- MUD CONTAINMENT AND DISPOSAL SERVICES
- Solicitation number
- 140G0323Q0223
About this file
This statement of work describes mud containment and disposal services required by the United States Geological Survey for groundwater monitoring well drilling projects in California's Central Valley between 2023 to 2025. The contractor will provide 20-yard bins for solid cuttings containment onsite, transport solids to the California Department of Water Resources facilities in Coalinga or Lost Hills for disposal. The contractor will also provide vacuum trucks to transfer drilling mud liquids from frac tanks to the same CADWR facilities for disposal. The statement of work outlines estimated solid and liquid waste volumes by site totaling 1,304 tons of solids and 1,301 tons of liquids to be removed. The contractor must have capability to respond within 48 hours of notification and work may occur seven days a week from 7am to 7pm. Pricing is required for bin delivery and rental, solids and liquids transportation and disposal per load, and vacuum truck standby rates.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| EXHIBIT_A_LINE_ITEM_PRICING_TASK_ORDER_NO_1_0001.xlsx | XLSX spreadsheet | |
| WAGE_DETERMINATION_(KERN_AND_FRESNO_COUNTY)_0001.pdf | ||
| Sol_140G0323Q0223_Amd_0001.pdf | ||
| Sol_140G0323Q0223.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Geological Survey, OAG Sacramento 140G0323Q0223
STATEMENT OF WORK
Containment, transport, and disposal of drilling solids and fluids generated during the drilling of Groundwater
Monitoring Wells in the Central Valley of CA
I. General Information:
INTRODUCTION: the United States Geological Survey (USGS) Research Drilling Program (RDP) has the need for a vendor to provide materials and labor for the management of drilling fluids and solids resulting from the drilling and constructing monitoring wells at multiple sites in the southern half for the California Central Valley during calendar year 2023 – 2025. The vendor will need to provide a 20-yard bins to contain the drill cuttings and drilling mud generated during the well installation process. Then transportation of both bins and fluids (vacuum truck) to a local California Department of Water Resources (CADWR) facilities. As part of the management process the vendor will be required to coordinate disposal with (CADWR) facility (site contacts will be provided).
VENDOR SHALL PROVIDE LINE-ITEM COSTS FOR SERVICES NOTED BELOW SEE
ATTACHMENT 2-EXHIBIT A, LINE-ITEM PRICING AND FILL OUT PRICING FOR YEAR 1 AND 2.
*ALL TASK ORDERS ARE IN ACCORDANCE WITH THE STATEMENT OF WORK HEREIN.
PLEASE REFER TO ATTACHMENT 2- TO QUOTE ON FIRST TASK ORDER.
**TASK ORDER #1 WELL LOCATION: # 6 REFER TO TABLE 2 HEREIN.
• SOLIDS AND LIQUIDS DISPOSAL
1. DELIVERY & PICK UP OF 20 YARD BIN
2. WEEKLY RATE OF 2O- YARD BIN
3. 2O-YARD BIN PLASTIC LINERS
4. STAND-BY RATE PER HOUR
5. 20 YARD BIN FOR PICK UP, TRANSPORT, AND DISPOSE OF SOLID WASTE
6. 4000 GALLONS- PICK UP, TRANSPORT, AND DISPOSE OF LIQUID WASTE
PLEASE NOTE:
*INCLUDE ANY FUEL RELATED SURCHAGES IN THE QUOTE
*NO COST TO DUMP SOLIDS OR LIQUIDS AT (CADWR)
PERIOD OF PERFORMANCE- SEPT 22, 2023, TO SEPT 21, 2025
• SOLIDS
• Cost to haul bins with material and dump from work sites to CADWR yards (map 3). – Quote price to haul and dump each 20-yard bin. Include all labor and, any fuel relates surcharges. Please Note: (NO Cost to dump at closest CADWR facilities). Quote price per trip (dump then return empty bin to drill site).
• LIQUIDS:
• Vacuum truck costs to suck fluids from frac tanks and haul then dump at the closest Coalinga or Lost Hills CADWR facility (map 3). Include all labor and, any fuel relates surcharges.
