This statement of work describes a requirement for a contractor to replace the uninterruptible power supply (UPS) system and power inverter at the Bureau of Indian Affairs' Headgate Rock Dam hydroelectric power plant. The contractor will be responsible for analyzing the existing UPS and inverter loads, procuring and installing a new 208/120V 20kVA UPS and 120V 5kVA inverter, conducting testing, and providing documentation. The contractor must have experience with similar projects. Key deliverables include a project management plan, test reports, and completion within 90 days of award. The performance period is also one year from completion. The solicitation was released by the Department of the Interior Bureau of Indian Affairs Western Region as solicitation number 140A1122Q0023.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140A1122Q0023_Amd_0002.pdf | ||
| Sol_140A1122Q0023_Amd_0001.pdf | ||
| 140A1122Q0023_Terms_and_Conditions.pdf | ||
| Sol_140A1122Q0023.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work HGRD Replace UPS System and Power Inverter
Bureau of Indian Affairs / Colorado River Agency / Electrical Branch
12124 1st Ave, Parker, La Paz County, AZ 85344
1.0 INTRODUCTION
The Bureau of Indian Affairs (BIA), Colorado River Agency, Branch of Electrical Services (CRA-ES) is in the need of a replacement UPS System and Power Inverter for the Headgate Rock Dam (HGRD). CRA-ES seeks an experienced and knowledgeable contractor to procure, install and commission a replacement UPS System and Power Inverter for the HGRD.
A key mission of the BIA, CRA-ES is to provide economical and reliable power to the residential and commercial customers that reside within the boundaries of the Colorado River Indian Tribe (CRIT) reservation. Owned and operated by the BIA, CRA-ES HGRD is located on the lower Colorado River, about 15 miles downstream of Parker Dam near the town of Parker, Arizona. HGRD, which impounds a body of water known as Lake Moovalya, has 10 radial gates in which 3 of the feed the hydroelectric power plant that was retrofitted to the Head Gate Rock Dam (HGRD) circa 1992. It was designed as a low head, axial flow turbine powering the generation units to nearly 19.5 Mega Watt (MW) of power serving the Colorado River Indian Tribes (CRIT) Reservation.
The UPS provides power for the emergency lighting, fire detection, security, control system computers, microwave transceiver, electronic phone system, logger/printer, and power to Inverter. The power inverter is located on panel C2B and it supplies power for the Supervisory Control And Data Acquisition (SCADA), Remote Terminal Units (RTU) A and B, RTU A and B sub-nodes, RTU panel lighting, remote pressure level sensors power support. The UPS system and the Power Inverter are key components of the control systems for the HGRD power plant.
2.0 OBJECTIVE
The objective of this effort is to perform an analysis of the existing UPS load and identify required systems to be connected to the UPS, to replace the existing UPS and inverter to provide the connected systems (load) with uninterrupted power for at least 3 hours in the event of a utility power loss. The load may be negotiated to supply only the minimum systems/subsystems to achieve the minimum of 3 hours.
3.0 SCOPE
The contractor shall provide all personnel, supervision, mobilization, tools, equipment, vehicles, lodging, travel, meals, materials, labor, expertise, logistics, testing, freight, and other direct cost required to perform the following.
• Analysis of UPS/inverter load
• Remove and dispose of existing UPS/inverter system
• Installation, test, configuration, and commissioning of one (1) new 208/120 VAC, 20 kVA or comparable UPS system
• Remove and dispose of existing Power Inverter
• Installation, test, configuration, and commissioning of one (1) new 120 VAC, 5 kVA or comparable Power
Inverter
These services will require interaction with Government staff to collect/gather the required information and perform safety procedures.
• The contractor shall perform, along with HGRD personnel, Lock Out Tag Out (LOTO) procedures of equipment and devices; to include providing their own locks.
• The contractor shall provide and install their own protective grounds for personnel safety
• The contractor shall provide their own required PPE applicable to task as recommended by industry standards.
• The contractor shall follow HGRD LOTO Clearance Procedures.
4.0 REQUIREMENTS AND TASKS
The contractor shall provide all personnel, supervision, mobilization, tools, equipment, vehicles, materials, supplies, lodging, travel, meals and other direct cost to accomplish all tasks identified in this work statement.
