This document is an amendment to a solicitation for the SFIR 3(1)_INDIAN BEND BRIDGE project. The amendment provides responses to questions from offerors regarding technical requirements for hollow steel pipe piles, tie rods between precast girders, and grout details. It clarifies that all piles must be driven to minimum tip elevations and reach bearing capacity before being filled with structural concrete to the abutment elevations. For grout between precast girders, a backer rod width of 1-3/4 inches and grout key width of 1-3/8 inches is acceptable even if less space remains between the bottom of girders. No other terms or conditions were changed in the amendment.

View the file

Other files for this federal contract opportunity

Other files attached to SFIR 3(1)_INDIAN BEND BRIDGE, newest first.
File Type Posted
Sol_140A1122B0003_Amd_0005.pdf PDF
Sol_140A1122B0003_Amd_0003.pdf PDF
Sol_140A1122B0003_Amd_0002.pdf PDF
Sol_140A1122B0003_Amd_0001.pdf PDF
Sections_B_-_M_-_Full_And_Open.pdf PDF
Sol_140A1122B0003.pdf PDF
Section_C_DESCRIPTION_SPECIFICATIONS.pdf PDF
DRAWINGS_(Drawings_NV_Indian_Bench_Bridge_Full_100__(2018-03-06).pdf PDF
ADDENDUM_NO_1_-_SFIR_3(1)_SCRs_-_Revised_Section_628.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140A1122B0003 x x

0 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Phoenix AZ 85004

A11

SUITE 400 MAILROOM

2600 N CENTRAL AVENUE

Contracting Office

DOI, BIA WRO

Phoenix AZ 85004

A11

SUITE 400 MAILROOM

Contracting Office

2600 N CENTRAL AVENUE

BIA WRO 00011

09/23/20220004

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

09/01/2022

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Amendment No. 4 is issued as follows:

1. Response to questions are provided:

Re: Hollow Steel Pipe Pile, Page 9 of 57 - Note: Pipe Pile will be filled with Class A(AE)

Concrete after Driving.

Question: It is assumed pile will have to drilled after being driven to what depth will the internal pile be required to drilled to. What is the depth of Concrete to placed

(Elevation) prior to placing welded steel cap? Will the concrete require Air ? If so what percent ?

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Renee Holly

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140A1122B0003/0004

Answer: All piles will be driven to minimum tip elevation (South Abutment - 5466.785, North

Abutment- 5466.5) and reach bearing capacity as well. Then filled with Class A(AE) structural concrete. Please see sheet 10 of 57 that shown the abutment elevations (South Abutment

-5579.785, North Abutment- 5579.50) and the pile being 9" into the abutment from these elevations(Sheet 12 of 57). This is a good volume to use for structural concrete. Air is required in all structural concrete mixes. Please see

Table 552-2 of the FP14. It requires 4.5-7.5 percent.

Re: Tie Rod, Page 17 of 57

Question: The Pile Caps per design are sloping to both sides of Centerline. Our Pre-cast Supplier has noticed that it is not feasible to thread the

Tie Rod through the girders as designed. Please provide Clarification.

Answer: We have a history of installing girders that are tied together with these tie rods, on a normal crown, with no issues during installation.

If there was any issues it was not brought to our attention and the Contractor resolved it with the manufacture during installation.

Re: Keyway Grout Detail - Page 18 of 57

Question: Drawing Typical Section : Due to

Design of the Cap , the bridge slopes each direction from centerline. Our Pre-cast Supplier has laid out the drawings and determined that between Girder D and Girder E, the bottom of the

Girders will have no space between the girders and the Joint at the top will be 7/8" wide. The

Backer Rod will have to 1 3/4" wide and the grout key 1 3/8 " . Will this be acceptable?

Answer: This is acceptable.

2. All other terms and conditions remain unchanged.

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)