Answers_to_RFIs_-_6-6-2024.docx
DOCX document 25 KB Posted
- Attached to
- LOOKOUT PASS TOPO SURVEY Federal contract opportunity
- Solicitation number
- 140L3624Q0090
About this file
This document is a set of Answers to Requests for Information (RFIs) related to a federal contract opportunity for a Topographic Survey at Lookout Pass.
The key details are:
- The contract will allow the use of contractor-owned, contractor-operated unmanned aircraft systems (UAS or drones) for the project.
- The contractor is responsible for determining and obtaining the necessary aerial imagery, as the Bureau of Land Management (BLM) is not providing any historic aerial imagery.
- BLM will assist by setting up ground control points, but will not provide any additional support beyond what is specified in the Statement of Work.
- Resumes do not count towards the 15-page limit for the technical capabilities and plan volume.
The related federal contract opportunity is a solicitation from the Department of the Interior Bureau of Land Management for the Lookout Pass Topographic Survey project.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| WD_2015-5401_rev__21.pdf | ||
| Sol_140L3624Q0090.pdf | ||
| A04_-_SOW_Lookout_Pass.doc | DOC document | |
| Lookout_Pass_Attachment_A.pdf | ||
| Answers_to_RFIs_-_5-29-2024.docx | DOCX document | |
| Past_Performance_Questionnaire.pdf | ||
| Lookout_Pass_Attachment_B.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Can BLM please confirm that this contract will allow for use of a contractor-owned, contractor-operated unmanned aircraft system (UAS, or drone) for this project?
Yes, the contract will allow the use of UAS or drone for this project.
2. Please provide a list and description of historic aerial imagery BLM will provide to the contractor upon award.
The BLM is not providing historic aerial imagery, it is the contractors responsibility, using professional judgement, to determine the relevant aerial imagery for the development of the historic topographic surface.
3. Beyond the GFP noted in SOW IV.C, what resources and support will BLM provide for this project?
As noted in SOW IV.C.1, the BLM will assist with setting ground control, typically two control points (rebar with aluminum cap), to be used to ensure coordination and acceptance of coordinate system.The BLM is not anticipating providing any additional support other than what is in SOW IV.C.
4. Do resumes count against the 15-page limit for the technical capabilities and plan volume, or are resumes outside of the 15-page limit?
No. The 15 page limit is for the technical capabilities narrative. Resumes do not count toward this limit.