4.1 QUOTATION REQUIREMENTS
4.1.1 The quotation shall provide evidence of at least ONE successfully completed projects of similar scope.
• Project Customer
• Project Name
• Site Location
• Summary of Scope
4.1.2 Included in the contractor’s quotation shall be a brief narrative of the technical solution and proposed.
• Manufacturer and model number
• Description and justification for system/subsystem
• Title and description service to be provided (if service)
4.2 SITE VISIT
4.2.1 A site visit may be coordinated through the contracting office prior to submitting a quotation.
4.2.2 The site visit is intended to allow the contractor to familiarize themselves with the requirements defined in this work statement and the conditions that they will be required to perform.
4.2.3 Any costs associated with the quotation shall be at the contractor’s cost; no reimbursement shall be paid.
4.2.4 There will only be a single scheduled site visit where all potential offerors will gather and be escorted by the assigned project Contracting Officer’s Representative (COR).
4.2.5 All questions shall be directed in writing to the CO; during the site visit there will be no documentation provided nor questions answered by BIA/CRA-ES personnel.
4.2.6 Photos and video will be allowed.
4.2.7 Those attending the group site visit shall be required to provide their own Personnel Protective Equipment
(PPE); as a minimum shall include.
• Work boots with safety toe
• Hard Hat
• Pants (Preferably Jeans or a Material that Resist Tearing)
• CDC Recommended COVID-19 PPE
• Adhere to all guidelines established by Executive Order. 14043
4.3 REQUIRED TASKS
4.3.1 TASK 1: PROJECT MANAGEMENT
4.3.1.1 The contractor shall designate a PM/PL to interface with the projects COR.
4.3.1.2 Within 10 days of the notice-to-proceed, the contractor shall schedule a kick-off/design review meeting with the COR to discuss the proposed technical solution, requirements, scheduling, and known issues and potential pitfalls.
4.3.2 TASK 2a: UPS SYSTEM
4.3.2.1 The contractor shall perform analysis to determine the load requiring interruption at HGRD.
4.3.2.2 The contractor shall coordinate with the COR to gain acceptance of the recommended loads for the new UPS system.
4.3.2.3 Once Government concurrence is achieved, the contractor shall acquire the required UPS and inverter system along with its support equipment.
4.3.2.4 The contractor shall remove and disposal of existing UPS System (plate data in table below).
Existing UPS System Plate Data
4.3.2.5 The contractor shall install, test, configure, and commission of one (1) New 208/120 VAC, 20 kVA replacement UPS system that is a continuous duty, three phase, solid-state, on-line double conversion reverse transfer static UPS that is compatible with existing charging system.
4.3.2.6 The UPS system shall be of a comparable footprint or size of the existing system.
4.3.2.7 The system shall be supported in racks and be in an industry standard enclosure.
4.3.2.8 The system shall utilize a battery system with Lithium-Ion Batteries (where possible).
4.3.2.9 The UPS shall, by means of solid-state conversion techniques, provide continuous regulated AC power to its output terminals, while operating from an input power source, cabinet mounted direct current (DC) storage battery or other approved means.
4.3.2.10 The UPS system shall conform to UL 1778.
4.3.2.11 The UPS system shall exhibit the following features.
4.3.2.11.1 A battery protective device
4.3.2.11.2 A static bypass transfer switch
4.3.2.11.3 A Maintenance-Bypass Switch
Item Description
Manufacturer Toshiba International Corporation
Type Form C42D3F150XAMXN
AC Input 3PH, 3wire, rated 480VAC, 50/60 Hz, 18.1A
Input power factor 0.98 lagging
AC Output 3PH, 4wire, rated 208/120VAC, 50/60 Hz, 15kVA
Output power factor 0.80 lagging
DC Input 46.0 A at 288 VDC
Serial No 110303027
4.3.2.11.4 A human-machine interface for manual control and monitoring
4.3.2.11.5 System protection (surge, safety, etc…) devices
4.3.2.11.6 A means of isolating the UPS system from the critical load
4.3.2.11.7 A remote monitoring interface
4.3.2.11.8 A Power Distribution Unit (PDU) with step down transformer and five sub-feed breakers, five busway sections with bus taps (to be sized based on earlier analysis)
4.3.2.12 A UPS system shall include all other associated equipment for correct operation.
4.3.2.13 The contractor shall include all required conduit, wire, electrical boxes and fittings for the correct installation.
4.3.2.14 The UPS system shall be installed to comply with industry standards and/or applicable electrical or fire codes to include maintaining adequate physical and electrical clearances; and physical clearances to facilitate maintenance actions.
4.3.2.15 The performance of the UPS system must not be degraded when operating without a system battery, provided the input AC source is within tolerance.
4.3.2.16 The performance of the systems/subsystems supplied by the UPS system must not be degraded when supplied from the UPS system.
