Design-Build: Lahontan NFH Well Replacement
Solicitation number
140F0121R0019
Issued by

About this file

This document contains questions and answers related to a federal design-build contract opportunity for replacement of wells and improvements at the Lahontan National Fish Hatchery in Nevada. The U.S. Fish and Wildlife Service is seeking a firm fixed price contract for well replacement and control building upgrades between $1-5 million. The NAICS code is 237110 and small businesses under $39.5 million are eligible to submit proposals. Subcontractors must be listed in Phase I, and substitutions may be allowed after award at the discretion of the contracting officer. Responsibility for utility upgrades and charges will be determined in Phase II. A two-phase design-build evaluation process will be used, with recent experience and past performance evaluated in Phase I and technical approach in Phase II. Award is expected by August 1, 2021 for work through December 31, 2022. The opportunity is set aside for small businesses only.

View the file

Other files

File Type Posted
Sol_140F0121R0019_Amd_0001.pdf PDF
B03 DOL Wage Determination.pdf PDF
Sol_140F0121R0019.pdf PDF
Subcontractor List.docx DOCX document
A04 Statement of Work.docx DOCX document
35 Percent Design Drawings .pdf PDF
Design Technical Memorandum.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Are there soil reports for below and will they be provided prior to Phase II: No

a. Location of proposed well #6 placement

Drawing G-06 indicates 60’ East of existing well #6

b. Subgrade for control building well #6

As necessary to support the slab required for the proposed design

c. Subgrade for control building well #4

As necessary to support the slab required for the proposed design

2. The submission for Phase I requires a sub-list and the contract REQUIRES prime contractor to utilize those listed if awarded. What options are there to modify the list if a sub-contractor cannot perform at time of award?

a. Substitutions with a subcontractor of equal or better qualifications may be allowed at the discretion of the contracting officer after award. The Phase I subcontractor list only requires well drilling and design subcontractors to be listed.

3. Will contractor or FWS be responsible for NVE charges and fees if upgrades to service and transformers are required?

FWS believes the existing power at existing well #6 is adequate. However, the FWS will provide additional information, if available, as part of phase 2 of the proposal. Therefore, the specific responsibility for NVE charges are to be determined.