Milner_Chip_Seal_RFI_0001.pdf

PDF 105 KB Posted

Attached to
MILNER CHIP SEAL
Solicitation number
140L2621Q0041
Issued by

View the file

Other files

File Type Posted
Sol_140L2621Q0041_Amd_0001.pdf PDF
Site_Tour_Sign_In_0001.pdf PDF
Milner_chip_seal.docx DOCX document
Milner_Chip_Seal_Dwg_s.pdf PDF
Sol_140L2621Q0041.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Milner Chip Seal RFI

1. Is there a location where the contractor will be allowed to stockpile chips?

Yes.

2. Are Class A (1/2") chips required or Class B chips (3/8”)?

½” Gradation on Section 703.09 Table 703-7 C.

3. Will we be able to shut the whole road down? It should only take a day to chip and a day to fog/stripe.

Only half the site can be shut down at a time.

4. I don’t see any application rates specified. Should we just use the local state standard?

See Section 407.

5. Type of Aggregate/Gradation Required (if any)?

½” Gradation on Section 703.09 Table 703-7 C.

6. Acceptance Parameters (Statistical analysis, warranty, etc.)?

See Section 407-3.

7. Side cast Brooming, accepted?

Yes.

8. Any Stormwater Prevention Plan Required?

No.

9. Are Traffic Control Plans Required to be submitted for approval or is under the direction of the contractor?

Yes, Traffic Control plans are required to be submitted for approval.

10. Is a record of existing required or are temporary tabs adequate to marking existing pavement markings?

Temporary tabs adequate.

11. I don’t know if you’re aware, but there is a pretty severe paint shortage that is affecting most of our jobs. Are you aware of this and how do you want to handle that?

Upon receipt of proof from the Contractor that the paint has been ordered and all other work is complete. The period of performance will be extended to allow for the delivery and application of the paint.