B09_SF30_Amendment_0003_Q_A_Attachment_01_0003.docx
DOCX document 13 KB Posted
- Attached to
- PASS CREEK HANDTHINNING Federal contract opportunity
- Solicitation number
- 140L3725Q0021
About this file
This is a Questions and Answers document (Amendment 0003) for RFQ 140L3724Q0021 for Pass Creek Handthinning issued by the Bureau of Land Management Idaho Region.
The Q&A clarifies that contractors are not responsible for burning piles but must follow piling specifications in the Statement of Work, pile covering is not required, and current site conditions have patchy snow drifts up to 1 foot deep but are mostly dry and accessible. The document also confirms that government personnel will fill CO, COR, and PI roles, and while constant traffic control is not required, work zone signage is recommended. All answers reference specifications detailed in the original Statement of Work.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L3725Q0021_Amd_0005.pdf | ||
| Sol_140L3725Q0021_Amd_0004.pdf | ||
| B09_SF30_Amendment_0004_Q_A_Attachment_01_0004.docx | DOCX document | |
| Sol_140L3725Q0021_Amd_0003.pdf | ||
| B09_SF30_Amendment_0002_Q_A_Attachment_01_0002.docx | DOCX document | |
| Sol_140L3725Q0021_Amd_0002.pdf | ||
| Sol_140L3725Q0021_Amd_0001.pdf | ||
| Sol_140L3725Q0021.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pass Creek Q&A RFQ 140L3724Q0021
1. Question: Is the contractor responsible for burning the piles created during the contract?
Answer 1: Contractor is not responsible for burning piles, but they are responsible for closely following the piling specs outlined in the statement of work.
2. Question: How is the current access and snow accumulations looking for these two projects?
Answer 2: Conditions are relatively dry. There are patchy drifts up to 1 foot deep, but the majority of the acres are dry and accessible.
3. Question: Will this require covering?
Answer 3: No pile covering required. See piling specifications in the SOW.
Amendment 0003 03/04/2025
4. Question: Can the contractor representative be the contractor itself?
Answer 4: The role of the CO, COR, and PI are described in section C.2.1 of the SOW. They are government positions furnished by BLM.
5. Does the contractor need to have employees with different titles for the key personnel on site?
Answer 5: See answer 4.
6. Will the contractor will need someone to constantly control traffic in the work zone?
Answer 6: It is not required. Signage on roads indicating work ahead is recommended.