B09_SF30_Amendment_0003_Q_A_Attachment_01_0003.docx

DOCX document 13 KB Posted

Attached to
PASS CREEK HANDTHINNING Federal contract opportunity
Solicitation number
140L3725Q0021
Issued by
Department of the Interior Bureau of Land Management Idaho Region

About this file

This is a Questions and Answers document (Amendment 0003) for RFQ 140L3724Q0021 for Pass Creek Handthinning issued by the Bureau of Land Management Idaho Region.

The Q&A clarifies that contractors are not responsible for burning piles but must follow piling specifications in the Statement of Work, pile covering is not required, and current site conditions have patchy snow drifts up to 1 foot deep but are mostly dry and accessible. The document also confirms that government personnel will fill CO, COR, and PI roles, and while constant traffic control is not required, work zone signage is recommended. All answers reference specifications detailed in the original Statement of Work.

View the file

Other files for this federal contract opportunity

Other files attached to PASS CREEK HANDTHINNING, newest first.
File Type Posted
Sol_140L3725Q0021_Amd_0005.pdf PDF
Sol_140L3725Q0021_Amd_0004.pdf PDF
B09_SF30_Amendment_0004_Q_A_Attachment_01_0004.docx DOCX document
Sol_140L3725Q0021_Amd_0003.pdf PDF
B09_SF30_Amendment_0002_Q_A_Attachment_01_0002.docx DOCX document
Sol_140L3725Q0021_Amd_0002.pdf PDF
Sol_140L3725Q0021_Amd_0001.pdf PDF
Sol_140L3725Q0021.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pass Creek Q&A RFQ 140L3724Q0021

1. Question: Is the contractor responsible for burning the piles created during the contract?

Answer 1: Contractor is not responsible for burning piles, but they are responsible for closely following the piling specs outlined in the statement of work.

2. Question: How is the current access and snow accumulations looking for these two projects?

Answer 2: Conditions are relatively dry. There are patchy drifts up to 1 foot deep, but the majority of the acres are dry and accessible.

3. Question: Will this require covering?

Answer 3: No pile covering required. See piling specifications in the SOW.

Amendment 0003 03/04/2025

4. Question: Can the contractor representative be the contractor itself?

Answer 4: The role of the CO, COR, and PI are described in section C.2.1 of the SOW. They are government positions furnished by BLM.

5. Does the contractor need to have employees with different titles for the key personnel on site?

Answer 5: See answer 4.

6. Will the contractor will need someone to constantly control traffic in the work zone?

Answer 6: It is not required. Signage on roads indicating work ahead is recommended.