4.3.2.17 The Power switching from utility power (AC power provided by station service) to UPS system
(loss of station service power) must be seamless and not cause the power generation control system to fault- no outage.
4.3.2.18 The UPS unit shall be scalable and shall be sized sufficiently to provide power to the current load for 3 hours minimum.
4.3.2.19 The contactor shall supply and install all ancillary (connect from/connect to) interconnecting wiring and conduit, and electrical feeds.
4.3.2.20 The contractor shall prepare a UPS System and Components Report, to include wiring diagrams that identify circuit terminals and indicate equipment internal wiring and the interconnections between each item of equipment.
4.3.2.21 The contractor shall provide a factory acceptance test report to the COR and shall contain the following information.
o Series/kVA o Serial number o Date of test o Approved by / Inspected by / Tested by o Inspection of construction o Checking of wiring (Black/Red marking on each connection point) o Grounding continuity o Insulation strength test o Control circuit operation o Measurement of steady state characteristics (Voltage/ current/ efficiencies) o Transient characteristics (0-100% step load, AC input failure) o Overload testing o Transfer switch operation
4.3.3 TASK 2b: UPS SYSTEM TEST
4.3.3.1 The contractor shall perform an on-site Installation Test in the presence of at least one CRA-ES staff member the UPS shall have completed at minimum the following field installation and tests.
4.3.3.2 Power switching from utility power (AC power provided by station service) to UPS system (loss of station service power) must be seamless and not cause the control system to fault- no outage.
4.3.3.3 Visual Inspections
• Ensure that shipping members have been removed.
• Ensure that interiors are free of foreign materials, tools and dirt.
• Check for damage (dents, scratches, frame misalignment, damage to panel devices, etc.).
• Check doors for proper alignment and operation.
4.3.3.4 Mechanical Inspections
• Check all the power wiring connections for tightness.
• Check all the control wiring connections for tightness.
4.3.3.5 Electrical inspections
• Check input and bypass for proper voltage and phase rotation.
• Check battery for proper voltage and polarity.
4.3.3.6 Start-up (energize or activate device)
• Energize the UPS.
• Check the DC output voltage and inverter output voltage.
• Check the inverter output voltage on battery operation.
• Check for the proper synchronization.
• Perform manual transfers and returns.
• Operate UPS Unit under full KW load for a minimum of one hour (provide load bank if necessary)
• Test static transfer from inverter to bypass and back
• Test DC under-voltage trip level on inverter input breaker/relay (set according to manufacturer’s published data)
• Test alarm circuits
• Verify synchronizing indicators for static switch and bypass switch
• Perform electrical tests for batteries including:
Measure negative post temperature and connectors (IR Camera) Measure charger float and equalizing voltages
• Verify all charge functions and alarms
• Verify operation of the maintenance and bypass switching
4.3.4 TASK 3a: POWER INVERTER
4.3.4.1 The contractor shall perform analysis to determine the correct size power inverter system suitable for the UPS system; preferably concurrent with, the UPS system analysis.
4.3.4.2 The contractor shall coordinate with the COR to gain acceptance of the recommended power inverter.
4.3.4.3 The contractor shall install, test, and commission of one (1) new 120 VAC, 5 kVA replacement
Power Inverter.
4.3.4.4 The contractor shall provide a power inverter that comparably meets the form, fit, and function of the existing power inverter (located Panel C2B) if possible (plate data in table below).
Existing Power Inverter Name Plate Data
Item Description
Type Form Power Inverter
DC Input 105 – 150 VDC, 53 ADC
AC Output 120 VAC, 41.7 AAC
Hz Output 60 Hz
4.3.4.5 The power inverter shall have a means to disconnect for maintenance via a maintenance bypass switch.
4.3.4.6 The power inverter shall display a visual indication of a fault and/or correct operation.
4.3.4.7 The power inverter shall meet the following specifications.
• MIL-STD-810
• MIL-S-901
• MIL-STD-1472
• MIL-STD-461
• MIL-STD-167
4.3.4.8 The power inverter shall include associated racks, interconnecting wire, conduit, electrical feeds, and include all other associated equipment for correct operation.
4.3.4.9 The power inverter shall be designed for harsh environments and feature an optional advanced
Internal Suppression Filter Network (ISFN) to suppress the significant transients associated with these types of conditions.
4.3.4.10 The contractor shall prepare a Power Inverter and Components Report, to include wiring diagrams that identify circuit terminals and indicate equipment internal wiring and the interconnections between each item of equipment, and installation details, as well as, maintenance requirements.
4.3.5 TASK 3b: POWER INVERTER TEST
4.3.5.1 The contractor shall perform an on-site Installation Test in the presence of at least one CRA-ES staff member the power inverter at minimum the following field installation and tests.
4.3.5.2 The Power switching from utility power (AC power provided by station service) to UPS system
(loss of station service power) must be seamless and not cause the power generation control system to fault- no outage.
4.3.5.3 One (1) copy of a Field Installation Test report shall be supplied to the COR; the Power Inverter shall have at minimum the following field installation tests completed.
4.3.5.3.1 Visual Inspection
• Ensure that shipping members have been removed.
• Ensure that interiors are free of foreign materials, tools and dirt.
• Check for damage (dents, scratches, frame misalignment, damage to panel devices, etc.).
• Check doors for proper alignment and operation, if applicable.
4.3.5.3.2 Mechanical Inspection
• Check all the power wiring connections for tightness.
• Check all the control wiring connections for tightness.
4.3.5.3.3 Electrical Inspection
• Check battery for proper voltage and polarity.
4.3.5.3.4 Start-up (energize or activate device)
• Energize the Power Inverter.
• Check the DC output voltage and inverter output voltage.
• Operate Power Inverter under full KW load for a minimum of one hour
(provide load bank if necessary)
• Test DC under-voltage trip level on inverter input breaker/relay (set according to manufacturer’s published data)
• Test alarm circuits
5.0 DELIVERABLES / DELIVERY SCHEDULE
5.1 Activity and Deliverable Timetable: Deliverable products shall be submitted to the addresses shown in Section 5.6, in accordance with the following schedule:
Item # Description Section # Distribution Acceptance Required Due Date
001 Initial Kick-Off Meeting and Minutes N/A N/A N/A 10 days after award
Project Management Plan/UPS & Power Inverter Analysis
4.2.2, 4.2.4, 5.2
COR- One (1) copy
BIA CO- One (1) copy Yes 30 days after award
Milestone Acceptance of recommended solution
4.3.2.3, 4.2.4.3
COR- One (1) copy
BIA CO- One (1) copy Yes 10 days after analysis
003 UPS Test Reports 4.2.3 COR – One (1) copy Yes 10 Days after Completion
004 Power Inverter Test Reports 4.2.5 COR – One (1) copy Yes 10 Days after
Completion
Table 1 - Activity and Deliverable Timetable
5.2 Project Management Plan: The contractor shall prepare a Project Management Plan identifying the PM/PL, and describing the technical approach and system solution analysis to be employed to meet the cost, performance, and schedule requirements for this effort.
5.3 Acceptance/Disapproval of Deliverables:
Unless otherwise specified, the Government will have a maximum of ten (10) working days from the day the deliverables are received to review the document, provide comments back to the contractor, accept or disapprove the deliverable(s). The contractor will also have a maximum of ten (10) working days from the day comments are received to incorporate all changes and submit the final deliverable to the Government.
5.4 Address for Deliverables:
Colorado River Agency Electrical Services 12000 1st Ave Parker, Az. 85344
6.0 PLACES OF PERFORMANCE
The places of performance will be at:
Main Meeting Location HGRD
Colorado River Agency Colorado River Agency Electrical Services Electrical Services 12000 1st Ave. Headgate Rock Dam Parker, AZ. 85344 Parker, AZ. 85344
7.0 WARRANTY
The contractor shall warrant all products, materials, and workmanship for a minimum of one (1) year from the date of work completion. Conveyance of all manufacturer/source commercial warranties, including a warranty summary documentation shall be part of submittal documentation.
8.0 TRIBAL TAXES, REQUIREMENTS AND/OR RESTRICTIONS
Special attention is called to FAR Clause 52.236-7, Permits and Responsibilities and FAR Clause 52.229-3, Federal, State, and Local Taxes. Offerors are responsible for contacting the tax authorities and tribe or tribal organization involved with regard to any requirements regarding state taxes, tribal taxes, royalties and/or other applicable tribal laws or ordinances. Any costs associated with this section shall be included in the contractor’s proposal. The contractor is responsible for contacting the appropriate TERO office for coordination and approvals.
| 1.0 INTRODUCTION |
| 2.0 OBJECTIVE |
| 3.0 SCOPE |
| 4.0 REQUIREMENTS AND TASKS |
| 5.0 DELIVERABLES / DELIVERY SCHEDULE |
| 6.0 PLACES OF PERFORMANCE |
| 7.0 WARRANTY |
| 8.0 TRIBAL TAXES, REQUIREMENTS AND/OR RESTRICTIONS |