Please Note: (NO Cost to dump at closest CADWR facilities). Quote for 4000- gallons vacuum trucks. Quote price per trip to both suck fluids, transport fluids to facility and dump fluids at closest facility (CADWR)facility.
• II. BACKGROUND:
The USGS RDP will begin drilling and construction of monitoring wells September 22, 2023. Sites listed and mapped below (Map 3).
At each site, solid debris and liquids will be generated from the mud-rotary drilling process. The solid phase is composed of moist clays, silts, sands, and gravels from the borehole; this debris will be collected and contained in 20-yard bins provided by the vendor. On some occasions, a liquid component composed of sediment-laden bentonite clay drill mud, will need to be vacuumed (skimmed) from the same bins and transported for disposal.
This task shall be charged at the *standby hourly rate quoted.
The liquid phase is composed of local city potable hydrant water, bentonite mud, and groundwater. These fluids will be generated during drilling and well development and store at each site in a 20,000-gallon Baker tank. This tank will be provided by the USGS (RDP). The actual weight of solids and liquids generated at each site is not known. Actual volumes depend on depths drilled, how many holes (some sites may be eliminated, or some added), lost circulation issues can decrease fluids, well development discharge volumes are variable. NOTE: All additives used during the drilling process are NSF60 drinking water approved.
Solids: Will be contained in 20-yard bins will be transported and dumped at either the Coalinga or Lost Hills (CADWR) yards. (See table 1).
Liquids: Will be stored in frac tanks. The vendor shall supply vacuum trucks to suck fluids from frac tanks then haul to one of the (CADWR) yards (See table 1). NOTE: some liquids may need to be vacuumed from the 20-yard bins on occasion. This cost should be charged at the *standby hourly rate.
The solids and liquids generated during the drilling process are expected to be free from contamination. One sample of the drilling mud will be collected by the USGS and sent off to a local laboratory for analysis (see table 3). The results will be shared with the vendor.
QUANTITIES/LOCATIONS:
Coalinga Region: Estimate of 842 tons of solids and 548 tons of liquids will need to be disposed of from 3 sites (2 holes next to each other. All solids generated in this region will be disposed of at the Coalinga CADWR facility. Liquids from the Coalinga region will be dumped at the CADWR Coalinga facility until the holding area is full.
Lost Hills: Estimate of 462 tons of solids and 753 liquid tons will need to be disposed from 4 sites (table 1&2). Both solids and liquids will be transported to the CADWR Lost Hills facility.
Table 1. Summary of site information and expected borehole solid/liquid amounts.
ESTIMATED VOLUMES
name well type Depth liquids Solids
Site Region
Predicted Dump
Location Liquids
Predicted Dump
Location Solids
Est Total Liquids per dump site
Est Total Solids per dump site
1 extens 2400 89 69 Coalinga Coalinga Coalinga 1a piezo 2400 144 164 Coalinga Coalinga Coalinga 2 extens 2400 89 69 Coalinga Coalinga Coalinga 2a piezo 2400 144 164 Coalinga Coalinga Coalinga 548 3 extens 2200 82 63 Coalinga Coalinga Coalinga 3a piezo 2200 123 133 Coalinga Coalinga Coalinga 4 extens 1600 61 47 Coalinga Lost Hills Coalinga 4a piezo 1600 106 133 Coalinga Lost Hills Coalinga 842
5 extens 900 36 28 San Joaquin Lost Hills Lost Hills
6 extens 900 36 28 San Joaquin Lost Hills Lost Hills
7 extens 1400 53 41 San Joaquin Lost Hills Lost Hills
7a piezo 1400 78 88 San Joaquin Lost Hills Lost Hills
8 extens 2800 103 80 San Joaquin Lost Hills Lost Hills
8a piezo 2800 157 197 San Joaquin Lost Hills Lost Hills 753 462
Table 1
WELL LOCATIONS
Well Number
Updated Proposed Mile Post (refined location)
Proposed well plan depth (ft)
Lat. Long. Expected Location for Cuttings and
