 Assignment of Claims (May 2014) 52.232-27 Prompt payment for Construction Contracts (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer - System for Award Management (Oct 2018) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-1 Disputes (May 2014) 52.233-3 Protest after Award. (Aug 1996) 52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004) 52.236-2 Differing Site Conditions. (Apr 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984) 52.236-5 Material and Workmanship (Apr 1984) 52.236-6 Superintendence by the Contractor (Apr 1984) 52.236-7 Permits and Responsibilities (Nov 1991) 52.236-8 Other Contracts (Apr 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984) 52.236-10 Operations and Storage Areas (Apr 1984) 52.236-11 Use and Possession Prior to Completion (Apr 1984) 52.236-12 Cleaning Up (Apr 1984) 52.236-13Alt 1 Accident Prevention (Nov 1991), Alternate 1 (Nov 1991) 52.236-14 Availability and Use of Utility Services (Apr 1984) 52.236-17 Layout of Work (Apr 1984) 52.236-21 Specifications and Drawings for Construction (Feb 1997) 52.236-26 Preconstruction Conference (Feb 1995) 52.242-13 Bankruptcy (Jul 1995) 52.242-14 Suspension of Work (Apr 1984) 52.243-4 Changes (Jun 2007) 52.243-7 Notification of Changes (Jan 2017) 52.245-1 Government Property (Jan 2017) 52.245-9 Uses and Charges (Apr 2012) 52.248-3 Value Engineering-Construction (Oct 2020) 52.249-2 Alt I Termination for Convenience of the Government (Fixed-Price) (Apr 2012), Alternate I (Sep 1996) 52.249-10.1 Default (Fixed-Price Construction) (Apr 1984)
52.216-18 Ordering (Aug 2020)
(a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the Schedule. Such orders may be issued from date of award of the IDIQ to the last date of the ordering period not to exceed three years.
(b) All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.
(c) A delivery order or task order is considered "issued" when—
(1) If sent by mail (includes transmittal by U.S. mail or private delivery service), the Government deposits the order in the mail;
(2) If sent by fax, the Government transmits the order to the Contractor's fax number; or
(3) If sent electronically, the Government either—
(i) Posts a copy of the delivery order or task order to a Government document access system, and notice is sent to the Contractor; or
(ii) Distributes the delivery order or task order via email to the Contractor's email address.
(d) Orders may be issued by methods other than those enumerated in this clause only if authorized in the contract.
52.216-19 Ordering Limitations (Oct 1995)
(a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than $5,000, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.
(b) Maximum order. The Contractor is not obligated to honor-
(1) Any order for a single item in excess of $500,000;
(2) Any order for a combination of items in excess of $500,000; or
(3) A series of orders from the same ordering office within 30 days that together call for quantities exceeding the limitation in paragraph (b)(1) or (2) of this section.
(c) If this is a requirements contract (i.e., includes the Requirements clause at subsection 52.216-21 of the Federal Acquisition Regulation (FAR)), the Government is not required to order a part of any one requirement from the Contractor if that requirement exceeds the maximum-order limitations in paragraph (b) of this section.
(d) Notwithstanding paragraphs (b) and (c) of this section, the Contractor shall honor any order exceeding the maximum order limitations in paragraph (b), unless that order (or orders) is returned to the ordering office within 15 days after issuance, with written notice stating the Contractor’s intent not to ship the item (or items) called for and the reasons. Upon receiving this notice, the Government may acquire the supplies or services from another source.
52.216-22 Indefinite Quantity (Oct 1995)
(a) This is an indefinite-quantity contract for the supplies or services specified, and effective for the period stated, in the Schedule. The quantities of supplies and services specified in the Schedule are estimates only and are not purchased by this contract.
(b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause.
The Contractor shall furnish to the Government, when and if ordered, the supplies or services specified in the Schedule up to and including the quantity designated in the Schedule as the "maximum." The Government shall order at least the quantity of supplies or services designated in the Schedule as the "minimum."
(c) Except for any limitations on quantities in the Order Limitations clause or in the Schedule, there is no limit on the number of orders that may be issued. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.
(d) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor’s and Government’s rights and obligations with respect to that order to the same extent as if the order were completed during the contract’s effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after the date identified for the completion of the project as stated in the last Task Order issued within the effective period of the contract.
52.219-14 Limitations on Subcontracting (OCT 2022) (Deviation, OCT 2022)
(a) This clause does not apply to the unrestricted portion of a partial set-aside.
(b) Definition. Similarly situated entity, as used in this clause, means a first-tier subcontractor, including an independent contractor, that—
(1) Has the same small business program status as that which qualified the prime contractor for the award (e.g., for a small business set-aside contract, any small business concern, without regard to its socioeconomic status); and
(2) Is considered small for the size standard under the North American Industry Classification System (NAICS) code the prime contractor assigned to the subcontract.
(c) Applicability. This clause applies only to—
(1) Contracts that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(2) Part or parts of a multiple-award contract that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(3) Contracts that have been awarded on a sole-source basis in accordance with subparts 19.8, 19.13, 19.14, and 19.15;
(4) Orders expected to exceed the simplified acquisition threshold and that are—
(i) Set aside for small business concerns under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to small business concerns under multiple-award contracts as described in 19.504(c)(1)(ii);
(5) Orders, regardless of dollar value, that are—
(i) Set aside in accordance with subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to concerns that qualify for the programs described in subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 19.504(c)(1)(ii); and
(6) Contracts using the HUBZone price evaluation preference to award to a HUBZone small business concern unless the concern waived the evaluation preference.
