EMDD CARPET REPLACEMENT
140L3422Q0003
QUESTION AND ANWER DOCUMENT
| 1.Q. | How do prospective contractors turn in bids? | |
| 1.A. | | Please see the solicitation for quote submission instructions |
| 2.Q. | Will the Government require carpet Samples? |
| 2.A. | Yes. Review the Statement of Work Section 2.2.1.1.1; Section 2.2.1.2.1 and Section 2.3.1.1 |
| 3.Q. | Has there been any changes to the total square footage of carpet and baseboards according to the blueprints? |
| 3.A. | No Changes |
| 4.Q. | For disposal, would a dumpster be permitted to be left onsite while job is in progress? |
| 4.A. | Yes. The contractor can order/pay for a dumpster to be placed outside of the buildings - Contractor is responsible for cost and ensure it gets dumped/picked up. |
| 5.Q. | What are the permitted times we are allowed to be working on site? |
| 5.A. | You can work from 7:30 am to 5:30 pm. Monday through Friday – no holidays. Any requests to the work times must be pre-approved by the contracting officer. Contractor will not have access to the buildings without Federal personnel present. |
| 6.Q. | How soon are you ready to get the job commenced and time frame for completion? |
| 6.A. | Please see the solicitation for the period of performance. |