Fluid Disposal
Field Division
(N, WGS 84) (W, WGS 84)
1 132.9L 2400 36.45605 -120.304042 Coalinga Facility San Luis 2 143.4L 2400 36.325589 -120.226844 Coalinga Facility San Luis 3 160.5L 2200 36.151072 -120.048867 Coalinga Facility San Luis 4 166.7L 1600 36.079492 -120.031628 Lost Hills San Luis 5 198.5L 800 35.691944 -119.766389 Lost Hills San Joaquin 6 207.9L 853 TD 35.581669 -119.677544 Lost Hills San Joaquin 7 256.1R 1400 35.1006 -119.369369 Lost Hills San Joaquin 8 271.2L 2800 35.065747 -119.114919 Lost Hills San Joaquin
Table 2
21121 CA-46 (lat/long is: 35.6155970993877, -119.69513437156118) Lost Hills, CA 93249
Coalinga Operation & Maintenance Subcenter (near MP-143) MAP 2
California Department of Water Resources Locations:
Lost Hills Operation & Maintenance Subcenter (near MP-205) MAP 1
24001 Fresno Coalinga Rd. (lat/long is: 36.326724086167665, -120.22869346367297) Coalinga, CA 93210
Map 1 (CADWR) Lost Hills Dump Location
Map 2 (CADWR) Coalinga Dump Location
III. WORK REQUIREMENTS
a. Delivery of at least two 20-yard rock bins to the site on the first day of the project. Plastic bin liners will need to be installed. Additional bins may need to be delivered during the project with a 48-hour notice.
Vendor will install all plastic liners.
b. Pickup, transport, and dispose of solids. Dual axle trucks with trailer are preferred for maneuverability around site and to negotiate off road conditions. A 40-foot trailer may be use for deliveries if site conditions permit. Bins will be filled by the USGS to about half capacity to avoid overweight loads and spills during pick up. Vendor will take appropriate measures to avoid or mitigate spills during pickup.
c. Vacuum truck to recover, transport, and dispose of liquids. Solid and liquid material generated during the drilling process will be picked up by, transported by, and disposed of by the vendor at (CADWR) yards.
d. Vendor must coordinate all activities with the local (CADWR) facility Including advance notice to facility contact and verifying location to dump solids vs liquids.
e. Vendor must be able to provide services with 48-hour notification.
f. Work may be completed on site by the vendor between the hours of 7am and 7pm seven days a week. The vendor will not be required to complete work on weekends or holidays.
Vendor will complete all invoicing within 60 days of the completion of the project. Invoicing will include an itemized listing of the charges per line item.
IV. Supporting Information (for vendor)
a. No Government-owned property or services will be provided to the vendor, except for a 20,000 Baker tank.
The vendor will provide all related equipment needed to complete the Work Requirements. Space will be made available for staging and work performance.
b. The full PERIOD OF PERFORMANCE will begin as early as September 22, 2023 and expected to be completed September 21, 2025.
c. A two-week advance notification will be provided to the vendor regarding the precise location, start date, and anticipated end date, of the project.
d. Table 2. Standard laboratory analysis of the drill mud ordered by the USGS.
Map 3 site and dump facility locations
TABLE 3. Standard laboratory analysis of the drill mud ordered by the USGS.
ITEM METHOD
VOCs by GCMS EPA 8260B Metals Title 22 no Hg (rush) EPA 6010B Specific Conductance SM 2510B Extractable Hydrocarbons (rush) EPA 8015B Mercury EPA 7471A Perchlorate (rush) EPA 314.0 pH EPA 9045C TPH Gasoline (C4-C12) CA LUFT Density ASTM D1475 Solids, Total Dissolved SM 2540 C
WORK SITES DESIGNATED BY CIRCLES.
Latitude and Longitude Locations
Mile Post 275 Lat 35.04083 Long -199.05638
Mile Post 256 Lat 35.10083 Long -119.36916
Mile Post 208 Lat 35.58117 Long -119.67819
Mile Post 200 Lat 35.67111 Long -119.745
Mile Post 167 Lat 36.07944 Long -120.03167
Mile Post 161 Lat 36.150833 Long -120.04889
Mile Post 143 Lat 36.32583 Long -120.22694
Mile Post 128 Lat 36.5125 Long -120.364.16