(d) Independent contractors. An independent contractor shall be considered a subcontractor.
(e) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees to the following requirements in the performance of a contract assigned a North American Industry Classification System (NAICS) code applicable to this contract:
(1) Services (except construction). It will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding certain other direct costs and certain work performed outside the United States (see paragraph (e)(1)(i)), to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract.
(i) The following services may be excluded from the 50 percent limitation:
(A) Other direct costs, to the extent they are not the principal purpose of the acquisition and small business concerns do not provide the service. Examples include airline travel, work performed by a transportation or disposal entity under a contract assigned the environmental remediation NAICS code (562910), cloud computing services, or mass media purchases.
(B) Work performed outside the United States on awards made pursuant to the Foreign Assistance Act of 1961, or work performed outside the United States required to be performed by a local contractor.
(2) Supplies (other than procurement from a nonmanufacturer of such supplies). It will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 50 percent subcontract amount that cannot be exceeded. When a contract includes both supplies and services, the 50 percent limitation shall apply only to the supply portion of the contract.
(3) General construction. It will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 85 percent subcontract amount that cannot be exceeded.
(4) Construction by special trade contractors. It will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 75 percent subcontract amount that cannot be exceeded.
(f) The Contractor shall comply with the limitations on subcontracting as follows:
(1) For contracts, in accordance with paragraphs (c)(1), (2), (3) and (6) of this clause –
[Contracting Officer check as appropriate.] __ By the end of the base term of the contract and then by the end of each subsequent option period; or X By the end of the performance period for each order issued under the contract.
(2) For orders, in accordance with paragraphs (c)(4) and (5) of this clause, by the end of the performance period for the order.
(g) A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph (e) of this clause will be performed by the aggregate of the joint venture participants.
(1) In a joint venture comprised of a small business protégé and its mentor approved by the Small Business Administration, the small business protégé shall perform at least 40 percent of the work performed by the joint venture.
Work performed by the small business protégé in the joint venture must be more than administrative functions.
(2) In an 8(a) joint venture, the 8(a) participant(s) shall perform at least 40 percent of the work performed by the joint venture. Work performed by the 8(a) participants in the joint venture must be more than administrative functions.
52.223-3 Hazardous Material Identification and Material Safety Data. (Feb 2021)
(a)“Hazardous material,” as used in this clause, includes any material defined as hazardous under the latest version of Federal Standard No. 313 (including revisions adopted during the term of the contract).
(b)The offeror must list any hazardous material, as defined in paragraph (a) of this clause, to be delivered under this contract.
The hazardous material shall be properly identified and include any applicable identification number, such as National Stock Number or Special Item Number. This information shall also be included on the Material Safety Data Sheet submitted under this contract.
(c)
(d) This list must be updated during performance of the contract whenever the Contractor determines that any other material to be delivered under this contract is hazardous.
(e) The apparently successful offeror agrees to submit, for each item as required prior to award, a Material Safety Data Sheet, meeting the requirements of 29 CFR 1910.1200(g) and the latest version of Federal Standard No. 313, for all hazardous material identified in paragraph (b) of this clause. Data shall be submitted in accordance with Federal Standard No. 313, whether or not the apparently successful offeror is the actual manufacturer of these items. Failure to submit the Material Safety Data Sheet prior to award may result in the apparently successful offeror being considered non responsible and ineligible for award.
(f) If, after award, there is a change in the composition of the item(s) or a revision to Federal Standard No. 313, which renders incomplete or inaccurate the data submitted under paragraph (d) of this clause, the Contractor shall promptly notify the Contracting Officer and resubmit the data.
(g) Neither the requirements of this clause nor any act or failure to act by the Government shall relieve the Contractor of any responsibility or liability for the safety of Government, Contractor, or subcontractor personnel or property.
(h) Nothing contained in this clause shall relieve the Contractor from complying with applicable Federal, State, and local laws, codes, ordinances, and regulations (including the obtaining of licenses and permits) in connection with hazardous material.
(i) The Government’s rights in data furnished under this contract with respect to hazardous material are as follows:
Material Identification No.
(If none, insert “None”)
(1) To use, duplicate and disclose any data to which this clause is applicable. The purposes of this right are to --
(i) Apprise personnel of the hazards to which they may be exposed in using, handling, packaging, transporting, or disposing of hazardous materials;
(ii) Obtain medical treatment for those affected by the material; and
(iii) Have others use, duplicate, and disclose the data for the Government for these purposes.
(2) To use, duplicate, and disclose data furnished under this clause, in accordance with subparagraph (h)(1) of this clause, in precedence over any other clause of this contract providing for rights in data. The Government is not precluded from using similar or identical data acquired from other sources.
(j) Except as provided in paragraph (i)(2), the Contractor shall prepare and submit a sufficient number of Material Safety Da ta Sheets (MSDS’s), meeting the requirements of 29 CFR 1910.1200(g) and the latest version of Federal Standard No. 313, for all hazardous materials identified in paragraph (b) of this clause.
(1) For items shipped to consignees, the Contractor shall include a copy of the MSDS’s with the packing list or other suitable shipping document which accompanies each shipment. Alternatively, the Contractor is permitted to transmit MSDS’s to consignees in advance of receipt of shipments by consignees, if authorized in writing by the Contracting Officer.
(2) For items shipped to consignees identified by mailing address as agency depots, distribution centers or customer supply centers, the Contractor shall provide one copy of the MSDS’s in or on…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .