This document is a detailed Statement of Work (SOW) for aftercooler core replacement and cleaning on the NOAA Ship FERDINAND R. HASSLER. The work involves replacing aftercooler cores on four engines (two main propulsion diesel engines and two ship's service diesel generators), all Caterpillar models C32 and C9. The government will furnish two sets of aftercoolers, and the contractor must wash, chemically clean, and test the cores, install new OEM seals and gaskets, inspect related components, and perform operational tests. The work is scheduled to be performed at the UNH Judd Gregg Marine Research Complex in New Castle, NH between 10/1/2025 and 10/6/2025, with a specific focus on cleaning the cores using recommended Caterpillar cleaning solutions at specific concentrations and temperatures. Upon completion, the contractor must provide a service summary report including individual engine hours, total fuel burn, inspection observations, and maintenance recommendations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_1333MK25Q0144.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOAA Hassler
( NOAA-S 250 )
Propulsion Machinery CONTRACT NO. N00000-00-X-0000
ITEM NO. 20002 CATEGORY "A" 2025-08-05
Aftercooler Core Replacement Plus Cleaning Kusterer, Justin
20001 - 1
1.1 Intent:
1.1.1 This item describes the requirement to change out and
clean aftercoolers on the port and starboard main engines (MPDE) and ship’s service diesel generators (SSDG) aboard NOAA Ship
FERDINAND R. HASSLER.
1.2 References:
1.2.1 None
1.3 Government Furnished Material:
1.3.1 2 sets of aftercoolers for MPDEs (C32)
1.3.2 2 sets of aftercoolers for SSDGs (C9)
1.4 Requirements:
1.4.1 Wash, chemically clean and test the GFM aftercooler
cores. Test to 30 psi.
1.4.2 Remove existing and install GFM aftercooler cores on both the PORT and STARBOARD main diesel engines, and both the port and starboard SSDGs.
1.4.3 Provide new OEM seal and gasket sets to accommodate
aftercooler changes on each engine.
1.4.4 Provide sealant for aftercooler cores. See 1.6.4.
1.4.5 Inspect and clean turbo housings and air lines.
1.4.6 Inspect intake plenum.
1.4.7 Inspect remaining connection points and parts removed to facilitate aftercooler core change.
1.4.8 Checkpoint: Submit a condition found report to the port engineer and contracting officer to recommend additional replacement parts and maintenance, as required.
1.4.9 Reinstall all components, utilizing new OEM seals and
gaskets.
1.4.10 Upon completion of all work, perform an operational test of all four engines. Observe engines for proper operation and control, to the satisfaction of the Chief Marine Engineer or Port Engineer.
1.4.11 Wash, chemically clean and test the removed aftercooler cores. Test to 30 psi.
1.4.12 Return removed aftercooler cores to port office.
Propulsion Machinery CONTRACT NO. N00000-00-X-0000
20001 - 2
1.4.13 Provide a service summary report. Include individual
engine hours and total fuel burn, inspection observations and any recommendations for additional maintenance or repairs.
1.5 Quality Assurance:
1.5.1 Run each engine until normal operating temperatures and conditions are met. Verify no leaks and proper operational parameters are met.
1.5.2 Perform a submerged hydrostatic test on each core to 30 psi. Provide testing report.
1.6 Notes:
1.6.1 MPDEs are CAT C-32 Engines, SSDGs are CAT C9 Engines.
Engine S/Ns as follows:
PME RND00123
SME RND00124
PDG C9J00506
SDG C9J00507
1.6.2 The replacement work is expected to be performed at the vessel’s homeport UNH Judd Gregg Marine Research Complex 29 Wentworth Road New Castle, NH 03854 facility between 10/1/2025 and 10/6/2025.08/18/
1.6.3 The point of contact for this work is the Port Engineer Justin Kusterer. He can be reached at 240-704-2815 or justin.kusterer@noaa.gov
1.6.4 Caterpillar recommends the following core cleaner:
Part Number Description Size
1U5490 *Hydrosolv 4165 19L (5 US gallon)
174-6854 *Hydrosolv 100 19L (5 US Gallon
*: Use a two to five percent concentration of the cleaner at temperatures up to 93deg C (200 degF). Refer to application guide, NEHS050526 or consult your Caterpillar dealer for more information.
1.6.5 It has been noted that after having been cleaned and
hydro tested, sealant may be removed from the aftercooler cores outer perimeter. The Contractor shall provide the required sealant in the event that GFE cores are lacking. Example:
Propulsion Machinery CONTRACT NO. N00000-00-X-0000
20001 - 3
| 1.1 Intent: |
| 1.1.1 This item describes the requirement to change out and clean aftercoolers on the port and starboard main engines (MPDE) and ship’s service diesel generators (SSDG) aboard NOAA Ship FERDINAND R. HASSLER. |
| 1.2 References: |
| 1.2.1 None |
| 1.3 Government Furnished Material: |
| 1.3.1 2 sets of aftercoolers for MPDEs (C32) |
| 1.3.2 2 sets of aftercoolers for SSDGs (C9) |
| 1.4 Requirements: |
| 1.4.1 Wash, chemically clean and test the GFM aftercooler cores. Test to 30 psi. |
| 1.4.2 Remove existing and install GFM aftercooler cores on both the PORT and STARBOARD main diesel engines, and both the port and starboard SSDGs. |
| 1.4.3 Provide new OEM seal and gasket sets to accommodate aftercooler changes on each engine. |
| 1.4.4 Provide sealant for aftercooler cores. See 1.6.4. |
| 1.4.5 Inspect and clean turbo housings and air lines. |
| 1.4.6 Inspect intake plenum. |
| 1.4.7 Inspect remaining connection points and parts removed to facilitate aftercooler core change. |
| 1.4.8 Checkpoint: Submit a condition found report to the port engineer and contracting officer to recommend additional replacement parts and maintenance, as required. |
| 1.4.9 Reinstall all components, utilizing new OEM seals and gaskets. |
| 1.4.10 Upon completion of all work, perform an operational test of all four engines. Observe engines for proper operation and control, to the satisfaction of the Chief Marine Engineer or Port Engineer. |
| 1.4.11 Wash, chemically clean and test the removed aftercooler cores. Test to 30 psi. |
| 1.4.12 Return removed aftercooler cores to port office. |
| 1.4.13 Provide a service summary report. Include individual engine hours and total fuel burn, inspection observations and any recommendations for additional maintenance or repairs. |
| 1.5 Quality Assurance: |
| 1.5.1 Run each engine until normal operating temperatures and conditions are met. Verify no leaks and proper operational parameters are met. |
| 1.5.2 Perform a submerged hydrostatic test on each core to 30 psi. Provide testing report. |
| 1.6 Notes: |
| 1.6.1 MPDEs are CAT C-32 Engines, SSDGs are CAT C9 Engines. Engine S/Ns as follows: |
| PME RND00123 |
| SME RND00124 |
| PDG C9J00506 |
| SDG C9J00507 |
| 1.6.2 The replacement work is expected to be performed at the vessel’s homeport UNH Judd Gregg Marine Research Complex 29 Wentworth Road New Castle, NH 03854 facility between 10/1/2025 and 10/6/2025.08/18/ |
| 1.6.3 The point of contact for this work is the Port Engineer Justin Kusterer. He can be reached at 240-704-2815 or justin.kusterer@noaa.gov |
| 1.6.4 Caterpillar recommends the following core cleaner: |
| 1.6.5 It has been noted that after having been cleaned and hydro tested, sealant may be removed from the aftercooler cores outer perimeter. The Contractor shall provide the required sealant in the event that GFE cores are lacking. Example: |